07-01-14

QUOTATION
N° 2/ 01.14

Owner Serge Abi Saleh Phone N°


Boat location La Marina Mobile N°
Boat Pershing 46 Fax N°
Hull # 39 Boat Name SAS

Dear Mr. Abi Saleh,


Please find here below our quotation for the works to be carried out on your boat:

Item Description Qty U.P $ T.P $


#
Dry dock fees

Lifting / launching fees with 7 days on the


1 1 1,350 1,350
dry in La Marina Dbayeh

Transmission line works and Bottom FRP repair


Labor for dismantling and re-assembly of
transmission components both sides
(propeller, shafts, shafts supports, shaft
logs, shaft seals) and rudder / rudder hub
port side.
1 Re-installation of the shaft support and 2 2,500 5,000
alignment with gearbox and intermediate
shaft support.
Replacement of shaft bearings.
Sea trial and vibration tests for approval.

Misc. consumable used for transmission


2 1 225 225
works
FRP works - repair of the Fiber Glass
damage at shaft supports port sides -
3 Labor and material 1 1,250 1,250
Manufacturing of new covers for shaft log
port and stbd sides
Transmission line parts
1 Propeller 4 blades PS 1 5,655.00 5,655.00
2 Propeller shaft 1 4,564.00 4,564.00
3 Shaft support 2 3,423.00 6,846.00
4 Shaft support bearing 2 580.00 1,160.00
5 Rudder PS 1 3,880.00 3,880.00
07-01-14
QUOTATION
N° 2/ 01.14

Owner Serge Abi Saleh Phone N°


Boat location La Marina Mobile N°
Boat Pershing 46 Fax N°
Hull # 39 Boat Name SAS

Shipping charges - Delivery time is 25 days


6 1 2,450.00 2,450.00
after confirmation -
7 Customs duties - Transit procedure- 1 950.00 950.00
Bottom Works
1 Antifouling (Int'l paint - Interspeed Ultra) 5 195 975
2 Primer (Int'l paint - Interspeed Ultra) 3 135 405
3 Metal Primer 1 85 85
4 Metal T coat 1 85 85
5 Metal Antifouling 1 85 85
Labor for pressure washing and cleaning
hull and transmission components,
6 stripping old antifouling, applying 2.5 1 1,350 1,350
coats of new antifouling and replace zinc
anodes
7 Zinc anode kit 1 750 750
Labor for checking seacock valves,
8 underwater gear and cleaning sea water 2 75 150
strainers
Labor and material for polishing hull's
9 1 750 750
topsides and superstructure

S- TOTAL $ 37,965.00
V.A.T. 10 % $ 1,246.00
TOTAL $ 39,211.00

NB:
1- Payment terms are 75% on approval and 25% upon work completion.
2- Work done out of the scope mentioned above will be charged separately
3- Quotation valid for 15 days.

Sea Pros Customer Approval


Name: Ziad Maalouf Name:
Customer Service