Method Statement for Concreting Work

PROJEK PEMBAIKAN CERUN DAN KERJA –


KERJA BERKAITAN DI SEKOLAH KEBANGSAAN
KAULUAN RANAU , SABAH . MS/2019 - 11 Rev.: 00 Page 1 of 7

Project Name:
PROJEK PEMBAIKAN CERUN DAN KERJA – KERJA
BERKAITAN DI SEKOLAH KEBANGSAAN KAULUAN RANAU
SABAH .

Document Title:
METHOD STATEMENT
FOR
CONCRETING WORK
(SHEAR WALL)

Submission Record

Revision Date Revision Information

00 14/02/2020 First issue.

Prepared by Date 14/02/2020


ASDIA FATHIYA BINTI SIMUDAH

Reviewed by CHARNOLD BIN MIOL Date

Approved by KHAMIRUL ALMY BIN AMINUDDIN Date

APPROVED APPROVED WITH COMMENTS REJECTED,


Proceed with the works Proceed with the works and to comply (pls. specify): REVISE AND
RESUBMIT

Note: Please tick the appropriate box


Method Statement for Concreting Work
PROJEK PEMBAIKAN CERUN DAN KERJA-KERJA
BERKAITAN DI SEKOLAH KEBANGSAAN
KAULUAN , RANAU , SABAH MS/2019 - 11 Rev.: 00 Page 2 of 7

TABLE OF CONTENTS

Items
Title Page
No.
1.0 INTRODUCTION 3
2.0 OBJECTIVE 3
3.0 WORKS METHODOLOGY 3
4.0 HEALTH, SAFETY AND ENVIRONMENT REQUIREMENT 4
5.0 QUALITY ASSURANCE & CONTROL REQUIREMENT 5
6.0 PLANT, MACHINERY AND EQUIPMENT 5
7.0 MANPOWER – KEY PERSONNEL 5
8.0 MATERIALS 6
9.0 REFERENCES 6
10.0 REQUEST FOR INSPECTION 6
11.0 ANNEXURES 6
Method Statement for Concreting Work
PROJEK PEMBAIKAN CERUN DAN KERJA –
KERJA BERKAITAN DI SEKOLAH KEBANGSAAN
RANAU , SABAH MS/2019 - 11 Rev.: 00 Page 3 of 7

1.0 INTRODUCTION

Under the scope of work for Projek Pembaikan Cerun Dan Kerja – Kerja Berkaitan di
Sekolah Kebangsaan Kauluan Ranau,Sabah Concreting work for Shear Wall and its
associated works need to be carried out.

2.0 OBJECTIVE

Shear wall is a vertical structural element used to resist the horizontal forces such as
wind force, seismic force. These forces acts parallel to the plane of the wall. Shear
walls are generally used in high rise buildings where effect of wind forces and
seismic forces is more.

3.0 WORKS METHODOLOGY

3.1 Preparation Stage

a) Setting Out shall be carried out based on reference points on site by survey or
shown in the drawings.

b) Timber pegs or others will be used to set out RC Slab and RC Wall positions as
per drawing.

c) A blinding layer (lean concrete Grade 15) of 50mm thickness is normally


provided in the design to provide a clean working platform.

3.2 Construction Procedure

Reinforcement Fabrication & Installation

a) All reinforcement T12 and BRC A10 for the works shall be approved by
Engineer. Material approval from SESB to be obtained prior to delivery to the
project site.

b) The reinforcement shall be cut, bent and fixed according to the construction
drawing by an experienced supervisor or bar-bender.

c) 75mm dia. PVC weepholes to be installed (for RC Wall) as per shown in


construction drawing.

d) Once fabrication and fixing work of reinforcement bar completed, final joint
inspection between SESB Representative and Contractor to be arranged
prior to commencement of concreting work.
Method Statement for Concreting Work
PROJEK PEMBAIKAN CERUN DAN KERJA –
KERJA BERKAITAN DI SEKOLAH KEBANGSAAN
RANAU , SABAH MS/2019 - 11 Rev.: 00 Page 4 of 7

Formwork Installation

a) In case of openings to improve the efficiency of shear wall, connect the piers of

shear walls by spandrels.  Pier is nothing but the portion of shear wall between

two openings and spandrel is the portion of shear wall above the opening. The

resulting wall appeared by interconnecting spandrels of piers of shear walls is

known as coupled shear wall. Provision of openings in balanced pattern can also

make the shear wall efficient.

b) In flanged shear walls, the walls will meet at right angles to each other. This type

of shear walls are less efficient since they are effected by seismic forces in both

principal directions of the building.

Concreting Work

a) Trial Mix for Concrete Grade 25 and Grade 30 shall be carried out witnessed
by SESB representative and Contractor prior to commencement of
concreting work.

b) The concrete casting sequence is such that cold joints are to be avoided.

c) Portable internal porker vibrators shall be used to compact the concrete.

d) Slump test to check the workability of the concrete shall be carried out on site.
Refer Design Mix of Concrete Grade15, Grade 25 and Grade 30 attached.

e) Six (6) nos. of cube sample (150mm x 150mm x 150mm) shall be collected for
the batch of Concrete G25 or G30 on each day. These cube samples shall be
tested for 7 days (3 nos) and 28 day (3 nos) at an Independent Laboratory.

f) After 3 days (or more) completion of concreting work, Contractor to arrange


Post-Concreting work in order to proceed the next activity related to the
completed structure.
Method Statement for Concreting Work
PROJEK PEMBAIKAN CERUN DAN KERJA –
KERJA BERKAITAN DI SEKOLAH KEBANGSAAN
RANAU , SABAH MS/2019 - 11 Rev.: 00 Page 5 of 7

4.0 HEALTH & SAFETY REQUIREMENT

4.1 Health & Safety Requirement

4.1.1 All personnel involve with the event shall have;


a) Compulsory to provide and wearing Personal Protective Equipment
(PPE) at all times during commencement of works at site;

(i) Safety vest.


(ii) Safety shoes.
(iii) Safety helmet (if required).

4.1.2 Housekeeping need to maintain at all time.


Method Statement for Concreting Work
PROJEK PEMBAIKAN CERUN DAN KERJA –
KERJA BERKAITAN DI SEKOLAH KEBANGSAAN
RANAU , SABAH MS/2019 - 11 Rev.: 00 Page 6 of 7

5.0 QUALITY ASSURANCE & CONTROL REQUIREMENT

The quality assurance & control requirements shall be in accordance with this method
statement. In carrying this works the following documents & forms and procedures shall
be implemented before commencement of work;

(i) Request for Inspection (RFI) form.


(ii) Inspection Checklist.

6.0 PLANT, MACHINERY AND EQUIPMENT


The equipment involved in the Concreting work (but not limited to), according to type and
suitability: -

No Equipment / Plant / Tools Description

1 Survey Equipment To determine level & position of Structure


To transport Concrete Mix from batching plant to
2 Mixer Truck (Ready Mix) site
3 Portable Concrete Vibrator To compact fresh concrete during concreting

7.0 MANPOWER – KEY PERSONNEL


Typical manpower involved in Concreting work (but not limited to) are as follows: -

Item Type of Manpower Job Function

1. Project Engineer Supervising work in progress at site

2 Site Supervisor Standing supervision at site

3 Competent Person Implementing site safety procedures

4 Machinery Operator Operating the plant and machineries

5 General Worker Carrying out works on the ground

6 Surveyor & Chainman Setting out of alignments and levels.


Method Statement for Concreting Work
PROJEK PEMBAIKAN CERUN DAN KERJA –
KERJA BERKAITAN DI SEKOLAH KEBANGSAAN
RANAU , SABAH MS/2019 - 11 Rev.: 00 Page 7 of 7

8 .0 MA TER IA L
i) T12 Reinforcement Bar
ii) R10 Bar for Shear Link
iii) Timber Formwork
iv) 75mm dia. PVC Weepholes
v) BRC A10
vi) Concrete Grade 15, Grade 25 & Grade 30.

9.0 REFERENCES
The work is carried out in accordance to the following: -
(i) Bill of Quantities.
(ii) Approved Project Construction Drawing.

10.0 REQUEST FOR INSPECTIONS


The Contractor shall submit the request for work inspection (RFI) form to the Supervising
Engineer, or his representative with all the relevant attachment, to allow inspection being
conducted before any subsequent work start.

11.0 ANNEXES
(i) Design Mix for Concrete G15, G25 & G30
(ii) Request for Inspection (RFI) Form
(iii) Concreting Checklist Form