Professional Documents
Culture Documents
G Writereaddata FormB TOR PFR 14052020WZWG7T71dpr
G Writereaddata FormB TOR PFR 14052020WZWG7T71dpr
TEHSIL:-KURWAI DISTRICT:-VIDISHA
VOLUME-I
REPORT
CHIEF ENGINEER
CHAMBAL BETWA BASIN
BHOPAL (M.P.)
1
PREAMBLE
The Betwa basin is one among the six major river basins of Madhya Pradesh. The river
Betwa which is also called river Vetrawati in Sanskrit and is an interstate river flowing between
MP and UP. The river basin is a part of Yamuna basin which ultimately forms part of Ganga basin.
The river flows about 216 km in MP , makes common boundary there afterwards in 98 kms and
then it runs for about 261 kms in UP before finally joining river Yamuna. The river Betwa covers
areas of Sehore, Bhopal, Raisen, Vidisha, Guna, Shivipuri and Datia district of MP. Out of these for
the districts of Bhopal, Raisen and Vidisha the river by all means acts as a main lifeline for all the
activities related to irrigation, domestic water supply, industrial water needs, nistar and other
minor activities.
The Betwa sub-basin for the purpose of use and in accordance with the interstate
agreement with UP is divided in three subparts namely upper, middle and lower Betwa sub-
basins. The river Betwa has 14 principal tributaries and out of which 11 lies completely in M.P.
whereas, 3 lies partly in both of the states. Fast industrial development , outbreak of population
due to formation of capital and setting up of industrial hub in Mandideep and other places and
promotion of high intensity, high yielding crops, in the agricultural sector has resulted in multifold
increase in water demand as compared to other part of the basin and in comparison of other
river basins.
This growing need of water has to be satisfied within the constraints of limited surface
water and ground water availability in the upper Betwa basin. So for construction of one major
project and four medium project (seven medium projects on u/s of rajghat dam) along with
about 100 odd minor irrigation schemes were completed, thereby providing about 800 - 900
Mcum of water. However, there is a further increased demand from irrigation and water supply
particularly in the middle part of upper Betwa basin. The most water short area in this context is
in between Gulabganj to Kurwai of M.P. Efforts were made for creation of storage reservoir at
various identified locations such as Richhan Dam, Neemkheda Barrage, Barri Barrage, Darriya
Dam and at other locations also, but construction of this structures were not found techno-
economic feasible due to submergence of large areas of good agricultural land, number of
villages and habitations and rail road infrastructures etc. Thus Proposals of number of dams and
barrages are to be dropped on account of this problems in past on this account. Furthermore the
middle and lower part of upper Betwa basin do not offer good sites for construction of large dam
and reservoirs.
It is in this situation the concept of creation of river bank confined storage schemes were
analyzed. This would unable to store sufficient quantity of water for various growing demand in
the areas of Vidisha distt. Which falls in middle of upper betwa basin without submerging much
of the costly private land, forest land submergence of habitation and infrastructures. as
compared to conventional storage reservoir.
2
Considering this facts in to consideration it is proposed to construct a high barrage on the
junction of river betwa and Keotan just U/S of confluence of river Bina with Betwa. About 85
Mcum of is proposed to be stored within the banks of river Betwa and Keoten by constructing a
Barrage of about 16.50 m. height. The command on left and right bank to a magnitude of 10,000
and 10,000 Ha would be provided irrigation by lifting water and than providing micro irrigation
down to 0.60 Ha. to 1.20 Ha. Through a pressurized irrigation system and by way of sprinkler
irrigation system. The project will further utilize the consumptive use of regenerated water from
the u/s irrigation projects to a tune of about 20 Mcum by arresting the post monsoon flow of
river Betwa and Keotan and regenerated water at a rate of 10% from the irrigation being done by
already built up reservoir of about 900 Mcum on u/s of proposed Kotha barrage.
The proposed scheme will not involve submergence of any forest area, any wild life or any
villages or habitation. The submergence created on the back of barrage will require about 681 Ha
of private land and about 678 Ha of Govt. land only. The main benefits from the proposed project
can be summarized as below:
(1) Assured Irrigation to 20,000 Ha. of land on left and right flank of Betwa river through
lifting of water by micro irrigation system.
(2) Providing 5.0 Mcum of water for the proposed new industrial activities in the sub
basin area.
(3) Providing 2.5 Mcum of water for the proposed new Domestic water supply in the sub
basin area.
(4) Providing 2.5 Mcum of water for maintaining environmental flow in lean 4 months in
river Betwa.
3
Index Map
4
Table of Contents
PREAMBLE ..................................................................................................................................... 2
CHAPTER-I ................................................................................................................................... 17
Location: ........................................................................................................................... 20
Access: .............................................................................................................................. 20
Area:.............................................................................................................................. 21
CLIMATE ................................................................................................................................ 22
POPULATION ......................................................................................................................... 22
GEOLOGY: ......................................................................................................................... 23
GEOTECHNICAL INVESTIGATIONS..................................................................................... 23
SEISMICITY ............................................................................................................................ 23
POWER: ............................................................................................................................. 28
Sand .................................................................................................................................. 33
Pozzolona .......................................................................................................................... 33
Resettlement: ................................................................................................................... 36
Unit-II: ............................................................................................................................... 37
Cost Breakup:.................................................................................................................... 38
BC Ratio............................................................................................................................. 39
CONCLUSIONS ....................................................................................................................................... 40
6
CHAPTER-II ................................................................................................................................. 42
BACKGROUND INFORMATION .............................................................................................................. 42
JUSTIFICATION AND OBJECTIVE OF THE PROJECT ................................................................ 42
CHAPTER-III ................................................................................................................................ 44
PROJECT AREA ....................................................................................................................................... 44
GENERAL ............................................................................................................................... 44
Present and Proposed Projects in the Betwa Basin upstream of Kotha Barrage ............. 46
River .............................................................................................................................. 47
Reservoir ....................................................................................................................... 47
Mineral, (useful and harmful) Surveys in the Catchment and Reservoir Areas ........... 49
Geology ......................................................................................................................... 50
Seismicity ...................................................................................................................... 51
7
Foundation Investigation ...................................................................................................... 51
Humidity ....................................................................................................................... 56
Temperature ................................................................................................................. 56
Discharge ...................................................................................................................... 56
Sedimentation .............................................................................................................. 57
Evaporation................................................................................................................... 57
EVAPO-TRANSPIRATION ....................................................................................................... 58
Hindcast flow series at proposed project sites from independent sub-basins ............ 70
8
Estimation of net yield series at proposed project sites .............................................. 70
Sediment data................................................................................................................... 82
Scour depth....................................................................................................................... 83
Piers .............................................................................................................................. 83
Type (concrete/Masonry)/profile cut off, upstream and downstream aprons, uplift pressure
relief arrangements etc. ................................................................................................... 84
Gates, types of gates and hoist bridge and stop logs ....................................................... 86
9
Spillway Fixed Wheel Vertical Lift Gates....................................................................... 86
Abutment ...................................................................................................................... 87
CHAPTER-V.................................................................................................................................. 89
Irrigation Planning..................................................................................................................................... 89
Existing Cropping Pattern ...................................................................................................................... 89
Proposed Cropping Pattern in the command of Kotha barrage ............................................................ 90
Crop Water Requirement ...................................................................................................................... 90
Reference Potential Evapo Transpiration (ETo) ..................................................................................... 90
Effective Rainfall .................................................................................................................................... 91
Irrigation Efficiency ............................................................................................................................... 91
Irrigation Demand ................................................................................................................................. 91
Command area planning on the basis of simulation studies ................................................................ 92
Classification of land (forest, grass land, cultivable and, cultivable waste, barren land) ...................... 92
Size of land holding ............................................................................................................................... 92
Climate of the command area ............................................................................................................... 93
Irrigation ................................................................................................................................................ 93
Socio-economic aspects ........................................................................................................................ 94
Infrastructure facilities .......................................................................................................................... 95
Topography and soils ............................................................................................................................ 95
Drainage ................................................................................................................................................ 96
Agriculture ............................................................................................................................................. 96
Farmers’ attitude towards improved agricultural practices ................................................................. 96
Identification of problems in command area ........................................................................................ 97
Financial problems ................................................................................................................................ 97
Proposed cropping pattern ................................................................................................................... 97
Land development work proposals ....................................................................................................... 97
Ayacut roads.......................................................................................................................................... 98
Benefits ................................................................................................................................................. 98
10
B. Land : ...................................................................................................................... 101
11
List of Figures
Figure – 1 : Line diagram of Betwa River .......................................................................................... 19
Figure – 2 : Sub-catchment boundaries of project site with drainage map ..................................... 26
Figure – 3 : Line diagram of Ken – Betwa link Project ...................................................................... 42
Figure – 4 : Kotha Barrage in Betwa Basin ........................................................................................ 45
Figure – 5 : Betwa River Basin with Kotha Barrage .......................................................................... 46
Figure – 6 : Layout of Raingauge Station ……………………………………………………………………………………55
Figure – 7 (a) : Plot of r-R data for Basoda catchment for month of June ....................................... 67
Figure – 7 (b) : Plot of r-R data for Basoda catchment for month of July......................................... 67
Figure – 7 (c) : Plot of r-R data for Basoda catchment for month of August .................................... 68
Figure – 7 (d) : Plot of r-R data for Basoda catchment for month of September ............................. 68
Figure – 7 (e) : Plot of r-R data for Basoda catchment for month of October ................................. 69
Figure – 8 (a) : Synthetic Unit Hydrograph for Kotha (U) sub-catchment ........................................ 78
Figure – 8 (b) : Synthetic Unit Hydrograph for Kotha (D) sub-catchment ........................................ 78
12
List of Tables
Table – 1 : Breakup of yield distributaries wise .................................................................................. 23
Table – 2 : Water account & water balance for Kotha barrage .......................................................... 24
Table – 3 : Principal Features of Kotha Barrage ................................................................................. 27
Table – 4 : Head Works ....................................................................................................................... 31
Table – 5 : Canal.................................................................................................................................. 32
Table – 6 : Abstract of cost ................................................................................................................. 38
Table – 7 : BC Ratio ............................................................................................................................. 39
Table – 8 : Thiessen weights of rainfall stations ................................................................................. 56
Table – 9 : Monthly Evaporation values at Raisen IMD station.......................................................... 57
Table – 10 : Computed ET0 values for raisen station .......................................................................... 58
Table – 11 : Percent areas of districts in basin of Kotha Barrage ....................................................... 59
Table – 12 : Medium variant population growth rate (%) for India ................................................... 59
Table – 13 : Present and projected populations in different districts (in thousand) ......................... 60
Table – 14 : Water use u/s of Kotha Barrage ...................................................................................... 61
Table – 15 : Computed virgin flows (MCUM) at Basoda G & D site ................................................... 65
Table – 16 : Computed dependable flows (MCUM) at proposed project site ................................... 72
Table – 17 : Computed monthly net flow (MCUM) series at Kotha project site ................................ 73
Table – 18 : Elevation Area Capacity Table ......................................................................................... 75
Table – 19 : Geomorphologic characteristics of sub-catchments used for SUH derivation ............... 77
Table – 20 : Salient points of sub-catchments for SUH derivation ..................................................... 77
Table – 21 : Flood hydrograph (SPF) for Kotha sub-catchment using SUH ........................................ 79
Table – 22 : Design floods for different return periods ...................................................................... 80
Table – 23 : Design flood for diversion ............................................................................................... 81
Table – 24 : Design flood Values ......................................................................................................... 82
Table – 25 : Existing cropping pattern in Upper Betwa sub-basin for the year 2011-12 ................... 89
Table – 26 : Proposed cropping pattern in the command of Kotha barrage...................................... 90
Table – 27 : Evapo-transpiration (ETo) values for Bhopal IMD station ............................................... 91
Table – 28 : Monthly rainfall in the Raisen district ............................................................................. 91
Table – 29 : Month wise irrigation water demands for Kotha barrage .............................................. 91
Table – 30 : CCA, Annual Irrigation, Annual Utilisation under barrages............................................. 92
Table – 31 : land use particulars in Upper Betwa command .............................................................. 92
Table – 32 : Size of land holding in the command area of Upper Betwa barrages ............................ 93
Table – 33 : Socio-economic aspects in the Upper Betwa command ................................................ 94
13
List of Abbreviations
Abbreviation Full Name
AFC - Agricultural Finance Corporation
BH - Bore Hole
BIS - Bureau of Indian Standard
BODHI - Bureau of Design for Hydel & Irrigation projects
BM - Bench Mark
BPL - Below Poverty Line
CA - Catchment Area
CAD - Command Area Development
CAT - Catchment Area Treatment
CBIP - Central Board of Irrigation & Power
cc - Cement Concrete
CCA - Culturable Command Area
CD - Cross Drainage
0C - Degree Centigrade
Cfm - Cubic feet metre
CGWB - Central Ground Water Board
cm - Centimetre
CS - Cross Section
CSMRS - Central Soil and Material Research Station
Cum - Cubicmetre
Cumec - Cubic metre per second
Cusec - Cubic feet per second
CWC - Central Water Commission
d/s - Down Stream
DH - Drill Hole
DBE - Design Basis Earthquake
DPR - Detailed Project Report
DSL - Dead Storage level
E - East
EIA - Environmental Impact Assessment
E&M - Electrical & Mechanical
EL - Elevation level
Eto - Evapo-transpiration
FRL - Full Reservoir Level
FSD - Full Supply Depth
g - Acceleration due to gravity
GD&S - Gauge Discharge & Silt
G&D - Gauge & Discharge
GCA - Gross Command Area
14
GIR - Gross Irrigation Requirement
GSI - Geological Survey of India
GW - Ground Water
H - Horizontal
ha - hectare
HP - Horse Power
hr - Hour
ham - hectare-metre
HE - Hydro Electric
HEP - Hydro Electric Project
HT - High Tension
HYV - High Yield Varieties
IC - Installed Capacity
IIT - Indian Institute of Technology
IMD - Indian Meteorological Department
IMF - International Monitory Fund
IMO - Irrigation Management Organisation
IRR - Internal Rate of Return
K-B Link - Ken-Betwa Link
km - Kilometre
km/hr. - Kilometre per hour
KMPP - Ken Multi-purpose Project
KV - Kilo Volt
Kwh - Kilowatt hour
LBC - Left Bank Canal
LS - Longitudinal Section
lpm/m - Litres per minute per metre
m - Metre
mbgl - metres below ground level
MCE - Maximum Considered Earthquake
MCM - Million Cubic Metre
MDDL - Minimum Draw-down Level
Mg/L - Milligram per litre
MIV - Main Inlet Valve
Mkh/MU - Million Kilowatt hour/Million Units
mm - Millimetre
MMI - Modified Mercalli Intensity
MoEF - Ministry of Environmental & Forests
MoU - Memorandum of Understanding
MP - Madhya Pradesh
MPEB - Madhya Pradesh Electricity Board
MS - Mild Steel
15
MU - Million Unit
MWL - Maximum Water Level
MW - Mega Watt
N - North
NA - Not Available
NH - National Highway
NIH - National Institute of Hydrology
NOF - Non Over-Flow
NPP - National Perspective plan.
NRSA - National Remote Sensing Agency
NSL - Natural Surface Level
NTPC - National Thermal Power Corporation
NWDA - National Water Development Agency
OAF - Other Affected Families
OF - Over-flow
OFD - On Farm Development
PAPERP - Project Affected Persons Economic Rehabilitation Plan
PAF - Project Affected Families
PAP - Project Affected People
PCC - Plain Cement Concrete
PGA - Peak Ground Acceleration
PH - Power House
PLF - Power Load Factor
PMF - Probable Maximum Flood
PMP - Probable Maximum Precipitation
POL - Petrol Oil Lubricants
Ppt - Precipitation
PUW - Pick Up Weir
R&R - Resettlement & Rehabilitation
RBC - Right Bank Canal
RCC - Reinforced Cement Concrete
RD - Reduced Distance
RH - Relative Humidity
RL - Reduced Level
RMR - Rock Mass Rating
SC - Scheduled Caste
SE - Superintending Engineer
SES - Socio Economic Studies
SFR - Sheep Foot Roller
SOR - Schedule of Rates
SPS - Standard Project Strom
sqkm - Square Kilometre
16
ST - Schedule Tribe
t - tonnes
T&P - Tools & Plants
TAC - Technical Advisory Committee
TD - Temporal Distribution
TMC - Thousand Million Cubic feet
TWL - Tail Water Level
UB - Upper Betwa
UH - Unit Hydrograph
u/s - Up-stream
USAID - United States Agency for International Development
USR - Unified Schedule of rates
V - Vertical
W - West
WBM - Water Bound Macadam
WR - Water Resources
17
CHAPTER-I
EXECUTIVE SUMMARY
INTRODUCTION
The proposed barrage site is located on Betwa river near the village Kotha in the tehsil
of Kurwai of Vidisha district of Madhya Pradesh. The total catchment area up to Kotha
barrage site is 8711 sq km. The yield upto the proposed site as per the master plan of 1972,
2004 and as agreed upon in the interstate agreement works out 1794.36 Mcum for a
catchment area of 8694 sq km. Thus giving a yield factor 0.206 Mcum/sq km. The expected
yield (virgin) at the site at 75% dependability on the basis of current datas has been again
worked out to Error! Not a valid link. Mcum. This gives a yield factor of 0.183 Mcum/sq km.
To avoid any further interstate dispute with UP, the yield factor as mutually agreed by both
of these two states as 0.20 Mcum /sq km has been finally retained for the purpose of water
planning, irrigation planning and water balance studies.
Kotha Barrage benefitted area lie in the zone of Upper & Medium part of upper
betwa sub-basin. In this part of basin, the existing projects are mostly of medium and minor.
The only major project in the Upper Betwa sub-basin is Halali dam whereas in all about 4
medium tanks namely Sanjay Sagar(Bah) Sagar, Kaliasote and Kerwa are all ready constructed
in the upstream of proposed barrage and projects namely Naren, Kethan, Mola and Koncha
18
are completed on the tributaries of river betwa which joins the main river downstream of
kotha barrage.
19
Location:
0 ’ ” 0 ’ ”
Kotha 78 01 16 E 24 3 28 N 54L/4
Access:
Error! Not a valid link.
20
Key Details:
Area:
Error! Not a valid link.
Betwa Keotan 383.52 395.00 8711 63.51 20.736 84.246 1359 20000 Vidisha
and Sagar
Interstate aspect
The state of MP after the agreement has so far constructed 1 major and 8 medium
schemes besides about 100/120 minor storage and lift irrigation schemes. The total water used
by these schemes is about 900 Mcum up to Kotha barrage and about 1100 Mcum up to rajghat
dam. Whereas schemes of about 200 - 300 Mcum are either in the stage of construction or falls
under the category of new proposed schemes. Thus, sufficient availability of water under the
allocated share is available for taking up of the proposed project of Kotha barrage in the upper
Betwa basin.
Further the MP has been given authority to use about 591 Mcum of water in
upper Betwa basin in lieu of water being provided to UP in the agreement held between MP &
UP from Ken river baisn to UP in lower Betwa Basin. Thus, this scenario provides an authority to
use about 1500 + 591 = 2091 Mcum in upper Betwa basin whereas the present and likely future
use in upper Betwa basin will be well within the limit to 2091 Mcum even after execution of all
future proposed projects.
21
SURVEYS & INVESTIGATIONS
Major part of the detailed surveys and investigations of the project has been
done by NWDA under Ken Betwa link project phase – II, and other specialized surveys and
investigations along with technical studies like construction material survey, borrow area survey,
geological survey etc. were carried out by outsourcing by NWDA, mostly to other Government
Agencies like CSMRS, GSI etc. Hydrological studies have been conducted by NIH. Details are
attached in chapter – III.
CLIMATE
The climate of the upper Betwa basin is characterized by hot summer and
mild winter. The temperature in the upper reach sometimes goes beyond 40°C. The maximum
and minimum values of mean monthly relative humidity are reported to be 83% (August) and
20.5% (April) respectively. The wind velocities in the upper reaches (varying between 6.6 km/h to
18.9 km/h) of the basin are generally higher than that of the lower reaches in the basin (varying
between 2.9 km/h to 13 km/h). The cloud cover remains higher in upper part of the basin as
compared to lower parts.
The region receives more than 90% of its total rainfall during the south-west monsoon period
(June to October). The upper part of the region receives about 1100 mm of rainfall annually.
Details are attached in chapter- III
POPULATION
The human population in Vidisha, Ashok Nagar and Sagar districts of Madhya
Pradesh will be benefited due to the assured irrigation supply. The total population as per 2011
census in the catchment of Upper Betwa sub- basin is 30.70 lakh. The human population has
been projected for the year 2050 AD on the basis of medium variant growth rate as given in U.N.
Publication ‘World Population Prospects – 2010 revision' and is likely to increase 40.26 lakhs.
Most of this population will be dependent entirely for their domestic, industrial and irrigation
needs on Betwa river basin water only.
As the proposed barrage is within the gorge portion of the river therefore no
village is coming under the submergence of the barrage. Also sizeable population depending
on agriculture in the command areas will be benefitted due to increased agricultural
activities. Details are attached in chapter- III
22
GEOLOGY, GEOTECHNICAL & SEISMIC ASPECTS
GEOLOGY:
Geology of region comprises of the Vindhyan sandstones which are of pre-
cambrian age occupying an area of 3900 sq. km. It is exposed at two widely apart localities, one
forming a linear ridge trending North –West to South – East in the north and the other forming
ridges and hillocks around Vidisha and Raisen located south of Bhopal. The different geological
formations occurring in the region include: Alluvium, Lateritic and Deccan traps. The coarse-
grained Bundelkhand gneiss overlying granite basement formations are found in the basin.
GEOTECHNICAL INVESTIGATIONS
In view of the presence of fresh, inherently hard, massive / dense sandstone in the
river bed, the location and alignment of the structure for the proposed barrage site of Kotha is
considered to be geo-technically favorable in view of the absence of significant tectonic
disturbance.
SEISMICITY
The project area is practically devoid of active lineament, fault or shear. As per the
seismic zoning map of India (1990), the proposed layout of Kotha barrage falls under seismic
zone-II which signifies low seismic events not exceeding magnitude 3 and hence seismo-
tectonic hazards could be considered as minimum.
The master plan of Betwa indicates a expected yield of about 1794.36 Mcum up to
the proposed kotha barrage site on the basis of studies carried out during framing of master plan
of river betwa in the year 1972 which also form basis of interstate agreement between M.P. and
U.P. for upper betwa basin. Whereas the expected yield (virgin) at this site at 75% dependability
on the basis of current data has been worked out to Error! Not a valid link. Mcum.
23
2 Direct catchment of Bhopal + 1794.00 370.07
Raisen + Sehore district
The rivers Naren, Kethan, Bina and Narayani join betwa on downstream of kotha
barrage site, and therefore were not included in the yield statistics, However fresh Hydrological
study of Kotha barrage were again carried out in detail by National Institute of Hydrology,
Roorkee. The net 75% dependable yield as assessed by NIH, Roorkee at the proposed barrage site
is about Error! Not a valid link. Mcum.
Thus it can be seen that in both of the studies the expected yield up to the proposed site
is in the range of 1594 to 1794 Mcum. However to avoid any unwanted situation in terms of
water use in upper betwa basin, the yield value i.e. 1794 Mcum has been taken for all water
balance and water planning purposes.
Abstract for Water account & water balance for Kotha barrage shown in Table-2
25
Fig – 2 : Sub - Catchment boundaries of project site with drainage map
26
FLOOD CONTROL AND DAMAGE
No flood cushion has been provided in the proposed project being a barrage with
storage mainly allowed upto banks only and the waterway area has been kept wide enough to
pass a design flood of 1 in 200 year return period flood without creating any sizable afflux. But
due to the impoundment of water in Kotha Barrage, there will be control of flood damages in
d/s of the barrage site. Since topography of area is having mild slopes, drainage problem is not
expected.
27
Total water available at Kotha Barrage for Utilisation
POWER:
Being a medium height barrage, no power generation is possible from the project.
However considering the requirement of power for Telescopic pressurized irrigation system, It is
proposed to install solar power panels in the project area for generating about 8.00 MW power
mainly in the period of October to March. The total power requirement is 5.39 MW, thus the
power being produced in remaining period and surplus power i.e. 2.61 MW can be diverted to
National Power Grid as a clean green energy. However this an opinion in project planning and is
to be finalized during next stages of execution.
By providing micro irrigation down to 0.60 Ha. to 1.20 Ha. in 10000 Ha of left flank and
10000 Ha on right flank by lifting the water and providing water in a pressurised irrigation
network through booster pumping.
The command on both of flanks which is basically a doab between bina and betwa on right flank
and doab between Betwa and Kaithan are very fertile. The command is mainly consisting of
medium to deep black cotton soil area and is having a good water retention capacity. The
command on both of flanks, particularly on left flank is having good natural drainage in form of
Naren river, khariya nalla, kethan river and other number of local nallas joining river betwa at
regular intervals . Thus drainage will not be a severe problem.
The farmers of Command area are already practicing high yielding crops in kharif and rabi,
but due to absence of assured irrigation not only their productivity is low but they are also not
getting encouragement for further adoption of new improved agriculture technology and
advancement in agriculture. The proposed command area is having a general levelled terrain with
a gentle slope towards river betwa but the fields are not subjected to levelling nor chakbandi has
been exercised in this area. The quantum of water in river betwa is limited as compared to large
agriculture areas of vidisha where rabi is exercised in more than 5 lakhs Ha and kharif is also
more than 2.50 lakhs ha. Thus to have a maximum coverage of irrigation with limited water
28
quantity available, micro irrigation system has been proposed for whole of command area down
to 0.60 to 1.20 Ha where water for irrigation will be provided through pressurised irrigation pipe
line network system with a available residual pressure head of about 15 - 20 m i.e. a pressure of
1.5 - 2 kg/ cm2 for running of sprinkler system.
The proposed command is having a very good network of CMGSY road , PMGSY road,
PWD road, state highway and main WCR railway network running all through the command area
between Gulabganj and kurwai railway station . Thus post irrigation problems in terms of selling
of increased agricultural produces, exercising other allied agricultural activities with the irrigation
facility will not be a problem.
As per the availability of water, a total of 20000 Ha area will be irrigated by utilizing
84.246 Mcum water together satisfying other water needs also. The cropping pattern in the
proposed command area of has been adopted as per the suggestion of Madhya Pradesh
Agriculture Department. Major crops of the command areas of the Project are Soybean, Wheat
(Ordinary and HYV) and Gram. The detail of CCA under Kotha barrage, annual irrigation and
utilization are furnished below:
20000 73.651
A prepaid smart farmer card system is proposed for the Kotha Barrage. The prepaid system is
based on providing every farmer with a user card with a photo ID and user number. The cards
are loaded with credit and are inserted into a slot in the prepaid meter and water pumps
automatically with the charge levied against the credit on the card. The smart cards are topped
up by a vendor who would collect payments from users (farmers) and deposit the
collected funds into the bank account of the system operator. The vendor would be paid,
typically on a commission basis, according to the amount of water sold. The process uses
technology and management similar to cell phones.
29
With buried pipes, paddy “lock-in” is averted and farmers may cultivate a range of crops
in efforts to reduce water bills as well as increased incomes. Farmers can irrigate throughout the
year including options for supplementary irrigation in the Kharif as well.
At first, this pre-paid smart card control system appears as a magic to the farmers in
Madhya Pradesh. The farmers would be able to implement irrigation after recharging this card.
This is quite a surprising facility that farmers have had ever hoped for. The pre-paid meter usage
in the irrigation program will entirely change the canvas of agriculture alike the cell phone
prepaid system. Farmer receives the amount of water as much as he has recharged. Getting the
irrigation facility through the taxation system is now under the complete control of the farmers.
The farmers as well as the pre-paid card dealers now have hold of the total concept. Farmers can
avail water for their cultivable lands while inserting the card at the right place. Even, they get to
know their balance amount and what amount of water could he avail from the specific balance.
The farmers had to face a variety of harassment while roaming here and there to fetch
irrigation facility. There were incidents of looting of the total payment for the irrigation tax and at
the same time, incidents like farmers being cheated and devastated at the hands of the
intermediaries. The technology has reached every corner and farmers getting easily access too.
Through this technological advancement, farmers are being benefited, the same way the
waste of irrigation-water is being stopped. Agriculture is becoming technology reliant, which is
the current tide of time worldwide. After buying pre-paid irrigation card, water is reaching the
cultivable lands of the farmers through the pressurized pipe outlet. This is undoubted great
innovative system for the farmers but it is responsibility to the respective authority to ensure the
benefits all over Kotha Barrage command.
A pre-paid smart card control system have been considered which is comprising a smart card
controlled volumetric water meter and valve which would be installed at the head of buried pipe
system downstream of the header tank. This system would be new to Vidisha (even in Madhya
Pradesh and India too) is suited to locations where there is no / little electric power.
The smart card with a volumetric water meter can be used if there is a diesel pump.
30
DESIGN FEATURES
31
Table-5: Canal:
CONSTRUCTION MATERIALS
The requirement of construction materials for the project can be met from the nearby
quarries. The quality of the materials available in these quarries has been tested by CSMRS,
New Delhi and found suitable for usage as construction materials. Further, the requirement
of construction materials like cement, steel, etc. can be brought to the nearest railheads i.e.
Mandi bamora, Ganj Basoda, , Bina and Vidisha.
Soils
The proposed barrage which will be a masonry/concrete structure, no detail
investigations for borrow areas were carried out. However, borrow area survey for proposed
barrage, distribution chambers, pump houses, booster pumping stations , rising mains etc. is
proposed to be carried out in due course of time.
32
Sand
The CSMRS, New Delhi carried out construction material survey and laboratory
investigations of sand samples for their use as fine aggregate in concrete during construction of
the project for Kotha barrage. The test results of the above sand samples are furnished as
Appendix.
Pozzolona
The pozzolonic materials are not considered to be used in the construction of the project.
Scarce Materials
No scarce materials are anticipated to be use in the construction of the project which may
cause hindrance to the construction of the project.
33
Cement and steel will be transported by rail and stacked at the nearest rail head points in
the proposed stores/stack yards all along the canal and from there these will be conveyed to the
site with minimum lead.
Similarly the command area of is also having good net work of roads which facilitate
transport of heavy machinery and construction materials to the various locations.
34
ENVIRONMENTAL AND ECOLOGICAL ASPECTS
The objective of EIA study is to identify the possible beneficial and adverse
environmental impacts due to project and to suggest measures to minimize, to the extent
possible, the anticipated adverse impacts. The study for Kotha barrage has been carried out by
M/S AFC Ltd., Hyderabad on the following lines:
35
As a result of implementation of this project, a large new area of Upper Betwa basin
(30000 ha. of MP) will come under assured irrigation which will increase agricultural
production and productivity in the area. No major adverse impact due to the project is
anticipated on environmental and ecological angle. No significant rich mineral deposits have
been identified in the catchment and hence no acidification of the reservoirs is anticipated.
Necessary minimum flows in the Betwa river during lean season will flush the
untreated sewage and hence no impact is forthcoming on river water quality. The flooding
of previously forested and agricultural land in the submergence area will increase the
nutrients resulting from decomposition of vegetative matter. Enrichment of impounded
water with organic and inorganic nutrients will be main water quality problem which will
last for a short duration of few years from the filling up of the reservoirs. No eutrophication
problem is anticipated due to controlled use of fertilizers in the commands. The ground water
level will increase in the adjoining area due to assured water supply to the fields. No possibility
of leakage in the bed of the reservoirs is anticipated as it is covered by semi quartzitic
sand stone which is compact and hard. Hence, reservoir can be considered as water tight.
The water samples tests indicate that organic and heavy metal components in the water
are within permissible limits.
SOCIO-ECONOMIC ASPECTS
Socio-economic Impact Assessment Studies and R&R Plan of Kotha barrage has
been carried out by M/s AFC Limited, Hyderabad.
Land Acquisition:
According to the Socio-economic survey (SES), the total land acquisition required for
the project is estimated to be Error! Not a valid link. ha - of which Error! Not a valid link. Ha is
Government land and Error! Not a valid link. Ha is private land. The total compensation for
land acquisition is estimated to be Rs Error! Not a valid link. crores considering voluntary as
well as involuntary acquisition costs of irrigated/ unirrigated lands from PAFs, solatium
(100%), standing crop loss, interest, demarcation, legal and establishment charges, etc.
Resettlement:
No resettlement is anticipated.
Economic Rehabilitation:
No economic rehabilitation is anticipated.
36
Compensation for Properties:
No property is affected.
Unit-I:
The cost of head works of Kotha barrage including spillway, outlet works, gates, energy
dissipation devices, regulator including intake structures, Pump Houses, cost of pumps,
motors & electromechanical work, land acquisition & construction of the all components, etc.
have been worked out under this head and estimated as Rs. Error! Not a valid link. crore at
USR - 2016 price level.
Unit-II:
The cost of proposed main telescopic pipe canal network, piped distribution network,
micro irrigation works inclusive of all pucca works, drainage works etc. has been worked out
and is estimated as Rs. 347.28 crore at USR - 2016 price level.
Unit-III:
The cost of solar panels and solar power is included in this head and worked out to be
Rs. 48.00 crore at USR - 2016 price level
Thus, the total cost of the project has been estimated as Rs. 814.53 crore Sub -
head wise details shown in table below:
37
Table-6: Abstract of cost
General Abstract of Cost of Kotha Barrage
figures are Rs in Crore.
S.No. Subhead Unit-I Unit-II Unit-III Total
1 A-Preliminary 1.06 0.64 0 1.70
2 B- Land 229.40 0.75 0 230.15
3 C-Works 172.25 0.00 0 172.25
4 D-Regulator 0.00 0.00 0 0.00
5 E-Fall 0.00 0.00 0 0.00
6 F-CD Works 0.00 0.00 0 0.00
7 G-Bridges 7.00 0.00 0 7.00
8 K-Building 0.20 0.20 0 0.40
9 L-Earth Work 0.00 117.43 0 117.43
10 M-Plantation 0.50 0.00 0 0.50
11 O-Misc. 1.00 0.00 0 1.00
12 P-Maintenance 1.06 1.67 0 2.73
13 Q- Special T & P 0.00 0.00 0 0.00
14 R-Communication 1.00 1.50 0 2.50
15 S-Power plant for 8 MW @ Rs 6 Cr/MW 0.00 0.00 48 48.00
16 T-Water Supply 0.00 0.00 0 0.00
17 U- Distributory & Minors up to 1.2 to 0.6 Ha 0.00 215.00 0 215.00
18 'X'-Environment 0.25 0.00 0 0.25
Total 413.72 337.19 48.00 798.91
Add 3% Establishment except B - Land and 5.53 10.09 0 15.62
S - Power Plant
Total Cost 419.25 347.28 48.00 814.53
Error! Not a valid link.Cost Breakup:
38
FINANCIAL ASPECTS
The economic and financial evaluation is tabulated below:
Table-7: BC Ratio
GOVERNMENT OF MADHYA PRADESH
WATER RESOURCES DEPARTMENT
KOTHA BARRAGE PROJECT
( Rs. In Lakhs)
BC Ratio Calculation
S. Item Before After
No. Irrigation Irrigation
1 Gross Receipt
(i) Gross value of farm produce 10601.09 59240.00
(ii) Dung receipts (at 30% of the fodder expenditure) 477.05 1777.20
Total Gross Receipts (1) = (i+ii) 11078.14 61017.20
2 EXPENSES
(i) Expenditure on Seeds 514.04 827.50
(ii) Expenditure on Fertilizers,Chemicals etc. 857.88 1675.00
(iii) Expenditure on hired labour (human, animal & machinery) & 590.00 2775.00
Misc
(iv) Expenditure on Pumping system 2283.90
(v) Expenditure on Rising Mains 9458.69
(vi) Expenditure on Solar Power System for Lift 4800.00
(vii) Fodder expenses (as percentage of gross value of produce)
39
(ii) Net value before irrigation 6497.76
from Irrigation 22213.87
(iii) from Fish production 212.55
(iv) from Power production (Being incidental, not considered) 0.00
(v) from Water Supply 0.00
a) Domestic 0.00
b) Industrial 0.00
Net Annual Benefits (4) = (i-ii)+(iii)+(iv) 22426.42
5 COST OF PROJECT
(i) Estimated cost of the Project 81453.00
(ii) Cost of land development 4000.00
Total 85453.00
6 ANNUAL COSTS
(i) Interest on capital @ 10% (Estimated total cost of the project 8545.30
including cost of land development)
(ii) Depreciation of the project @ 1% of the cost of project for 100 1709.06
years life of the project and @ 2% for 50 years life of the project
(iii) Annual operation and maintenance charges 235.00
(iv) Maintenance of the head works @ 1% of H/W cost less B Land 413.72
(v) Depreciation of the pumping system @ 8.33% of the estimated 190.25
cost of the pumping system assuming life of the system as 12 years
(Applicable to lift irrigation)
(vi) Depreciation of the rising mains @ 8.33% of the estimated cost 787.91
of the rising mains assuming life of the system as years (Applicable
to lift irrigation)
(vii) Power Charges for lift water @ per Ha. 0.00
Total Annual Costs (6) = (i + ii + iii + iv + v + vii + vii) 11881.24
Average Benefit Cost Ratio = Annual Benefits (4) / Annual Costs 1.89
(6)
CONCLUSIONS
The Study of this region reveals that the region is suffering acute scarcity of water for
irrigation, Drinking, Industries purposes, Because of that, the overall development of the region
has worstly affected. Further it is observed that day by day the ground water table is depleting
and there is a possibility that in future the water may not be available even for drinking purpose
also.
1
The study also reveals that the percentage of irrigation in Vidisha & Sagar district by
Government Sources i.e. tanks & Canals is very much less as compared to national irrigation
percentage.
40
The command is well connected with road network by NH, PMGSY & CMGSY. The soil is
highly fertile, land is highly cultivable, topography is mild in slop, the only drawback is water
availability. If assured irrigation, proper care of soil and application of fertilizers inputs are
availed, higher intensities (normally to a range of 130% - 145%) can easily be achieved
2
Thus to fulfill the requirement of this region, the Betwa Water through Kotha barrage is
the only alternate. Considering above facts & necessity of water in this irrigation prone area,
the Kotha barrage irrigation scheme is proposed.
(U.C.Jain)
Chief Engineer
Chambal Betwa Basin
Bhopal
41
CHAPTER-II
BACKGROUND INFORMATION
Since, the link project has taken into consideration in-basin requirements of
all the existing, ongoing and proposed projects upstream and downstream of Ken basin
while working out surplus water at Daudhan dam, the proposed diversion of water
42
from Ken to Betwa through link and its utilization in Betwa basin on substitution
basis is justified.
Further, the command area identified under Kotha barrage project lie in deep
black cotton soils and is water scarce region of Betwa basin. This link project will
definitely bring economic prosperity to this area due to increased agricultural activities
by fulfilling the demand of irrigation water required by farmers.
Though not planned, many other incidental benefits like recharge of ground
water in command area, development of agro based industries/food processing units,
employment generation in construction phase and afterwards, development of tourist
spots, development of infrastructure etc. will accrue from the project. This will result
in upliftment of socio - economic condition of people in general living in water scarce
areas of Vidisha and Sagar district of Madhya Pradesh State.
43
CHAPTER-III
PROJECT AREA
GENERAL
The barrage site is proposed across Betwa River near village Kotha in Kurwai Tehsil
of Vidisha district and located on toposheet No. 54 L/4. The latitude and longitude of the
barrage is 24003'28" N and 78001'16" E respectively. The proposed barrage site is about 6 km
from Mandi Bamora on Ganj Basoda – Bina road. Vidisha is the nearest town and nearest
railway station. Bhopal is the nearest airport, which is about 115 km from the site. The total
catchment area of Betwa river upto Kotha barrage is Error! Not a valid link. sq km.
Considering the site conditions at the barrage site and as recommended by CWC,
the height of barrage has been proposed as 16.50 m. The proposed pond level of this
barrage is Error! Not a valid link. m and river bed is Error! Not a valid link. m.
Submergence area at proposed pond level is Error! Not a valid link. Ha and storage
capacity is 63.51 Mcum. The barrage will provide irrigation to an area of 20000 Ha in the
districts of Vidisha and Sagar of MP.
44
Fig-4-Kotha Barrage in Betwa Basin
45
Fig-5-Betwa River Basin with Kotha Barrage
During its course from the source up to the confluence with the Yamuna, the river is
joined by a number of tributaries and sub-tributaries; the important among them being the
Newan, Keotan, Bina, Nairan, Jamini, Dhasan and Birma on the right bank and Kaliasote, Halali,
Bah, Sagad, Narain and Kaithan on the left bank. Out of the 14 principal tributaries, 11 lie
completely in M.P. and 3 lie partly in M.P. and partly in U.P. Betwa covers the areas of
Bundelkhand uplands, the Malwa plateau and the Vindhyan scrap lands in the districts of
Tikamgarh, Sagar, Vidisha, Raisen, Bhopal, Guna, Shivpuri and Chhatarpur of M.P. and
Hamirpur, Jalaun, Jhansi and Banda districts of U.P.
Present and Proposed Projects in the Betwa Basin upstream of Kotha Barrage
The existing projects are mostly of medium and small size. The only major project in the
Upper Betwa sub-basin is Halali dam. Halali dam is constructed on the Halali river and Barwa
Sagar is located over the Barwa Nala near village Barwa in Jhansi district of U.P. The proposed
Ken-Betwa link canal, through which surplus water of Ken River is to be diverted to Betwa
46
basin, will terminate in this reservoir. Parichha weir, located near Jhansi city, is the last
structure over the Betwa River which has been operational, primarily for irrigation, since 1906.
In the Phase-II of the Ken-Betwa Link project, it is proposed to construct a dam and 4 number of
barrages in the Betwa basin viz. Lower Orr dam and Neemkheda, Barari, Kesari and Kotha
barrages.
River
No separate river course survey has been carried out for river Betwa near the
barrage site.
Reservoir
No separate reservoir survey has been carried out for Kotha barrage since initially
the entire submergence lies within the gorge portion of the banks of Betwa river. However
pond level of the Kotha barrage has been refixed by Central Water Commission as 396 m after
their site visit during 20 - 22 Nov.2013. Submergence area and capacity have been increased
due to increase in the pond level. Revised submergence map has been prepared based on
barrage axis survey details L-Section of Betwa river carried out by NWDA and contours available
on the Survey of India (SOI) toposheets. Submergence area survey, river survey and barrage axis
survey of this project will be carried out in due course of time in view of change in parameters
of the barrage as a fresh at next stage of project. The submergence area map of Kotha barrage
is given as Annexure. It is proposed carry out detailed submergence survey and river survey for
this project at next stage of the project before taking up its implementation with the revised
stage-I FRL of 395.00 m and final FRL of 396.00 m for future development in stage-II.
Head works
The Kotha barrage site is proposed across Betwa river near village Kotha in Kurwai
Tehsil of Vidisha district. Kotha barrage axis survey was carried out by NWDA. The block
levelling for the 215 m length of Kotha barrage axis has been carried out by single levelling at 50
m grid interval. The cross sections survey of dam axis were taken at 50 m interval and extended
upto 300 m in the upstream and 500 m in the down stream of dam axis. The grid plan of the
barrage and cross section of betwa river at Kotha barrage axis is plotted and enclosed in
Annexure.
47
Plant & Colony layout
Suitable Govt. land is not available for establishment of plants and colony,
therefore plant and colony survey has not been done. Private land near to the project site is
proposed to be identified and acquired.
Command Area
The required sample command area survey of the project has not been carried
out due to enhancement of CCA as per the change in parameter of the barrage. However the
command area map has been prepared on the basis of Survey of India (SOI) Toposheet
(1:50,000) scale and shown in Annexure.
Soil Conservation
M/s Agricultural Finance Corporation Ltd., Hyderabad has been assigned the
Rapid EIA, EMP, SIA and R&R study of Kotha barrage. In order to contain soil erosion in the
catchment and reduce the silt being carried out by the rivers and streams leading to Kotha
barrage, soil conservation measures would be taken up as per the studies carried out by the
consultant. Necessary provision for this work has been kept in the project estimate.
Any other
Nil
Nil
48
Archaeological surveys in the reservoir area
No sites of archaeological, historical and cultural importance maintained by
archaeological Survey of India and department of archaeology MP are present within the pond
area of Kotha barrage as most of the reservoir area lies in river gorge portion.
Mineral, (useful and harmful) Surveys in the Catchment and Reservoir Areas
As ascertained from the Mining department, Govt. of Madhya Pradesh, no
minerals of economic importance are present in the pond area of Kotha barrage and its vicinity.
Letter is enclosed at Annexure.
Communication Surveys
The Kotha barrage is proposed across Betwa river near village Kotha in Kurwai
Tehsil of Vidisha district. The barrage site is about 6 km from Mandi Bamora on Basoda - Bina
road. Vidisha is the nearest railway station/town. The project site is well connected by road.
Bhopal is the nearest airport which is about 115 km from the project site.
The command area under Kotha barrage is well approachable from district roads. All the
villages in the vicinity of Kotha barrage and its command area are electrified. Suitable provision
is made for communication surveys for laying telephone lines etc. in the project estimate. Map
showing communication network of project is enclosed as plate: 2.2.6 in Volume - V (Part-1).
Drainage Surveys
The proposed command area under the Kotha barrage is drained by a network of
small rivers/ nallas. The command has good draining facilities. However, with the introduction
of irrigation, as the command area develops, drainage problem may crop up in course of time.
Suitable provision is, therefore, being made in the project estimate towards chak and collecting
drains in the command area.
49
Soil Surveys
Soil survey has not been carried for the command under Kotha barrage. However,
on the basis of a map prepared for Upper Betwa sub-basin from National Atlas of India (1982),
and based on the information provided by the National Bureau of Soil Survey and Land Use
Planning (NBSS & LUP), Nagpur/Delhi the soils of the command area can be broadly classified
into medium to deep black soils. The deep black soils are predominantly clayey in texture while
the medium black soils are fine textured. The black soils are suitable for cultivation. With good
management practices, it is possible to cultivate areas under these soils both under wet and dry
conditions. The lands in the command are good to very good cultivable lands with moderate
erosion. These are suitable for irrigation with moderate limitations due to heavy texture and
require drainage.
Geology
The regional geology of the proposed project site of Kotha barrage constitute a part of
basaltic lava flows belonging to the Malwa group of the Deccan Trap Complex comprising low
lying hills, hill clusters, valleys and extensive plains. The general slope is towards northeast as
exhibited by the flow of the Betwa river and its tributaries. The proposed project area of
Vidisha district fall in seismic zone-I/II. The Betwa River flows In north - northeast direction with
about 200 m wide channel at project site with steeper bank slopes on either flanks. The
outcrops exposed in the river bed of Kotha Project site is occupied by different variants of
Basalt which occur under 2 – 5 m thick soil cover along the alignment. The basalt is medium to
dark grey, vesicular to non – vesicular, fine to medium grained, massive, hard and compact,
moderately to highly strong and subjected to weathering to varying depths. Some of the
outcrops are suffered with spheroidal weathering with criss-cross veins of secondary
silica/zeolite and calcareous material. Besides sub horizontal rolling joints, 3 prominent sets of
steeply inclined to vertical joints trending (i) east-west, (ii) NNW-SSE, (iii) NNE-SSW are often
present in basalt variants in the project area.
Geotechnical assessment
The Betwa river is a monsoon-fed, ephemeral river having a general north-northeast
(NNE) direction of flow with an open meandering course near the proposed dam site. In view
50
of the presence of different variants of basalt (vesicular/amygdular, massive/dense, non-
vesicular and fragmentary) in the river bed, the proposed barrage Site of Kotha project appear
to be suitable for the proposed structure.The location and alignment of the structure appear to
be geotechnical favorable in view of the absence of significant tectonic features and buried
channel. Seismically also the area has a least tectonic disturbance. The bedrock is blocky with 3-
4 prominent sets of open to tight and interconnected joints. Joints are oriented both parallel
and across to the barrage axis. Large scale leakage through joints is anticipated necessitating
the need of sub-surface exploration to quantify the intensity of seepage and also to assess the
tentative foundation grade and the depth of grouting for reservoir tightness. Summarised
details of sub-surface exploration is given in Annexure of Volume-II. A pre-construction note on
geo-technical investigations of Kotha barrage is given as Appendix: in Volume-II.
Geophysical Investigation
Geophysical investigation at this site was not needed as sub-surface exploration
has been carried out by deep drilling at this site as recommended by GSI.
Seismicity
Seismo-tectonically, the Bundelkhand–Malwa area is a stable land mass with a
history of least tectonic disturbances. The area of the Upper Betwa basin is practically devoid of
active lineament, fault or shear. As per the seismic zoning map of India (1990), the proposed
layout of the kotha barrage including storage dams/barrages in Upper Betwa falls under seismic
zone-II which signifies low seismic events not exceeding magnitude 3 and hence seismo-
tectonic hazards would be considered as minimum.
Foundation Investigation
The work of foundation investigations (geotechnical) was carried out through GSI,
Bhopal in association with CSMRS, Delhi. Geotechnical assessment of surface and sub-surface
data along the alignment of the Kotha barrage gathered through geological mapping (1:2500
scale) of the project area and core logging of 3 exploratory drill holes on left, centre & right
flanks (BH-1, BH-2 & BH-3) aggregating to about 64m depth of drilling to precisely assess the
subsurface geological condition and water conductivity of bedrocks. Depth of drill holes ranges
from 18.25 m to 26.40 m. A geotechnical note on sub-surface exploration of Kotha barrage is
enclosed as Appendix.
The rock samples were got tested from CSMRS, Delhi and the parameters are
51
appropriately used by CWC in the design of the structure. The test results of rock samples are
furnished as Appendix:
Since barrage is proposed, no investigation was required under this sub -head.
Barrage
The extent of foundation exploration carried out for the earlier proposal of
barrage as per the recommendation of GSI. However, the geotechnical investigation for
modified parameters of the barrage as per the recommendations of CWC visit to site during
Nov. 2013 is to be reviewed in consultation with GSI at next stage of the project.
On the basis of a map prepared for Upper Betwa sub-basin from National Atlas of India
(1982), and based on the information provided by the National Bureau of Soil Survey and Land
Use Planning (NBSS & LUP), Nagpur/Delhi the soils of the command area can be broadly
classified into medium to deep black soils. The deep black soils are predominantly clayey in
texture while the medium black soils are fine textured. The black soils are suitable for
cultivation. With good management practices, it is possible to cultivate areas under these soils
both under wet and dry conditions. The lands in the command are good to very good cultivable
lands with moderate erosion. These are suitable for irrigation with moderate limitations due to
heavy texture and require drainage.
FOUNDATION INVESTIGATION
The work of foundation investigations (geotechnical) was carried out through GSI,
Bhopal in association with CSMRS, Delhi. Geotechnical assessment of surface and sub-surface
data along the alignment of the Kotha barrage gathered through geological mapping (1:2500
scale) of the project area and core logging of 3 exploratory drill holes on left, centre & right
flanks (BH-1, BH-2 & BH-3) aggregating to about 64m depth of drilling to precisely assess the
52
subsurface geological condition and water conductivity of bedrocks. Depth of drill holes ranges
from 18.25 m to 26.40 m. A geotechnical note on sub-surface exploration of Kotha barrage is
enclosed as Appendix:
The rock samples were got tested from CSMRS, Delhi and the parameters are appropriately
used by CWC in the design of the structure. The test results of rock samples are furnished as
Appendix:
53
The upper part of the basin is dominated by deep black soil and medium black soil
with patches of mixed red and black soil. The black soils are suitable for cultivation. Most of the
Lower Betwa basin is covered by alluvial and plateau soils.
54
Fig-6- Layout of Raingauge Station
Thiessen polygons of various rainfall stations have been prepared and overlaid
with the sub-basin map of proposed project site. Thiessen weights of different rainfall
stations of each Kotha barrage site have been worked out and as given in Table below
correlation exists between Basoda, Khurai and Kurwai rainfall stations.
55
Table -8: Thiessen weights of rainfall stations
RF_Station Theissen Average Annual RF
Weight (mm)
The normal monthly rainfall data shows that this station receives 92% of its total rainfall
during the south west monsoon period (June to September). The maximum rainfall occurs
during August and the minimum rainfall occurs during April. The annual normal rainfall is 1190
mm are furnished in Annexures.
Humidity
The maximum and minimum mean monthly relative humidity varies from 23% (April) to
88% (August). The values of monthly relative humidity of Raisen IMD observatory are furnished
in Annexure.
Temperature
The climate of the Kotha barrage area is characterized by hot summer and mild winter.
The daily maximum and minimum temperature varies from 7ºC to 41.9 ºC. The month wise
daily maximum and minimum temperatures of Raisen IMD observatory are furnished in
Annexure.
Discharge
No gauge and discharge site is available in the vicinity of Kotha barrage site. Gauge and
Discharge data being observed by CWC at Basoda on river Betwa have been collected and the
same have been utilized in hydrological study carried out for this project.
56
Sedimentation
There is no silt observation site located at proposed Kotha barrage being a barrage.
However, a nearby silt observation site, has been established by NWDA at Neemkheda G&D
site, located 7 km d/s of Makodia dam (now dropped) site on Betwa river and observation
started w.e.f. 25.07.2007. This site is closed now.
Water quality
The results of the water quality samples taken at the proposed Neemkheda barrage
located u/s of the Kotha barrage site & tested at water quality testing laboratory of CWC,
Bhopal is representative for this site. The result are enclosed in Annexure
Evaporation
There is no pan evaporimeter installed near the Kotha barrage site. The monthly
evaporation values computed at Raisen IMD observatory has been used for the hydrological
study and the same are furnished in Table 9 below.
Table – 9 : *Monthly Evaporation values at Raisen IMD station
Month Evaporation
(m)
January 0.0753
February 0.0918
March 0.1507
April 0.2046
May 0.2638
June 0.1995
July 0.1156
August 0.0992
September 0.1230
October 0.1287
November 0.0930
December 0.0738
Total 1.6190
57
EVAPO-TRANSPIRATION
Based on the proximity of project site and meteorological station, estimate of evapo-
transpiration of Raisen station has been used for Kotha barrage. The computed ET0 values for
raisen station using Penman’s method are given in Table 10 below.
WATER DEMAND
Assessment of water demands in foreseeable future for various purposes including
domestic, industries, irrigation, hydropower and navigation etc. is essential for planning of
water resources development and management. Water needs are to be met either from
surface flows or ground water resources or a combination of both. The procedure adopted for
estimation of water demands for different purposes in Betwa basin is detailed below.
To assess the domestic and industrial water demands in a sub-basin, the population is
assumed to be distributed uniformly in a district and based on the percent area of a district
within each sub-basin, the human and livestock population is assessed. Table–11 shows the
percent areas of districts in basin of Kotha Barrage.
58
Table - 11: Percent areas of districts in basin of Kotha Barrage
Error! Not a valid link.
The human population has been projected for the year 2050 AD on the basis of
medium variant growth rate as given in U.N. Publication ‘World Population Prospects – 2010
revision’ (given in Table - 12). For livestock population, annual population growth rate of 1 %
has been considered uniformly. The formula used for population projection is of the form:
Table – 12: Medium variant population growth rate (%) for India (World Population
Prospects–2010 revision)
Error! Not a valid link.
District-wise census data for human population (in the year 2011) and livestock population (in
the year 2008) and their projected population for the year 2050 AD are computed as shown in
Table –13.
59
Table – 13: Present and projected populations in different districts (in thousand)
Error! Not a valid link. Based on the human and livestock population in the
district and its percent area in the sub-basins, domestic and industrial demands have been
worked out as per the following guidelines:
a) Urban population is considered as 55.2% and rural population is considered as
44.8% of the total projected population.
b) Per capita water demands for urban, rural and livestock population is
considered as 135 lpcd (litres per capita per day), 70 lpcd, and 50 lpcd
respectively.
c) 40% of the surface water supply (for urban and rural population demands and
industrial demands) is consumed while 60% is regenerated back to the surface
flows at downstream node. Regeneration for ground water supply is also
considered.
Based on these guidelines, the domestic and industrial water demands and regeneration
have been worked out on annual basis.
Irrigation Demand
The existing and proposed major, medium, and minor projects in sub-basin upstream of
Kotha Barrage have been taken from MP WRD EIMS portal. Halali is the only major project in
this sub-basin with intercepted virgin catchment of 655.239 Sq km having live capacity of
252.13 Mcum at full reservoir level. Details of various major and medium projects in the sub-
basin are given in Table – 3.10.2. The list of minor projects in sub- basin are attached in
Annexure. Since the present analysis is carried out at monthly time step, monthly utilization
pattern is required. In the study area, Kaliasote and Kerwan are the two existing medium
projects whose actual monthly utilizations from 1996 – 2006 were available. Average of these
monthly utilizations has been used for these projects.
60
Table-14: Water use u/s of Kotha Barrage
As per the guidelines, 10% of the utilization from major medium and minor projects is
regenerated back as surface flow.
Transmission losses have not been considered because water is assumed to be utilized in the
vicinity of the pond area through local pumping for irrigation purposes and for domestic water
supplies to the towns situated on banks of river Betwa like Raisen, Vidisha, Basoda, Mandi
Bamora, Bhopal, Mandideep and other towns & villages.
Environmental Flows
For the proposed project in the Upper Betwa basin, the environmental flows have been
computed from the estimated monthly flow patterns at the project site. For the monsoon
months from June to October, 75% dependable flows have been computed on monthly basis
and 20% of the 75% dependable flows in each monsoon month have been reserved for
environmental and ecological purposes. For the non-monsoon months, average monthly flows
61
have been worked out and 15% of the average monthly flows in different non-monsoon months
have been reserved for environmental and ecological purposes. For estimation its taken as 2.50
Mcum to be released in dry lean period downstream of Kotha barrage perticularly to safeguard
environmental requirement in Betwa basin from proposed barrage to the confluence point with
Bina river.
IMPORT/ EXPORT
Surface water available by Inter basin transfer from Kolar river of Narmada basin for
Bhopal town is 130 Mcum (65 Mcum existing + 65 Mcum future water use). From Narmada
river it is taken as 47.45 Mcum for Bhopal municipality water supply.
The average rainfall series has been worked out in the catchment areas of five
62
proposed project sites and in the catchment area of Basoda G & D site by using the rainfall
series of 15 raingauge stations and their thiessen weights in different sub-basins. Daily
observed discharge data at Basoda (in cumec) has been converted to monthly flow volume (in
Mcum). However, the observed flow at Basoda is affected by:
a) Spill from the Bhopal lake / kaliasote dam
b) Water utilizations and evaporation losses from existing Halali (S.A.S.) project
c) Water utilizations from existing Kaliasote and Kerwan medium projects & other
medium projects.
d) Water utilizations from minor surface irrigation projects.
64
Table – 15: Computed virgin flows (MCUM) at Basoda G & D site
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1976 26.67 327.80 879.87 815.78 41.94 19.50 42.59
1977 6.08 6.40 6.11 1.22 1.58 275.42 738.33 2820.84 2273.49 261.45 94.74 74.30
1978 16.00 18.73 13.69 7.01 6.22 195.72 1580.32 2567.89 503.95 89.81 22.50 45.28
1979 34.59 30.63 17.99 11.19 8.90 76.17 150.01 467.64 37.19 7.17 86.83 79.72
1980 9.14 6.78 6.69 1.08 0.86 194.66 229.98 1043.35 416.66 76.44 17.15 14.15
1981 22.16 12.54 12.48 10.03 14.13 68.71 208.33 798.86 95.06 39.41 19.98 20.14
1982 32.45 36.96 17.03 10.28 2.20 32.60 225.91 1479.22 492.22 268.02 116.20 118.74
1983 45.79 15.62 11.94 5.21 1.53 16.23 333.21 1248.11 1745.67 539.96 204.24 48.06
1984 64.92 31.49 20.20 8.81 4.78 15.72 53.86 2407.44 293.85 77.30 15.85 20.17
1985 18.50 10.50 9.51 1.65 0.86 16.78 296.42 2113.85 1323.73 1128.61 185.04 39.58
1986 34.20 38.89 33.35 8.55 2.33 131.25 3941.92 1353.81 244.15 75.81 16.50 22.29
1987 24.01 17.97 12.64 5.37 0.98 14.90 166.94 1492.79 446.23 89.56 29.27 17.60
1988 13.34 17.66 10.40 1.54 0.86 51.10 603.30 958.67 138.77 62.87 18.29 20.62
1989 18.35 12.83 6.23 2.92 0.86 32.08 188.20 1353.50 344.71 42.33 7.72 14.04
1990 8.82 3.13 1.14 0.14 0.86 309.40 785.82 1238.14 1592.30 202.54 37.78 15.12
1991 9.37 10.13 9.18 4.88 1.35 72.02 260.50 2042.90 385.78 31.72 11.02 14.58
1992 23.00 12.88 7.22 1.81 1.49 15.14 253.83 1072.36 397.53 53.15 4.32 7.35
1993 1.78 0.94 1.05 0.14 0.86 34.06 278.59 719.00 1574.21 432.84 31.74 22.23
1994 19.50 13.29 11.69 10.56 4.34 270.04 1215.71 2255.28 892.37 83.38 15.47 20.41
1995 18.77 24.86 32.29 10.98 3.32 16.87 278.27 530.31 563.64 115.41 14.68 19.36
1996 18.83 7.72 6.66 1.10 0.98 15.89 857.26 1889.40 961.17 180.18 69.71 26.27
1997 20.33 21.59 8.03 3.04 2.74 16.65 934.09 1209.96 716.90 132.64 108.19 415.14
1998 40.93 25.47 25.36 11.56 2.94 79.98 853.39 1017.37 967.57 613.10 140.51 25.92
1999 13.84 317.63 105.82 4.75 0.55 54.26 855.52 1224.02 2756.57 1200.61 97.77 24.21
2000 19.73 25.14 2.31 0.43 1.73 45.61 1676.38 550.35 132.88 32.22 7.00 19.76
2001 10.64 0.55 0.00 0.33 1.35 95.52 610.03 1109.05 185.83 59.03 6.88 9.40
2002 20.95 1.10 2.17 3.90 0.73 34.44 72.06 1040.28 755.33 28.52 0.57 7.08
2003 0.00 0.00 0.00 0.00 1.91 101.72 555.49 717.87 952.18 271.11 18.24 19.40
2004 17.58 26.01 15.95 0.80 1.19 41.57 374.71 1999.34 346.32 57.05 13.70 22.66
2005 35.36 19.40 7.33 0.74 0.38 28.96 1939.19 1158.09 378.43 99.32 10.27 21.51
2006 25.14 17.40 9.95 2.92 2.36 24.95 416.20 2260.46 2534.54 247.87 11.88 25.80
2007 31.16 110.59 12.89 1.28 1.13 29.98 331.21 310.99 283.13 49.76 0.00 0.07
2008 0.00 0.94 1.05 0.14 0.86 103.99 267.96 954.68 282.68 40.05 0.00 0.07
2009 0.00 0.94 1.05 0.14 0.86 16.06 507.85 341.19 653.62 215.00 177.15 54.55
Average 20.46 27.17 13.32 4.08 2.36 75.15 657.90 1312.56 778.95 204.30 47.96 39.65
Av_Mons
(Jun-Oct) 3028.86
Av_Non-
monsoon 155.00
Non-mon
flow as %
of Monsoon 5.118
% monthly
flow in
Non-
monsoon 13.201 17.530 8.590 2.630 1.526 30.942 25.581
65
Table – 15 also provides computation for average flows in different
months which is used to find the average flows in monsoon and non-monsoon periods. Non-
monsoon flows (November – May) come out to be 5.118 % of monsoon flows. In addition, flows
in different non-monsoon months, as percentage of the average non-monsoon flow, have also
been computed which are used to find the flows in non-monsoon months.
Development of r – R relationships
The average rainfall series in the catchment area of Basoda G & D site
has been worked out by using the thiessen weights of the rainfall stations in the Basoda sub-
basin. The virgin flows at Basoda G & D site computed for the period 1976 – 2009 have been
converted to depth terms (mm) and used to develop the r – R relationships in the Upper Betwa
basin in different monsoon months (June – October). These relationships are further used to
convert the average rainfall in the sub-basins of proposed projects to runoff depth.
For each month, plots of best fit line through the data points (rainfall and runoff)
have been obtained. In addition, bi-variate analysis (for the months of July, August, September,
and October) has been tried in which a correlation is established between the flow in a month
to the rainfall in the previous and current month. Plot of rainfall – Runoff relationships for
different monsoon months are shown in Figure – 7 (a – e).
66
Figure – 7 (a): Plot of r-R data for Basoda catchment for month of June
Figure – 7 (b): Plot of r-R data for Basoda catchment for month of July
67
Figure – 7 (c): Plot of r-R data for Basoda catchment for month of August
Figure – 7 (d): Plot of r-R data for Basoda catchment for month of September
68
Figure – 7 (e): Plot of r-R data for Basoda catchment for month of October
While finalizing the r - R relations for different months, the nature of the relations
has been considered in addition to the goodness of fit (in terms of r2 value). For example, in the
linear relationships, the negative constant term represents the initial abstractions in the
catchment while the multiplication factor with the rainfall represents the runoff coefficient. The
runoff coefficient is less in June (due to initial dry conditions) and it increases in July and August
months due to comparatively wet conditions. Bi-variate relationship is used only if its nature is
truly represented (positive runoff coefficients for different months and negative constant term)
and it shows appreciable improvement in the coefficient of determination (r 2). For months from
June to September, linear relationships are used while for October month, bi-variate
relationship is expected to be more representative. Final r – R relationships adopted for the
monsoon months are as follows:
r - R relationship for June
RunoffJune = 0.1239 * RainfallJune – 7.8113 r2 of the
relationship comes out to be 0.688.
r - R relationship for July
RunoffJuly = 0.4397 * RainfallJuly – 67.585
r2 of the relationship comes out to be 0.826.
From the virgin flow series computed above, net yield series has been derived
after accounting for the diversions from the existing and future major, medium, and minor
projects and net domestic and industrial demands from surface water resources in the sub-
basins of various proposed projects.
For the major projects (Halali is the only major project), detailed monthly reservoir operation
analysis has been carried out from June, 1901 to May, 2009 considering the virgin flows on pro-
rata basis, storage characteristics, diversion demands, and normal monthly evaporation losses.
For the existing and proposed medium projects in various sub-basins, contributing catchment
areas have been determined in GIS and virgin inflows have been estimated on pro-rata basis
depending on the virgin flows in the sub-basin in which they are located. The annual design
utilizations of medium projects have been converted to monthly utilizations using the average
monthly utilization pattern of medium projects. Storage capacity of medium projects has been
provided by NWDA. To account for the storage effect of medium projects, detailed simulation
analysis has been carried out for each medium project from June, 1901 to May, 2009 and
possible diversion and spill series at monthly time step has been generated.
For the minor projects in a sub-basin, annual design demands of all existing and
future projects have been disaggregated into monthly values using the monthly distribution
pattern. Finally, net monthly flow series at a proposed project site is computed as follows:
a) Net virgin flows from the free sub-basin of a proposed project site below any
70
existing or future major or medium project are computed on pro-rata basis.
b) Spills and 10% of the computed diversions from the major and medium projects (as
regeneration) is added to the virgin flows from the free catchment computed at
(a).
c) Diversions from minor projects are subtracted from the flows computed at (b).
d) From the upstream proposed project (if any), spill and environmental flow series
and 10% of the computed diversions (as regeneration) are added to flows
computed at (c).
e) Withdrawals for net domestic and industrial demands (after accounting for
regeneration) are subtracted from the flows computed at (d).
Integrated operation analysis has been carried out for the entire system (proposed
projects and various existing and proposed major and medium projects) at
monthly time step for the period from June, 1901 to May, 2009. Computed flow
series at monthly time step at each project site has been aggregated to annual
time step to compute the dependable flows at each proposed project site. The
annual runoff series is arranged in descending order and ranks for each value in
the series have been assigned in ascending order. Thus, the rank of the highest
value is 1 (one) and that of the lowest value is the number of data in the series
(108). Probability of exceedance (Pi) is computed using Weibull’s formula as
follows:
i
P=
i n +1 …(3.3)
where ‘i’ is the rank and ‘n’ is the number of data points (108) in the series.
For all the proposed projects under Ken-Betwa Link (Phase-II) in the Betwa basin,
the environmental flows have been computed from the estimated monthly flow pattern at each
proposed project site. For the monsoon months from June to October, 75% dependable flows
have been computed on monthly basis and 20% of the 75% dependable flows in each monsoon
month have been reserved for environmental and ecological purposes. However, for the non-
monsoon months, average monthly flows have been worked out and 15% of the average
monthly flows in different non-monsoon months have been reserved for environmental and
ecological purposes.
Monthly operation analysis has been carried out for the period from June, 1901 to May,
2009 for all proposed projects using the elevation-area-capacity table, specified upper and lower
pond levels, and the design demands and environmental flow requirements from the project.
The monthly evaporation estimates of nearest meteorological station have been used. In most
of the projects, it was inferred that more demands (in comparison to the design demands) can
be met from the projects with annual reliability of 75%. A number of iterations have been made
to finalize the project demands that can be satisfied with annual reliability of 75%.
71
Table-16: Computed dependable flows (MCUM) at proposed project site
Error! Not a valid link.
The simulation analysis carried out and the net inflow series at the proposed site is shown
in Table 17 below.
72
Table – 17 : Computed monthly net flow (MCUM) series at Kotha project site
Year Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1901-02 0 167.72 1679.6 154.45 5.25 19.984 15.97 7.037 7.913 3.356 0.307 0.12
1902-03 0 564.05 394.54 752.56 135.43 20.367 14.908 6.494 7.193 3.003 0.224 0.072
1903-04 0 210.99 793.71 1372.6 139.28 24.493 18.318 7.516 8.708 3.495 0.316 0.125
1904-05 0 428.99 411.74 319.24 13.347 15.735 10.854 5.927 6.439 2.319 0.165 0.037
1905-06 0 34.427 480.89 717.57 48.383 16.258 11.509 5.546 5.934 2.385 0.077 0
1906-07 0.566 611.7 112.68 887.56 61.289 19.913 14.531 6.851 7.667 3.235 0.295 0.113
1907-08 0 67.517 1498.4 42.389 2.134 14.007 11.622 6.323 6.92 2.653 0.183 0.047
1908-09 0 786.63 1017.2 150.36 6.952 15.648 15.406 7.011 7.879 3.339 0.306 0.119
1909-10 6.828 195.42 1212.4 89.489 2.146 16.415 12.924 5.858 6.34 2.405 0.096 0.003
1910-11 3.193 23.902 684.36 1137.3 102.27 20.641 15.133 6.882 7.707 3.255 0.246 0.085
1911-12 0 83.472 647.1 996.02 79.939 20.96 15.396 6.554 7.272 3.041 0.199 0.057
1912-13 0 290.55 967.79 433.17 20.927 18.442 13.315 6.206 6.81 2.815 0.18 0.046
1913-14 38.457 39.967 814.54 64.508 2.82 10.363 8.61 4.769 4.662 0.803 0 0
1914-15 3.827 744.54 590.02 356.58 17.474 19.962 14.571 6.115 6.69 2.756 0.144 0.025
1915-16 49.735 83.283 921.97 250.09 117.97 16.269 11.518 5.494 5.865 2.352 0.071 0
1916-17 52.671 224.8 2197.4 498.59 139.79 29.593 22.87 9.651 11.542 4.584 0.535 0.252
1917-18 53.649 494.44 1824.8 1034.8 111.85 33.704 26.626 10.34 12.48 4.665 0.558 0.266
1918-19 16.947 25.89 687.95 205.91 7.151 13.506 9.494 5.225 5.493 1.206 0.039 0
1919-20 0 389.22 2769.5 535.58 92.273 36.736 29.319 11.247 14.616 4.619 0.503 0.234
1920-21 8.103 469.93 172.68 108.49 1.973 12.16 8.747 4.625 4.617 0.829 0 0
1921-22 11.713 23.62 1336.3 969.51 64.015 23.124 18.066 6.867 7.688 3.245 0.263 0.094
1922-23 1.948 563.39 265.38 863.92 56.626 20.288 14.841 6.848 7.662 3.233 0.251 0.087
1923-24 0 1532.3 1344.5 981.6 54.733 38.807 31.031 11.076 17.008 4.446 0.52 0.243
1924-25 0 212 891.59 849.99 92.427 21.474 15.822 6.661 7.415 3.111 0.209 0.063
1925-26 21.097 264.23 454.74 162.01 5.154 12.777 9.139 5.042 5.121 1.276 0.032 0
1926-27 0 454.49 1618.6 856.23 101.82 29.906 23.652 8.528 10.527 3.73 0.334 0.135
1927-28 2.688 620.88 667.35 187.45 46.245 18.58 13.43 6.203 6.806 2.767 0.135 0.025
1928-29 0 943.42 348.68 50.846 19.71 15.503 10.886 5.419 5.765 2.267 0.047 0
1929-30 1.211 440.79 962.18 282.21 10.573 20.164 14.739 6.745 7.526 3.166 0.253 0.089
1930-31 0.21 893.22 424.15 352.1 39.281 18.602 13.448 6.051 6.604 2.714 0.149 0.028
1931-32 0 282.56 1072 1233 238.94 27.889 21.95 7.699 9.35 3.408 0.27 0.098
1932-33 0 1655.9 146.31 1627.5 127.99 34.455 27.343 10.394 13.168 4.231 0.452 0.204
1933-34 44.822 333.46 1038.8 1224.5 97.787 26.22 20.289 7.599 8.817 3.523 0.297 0.114
1934-35 23.459 325.4 1241.8 2552.6 188.71 43.934 35.402 12.283 19.44 5.243 0.733 0.367
1935-36 11.532 555.44 331.99 985.75 95.9 20.744 15.219 6.563 7.285 3.048 0.201 0.059
1936-37 19.259 250.51 949.47 1086.8 69.348 23.166 17.221 6.95 7.956 3.005 0.172 0.042
1937-38 20.126 1019.1 522.71 621.67 55.391 23.346 17.37 7.027 8.058 3.329 0.25 0.087
1938-39 124.87 731.83 876.35 162.48 125.19 20.76 15.231 6.162 6.752 2.787 0.157 0.033
1939-40 0 744.96 1038.9 825.46 43.208 25.339 19.561 7.585 8.8 3.304 0.255 0.09
1940-41 26.128 1115.6 1288.9 326.53 34.457 26.012 19.575 8.165 9.569 3.852 0.376 0.16
1941-42 0 26.897 1200.3 352.61 14.022 18.528 13.386 6.056 6.611 2.717 0.141 0.024
1942-43 26.868 1495 860.77 569.39 26.706 28.974 22.644 8.919 10.571 4.092 0.475 0.217
1943-44 0.358 729.4 458.16 497.86 106.18 19.818 14.453 6.744 7.524 3.165 0.256 0.09
1944-45 0 1463.9 1551.4 399.16 56.822 35.281 28.116 9.384 15.361 3.406 0.223 0.071
73
Year Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1945-46 221.22 1029 343.94 650.89 36.693 22.783 16.905 6.945 7.792 3.296 0.208 0.063
1946-47 135.89 680.44 1641 220.54 11.786 25.546 19.189 8.061 9.274 4.022 0.453 0.204
1947-48 0 647.14 1635.6 1503.9 133.72 38.437 30.726 11.229 16.308 4.638 0.53 0.249
1948-49 21.736 984.58 1461.9 1321.9 104.69 37.646 30.035 11.373 14.769 4.874 0.604 0.292
1949-50 15.294 347.04 328.01 2005.7 249.32 28.667 21.901 8.949 10.61 4.276 0.498 0.231
1950-51 0 452.23 452.29 531.72 32.575 14.998 10.468 5.141 5.396 2.122 0.04 0
1951-52 0 195.41 668.87 78.778 4.055 11.929 9.604 5.282 5.5 1.238 0.014 0
1952-53 27.146 516.4 822.71 49.191 1.783 13.76 11.417 6.218 6.826 2.534 0.204 0.06
1953-54 0 506.8 935.31 366.64 32.289 19.071 13.836 6.379 7.04 2.928 0.236 0.079
1954-55 0 497.78 292.65 1750.7 153.98 25.599 19.835 7.741 9.007 3.355 0.234 0.078
1955-56 27.223 25.89 1872.1 1822.1 264.25 38.41 30.925 10.59 17.073 4.551 0.498 0.231
1956-57 4.566 1356.9 1044.2 609.09 66.073 30.042 23.038 9.478 11.314 4.734 0.591 0.285
1957-58 0 139.24 850.83 317.91 29.561 16.345 11.582 5.9 6.404 2.514 0.107 0.009
1958-59 0 520.21 792.1 896.43 138.32 23.776 17.725 7.21 8.301 3.366 0.276 0.102
1959-60 1.19 834.09 1303.3 978.58 161.4 31.653 24.957 9.697 11.604 4.343 0.498 0.231
1960-61 4.725 230.63 1481 90.857 78.938 20.521 15.034 6.408 7.078 2.947 0.173 0.042
1961-62 0 604.35 1249 2554.3 360.44 48.113 39.021 14.386 21.888 5.363 0.67 0.33
1962-63 0 260.95 565.14 1225.4 85.265 21.95 16.216 7.049 7.93 3.364 0.255 0.09
1963-64 0 64.116 1431.8 547.68 37.736 20.657 15.147 6.588 7.317 3.064 0.215 0.067
1964-65 1.355 600.29 1304.5 844.61 44.257 26.398 20.317 7.969 9.31 3.512 0.277 0.102
1965-66 0 861.19 172.87 488.67 33.003 17.234 12.318 5.847 6.333 2.581 0.105 0.003
1966-67 0.428 368.23 450.97 138.13 3.8 13.272 9.529 5.243 5.221 1.1 0.046 0
1967-68 7.397 268.78 835.64 1087.7 78.094 23.115 17.179 7.155 8.07 3.432 0.264 0.095
1968-69 0 551.94 1008.7 284.59 11.003 20.154 14.731 6.32 6.962 2.889 0.142 0.024
1969-70 0 1450.2 1967.8 564.63 27.529 38.278 30.831 11.494 15.719 4.883 0.581 0.279
1970-71 47.813 636.11 1921.6 1295 93.465 39.012 31.333 10.976 17.347 4.541 0.473 0.216
1971-72 74.599 1049.4 379.69 906.65 137.95 25.754 19.361 8.276 9.559 4.162 0.464 0.211
1972-73 0 20.541 1461.8 146.86 4.406 17.156 12.252 5.716 6.159 2.426 0.08 0
1973-74 0 1410.4 2360.4 794.27 55.174 45.945 37.171 13.924 21.245 5.226 0.64 0.313
1974-75 0 341.68 1959.6 79.185 47.545 22.763 16.888 7.146 8.058 3.427 0.303 0.118
1975-76 45.989 437.77 1318.2 1093.2 144.55 28.93 22.598 9.188 10.928 4.523 0.564 0.269
1976-77 11.648 67.072 729.33 660.34 52.686 16.823 11.977 5.373 5.704 2.206 0.022 0
1977-78 56.404 656.22 1742.3 914.7 76.668 32.84 26.011 9.925 11.959 4.299 0.431 0.192
1978-79 54.012 661.18 1610.7 218.53 7.219 24.305 18.483 7.623 8.793 3.737 0.344 0.141
1979-80 0 16.704 237.77 53.082 1.895 8.835 5.395 2.48 0.686 0.051 0 0
1980-81 55.518 25.891 1289.2 221.67 8.551 18.173 13.093 6.054 6.608 2.716 0.135 0.02
1981-82 0 126.06 984.36 282.94 23.669 17.563 12.589 6.136 6.717 2.759 0.145 0.031
1982-83 0 111.73 2280.7 452.05 48.614 27.222 20.99 8.599 10.147 4.312 0.519 0.243
1983-84 0 232.57 1577.8 2047.4 210.93 40.421 32.366 11.591 18.273 4.827 0.632 0.309
1984-85 0 20.818 1769.4 101.27 2.696 15.434 12.119 5.471 5.834 2.28 0.037 0
1985-86 0 356.29 1467.2 1105.5 298.45 30.859 24.185 9.266 11.031 4.35 0.497 0.23
1986-87 22.425 1740.4 567.59 126.38 3.655 23.8 18.762 6.322 6.885 2.737 0.094 0.001
1987-88 0 121.58 1550.4 449.73 118.54 24.155 18.039 8.109 9.337 4.053 0.536 0.253
1988-89 28.296 515.95 725.8 209.33 23.332 18.609 13.453 6.193 6.793 2.751 0.157 0.038
1989-90 11.563 19.371 870.83 506.26 26.839 16.595 11.789 6.041 6.592 2.592 0.148 0.028
1990-91 64.89 396.73 1170.7 643.82 60.151 22.319 16.975 6.5 7.36 2.905 0.101 0
1991-92 35.887 271.17 1331.1 32.384 1.783 14.3 12.86 5.845 6.331 2.58 0.097 0
74
Year Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1992-93 0 336.07 1194.8 350.07 25.668 19.613 14.284 6.233 6.846 2.832 0.167 0.039
1993-94 0.117 327.51 1028.9 1798.7 163.65 31.288 24.463 9.933 11.917 4.776 0.618 0.3
1994-95 159.23 731.19 1757.5 406.61 18.549 28.994 22.598 8.932 10.588 3.964 0.39 0.168
1995-96 0 535.29 809.42 518.17 63.785 20.91 15.356 6.694 7.459 3.133 0.256 0.09
1996-97 0 1105.4 1835 558.32 106.48 34.224 26.981 10.285 13.032 4.374 0.487 0.224
1997-98 0.235 718 958.15 401.26 111.05 21.419 15.776 6.484 7.18 2.996 0.182 0.047
1998-99 20.435 585.32 586.56 839.34 78.296 20.562 15.068 6.222 6.832 2.826 0.134 0.019
1999-00 3.587 704.95 820.31 2540.3 360.82 44.922 36.381 12.914 20.093 4.606 0.553 0.263
2000-01 6.418 1251 330.59 40.056 1.783 14.946 12.399 6.724 7.498 3.152 0.294 0.113
2001-02 52.971 424.71 745.59 81.522 42.434 16.893 12.035 6.063 6.62 2.671 0.164 0.037
2002-03 0 0.528 1668.8 221.93 9.136 19.219 13.958 6.681 7.441 3.124 0.254 0.089
2003-04 0 418.68 870.86 936.3 62.228 23.572 17.557 7.747 8.856 3.818 0.357 0.149
2004-05 13.318 196.42 1350.7 135.46 52.376 19.049 13.817 6.471 7.161 2.987 0.16 0.035
2005-06 0.811 1215.6 308.65 537.79 32.415 21.434 15.789 6.907 7.741 3.271 0.26 0.093
2006-07 0 523.37 2094.2 1241.4 89.834 39.069 31.248 11.22 17.364 4.869 0.464 0.202
2007-08 4.942 331.54 319.33 511.91 27.698 15.448 10.777 5.756 6.212 2.237 0.074 0
2008-09 79.236 79.172 414.3 325.37 25.46 13.649 9.855 5.411 5.586 1.325 0.091 0
75
is necessary to determine the design storm for the project area. After the unit hydrograph for
the catchment is derived, the required flood hydrograph, i.e. the probable maximum flood
(PMF) is obtained by appropriate convolution of excess PMP rainfall after accounting for the
infiltration losses and base flow additions. In the case of large basins, it becomes necessary to
sub-divide the catchment and mark out the flood hydrographs of its sub-areas and route them
through the river channel to the desired site by following suitable flood routing method and
synthesizing them to obtain the design flood hydrograph. When there are existing reservoirs in
the basin upstream of the site, it will also be necessary to route the flood through such
reservoirs to account for the moderation provided by the storage. Wherever sufficient data
are not available for UH computation, synthetic methods are used to derive the UH. In case,
the statistical models are used for design flood estimation, at-site flood frequency analysis
shall be applied using annual maximum series of gauge site records for deriving a design flood
for a specific return period. The return period shall be selected as per the guidelines of the
Ministry of Irrigation (1980) report. For this study, design flood is derived as follows:
(i) Synthetic unit hydrographs (SUH) are developed for the sub-catchment up to
Neemkheda, Barari, Kesari, and Lower Orr projects because historic data is not available for
these sites. Furthermore, sub-catchments of Kotha and Barari are divided into two sub-basins
and SUH are developed for each sub-basin.
(ii) UH at step (ii) is convoluted with a critical design (critical sequencing of PMP) to
produce the corresponding PMF hydrograph of the sub-catchments. Network models have
been developed for Kotha sub-catchments for the computation of PMF.
(iii) Statistical approach
tp = 2.195(q p )−0.944
where L is the length of the main stream from the outlet to the catchment boundary in km; S is
the average channel slope of the catchment in m/km; and t p, and qp, are expressed in units of
hours and m3/s/Sqkm, respectively. The shape of the hydrograph is determined using the
parameters W50, W75, WR50, WR75, and TB (CWC, 1989). These parameters have been
determined by using the following equations:
Kotha (U) 332.21 0.087 22.11 25.11 10.35 7.89 3.66 83.96
Kotha (D) 416.97 0.086 22.36 25.42 10.46 7.99 3.69 84.90
77
Figure – 8(a): Synthetic Unit Hydrograph for
Kotha (U) sub-catchment (ER = 1 cm) Figure – 8(b): Synthetic Unit
Hydrograph for Kotha (D) sub-
catchment (ER = 1 cm)
Design Flood
The flood hydrographs for the excess rainfall derived from the SPS hyetograph for Kotha
(U), and Kotha (D) are convoluted using the respective derived SUH and adding the base flow.
The flood hydrograph are routed to the outlet and the downstream flood hydrographs are
added to the routed hydrograph in order to derive the SPF at the project site.
78
Table 21:Flood hydrograph (SPF) for Kotha sub-catchment using SUH
Time Flood Time Flood Time Flood Time Flood
(hrs) (m3/s) (hrs) (m3/s) (hrs) (m3/s) (hrs) (m3/s)
Flood Frequency:
Design floods for different return periods computed using the Gumbel distribution
(method of PWM) are shown in Table – 22.
Diversion Flood
The capacity of the diversion flood for barrages may be less because flood higher than
the designed one could be passed safely over the partly constructed barrage. The following
criteria would help in deciding the capacity:
a) Maximum non-monsoon flow observed at the site.
OR
b) 25 - year return period flow, calculated on the basis of non-monsoon yearly peaks.
The higher of the two should be taken as the design flood for diversion & shown in Table -
23.
80
Table - 23: Design flood for diversion
81
Chapter -IV
DESIGN ASPECTS
INTRODUCTION:
The main aim of proposing barrage across Betwa river under the project is to
provide irrigation water to the villages which lie in backward areas in Sagar and Vidisha districts
of Madhya Pradesh. The villagers shall utilise pounded water of barrages by lift irrigation in
water deficit upper area to cultivate farm land throughout the year. It will definitely bring
economic prosperity to these areas.
The design aspects are described in the following paragraphs.
The Kotha barrage envisages construction of a 16.50 m high and with 576 m long
barrage waterway across the river Betwa with a pond level of 395 m. The proposed site is
located near village Kotha in tehsil Kurwai, district Vidisha at 24003’28” N latitude and 780
01’16” E longitude (SOI Toposheet No. 54 L/4) to facilitate irrigation in the proposed 20000 Ha
command area.
Following Design flood Values have been proposed for design as shown in Table - 24
Considering the importance of barrage, 1 in 200 yr floods have been used for the
design of various components of barrage i.e. stilling basin dimensions etc. except freeboard.
Sediment data
No sediment data is available at the barrage site. However Silt Factor value is
required to access the depth of scour. In the present case as the barrage is founded on good
quality rock, Scour is not critical design issue. However to be on conservative side, a value of 1
has been assumed for the design calculations.
82
Assumed retrogression at maximum and minimum discharges
Following retrogression values have been assumed to consider retrogressed level.
S. No. Discharge (cumec) Retrogression (m)
1 Low flood 1.50
2 16457 (1 in 200 yr - Designed flood) 0.50
The provided water way has been checked for to pass the designed discharge,
for the assumed crest level & assumed afflux. In this barrage the crest level has been assumed
1.0 m higher than average floor level which is 384.59 m & assumed afflux is 1.50 m.
Scour depth
The scour holes can be occur both U/s & D/s so that cutoffs are required in the
U/s & D/s end of the floor to prevent failure by slipping of the soil in to the scour holes by
simple earth pressure. The value of scour in U/s & D/s has been taken R & 1.5 R respectively.
Piers
The total 32 nos. of piers are provided in barrage out of which 3 nos. are double
pier. The thickness of single pier is 3.0 m & thickness of double piers are 6.0 m. The length of
piers from U/s to D/s up to end of Floor i.e. 50 m up to the length of floor. The top thickness of
abutment has been fixed same as thickness of pier i.e. 3.0 m & side slope 0.7:1.
83
Crest width & level
Width of crest t=√H +√h where H is the height of barrage & h is depth of water
over crest. T has a minimum value of 3h/2w1 where w is the density of concrete. The crest level
of spillway of barrage is kept generally 1.0 to 1.5 m above the average u/s floor level. In this
barrage the crest width is kept 5.0 m & crest level is kept 1.0 m above the u/s floor level.
R.C.C. Raft
3.0 m thick combined RCC Raft (M-30) has been provided throughout the length
of barrage. The thickness of raft will increase up to 4.5 m below foundation of piers as well as in
abutments. Construction joints of 50 mm thick have been provided throughout the raft after
every 3 bays where double pier is provided.
The Hydraulic design of the barrage is given at Annexure . The General Layout
Plan and Detailed layout Plan are given at Appendix respectively.
The U/s cut off is provided at EL 376.0 m which is about 7.60 m below U/s floor
& D/s cut off is provided at EL 370.0 m which is 7.50 m below the cistern level.
Seepage control
Since rock is available at shallow depth, the cut-offs may be taken 1 m into good
quality rock. To relieve the seepage pressure built up underneath the floor, 75 mm dia.
drainage pipes 4.5 m deep and 3 m c/c (two rows per bay) shall be provided in the sloping
glacis. As the river bed is rocky, seepage may not pose much problem, provided presence of
impermeable rock is confirmed by further exploration at the construction stage. However for
preliminary design, upstream and downstream RCC cutoffs are provided. Some curtain grouting
at upstream and drainage arrangement for the stilling basin may also be required which may be
finalized at the construction stage.
85
Materials for use
Barrage bed is proposed as a RCC Raft having thickness minimum 3.0 m and
below piers/ abutment raised up to 4.50 m with M-30 concrete. Piers, Divide walls, Abutments
and gantry cum Road Bridge are proposed with M-30 Grade concrete. Return walls and CC
blocks are proposed with M15 grade plain unreinforced concrete. Skin reinforcement 16 mm
dia. 200 c/c shall be provided at water surface with 75 mm clear cover. 150 mm lean concrete
(M-10 grade) shall be provided below Pier footings, raft and other RCC work.
Fe 415 / 500 HYSD bars conforming to IS: 1789 are proposed as reinforcements.
Barrage Stoplogs
Stoplogs are proposed to carry out the maintenance of barrage gates. Four sets of
stoplogs of size 15000 mm X 1450 mm shall be provided. The stoplogs shall be operated in
balanced water head conditions. However, the top most unit can be lifted under unbalanced
water head for one unit height water head. All units are interchangeable. The stoplogs shall be
86
operated with gantry crane. The stoplog units shall be stored in stoplog groove above HFL. The
stoplog units shall have bronze pad sliding on stainless steel track. 32 mm guide shall also be
provided to guide the stoplog units. The skin plate and sealing of stoplog gate shall be kept d/s
side.
Gantry Crane
The spillway stoplogs shall be operated by moving Gantry Crane. The tentative
min. capacity of gantry crane shall be 30T. The Gantry Crane shall have hoist machinery
mounted on trolley. The trolley shall of moving type. The crane structure along with trolley
shall be capable of moving in longitudinal direction with the help of LT travel mechanism.
Suitable counter weight shall be provided to make the crane stable for different stability
conditions. The crane shall be designed as per IS: 3177 and IS: 807.
Abutment
The top width of abutments is kept as 3.0 m and side slope is kept as 0.7:1. The
length of abutment in u/s & u/s up to end of Floor i.e. 96.27 m. The return walls in the u/s & u/s
is provided at the ends of abutment on both side with 0.7:1 slope. The purpose of return wall is
for uniform flow and to make connection between abutments and banks of river.
Infrastructure Studies
Almost entire area of the project is well connected with road and rail net works.
No constraints on transportation of heavy equipment up to project sites are envisaged. For
transportation of heavy machinery to project sites some of the road bridges and culverts may
have to be strengthened at the time of preconstruction stage.
87
Operation and Maintenance
The proposed organizational set up at the construction stage of the
dam/barrages can be made available for operation and maintenance of the projects at post
construction stage.
Other Studies
The studies which are not covered will be planned at the preconstruction stage
and may be carried out at appropriate stage.
88
Chapter-V
Irrigation Planning
Existing Cropping Pattern
The existing cropping pattern in proposed command area of Kotha barrage in Upper
Betwa sub-basin is given in Table-25
Table - 25:Existing cropping pattern in Upper Betwa sub-basin for the year 2011-12
S.No. Name of crops % age of area
A Kharif
1 Paddy 0.1
2 Jowar 0.0
3 Maize 0.4
4 Bajra 0.0
5 Other pulses 6.2
6 Soyabean 30.7
7 Cotton (Fiber) 0.0
8 Ground nut 0.2
9 Vegetable 0.2
10 Til (Sesamum) 0.0
11 Other kharif 0.0
Total 37.8
B Rabi
1 Wheat 30.8
2 Barley 0.0
3 Gram 21.1
4 Mustard 0.1
5 Linseed 0.0
6 Other oilseeds 0.0
7 Other pulses 8.4
8 Other Rabi 0.0
9 Tur 0.8
10 Fodder crops 0.8
11 Vegetable 0.2
Total 62.2
C Perennial
1 Sugarcane 0.0
Total 100
89
The above pattern shows that in Kharif, Soyabean are the dominant crop whereas
Pulses & Maize are second major crops. While in Rabi, Wheat & Gram holds dominant crop
position in command.
Double cropping is being practiced under rain fed cultivation. It indicates that assured
irrigation, proper care of soil and application of fertilizers inputs, higher intensities (normally to
a range of 135% - 145%) can be achieved easily.
The proposed cropping pattern for providing irrigation in the command under Kotha barrage is
given in Table-26
Rabi
Total 25500
The crop water requirements for the Kotha Barrage command (CCA 20000 ha) has been
computed by Modified Penman Method. The irrigation demand for Kotha barrage command
works out as 73.651 MCUM for pressurised sprinkler system of irrigation with project efficiency
of 85%.
The Reference Evapo-transpiration (ETo) values in mm for Vidisha IMD station of Madhya
Pradesh is tabulated in Table - 27 and have been considered in the crop water requirement
computation:
90
Table - 27: Evapo-transpiration (ETo) values for Vidisha IMD station
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
ETo in
mm 89 111 167 213 254 244 170 129 149 152 97 81 1856
Effective Rainfall
Annual rainfall in Vidisha district is about 1126.4 mm and the same have been
considered computation of effective rainfall for various crops. The crops are proposed to be
irrigated in Rabi season and contribution of rainfall in meeting water demands is negligible. The
effective rainfall component in the crop water requirement has been computed and month
wise normal rainfall in the command area is as under:
Table-28: Monthly rainfall in the Vidisha district
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Avg RF
in
7.56 4.98 5.48 0.48 0.74 219.4 403.5 328.7 119.2 7.46 30.9 5.48 1126.4
mm
Irrigation Efficiency
Not all the applied irrigation water is utilized by the plants and some part of irrigation
water is lost due to percolation in field during irrigation. Therefore, the water application
efficiency has been considered as 85% for telescopic pressurised irrigation system followed by
sprinkler irrigation method upto 0.60 to 1.20 hectare chak for all crops. Sprinkler irrigation is a
method of applying irrigation water which is similar to natural rainfall. This method is more
effective in application of irrigation water to the crop than conventional method. The loss of
water in conveyance system i.e. telescopic pipe and micro distribution network etc. is
considered and is almost zero.
Irrigation Demand
Month Jun July Aug Sep Oct Nov Dec Jan Feb Mar Apr May Total
Irrigation
Demand 7.0 1.0 1.8 1.6 0.0 36.6 20.2 16.5 15.4 3.4 0.0 0.0 103.5
in
MCUM
91
Command area planning on the basis of simulation studies
Command area of the proposed barrage has been planned on the basis of water
availability for utilization computed by simulation study. The CCA, Annual Irrigation, water
utilization details are furnished in Table-30
Classification of land (forest, grass land, cultivable and, cultivable waste, barren
land)
Table - 31: land use particulars in Upper Betwa command (Unit: Ha)
Type of land Vidisha
District
Forest land 0
Fallow land 52
The size of land holding and area in the districts lying in the command area of 4
barrages during the year 2005-06 is given in Table-32.
92
Table – 32 : Size of land holding in the command area of Upper Betwa barrages
Description Vidisha
No. Area
(a) Rainfall: The command area receives most of its rainfall during the monsoon from
July to September from the southwest monsoon.
The coefficient of variation in annual rainfall is appreciable i.e. 22.05. The maximum and
minimum rainfall in the area is 1700 mm to 600 mm respectively.
(b) Temperature: The climate of the area is characterized by a hot
summer and a mild winter. The climate is hot during summer with the temperature as high as
450C.
(c) Relative humidity: The mean monthly relative humidity observed at Bhopal IMD
observatory, which is close to the command area varies between 22% to 78%.
(d) Wind velocity: The monthly mean wind velocity observed at Bhopal IMD
observatory varies between 6.9 km/hr to 19.4 km/hr.
Irrigation
Socio-economic aspects
M/s Agricultural Finance Corporation Limited, Hyderabad has carried out studies
for socio-economic aspects in the command area of kotha barrage. The same is reproduced in
Table-33.
94
Infrastructure facilities
(c) Agro-industries
No major agro-based industries are available within the command. However, few
oil mills and flour mills are located in the command which cater to the needs of command
people.
(d) Banks/credit societies etc.
Nationalized Banks are exists at district head quarters and tehsils and also in
selected locations of command area with extended banking facilities. Also, numbers of Gramin
Banks are functioning in rural areas.
(i) Topography
Isolated hill tops, valleys, forests and streams are dominating in the area. Coarse
grained formations are predominantly found in the command area.
(ii) Land slopes
The slopes of the land in the command area are moderate and in few places it is
steep.
(iii) Soils
Based on the information provided by National Bureau of Soil Survey and Land
Use Planning (ICAR), Nagpur, the soils in the command area can be broadly classified into three
categories. They are soil in hills and hill ranges, plateau soils, pediment soils, soils of level
alluvial plain and undulating flood plain and soils of dissected flood plan. Details are given
below:-
1. Deep, moderately well drained, clayey soils on very gently sloping plain land with
moderate erosion, associated with Deep, moderately well drained, calcareous, clayey soils on
very gently sloping with moderate erosion.
95
2. Deep, moderately well drained, clayey soils on very gently sloping plains with
valleys with valleys with moderate erosion, associated with: Deep, moderately well drained,
calcareous, clayey soils on very gently sloping with moderate erosion.
3. Shallow, well drained, loamy soils on gently sloping undulating upland with hummocks
with moderate erosion, associated with Very shallow, somewhat excessively drained, loamy
soils on moderately sloping with severe erosion.
Drainage
The command area has good surface drainage and sub-surface drainage. The
water holding capacity being low to medium is expected in clay patches. With the network of a
number of tributaries namely Newman, Sagar, Bah, Keotan etc., the command area has quite
good draining facilities.
Agriculture
The classification of lands and the present land use has already been discussed in
the chapter. Land use will change due to increase in cultivated area and increase in
developmental activities due to this project.
96
including inadequate financial resources, the extension services are yet to become popular
among the farmers of proposed command area.
(a) Land slopes: the land is generally undulating; therefore, canal distribution
system has to be aligned accordingly.
(b) Soil depth: There should be no problem on this account, as sufficient soil depth
is available in the area for providing canal irrigation.
(c) Salinity/Alkalinity: Since the waters of Betwa river and its tributaries are
proposed to be used for irrigation in these areas, which do not have salinity
problem, it need not be a cause of concern. However, slight alkaline nature of
the soils of the region is considered rather suitable for crops like Jowar,
Soyabean, Wheat and Moong.
In general, the soils in these areas are stable and not prone to erosion. However, in
certain area, the soils may be prone to erosion due to their coarse texture. Such soils can be
stabilized by putting them under permanent pastures and grazing lands.
(d) Water logging: No water-logging problem of serious nature has been reported from the
area.
(e) Drainage: Looking the general condition and topography of the command, special care
should be taken for construction of field channels and drainage, which can be managed by the
Agricultural Department at farmer’s cost or loans from the various land development banks.
Financial problems
There are number of wells and tanks in the area but due to less recharge in the area,
these wells and tanks either have less water or no water during lean season. Farmers should be
provided fund assistance for renovation of these tanks and wells for better irrigation.
Proposed cropping pattern, with justification based on land irrigability classification, agro
climatic conditions developed irrigated cropping pattern in adjoining project/area etc.
Proposed cropping pattern for kotha barrage has been supplied by Govt. of Madhya Pradesh in
consultation with Agriculture Department of Govt. of Madhya Pradesh and same has been
considered in the study.
A provision has been kept in the estimate for land development works. At the time of
implementation of the project, detailed survey of each command will be done and based on the
97
requirement, land development works will be taken up. This work will be done by state
Irrigation Department or state Agriculture Department or Command Area Development
Authority (to be decided by State Government).
At present, fairly good extension services exists in the command area and number of
commercial banks and co-operative banks have their branches there. Branches of land
development banks are also located in some rural areas of the command. Moreover, the
agricultural materials like seeds, fertilizers, insecticides, pesticides etc. are provided to the
farmers by the concerned government department at subsidized rates through different sale
booths or fair price shops. However, due to numerous reasons, especially inadequacy of
financial resources, extension services have not yet become very popular.
Ayacut roads
Benefits
(i) Crop wise increase in yield per Ha and total estimated output from the
command
The crop wise yield in pre & post project scenarios for proposed barrage is
furnished in Annexure.
(ii) Estimated cost of increased production
The yield in pre and post project scenarios have been assessed in Annexure.
Based on the increased production cost of increased production has been assessed in
Annexure .
(iii) Likely socio-economic aspects
Due to increase in food grain production, the socio-economic condition of farmers will
improve in general. Agricultural labourers will get employment in the nearby area.
Situation livestock will improve. Farmers will try to establish agro-based industries in
the area.Error! Not a valid link.
98
Table - 34: Benefit cost ratio
GOVERNMENT OF MADHYA PRADESH
WATER RESOURCES DEPARTMENT
KOTHA BARRAGE PROJECT
(Rs. In Lakhs)
BC Ratio Calculation
S. Item Before After
No. Irrigation Irrigation
1 Gross Receipt
(i) Gross value of farm produce 10601.09 59240.00
(ii) Dung receipts (at 30% of the fodder expenditure) 477.05 1777.20
Total Gross Receipts (1) = (i+ii) 11078.14 61017.20
2 EXPENSES
(i) Expenditure on Seeds 514.04 827.50
(ii) Expenditure on Fertilizers,Chemicals etc. 857.88 1675.00
(iii) Expenditure on hired labour (human, animal & machinery) 590.00 2775.00
& Misc
(iv) Expenditure on Pumping system 2283.90
(v) Expenditure on Rising Mains 9458.69
(vi) Expenditure on Solar Power System for Lift 4800.00
(vii) Fodder expenses (as percentage of gross value of produce)
a) 15% Gross value of farm produce before irrigation 1590.16
b) 10% Gross value of farm produce after irrigation 5924.00
(viii) Depreciation on implements at 2.7% of the gross value of 286.23 1599.48
farm produce
(ix) Share and Cash Rent
a) 5% Gross value of farm produce before irrigation 530.05
b) 3% Gross value of farm produce after irrigation 1777.20
(x) Land Revenue at 2% of gross value of farm produce 212.02 1184.80
Total Expenses (2) = (i+ii+iii+iv+v+vi+vii+viii+ix+x) 4580.38 32305.57
3 NET VALUE OF PRODUCE
(i) Total Gross receipts (Total 1) 11078.14 61017.20
(ii) Total Expenses (Total 2) 4580.38 32305.57
Net value of produce (3) = (i-ii) 6497.76 28711.63
4 ANNUAL BENEFITS
(i) Net value after irrigation (3) 28711.63
(ii) Net value before irrigation 6497.76
from Irrigation 22213.87
(iii) from Fish production 212.55
(iv) from Power production (Being incidental, not considered) 0.00
(v) from Water Supply 0.00
a) Domestic 0.00
b) Industrial 0.00
99
Net Annual Benefits (4) = (i-ii)+(iii)+(iv) 22426.42
5 COST OF PROJECT
(i) Estimated cost of the Project 81453.00
(ii) Cost of land development 4000.00
Total 85453.00
6 ANNUAL COSTS
(i) Interest on capital @ 10% (Estimated total cost of the project 8545.30
including cost of land development)
(ii) Depreciation of the project @ 1% of the cost of project for 1709.06
100 years life of the project and @ 2% for 50 years life of the
project
(iii) Annual operation and maintenance charges 235.00
(iv) Maintenance of the head works @ 1% of H/W cost less B 413.72
Land
(v) Depreciation of the pumping system @ 8.33% of the 190.25
estimated cost of the pumping system assuming life of the
system as 12 years (Applicable to lift irrigation)
(vi) Depreciation of the rising mains @ 8.33% of the estimated 787.91
cost of the rising mains assuming life of the system as years
(Applicable to lift irrigation)
100
Chapter -VI
Estimates
Unit – I : HEAD WORK : (Barrage )
A. Preliminary :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for the
investigations required for the execution of the works. This covers mainly the drilling work,
excavation of trenches, construction material survey, topographical survey, consultancy
charges, 3D Model study/ testing, Property survey coming under submergence fully/ partially
and other works.
B. Land :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for
payments against compensation of private land required for construction of Barrage, Telescopic
pipes, pump houses and solar panels and other Property coming under submergence fully/
partially.
C. Works :
A provision of Rs 172.25 Crore has been made under this sub head for construction of Barrage
& construction of the all components including grouting works of Rs 1.00 crore in central
portion and dykes & guide bunds
G. Bridges :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for the
construction of high level bridge in submergence in Betwa river at needy intervals to facilitate
people commutation.
K. Buildings :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for
construction of Non‐residential / residential buildings conference room & Store sheads.
M. Plantation :
A provision of Rs. Error! Not a valid link. Crore has been made under sub head for plantation
works which are required at Pump Houses & at government Land wherever available.
O. Miscellaneous :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head to cover the
expenditure on signboard, advertisement, display board, maintenance and cost of
electrification, recreation facilities, security arrangements and medical facilities. The provision
for laying foundation stone & inauguration ceremony visit of dignitaries during construction
period has also been made under this sub head.
P. Maintenance :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for
101
maintenance of works like Barrage, colony, pump houses & telescopic pipe system.
R. Communication :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for
the construction of adjoining existing national highway 5 km from Mandi Bamora which are
required to facilities the construction works.
UNIT – II : Canals :
A. Preliminary :
A provision of Rs. 0.64 Crore has been made under this sub head for the survey and
investigation works required for the Left & right Bank telescopic Pipe network. The main items
covered under this sub head are command area survey, alignment survey and excavation of
trial pits etc.
B. Land :
A provision of Rs 0.75 Crore are made under this sub head for the acquisition of private
land required for construction of canals in deep cutting.
C. Works :
A provision of Rs Error! Not a valid link. Crore has been made under this sub head.
D. Regulator :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head.
E. Fall :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head.
G. Bridges :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head.
K. Buildings :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head
for construction of residential, non‐residential buildings conference room & stores shad near
distributaries outlets
L. Earth Work :
A provision of Rs. 117.43 Crore has been made under this sub head for the earth
works, cost of telescopic M.S. Pipe network with all accessories.
102
M. Plantation :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head.
O. Miscellaneous :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head.
P. Maintenance :
A provision of Rs. 1.67 Crore has been made under this sub head for the maintenance
of works during construction period.
R. Communication :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for
the construction of adjoining existing village roads which are required to facilities the
construction works.
T. Water Supply :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head.
X. Environment :
A provision of Rs. Error! Not a valid link. Crore has been made under this sub head for
implementation of environment management plan if felt necessary
Abstract given below:
S. Solar Power :
The cost of solar panels and solar power is included in this head and worked out to be
Rs. Error! Not a valid link. crore at USR-2016 price level.
103
General Abstract of Cost of Kotha Barrage
figures are Rs in Crore.
S.No. Subhead Unit-I Unit-II Unit-III Total
1 A-Preliminary 1.06 0.64 0 1.70
2 B- Land 229.40 0.75 0 230.15
3 C-Works 172.25 0.00 0 172.25
4 D-Regulator 0.00 0.00 0 0.00
5 E-Fall 0.00 0.00 0 0.00
6 F-CD Works 0.00 0.00 0 0.00
7 G-Bridges 7.00 0.00 0 7.00
8 K-Building 0.20 0.20 0 0.40
9 L-Earth Work 0.00 117.43 0 117.43
10 M-Plantation 0.50 0.00 0 0.50
11 O-Misc. 1.00 0.00 0 1.00
12 P-Maintenance 1.06 1.67 0 2.73
13 Q- Special T & P 0.00 0.00 0 0.00
14 R-Communication 1.00 1.50 0 2.50
15 S-Power plant for 8MW @ 0.00 0.00 48 48.00
Rs 6 Cr/MW
16 T-Water Supply 0.00 0.00 0 0.00
17 U- Distributory & Minors 0.00 215.00 0 215.00
up to 1.2 to 0.6 Ha
18 'X'-Environment 0.25 0.00 0 0.25
Total 413.72 337.19 48.00 798.91
Add 3% Establishment 5.53 10.09 0 15.62
except “B” land and
“S” Power Plant
Total Cost 419.25 347.28 48.00 814.53
104
105