You are on page 1of 5

PROCEDURE FOR ESTIMATION OF RATE FOR ITEM NO 1001

Estimation of rate for this item has to be done as per the following procedure;

1) Based upon geotechnical investigations, ascertain type of soil (A/B1/B2/C) available locally along the alignment in different stretches
of earthwork in filling (not longer than a block section).
2) Decide upon the type of soil to be used in earth fill and prepared subgrade for each stretch.
3) Workout leads for soil to be used in earth fill and prepared subgrade for each stretch separately.
4) Workout quantity of earthwork required in earth fill and in prepared subgrade for each stretch separately.
5) Workout weighted average lead for soil to be used in earth fill and in prepared subgrade for entire package separately.
6) Use this average lead and cost of soil to work out the rate as per standard rate analysis for item no. 1001 separately for earth fill and
prepared subgrade.
7) Workout weighted average per cum rate of earthwork for item no. 1001 based on total quantities of earthwork in earth fill and prepared
subgrade and respective rates.
8) Required quantities of blanketing material (under BOQ item no. 1005) may also be worked out from blanket thickness required for
each stretch depending upon the type of soil used in fill and prepared subgrade.Example-1 may be followed for such cases.
9) In cases where only ‘C’ group soil is locally available and lead/cost of soils required in prepared subgrade is high then estimation of
rates may be done as per Example-2.
10) For better appreciation, two typical examples are given below;
EXAMPLE-1

Stretch Earthwork in Earth fill Earthwork in Prepared Subgrade Blanket


Thickness
in mm
From To Km Soil Qty in Cum Average Qty X Lead Soil Qty in Cum Average Qty X Lead
Km typ Lead in type Lead in
e Km Km
(1) (2) (3) (4) (5) (6)=(4)x(5) (7) (8) (9) (10)=(8)x(9 (11)
)
101 110 B1 300000 3 900000 B1 26425 3 79275 150
110 115 A 110000 2 220000 A 19625 2 39250 0/150*
115 120 B1 180000 2 360000 B1 13213 2 26426 150
120 132 B2 360000 4 1440000 B1 31710 8 253680 150
132 140 B2 240000 3 720000 A 31400 8 251200 0/150*
140 145 A 150000 2 300000 A 19625 2 39250 0/150*
145 150 C 120000 2 240000 A 19625 6 117750 0/150*
150 160 C 300000 2 600000 B1 26425 5 132125 150
      1760000   4780000   188048   938956  
= ([TOTAL OF COLUMN (6)]/ = ([TOTAL OF COLUMN (10)]/
Average weighted Lead (Km) 2.72   4.99
[TOTAL OF COLUMN (4)]) [TOTAL OF COLUMN (8)])
 

* - No separate Blanket layer to be provided if available A group soil is having CBR value of more than 25 otherwise blanket layer of 150 mm to be provided.
Total Qty Average Rate per cum Weighted
Item Remarks
(Cum) Lead (Km) (as per Std AOR) Cost

Earth-fill 1760000 2.72 226 397760000 Cost of earth assumed @ Rs. 75 per cum

Prepared Subgrade 188048 4.99 251 47200048 -do-

Total 1948048     444960048  

Weighted Rate for


item no. 1001 228.4
(Rs./Cum)
EXAMPLE-2

Stretch Earthwork in Earth fill Earthwork in Prepared Subgrade Blanket


Thickness in
mm
From Km To Km Soil type Qty in Cum Average Qty X Lead Soil Qty in Average Qty X Lead
Lead in Km type Cum Lead in
Km
(1) (2) (3) (4) (5) (6)=(4)x(5) (7) (8) (9) (10)=(8)x(9)  
201 240 C 1040000 2 2080000 A 157000 40 6280000 0/150*
240 260 C 600000 2 1200000 B1 52850 12 634200 150
      1640000   3280000   209850   6914200  
= ([TOTAL OF COLUMN (6)]/
Average weighted Lead (Km) 2.0  
[TOTAL OF COLUMN (4)])

* - No separate Blanket layer to be provided if available A group soil is having CBR value of more than 25 otherwise blanket layer of 150 mm to be provided.

Rate per
Total Qty Average cum (as
Item Weighted Cost Remarks
(Cum) Lead (Km) per Std
AOR)
Earth-fill 1640000 2 218 357520000 Cost of earth assumed @ Rs. 75 per cum
Prepared Subgrade
157000 40 598 93886000 Cost of earth assumed @ Rs. 160 per cum
with A group soil
Prepared Subgrade
52850 12 313 16542050 Cost of earth assumed @ Rs. 75 per cum
with B1 group soil
Total 1849850     467948050  

Weighted Rate for 253


item no. 1001
(Rs./Cum)

You might also like