Professional Documents
Culture Documents
Aggregate Planning
1
12/19/2014
QUARTER 2 system
April May June
100,000 130,000 150,000 ▶ Disaggregation breaks the plan down
into greater detail
QUARTER 3
July Aug. Sept. ▶ Disaggregation results in a master
180,000 150,000 140,000 production schedule
2
12/19/2014
3
12/19/2014
4
12/19/2014
5
12/19/2014
Total units of inventory carried over from one Total units of inventory carried over from one
month to the next = 1,850 units month to the next = 1,850 units
Workforce required to produce 50 units per day = 10 workers Workforce required to produce 50 units per day = 10 workers
6
12/19/2014
PRODUCTION
COST EXTRA COST OF EXTRA COST OF
DAILY (DEMAND X INCREASING DECREASING 70 –
FORECAST PROD 1.6 HRS/UNIT PRODUCTION PRODUCTION TOTAL
MONTH (UNITS) RATE X $10/HR) (HIRING COST) (LAYOFF COST) COST
60 –
Jan 900 41 $ 14,400 — — $ 14,400
7
12/19/2014
8
12/19/2014
40
2
42
4
44
0
0
100
e
levels of inventory needed to meet demand r
i
Regular time 700
50 52 54 0
700
requirements o
d
Overtime 50 50
70 72 74 0
Revenue Management
Aggregate Planning in Services Example
Room sales Demand Figure 13.5
9
12/19/2014
Revenue Management
Revenue Management Approaches
Example Figure 13.6
Room sales Demand
▶ Airlines, hotels, rental cars, etc.
Curve
Total $ contribution =
100 (1st price) x 30 rooms + (2nd price) x 30 rooms =
($100 - $15) x 30 + ($200 - $15) x 30 =
$2,550 + $5,550 = $8,100 ▶ Tend to have predictable duration of service
and use variable pricing to control availability
60
and revenue
▶ Movies, stadiums, performing arts centers
▶ Tend to have predicable duration and fixed
30
prices but use seating locations and times to
manage revenue
10
12/19/2014
11
12/19/2014
12
12/19/2014
Notes
▶ The requirements equals the maximum of the
forecast and the customer orders
▶ The net inventory before MPS equals the inventory
from previous week minus the requirements.
▶ The MPS = run size, will be added when the net
inventory before MPS is negative ( weeks 3, 5, 7,
and 8).
▶ The projected inventory equals the net inventory
before MPS plus the MPS (70).
13