Professional Documents
Culture Documents
MEMBERSHIPS Australia
AND AFFILIATIONS Queensland – Mulgrave River
• American Society of Civil
Engineers (ASCE) Canada
system. The downstream fish passage facilities consist of fish ports located
in the pier walls, an airlift pump system and a gravity bypass pipe to the
tailwater. The upstream fish passage facilities consist of an Alaska
steeppass fishway located on the left (southerly) abutment with a resting
pool and upper pool, a false weir and a gravity fish return to the forebay
with fish counter.
Alternatives currently under consideration include modifications to improve
performance of the existing facilities and construction of an innovative
baffled channel to provide nature-like fish passage over the range of River
and tidal variations. Early action items such as installation of fish
monitoring/counting devices, operational modifications and studies are
proposed to address stakeholder concerns, to improve fish passage and to
inform the final design process.
Tumwater Fishway Entrance Structure Foundation Maintenance;
Leavenworth, WA
Client: PUD No. 1 of Chelan County, WA
Title: Project Manager
Start/End Dates: 2018 to present
Scope/Description: Managing the emergency evaluation and development
of alternatives to stabilize an existing vertical slot fishway and dam. The
Wenatchee River near Tumwater Dam is a high-energy, dynamic system
and over time scour has advanced to the toe of the Dam and fishway.
Various short- and long-term modifications are being evaluated including
the installation of micropiles, secant piles and grout-fill sacks.
Sack Dam Fish Passage and Protection; Dos Palos, CA
Client: Henry Miller Reclamation District (HMRD)
Title: Senior Consultant
Start/End Dates: 2018 to present
Scope/Description: Providing fisheries engineering support for design of a
700 cfs fish screen on the Arroyo Canal, a diversion dam and a fishway.
Key species of concern include Chinook salmon, steelhead and sturgeon.
Fishway concepts currently under consideration include a vertical slot
ladder, a nature-like fishway, a pool-and-chute ladder and a baffled ramp
fishway.
Sites Reservoir Evaluation; Sacramento, CA
Client: Sites Project Authority and the U.S. Bureau of Reclamation (USBR)
Title: Senior Consultant
Start/End Dates: 2018 to present
Scope/Description: Sites Reservoir is a proposed 1.8 million acre-foot off-
stream reservoir intended to divert and store excess Sacramento River
streamflows, providing approximately 500,000 acre-feet per year of
additional water supply on average. The Reservoir would provide multiple
beneficial uses including a reliable water supply for cities and agriculture;
dedicated water for fisheries and environmental purposes; increased
habitat for migratory birds; and improved flexibility and drought resiliency
for the Central Valley Project and the State Water Project. Diversions from
the Sacramento River to Sites Reservoir would be via fish screen intake
facilities located at Red Bluff (2,100 cfs), Hamilton City (1,800 cfs) and
Delevan (2,000 cfs).
Prepared a comprehensive literature search and preparing a Plan of Study
to evaluate potential impacts to fisheries from project water diversions.
Preparing intake facility operations and hydraulic information to support
development of environmental documents and project hydrologic modeling.
Also supporting discussions with resource agencies including NOAA
Fisheries, USFWS and the California Department of Fish & Wildlife.
Carmen-Smith Hydropower Project License Implementation; Eugene,
OR
Client: Eugene Water and Electric Board (EWEB)
Title: Chief Engineer for Upstream Fish Passage
Start/End Dates: 2019 to present
Scope/Description: Managing the preliminary and final design of a fish trap
and haul facility located on the McKenzie River.
Harris Reservoir Expansion; Lake Jackson, TX
Client: Dow Chemical (Confidential Client)
Title: Intake Subject Matter Expert
Start/End Dates: 2015 to present
Scope/Description: Providing technical support for the design of a 334 cfs
(216 MGD) intake and pump station on the Brazos River near Freeport,
Texas. The intake will include two 84-inch diameter tee screens meeting
EPA §316(b) criteria with a mechanical brush system and retrieval rack.
The pump station will include two 2,250 Hp electric motor-driven centrifugal
pumps, and the reservoir consists of an earthen embankment providing
50,000 acre-feet of storage with an outlet/release structure. The work
includes a multi-beam sonar bathymetric survey, a geomorphology study
and a physical intake and pump station model per Hydraulic Institute (HI)
standards.
Mendota Pool Fish Screen Project; Los Banos, CA
Client: Central California Irrigation District (CCID)
Title: Senior Consultant
Start/End Dates: 2019 to present
Scope/Description: Managing the preliminary and final design of a fish trap
and haul facility located on the McKenzie River.
Eastside Bypass Improvements Project; Merced County, CA
Client: Lower San Joaquin Levee District
Title: Senior Consultant
Start/End Dates: 2019 to present
Scope/Description: Provided review and comments related to a California
Department of Water Resources (CA DWR) plan to modify the existing
Eastside Bypass Control Structure. The project is part of the Lower San
Joaquin River Flood Control Project. The plan includes modifications to the
existing spillway and construction of a rock ramp with sheet pile cutoff walls
to facilitate fish passage while maintaining flood control functionality.
33rd Street Intake and Pump Station; Colorado Springs, CO
Client: Colorado Springs Utilities
Title: Senior Consultant
Start/End Dates: 2015 to present
Scope/Description: Prepared an alternatives study, preliminary design and
now final design for modifications to an existing 14 cfs diversion, intake and
pump station for a municipal water supply. Fountain Creek is a high-
gradient stream with variable streamflows and recurring sediment and
debris events. The magnitude and frequency of these events have been
made worse by the 2012 Waldo Canyon wildfire which took place in the
basin upstream. The project is intended to reconfigure this aging facility to
reduce operations and maintenance requirements, while maximizing
withdrawals of valuable Front Range water and improving the quality of
water delivered to the treatment plant. Approximately 20 diversion and
intake configurations were evaluated. The preferred alternative includes a
Coanda screen with a pneumatic crest gate (Obermeyer-type) diversion.
The need for a sedimentation basin will be determined following the
collection of additional hydraulic data and sediment samples in 2016.
Construction started in 2019.
Elwha River Water Intake and Treatment Plant; Port Angeles, WA
Client: City of Port Angeles
Title: Senior Consultant
Start/End Dates: 2015 to present
Scope/Description: Providing the City technical support during the turnover
and acquisition of facilities associated with the removal of the Elwha and
Glines Canyon Dams. Also supporting negotiations with the National Park
Service and U.S. Department of Reclamation.
Coquitlam Intake No. 2; Coquitlam, BC, Canada
Client: Metro Vancouver
Title: Senior Consultant
Start/End Dates: 2017 to present
Scope/Description: Evaluated alternatives, participated in workshops and
prepared the indicative design for a second drinking water intake at Lake
Coquitlam. The project includes a 3,255 MLD (860 MGD) intake,
approximately 8,550 m of 5 m diameter tunnel in hard rock to be excavated
by a tunnel boring machine (TBM), and a water treatment plant with
filtration. Construction of the intake will require advanced tunneling
methods and specialized underwater construction due to difficult site
constraints including steep slopes, limited access, heavy timber, First
Nations archaeological sites and the need to maintain water quality and
limit environmental impacts. The intake structure consists of a shaft located
near the shoreline with three inlet tunnels constructed by Norwegian
method lake taps. Each 5m diameter inlet tunnel will include a trashrack
and will be sized for the selective withdrawal of full design capacity. The
shaft will house operating and backup gates for each inlet tunnel, vertical
traveling screens, and head gates for the main tunnel. Various fish
protection measures can be incorporated into the design as necessary. A
control building will house a bridge crane, a generator, and appurtenant
instrumentation and control equipment.
EPA §316(b) Evaluations; multiple locations
Client: Various clients
Title: Senior Technical Advisor
Start/End Dates: 2003 to present
Scope/Description: Evaluated cooling water intake structures for thermal
power plants and industrial/manufacturing facilities. Prepared compliance
strategies, including engineering evaluations, conceptual drawings and cost
estimates to meet EPA §316(b) requirements. A number of intake screen
technologies and configurations were considered, including modified
Ristroph-type fish protection traveling screens manufactured by Hydrolox,
Siemens, Geiger, Beaudrey and Brackett Green. Other screening
technologies included cylindrical wedge wire screens, vee screens, vertical
and inclined flat panel screens, cone screens, louver racks, conventional
traveling screens, rotary drum screens, velocity caps, porous dikes, barrier
nets, aquatic filter barriers, and electric and sound barriers. Also supported
due diligence process for sale of power generation facility by evaluating
costs and risks associated with future EPA §316(b) compliance.
AdvanSix/Honeywell
• Hopewell Facility. James River, Hopewell, VA. 216 MGD.
Ascend Performance Materials
• Alabama Facility. Tennessee River, Decatur, AL.
Dominion
• Bremo Power Station. James River, Fork Union, VA. 179 MGD.
• Chesapeake Power Station. Elizabeth River/Intercoastal Waterway,
Portsmouth, VA. 514 MGD.
• Chesterfield Power Station. James River, Chester, VA. 1,058 MGD.
• Kewaunee Power Station. Lake Michigan, Cooperstown, WI. 582 MGD.
• Kincaid. Sangchris Lake, Kincaid, IL. 922 MGD.
• Manchester Street Station. Narragansett Bay, Providence, RI. 337
MGD.
• Millstone Power Station. Niantic Bay, Waterford, CT. 2,700 MGD.
• Morgantown Power Station. Monongahela River, Morgantown, WV. 115
MGD.
• Mt. Storm Power Station, Mt. Storm Lake, WV. 1,184 MGD.
• North Anna Nuclear Station. Lake Anna, Lewiston, VA. 2,708 MGD.
• Possum Point. Potomac River and Quantico Creek, Dumfries, VA. 212
MGD.
• Salem Harbor. Salem Sound, Salem, MA. 646 MGD.
• State Line Power Station. Lake Michigan, Gary, IN. 621 MGD.
• Surrey Nuclear Station. James River, Surry, VA. 2,304 MGD.
during periods when the operators are not on duty, typically at night, can
result in decreased fish passage performance.
The objective of this project was to identify an alternative type of fishway
entrance that reduces operational complexity, including elimination of the
stop logs, while enhancing fish passage. Other benefits may include the
improved utilization and distribution of water throughout the lower fishway.
The entrances provide up to approximately 1,032 cfs of fish attraction flow
each.
CH2M is developing a slotted “keyhole” weir that passively maintains
transport velocities in the fishway while optimizing attraction flows at the
entrance. The weir operates over the full tailwater fluctuation of
approximately 30 feet. It is anticipated that various analytical models,
include 3-D computational fluid dynamic (CFD) models will be used to
refine this concept prior to prototype testing.
Rock Island Auxiliary Water Supply (AWS) Evaluation; Wenatchee,
WA
Client: PUD No. 1 of Chelan County, WA
Title: Project Manager
Start/End Dates: 2014
Scope/Description: Evaluated the fishway auxiliary water supply (AWS)
system at Rock Island Dam, including the ability of the existing diffusers to
exclude selected fish species. The existing system includes three pumps
providing approximately 1,300 cfs to the fishway. An additional 338 cfs is
provided by gravity. The project included the evaluation of the increase in
head losses associated with a lower porosity diffuser system.
Rock Island Emergency Fishway Modifications; Wenatchee, WA
Client: PUD No. 1 of Chelan County, WA
Title: Project Manager
Start/End Dates: 2014
Scope/Description: This project was driven by an emergency drawdown at
Grant PUD’s Wanapum Dam located 37 miles downstream. A 65-foot long
crack was discovered in a Wanapum spillway pier monolith on 27 February
2014, and the reservoir was immediately drawn down which impacted the
tailwater at Rock Island Dam. This reach of the mid-Columbia River was at
its lowest stage in 50 years. This condition was expected to persist
throughout the summer until Grant PUD could make repairs. As such,
Chelan PUD and CH2M implemented and emergency program to install
extensions on the adult fishways at Rock Island Dam. The fishway
extensions consisted of upper and lower resting pools and two 30-foot
lengths of Denil ladder. They are designed to provide passage down to
approximately 12 feet below normal low tailwater. The design flowrates for
the LPE and TRE fishways were 90 cfs (58 MGD) each, and the design
flowrate for the left fishway was 54 cfs (35 MGD). Each assembly weighed
approximately 60,000 lbs. The fishways also included side flumes for
lamprey passage. Up to approximately 600,000 adult fish utilize the Rock
Island fishways each year, with the migration starting in mid-April. Within a
period of 6 weeks the fishway extensions for the right bank were designed,
Fish Hatchery (NFH) located on Icicle Creek near Leavenworth. The facility
will be integrated with related improvements including modifications to an
existing headgate structure, an inflatable weir and a roughed channel for
upstream fish passage. The facility will be designed to operate over a range
of flow regimes and severe winter conditions including frazil ice formation.
Rocky Reach Juvenile Fish Bypass System Improvements;
Wenatchee, WA
Client: PUD No. 1 of Chelan County, WA
Title: Project Manager
Start/End Dates: 2009 to 2010
Scope/Description: Advised the District with respect to installation of a
passive integrated transponder (PIT) tag antenna on the existing Rocky
Reach Juvenile Bypass System designed by CH2M HILL in the late 1990’s
and constructed in 2003. The antenna is required as part of Douglas PUD’s
re-licensing of the upstream Wells Hydroelectric Project. In addition, CH2M
HILL evaluated alternatives to further optimize juvenile Spring Chinook and
steelhead fish passage efficiencies at the 1,300-megawatt (MW) Rocky
Reach project.
City of Buckland Intake; Buckland, AK
Client: U.S. Army Corps of Engineers, Alaska District
Title: Project Engineer
Start/End Dates: 2008 to 2010
Scope/Description: Assisted with an alternatives evaluation and final
design of a water supply intake and transmission line for the city of
Buckland, a small native village located 75 air miles southeast of Kotzebue,
Alaska near the Arctic Circle. The Buckland River is the primary water
source for the city and water is drawn from the river with a portable pump,
treated, and then stored in a steel reservoir. Operation and maintenance of
the existing system becomes increasingly difficult during extended periods
of cold, freezing weather. The project will provide a permanent water intake
system and transmission main to supply raw water to a water treatment
plant year round. The project includes evaluating surface water intakes,
infiltration galleries, Ranney wells, and other intake technologies. The
selected design will consider flood plain and bank erosion issues, spring ice
jams, construction in permafrost and freeze protection and recovery.
Brightwater North Mitigation Area Culvert Replacement; Woodinville,
WA
Client: King County, Wastewater Treatment Division
Title: Project Engineer
Start/End Dates: 2008 to 2009
Scope/Description: Prepared final plans and specifications, and provided
services during construction for installation of a nine-foot-wide by four-foot
high bottomless aluminum box culvert for fish passage. The culvert was
installed on Upper Unnamed Creek located within the North Mitigation Area
adjacent to the King County Brightwater Wastewater Treatment Plant.
Upper Unnamed Creek is tributary to Little Bear Creek, a known cutthroat
trout habitat. The project used the Washington Department of Fish and
Wildlife (WDFW) Stream Simulation Method to size the culvert for the
benefit of both aquatic and riparian species. A rounded streambed gravel
was placed through the culvert reach. The gravel was underlain by a low
permeability soil and supplemented with a sanding mix following
placement. An adjacent rock sill and a “V” log weir with plunge pool were
also considered during the design.
Fire Suppression Intake Structure; Warrenton, OR
Client: Oregon LNG
Title: Project Engineer
Start/End Dates: 2008 to 2009
Scope/Description: Prepared conceptual design for a 45-cfs deluge fire
suppression intake structure associated with a liquefied natural gas (LNG)
import/re-gasification and storage facility. The fire suppression system
includes an intake on the Skipanon Waterway near its confluence with the
Columbia River, pump station, and discharge line. The system is intended
to protect the LNG tanks in the event they are exposed to heat from an
adjacent fire. The proposed intake design includes a stainless steel wedge
wire screen in a conical configuration with a mechanical brush cleaning
system. This type of intake is particularly well-suited for estuaries and
shallow marine areas.
Bull Run Water Supply Habitat Conservation Plan (HCP) Projects –
Alder Creek Fishway; Sandy, OR
Client: City of Portland
Title: Task Manager
Start/End Dates: 2007 to 2013
Scope/Description: The Bull Run water supply system has served
residents of the Portland metropolitan area continuously since 1895. The
current system includes a 102-square-mile watershed on the slopes of Mt.
Hood, two reservoirs with high-head dams and a headworks facility. The
Bull Run Water Supply HCP was developed to support an application for an
incidental take permit that will allow the City to comply with the federal
Endangered Species and Clean Water Acts.
Assisting with the planning, design, and construction of fish passage
improvements on Alder Creek in the Sandy River watershed near Mt. Hood,
Oregon. The intent of the improvements is to provide upstream and
downstream volitional passage at two existing obstructions to facilitate
access to spawning and rearing habitat for winter steelhead and coho
salmon. The upper site includes modifications associated with the existing
City of Sandy municipal water supply diversion. The lower site includes
modifications to a natural bedrock cascade and an existing fish ladder
located under the Highway 26 bridge. Design of the lower site utilized
ground-based light detection and ranging (LiDAR) survey methods to
accurately depict the complex topography and flow conditions. The fishway
was integrated into the natural bedrock formation and selectively uses
reinforced concrete to enhance natural pools and to facilitate the upstream
movement of adult steelhead. The concrete structures were dyed to blend
in with the natural basalt rock. Guide slots were provided at each pool for
the future regulation of flows if required.
Chiwawa Rearing/Acclimation Facility Upgrades; Plain, WA
Client: PUD No. 1 of Chelan County, WA
Title: Project Manager
Start/End Dates: 2007 to 2010
Scope/Description: Managed preliminary design of retrofits to the existing
Chiwawa Rearing/Acclimation Facility located on the Wenatchee and
Chiwawa Rivers. The facility will be expanded to accommodate 450,000
steelhead in addition to the 672,000 Spring Chinook already reared on-site.
The project includes a 22-cfs pump station, six 110-foot-long by 25-foot-
wide ponds, smolt trap, drain, cleaning waste system, and various support
buildings associated with the facility.
Creswell Water Treatment Plant Intake; Creswell, OR
Client: City of Creswell
Title: Project Engineer
Start/End Dates: 2007
Scope/Description: Prepared final design drawings and construction
specifications for a 5-cfs (3.2-MGD) water treatment plant intake located on
the Coast Fork of the Willamette River near Creswell. The intake consisted
of flat panel screens oriented in a slant configuration with an air backwash
cleaning system. This intake replaced an existing Ranney-type horizontal
collection well system that had lost capacity over time.
Fish Protection Screen Evaluation; Lynn, MA
Client: General Electric
Title: Project Engineer
Start/End Dates: 2006 to 2013
Scope/Description: Advising GE with regard to Clean Water Act 316(b) and
Section 308 requirements for the screening of cooling water intakes at their
Lynn, Massachusetts facility located on the Saugus River. The work
includes evaluation of three existing cooling water intakes, development of
various alternatives for operational modifications and/or facility
improvements, and preparation of conceptual drawings and construction
cost estimates.
Basin 29 Watercourse Stabilization Project; Mercer Island, WA
Client: City of Mercer Island
Title: Project Manager
Start/End Dates: 2006 to 2008
Scope/Description: Managed design and construction of a stream
restoration project in Sub-basin 29 on Mercer Island. High streamflows in
the sub-basin caused channel down-cutting, transport and deposition of
sediment, and slope failures in the 1000-foot-long reach downstream of
West Mercer Way. Restoring this stream channel, considered one of the
most degraded on the island, was a top priority of the city and local
residents. The project restored the watershed by employing bioengineering
techniques, including placement of woody debris, log weirs, coir matting,
natural streambed rock material and native plantings. The project also
included installing an energy dissipation structure and slope stabilization
measures.
Chelan River Project Tailrace Pump Station; Chelan Falls, WA
Client: PUD No. 1 of Chelan County, WA
Title: Project Manager
Start/End Dates: 2006 to 2009
Scope/Description: Managed design and construction of a 250 cfs (162
MGD) intake, pump station, canal, and diffuser outlet structure. As part of
Federal Energy Regulatory Commission (FERC) re-licensing requirements
for the 59-MW Lake Chelan Hydroelectric Project, the District is required to
enhance steelhead and Chinook salmon spawning habitat in the Chelan
River. Diversions for power generation historically left little or no flows in the
Chelan River which is bypassed by the hydroelectric project.
CH2M HILL provided design and construction-phase services for a 250-cfs
(162-MGD) intake, pump station, canal, and diffuser outlet structure. The
project provides minimum flows in Reach 4 of the Chelan River to augment
releases of up to 80 cfs from the dam. The low-head pump station avoids
the lost energy of additional releases from the dam at this 377-foot head
project. The pump station includes five 150-Hp constant-speed submersible
pumps arranged in a slant configuration with 5-foot-diameter cylindrical
wedge wire tee screens dedicated to each pump. The 42- and 48-inch-
diameter pump columns are supported on 24-inch-diameter drilled piers.
The piers were constructed inside casings placed with a land-based Leffer
hydraulic oscillating drill rig. The pump station design approach saved
millions of dollars in construction costs in comparison to a traditional cast-
in-place wet well pump station. Other aspects of the project included
installation of a low-level outlet at Lake Chelan Dam and construction of
more than four acres of stream and riparian habitat (by others). Total
construction cost was approximately $12.1 million. At the time of the project
commemoration on November 5th, 2009, District biologists counted 281
Chinook redds (or nests) within the enhanced habitat area—a testament to
the success of the project. Fulfillment of the FERC re-licensing
requirements will allow the District to operate the hydroelectric facility for a
50-year license period. This project was winner of the 2010 National
Hydropower Association (NHA) Outstanding Stewards of America’s Waters
Award, and was a 2011 American Council of Engineering Companies
(ACEC) Engineering Excellence National Gold Award winner.
Bull Run Water Supply Habitat Conservation Plan (HCP) Projects –
Fish Passage; Sandy, OR
Client: City of Portland
Title: Task Manager
Start/End Dates: 2006 to 2008
Scope/Description: The Bull Run water supply system has served
residents of the Portland metropolitan area continuously since 1895. The
450,000 steelhead including a new intake and pump station, water supply
line, rearing ponds and appurtenant facilities.
Cougar Fish Collection and Transportation Facility; Rainbow, OR
Client: U.S. Army Corps of Engineers, Portland District
Title: Project Engineer
Start/End Dates: 2005 to 2006
Scope/Description: Evaluated site location, water supply, and facility
alternatives for a fish collection and transportation facility at the 28-MW
USACE Cougar Dam, and prepared conceptual-level designs of the
preferred alternative. With the construction of a temperature control tower
on the Cougar reservoir, there are opportunities to re-introduce Chinook
salmon and bull trout into the upper watershed. In collaboration with the
resource agencies, CH2M HILL evaluated various fish collection and water
supply alternatives for this project on the South Fork McKenzie River. Both
gravity and pumped water supply alternatives were considered. Direct-drive
turbine pumps powered by penstock or other water supplies were also
evaluated. The preferred alternative included a pool-and-weir fish ladder
with a pumped auxiliary water system (AWS), a sorting and holding facility
for four classifications of fish, passive integrated transponder (PIT) tag and
coded-wire detection, and three 20-foot-long holding pools with elevated
water-to-water transfer to fish transport trucks. The final design was
completed by the USACE, Portland District and the project was constructed
in 2009.
North Umpqua Hydroelectric Project - Soda Springs Fish Screen and
Fish Ladder; Toketee Falls, OR
Client: PacifiCorp
Title: Project Engineer
Start/End Dates: 2005
Scope/Description: Prepared conceptual designs and cost estimates for a
fish ladder and a hydropower intake screen at the PacifiCorp’s 11-MW
Soda Springs project on the North Umpqua River. The reservoir forebay
water surface elevation fluctuates approximately 16 feet necessitating
special features to accommodate the various operating conditions. The
pool-and-weir fish ladder includes 68 pools with a gravity auxiliary water
system (AWS), a false weir, and a return pipe. The 3,000-cfs vee screen
includes approximately 2,700 feet of bypass piping and a fish sampling and
evaluation facility. Spillway apron modifications were also considered to
facilitate downstream passage for juveniles.
Basin 26 Watercourse Stabilization Project; Mercer Island, WA
Client: City of Mercer Island
Title: Project Manager
Start/End Dates: 2005
Scope/Description: Managed design and construction of a stream
restoration project in Sub-basin 26 on Mercer Island. High streamflows in
the sub-basin caused historic channel down-cutting in the 500-foot-long
reach downstream of 84th Avenue SE. The project restored the