OPERATIONS RESEARCH
Workbook

SEQUENCING

1. n jobs × 2 machine problems


2. n jobs × 3 machine problems

Type 1: n jobs × 2 machine problems


PROBLEM 1:

There are six jobs, each of which must go through two machines A and B in the
order AB. Processing time in hours is given in table.

Processing time
Job Machine Machine
A B Determine the sequence for
1 2 3 a the six jobs which will
2 5 6 e
minimize the elapse time and
3 6 4 d
4 3 7 c idle time.
5 2 5 b
6 8 8 f

SOLUTION:
Step 1: To find the optimal sequence.

Processing time
Job
Machine A Machine B
1 2 3
2 5 6
3 6 4
4 3 7
5 2 5
6 8 8

Display (ie.: Optimal sequence)


1 5 4 2 6 3
Min processing time on machine A Min processing time on machine B
Dr.N.Panneerselvam, ASP, MECH, KIOT,O R Material - 01

Step 2: To calculate elapse time:


Order of processing – AB

Optimal Machine A Machine B


sequence Time in Time out Time in Time out
1 0 0+2=2 2 2+3=5
5 2 2+2=4 5 5+5=10
4 4 4+3=7 10 10+7=17
2 7 7+5=12 17 17+6=23
6 12 12+8=20 23 23+8=31
31+4=
3 20 20+6=26 31
35

Elapse time

Step 3: To calculate idle time

Idle time on Machine A = 35 – 26 = 9hrs

Idle time on Machine B = 2 hrs.