1 Project Summary
4 Detailed Procedure
1 Project Summary
1. Project Summary
▣ Project Summary
▣ Summary of Sub-Contractor
Concrete Pile
- Installation of WTG : Performed with Specialized Company,
Daeshin Wind Power co., Ltd & CDS Industries
1. Project Summary
2. No.7 Top & Bottom Jacket Installation : May 14th 2015 ~ Jul. 10th 2015
3. No.5 Top & Bottom Jacket Installation : Jun 21st 2015 ~ Aug. 18th 2015
4. No.6 Top & Bottom Jacket Installation : Jun 21st 2015 ~ Aug. 22nd 2015
5. No.3 Top & Bottom Jacket Installation : Aug. 26th 2015 ~ Sep. 10th 2015
6. No.2 Top & Bottom Jacket Installation : Sep. 16th 2015 ~ Sep. 31th 2015
7. No.1 Top & Bottom Jacket Installation : Apr. 22nd 2016 ~ Jun. 12th 2016
8. No.10 Top & Bottom Jacket Installation : May 24th 2016 ~ July 10th 2016
9. No.8 Top & Bottom Jacket Installation : Jun. 5th 2016 ~ Aug. 10th 2016
10. No.9 Top & Bottom Jacket Installation : Jun. 20th 2016 ~ July 25th 2016
2. Construction schedule/ Track Records
Total 11 15 15 15 15 15 15 15 11 15 22 14 6 6 190
3. Installation Vessel & Equipment
Completion
(Safety
Inspection &
COD)
Installation of Survey of
offshore TR seabed & soil
Construction of Design of
under sea cable FDN
Transport of
Installation of Component
WTG
(w. FDN)
FDN &
Installation of
Offshore
Tower
Construction
(1) Sub Structure (Jacket)
If it can be removed by manpower, the obstacle shall be transported to out of range of Jacket installation place
If it can not be removed by manpower, it shall be transported to out of range of Jacket installation place by using
of crawler crane
Underwater concrete form installing and filling concrete through aperture shall be carried out after leveling work
for seabed
(1) Sub Structure (Jacket)
Transporting the structure and turning over. Temporary placing the structure to subsea
foundation
(1) Sub Structure (Jacket)
Confirming the final excavation depth & injecting clean water in order to remove
slime
(1) Sub Structure (Jacket)
Grouting work for the mortar(1:1) into gap between jacket and Pin-pile
(1) Sub Structure (Jacket)
8) Move “Upper part of the Jacket” to the target point & Connection
- Connect “Lifting Wire” and “Shackle” to “Jacket Lug”
- It will be connected to lower part of the jacket, which it was already installed
(1) Sub Structure (Jacket)
9) Welding for the connecting point & NDT (Non Destructive Testing)
- Integrate and Strengthen the connecting point (for Lower and Upper part of the Jacket)
through “Welding” performance
- Conduct “NDT” in order to check a suitable and appropriate status of the welding point
(1) Sub Structure (Jacket)
- Painting performance will be followed for its better appearance and anti-corrosion.
(2) Upper Structure (WTG)
1) WTIV Mobilization
3) Hub Installation
3) Blade Installation
1) Connecting Lifting jig with the blade that is delivered by Transfer Barge
(2) Upper Structure (WTG)