Professional Documents
Culture Documents
Al Dhafra Region
07 Engineering S-Curve
08 Procurement S-Curve
09 Construction S-Curve
Existing Tank
Offshore
ne
P E Pipel
D
3 73 0m H
2
xi m ately
A ppro
FSHORE-
OF
Project Scope of Works
Scope Of Work:
Supply, installation, construction, testing, commissioning of pipeline works of approximately 24klm(offshore)+
2klm(onshore) with all associated civil work.
Sila Offshore
Al Yasat
2 OD 630mm – HDPE Pipeline Lm 1500m
Sl.No Description Unit Qty Remarks
3 Isolation Valve Chamber (500mm) Nos 2
1 HDPE Pipeline (630,500,355,250mm) Lm 950m
4 Motorized Valve Chamber (500mm) Nos 1 2 Gate Valve Chamber (300mm) Nos 2
Ge ne ra l & Pre lim ina rie s 75.00% 71.20% -3.80% 75.00% 71.20% -3.80%
Sho rt Le a d Ite m s 98.87% 43.44% -55.43% 100.00% 43.44% -56.56% 250 m m HDPE p ip e m a n u fa c t u rin g fin ish e d & d e liv e re d .
O D630 Pip e lin e in st a lla t io n w o rks 40.16% 5.68% -34.48% 42.40% 6.28% -36.12%
HDD Wo rks - O D630 p ip e lin e - O ffsh o re t o Ya sa t ( 300 m ) 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Te sting & Ste riliza tio n 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1. Sila(Onshore) – 450 meters 630mm Pipe laying completed and backfilling is ongoing progress
2. Remaining excavation is under progress, total of 945 meters of excavation completed out of 1500 meters.
3. Sila, 726 meters of sand bedding completed.
4. Sila, NDRC-1 casing pipe installation completed
5. Sila, NDRC-2 preparation work completed. ( Excavation & trench work in progress)
6. Offshore- 9.8 Km 630mm pipeline ready for Hydro pressure test.
7. Offshore- 10 strings (2,500 meters) Hydrotest completed.
8. Concrete collar casting and painting are under progress. A total of 2,798 Nos casting was finished and a total of 2,337 Nos
were delivered at the site
9. 750 Nos concrete collar painting completed
10. Yasat- Structural fill installation and compaction- 4 th Layer, tank 1 completed & Inspected
11. Structural fill installation and compaction- 4 th Layer Tank 2 completed & inspected
Overall Project S-Curve
100.00% 100.00%
96.91%
94.89%
90.00%
91.00%
86.12%
80.00% 81.11%
74.51%
70.00%
66.51%
60.00%
58.92%
55.12%
50.00%
49.91%
43.02% 45.40%
40.00% 41.09%
34.89%
30.00% 26.58%
30.30%
19.66%
20.00%
13.80% 19.22%
17.88%
8.95% 13.39%
10.00%
3.53% 8.60%
5.32%
0.00% 0.13%
0.05% 1.04%
0.96% 2.18%
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
- 2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 - 2 -2 -2 -2 -2 -2 -2 -2 - 2 - 2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2
ay Jun Jun Jun -Jul -Jul -Jul Aug Aug Aug Aug Sep Sep Sep Oct Oct Oct Oct Nov Nov Nov Dec Dec Dec Jan Jan Jan Jan Feb Feb Feb ar ar ar Apr Apr Apr Apr ay ay ay Jun Jun Jun Jun -Jul -Jul -Jul Aug Aug Aug Sep Sep Sep Sep Oct Oct Oct Nov Nov Nov Nov
-M 9- 18- 27- 6 15 24 2- 1- 0- 9- 7- 6- 5- 4- 13- 22- 31- 9- 8- 7- 6- 5- 4- 2- 11- 20- 29- 7- 6- 5- 5-M 4-M 3-M 1- 10- 19- 28- 7-M 6-M 5-M 3- 12- 21- 30- 9 18 27 5- 4- 3- 1- 0- 9- 8- 7- 16- 25- 3- 2- 1- 0-
31 1 2 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 1 2 1 2 3
Planned% Actual%
Updated Program High Level Summary
Engineering S-Curve
99.15% 100.00% 100.00%
100.00% 97.35% 100.00% 100.00%
94.21%
94.75% 94.75% 94.75%
90.00% 94.22%
91.00% 92.00%
88.37%
80.00%
73.16%
73.04%
70.00%
60.00% 59.48%
53.65%
50.00%
42.04%
40.00%
30.00%
25.38%
20.00% 19.80%
12.22%
10.00%
0.00% 0.25%
0.00%
31-May-23 30-Jun-23 31-Jul-23 31-Aug-23 30-Sep-23 31-Oct-23 30-Nov-23 31-Dec-23 31-Jan-24 26-Feb-24 29-Feb-24 18-Mar-24
Planned% Actual %
Procurement S-Curve
100.00%
98.93% 100.00%
85.67%
80.00% 77.46%
78.34%
74.35%
70.00%
69.01%
60.00%
62.38%
40.00% 40.65%
30.00%
30.98%
27.94% 29.56%
20.00%
21.10%
17.77%
10.00%
11.64%
2.01% 9.32%
0.00% 0.00% 0.16% 0.00% 0.00% 0.00% 0.00% 0.00%
3.39%
0.00%
Planned % Actual%
Construction S-Curve
100.00% 100.00%
98.88%
90.00%
94.82%
87.06%
80.00%
77.29%
70.00%
68.14%
60.00% 59.76%
50.00% 49.81%
40.00% 40.64%
36.31%
30.00% 30.28%
20.00% 21.92%
10.00%
13.47%
7.12%
6.39% 7.09%
1.51% 1.15% 2.16% 5.42%
0.00% 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Planned% Actual%
Concrete Collar Production status:
Day-wise Casting & Delivery Status: (11.03.2024 to 18.03.2024)
Description 12/03/2024 13/03/2024 14/03/2024 15/03/2024 16/03/2024 17/03/2024 18/03/2024 Total Average Total
Total Concrete Collar(Nos) Total Casted(Nos) Total Delivered at the site (Nos) Remaining for casting(Nos) Remaining for delivery(Nos)
Out of Casted
Total Concrete collar(Nos) Primer Painting First Coat Painting Second Coat Ready to Inspection Done
Inspection
Description 12/03/2024 13/03/2024 14/03/2024 15/03/2024 16/03/2024 17/03/2024 18/03/2024 Total Direct Average Direct
Manpower Manpower
Site Engineer 1 1 1 1 1 0 1 6 1
Foreman 3 3 3 3 3 0 3 19 3
Driver 6 6 6 6 6 0 6 49 8
Welder 11 11 11 11 11 0 11 66 11
Operator 8 8 8 8 8 0 8 48 8
Helper/Labors 36 36 36 36 36 0 36 227 32
Painters 5 5 5 5 5 0 5 30 5
Marine Engineer 1 1 1 1 1 0 1 6 1
Surveyor 1 1 1 1 1 0 1 6 1
Store Keeper 1 1 1 1 1 0 1 6 1
Electrician 1 1 1 1 1 0 1 6 1
Lifting supervisor 1 1 1 1 1 0 1 6 1
Concrete collar (Sub contract) 69 69 69 69 69 0 69 414 69
NDRC (Subcontractor) 6 6 6 6 6 0 0 30 6
Total 150 150 150 150 150 0 144 919 142
Average Equipment Status
Average Equipment Status Performed in this Period:
Heavy Machinery:
Description 12/03/2024 13/03/2024 14/03/2024 15/03/2024 16/03/2024 17/03/2024 18/03/2024 Total Equipment Average Total
Equipment
Excavator 3 3 3 3 3 0 3 18 3
Shovel 1 1 1 1 1 0 1 7 1
3 Tone Pickup 2 2 2 2 2 0 2 12 2
1 Tone Pickup 1 1 1 1 1 0 1 6 1
Crane 1 1 1 1 1 0 1 6 1
Welding machine 0 2 0 0 1 0 0 18 3
Hiab 0 2 0 0 1 0 0 18 3
JCB 1 1 1 1 1 0 1 6 1
Water Tank 1 1 1 1 1 0 1 6 1
Total 10 14 12 12 12 0 10 97 16
Average Equipment Status
Average Equipment Status Performed in this Period:
250mm HDPE pipe line 100 0 completed 108 meters manufacturing Delivered completely
completed
GRP Tank 2 0
HDPE Pipe Fittings 5
D.I. Pipe Fittings 0 15-March-2024
AIR RELEASE VALVES 0 27-April-2024
Altitude Valves 0 April-2024
Motorized Gate Valve & Flanged 0 27-April-2024
Gate valve
Plunger Flow Control Valves 0 25-Aug-2024
Motorized Butterfly Valve 0 27-April-2024
Actuator control valve 0 27-April-2024
DI Pipelines 0 April-2024
I&C Items 0 April-2024
Electrical Items 0
Submittal and Shop Drawing Log
1.DOCUMENT LOG SHEET (DTS).xlsx2.MATERIAL LOG SHEET (MAS).xlsx
NOCs Status
Area of concern
1. Sila- Layout submission after trial pits.
2. Offshore- Layout submission.
3. Offshore excavation and Pipelaying start
4. Material barge release for mobilization
5. Marine team mobilization
6. Fireline preparation at offshore area
Progress Photos
Yasat- Structural fill installation and compaction for GRP Tank installation
ThankYou!
Organization echo’s…
“Coming together is a beginning.
Keeping together is progress.
Working together is success.”
Visit to: https:addc.ae