MARGALLA BUILDING ISLAMABAD

GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT

JANUARY 2015

Client / Owner | Telenor Pakistan (Pvt.) Ltd. General Contractor | Paragon Constructors (Pvt.) Ltd.
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

REPORT CONTENT
1. PROJECT OVERVIEW AND EXECUTIVE SUMMARY
2. HEALTH & SAFETY
3. SITE CONDITIONS
4. PROGRESS UPDATE
4.1 FINANCIAL PROGRESS
4.2 PHYSICAL PROGRESS
5. DELAYS ENCOUNTERED
5.1 DELAYS AND VARIATIONS
5.2 IMPACT ON PROGRAMME
6. EARLY WARNINGS, VARIATIONS AND CLAIMS
7. STATUTORY APPROVALS & SIGNOFF’S
8. RESOURCE DEPLOYMENT
9. SUBMITTALS AND SHOP DRAWING STATUS AND RFI LOG

Annexure I - Construction schedule with progress update


Annexure II - Submittals and Shop Drawings Status
Annexure III - Request for Information (RFI) Log
Annexure IV - Resource Deployment Status

Client / Owner | Telenor Pakistan (Pvt.) Ltd. General Contractor | Paragon Constructors (Pvt.) Ltd. 1
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

1.0 PROJECT OVERVIEW & EXECUTIVE SUMMARY


PROJECT OVERVIEW

Project Margalla Building

Location Gulberg Greens, Islamabad

Client / Owner Margalla Building (Pvt.) Limited /


Telenor Pakistan

Architect ARCOP (Pvt.) Limited

Structural Consultant Mushtaq& Bilal

MEP Consultant S. Mehboob & Company

Environmental and Sustainability CP Green


Consultant
General Contractor Paragon Constructors (Pvt.) Ltd.

Date of Commencement 20-May-2014


Original Completion Date 3-Jul-2016

Completion Date after 70 day EOT 12-Sep-2016


Original Contract Value PKR 3,944,988,440

EXECUTIVE SUMMARY

The construction activities during the month of January 2015 primarily included steel reinforcement
and concreting for columns and retaining walls in parking building and block C, backfilling, lean
concreting, waterproofing, steel reinforcement fixing and concreting of SOGs in Blocks A, B, C and E.
Roof slabs were poured in the parking building and preparation for water body 1 and 2 slabs was
substantially progressed.

The financial progress achieved was 11.52% against planned 13.02%. Various structural works
particularly in main building have been on hold due to pending design issues. Construction of
underground tanks and boundary wall was also delayed due to pending or delayed issuance of
construction drawings. The MS Tower also remains on hold due to re-design.

The general contractor’s resource deployment was sufficient for planned activity including
machinery and human resource with recent additions to the technical team as well as addition in
formwork and concrete pump deployed at site.

Client / Owner | Telenor Pakistan (Pvt.) Ltd. General Contractor | Paragon Constructors (Pvt.) Ltd. 2
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

2.0 HEALTH & SAFETY

No accidents or safety incidents occurred on site during the reporting period.

Scheduled tool box talks and regular safety inspections were carried out.

Personal protective equipment (PPE) and required signage is in place. The shortfall due to new
deployment or damage has been replaced as per requirement. While majority of the PPE and
precautions are in place additional efforts are required to encourage use of safety wear by the
labour.

3.0 SITE CONDITIONS

The weather and site conditions generally remained suitable with the exception of occasional rain
which had a minor impact on progress.

4.0 PROGRESS UPDATE

Physical progress achieved – Refer to section 4.2 for details of work done.
Financial progress achieved – 11.5%. Refer to section 4.1 for details.

While a few activities including the sub-structure works and underground storm water retention
tank has progressed well and are ahead of the programme, due to the delays encountered primarily
related to the delayed responses on shop drawings and RFI’s the projected completion timelines of
the milestones and the overall completion date has been delayed as presented below.

MILESTONES PLANNED PROJECTED PROJECTED REASON


COMPLETION COMPLETION DELAY
UG Parking grey structure 25-Apr-2015 19-Jul-2015 85 days Refer to section 5
Main office building up to SOG 25-May-2015 06-Jul-2015 42 days Refer to section 5
including drainage
Main office building grey 09-Feb-2016 29-Mar-2016 49 days Refer to section 5
structure
MEP installations 29-May-2016 16-Jul-2016 48 days Refer to update schedule
External Development 07-Aug-2016 25-Sep-2016 49 days Refer to update schedule
Project Hand over 12-Sep-2016 04-Nov-2016 53 days Refer to update schedule

The financial production loss due to the delays is indicated in section 5.

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

4.1 FINANCIAL PROGRESS

The cumulative financial progress achieved by end of January 2015 was 454.37 million against a
target of 513.71 million. Majority of the shortfall in the financial progress achieved is due to held up
works due to design reasons which are explained in section 5 of the report.

Cumulative Cumulative Monthly Monthly


Timeline Financial Target Achieved Target (PKR Achieved
(PKR Million) (PKR Million) Million) (PKR Million)
May
June
July 35.91 35.91
August 73.71 37.8
2014

September 119.9 119.90 46.19


October 166.36 160.00 46.46 40.10
November 261.68 242.59 95.32 82.59
December 382.12 346.96 120.44 104.37
2015

January 513.71 454.37 131.59 107.41

4.2 PHYSICAL PROGRESS

The physical progress achieved in the various areas is presented below. While the physical progress
is on target for the sub-structure activities, the delays as described in section 5 of the report have
had an impact on the super structure works particularly in Blocks A and C. Please refer to schedule in
Annexure 1 indicating the progress and impact of delays on programme as currently projected.

TEMPORARY FACILITIES / PRELIEMINARIES


1 Temporary Site Fencing 100%
2 Client's Site Office 100%
3 Contractor's Site Office 100%
4 Batching Plant and Tower Cranes 100%
5 Labour Colony 100%
6 Workshops 100%
7 Steel Yard 100%
8 Staff Residence 100%
9 Truck Tire Wash 100%

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

PARKING BUILDING
1 Excavation 100%
2 Foundations 100%
3 Retaining Wall Level B2 98%
4 Columns Level B2 69%
5 Lower Basement Slab B2 15%

Parking Building Structural works and slab reinforcement in progress

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

BLOCK A
1 Excavation 100%
2 Pile Caps 100%
3 Stone Ballast 65%
4 Lean under SOG 60%
13 SOG 40%

Block A SOG preparation in progress

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

BLOCK B
1 Excavation 100%
2 Pile Caps 95%
3 Stone Ballast 92%
4 Lean under SOG 92%
13 SOG 92%

Block B SOG reinforcement in progress

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

BLOCK C & D LOWER GROUND


1 Excavation 100%
2 Pile Caps 98%
3 Stone Ballast 96%
4 Lean under SOG 96%
5 SOG 96%
6 Retaining Wall 45%
7 Columns 40%

Block C Lower Ground Structural Works in Progress

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

BLOCK D GROUND FLOOR


1 Excavation 100%
2 Pile Caps 100%
3 Stone Ballast 40%
4 Lean under SOG 40%
13 SOG 0%

Block D SOG preparation in progress


BLOCK E
1 Excavation 100%
2 Pile Caps 100%
3 Stone Ballast 75%
4 Lean under SOG 75%
13 SOG 40%

Block E SOG reinforcement in progress

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

BLOCK F
1 Excavation 100%
2 Pile Caps 100%
3 Stone Ballast 75%

Block F sunken slab reinforcement completed

WATER BODY 1
1 Excavation 100%
2 Pile Caps 100%
3 Ground Beams 100%
4 Backfill and Lean 100%
5 Slab Reinforcement 100%

Water body 1 slab reinforcement completed

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

WATER BODY 2
1 Excavation 100%
2 Pile Caps 100%
3 Ground Beams 100%
4 Backfill and Lean 25%

Water body 2 backfilling and lean concrete in progress

WATER BODY 3
1 Excavation 100%
2 Pile Caps 75%
3 Backfilling 70%

MS Tower foundation pending concreting due to design variation

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

UG STORM WATER TANK


1 Excavation 100%
2 Base Slab 100%
3 External Walls 100%

UG Storm water tank external wall concreting completed

5.0 DELAYS ENCOUNTERED

The following delays have been encountered to-date beyond the 70 day EOT which have had an
impact on the construction programme;

ACTIVITY DELAY IMPACT REASON FOR DELAY


UG Parking Basement Columns
Change in design (tender vs.
Columns put on hold 28th October 2014 construction drawing) - inclusion of
Columns concreting re-start 11th December 2014 groove in columns and quality
Delay Impact 48 days concern.

Inclusion of Contraction Joint and reduction in Pour


Segment Length Change in design detail (tender vs.
construction drawing) - inclusion of
contraction joint and variation in
Planned Pours @54m length 8 no. pours
approved methodology for wall
Revised Pours @18m length 24 no. pours
pours.
Planned Duration 57 days

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

Revised Duration @18m pour


length x 2 per week. 76 days
Wall activity on hold for detail
revision. 10 days
Delay Impact 29 days

RFI Response Delay - Slab pour on hold due to staircase.

RFI Generated 19th January 2015


Response Due (7 days) max. 26th January 2015 Delay in RFI Response
Delay Impact as of 10th February
2015 16 days

Collection Tank

Planned Start 8th November 2014


Delay in drawing
Drawing required (latest) 4 weeks
prior to start. 8th October 2014
Delays as of 10th February 2015 122 days

Domestic Water Tank

Planned Start 13th January 2015


Delay in drawing
Drawing required (latest) 4 weeks
prior to start. 13th December 2014.
Delays as of 10th February 2015 57 days

MS Tower
Planned Start 1st January 2015
Drawing required (latest) 4 weeks Delay in drawing
prior to start. 1st December 2014
Delays as of 10th February 2015 69 days

Boundary Wall

Planned Start 26th November 2014


Drawing required (latest) 4 weeks
prior to start. 26th October 2014 Delay in drawing
Drawing Issued 20th January 2014
Delay Impact 83 days

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

Block A, GF SOG - Shop drawing response delay

Shop Drawing for Fire Suppression


and Water Supply Submitted 5th December 2014
Delay in shop drawing response
Response Due 20th December 2014
Delays as of 10th February 2015 52 days

Block C, GF SOG and Retaining Wall on Hold - Shop drawing response delay

Planned Start (concreting) 1st January 2015


Domestic Water Tank and
Retaining Wall Design Delay
Delay in drawing
Drawing required (latest) 4 weeks
prior to start. 1st December 2015
Delays as of 10th February 2015 100 days

Shop Drawing for Fire Suppression


and Water Supply Submitted 5th December 2014
Delay in shop drawing response
Response Due 20th December 2014
Delays as of 10th February 2015 52 days

Other hold ups for Block C


Retaining wall include the
following; Delay in shop drawing and RFI
1. Access Control RFI response
2. MEP Shop drawings for GF,
Block C.

Block D, GF SOG - Shop drawing response delay

Shop Drawing for Fire Suppression


and Water Supply Submitted 5th December 2014
Delay in shop drawing response
Response Due 20th December 2014
Delays as of 10th February 2015 52 days

Block F, GF SOG - Shop drawing response delay


Shop Drawing for Fire Suppression
and Water Supply Submitted 5th December 2014
Delay in shop drawing response
Response Due 20th December 2014
Delays as of 10th February 2015 52 days

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

The production loss due to the hold up till 30th of January 2015 is presented below;

FINANCIAL PROGRESS VARIATION DUE TO HOLD UP / DESIGN DELAYS

S.No. Activity Value (PKR million )

1 Block A Ground Beams & SOG 1.5


2 Block C Retaining Wall 25% 1.2
3 Block F Ground Beams & SOG 3
4 Water Body 3 Ground Beams & SOG 4.5
5 Domestic Water Tank 3
6 Diesel Tanks (2 nos.) 1
7 Sewerage Tank (Collection Tank) 2
8 UG Tank Steel Reinforcement 4.6
9 Boundary wall structural works for 250m length. 2.5
10 Rammed earth on boundary wall for 100m length. 1.75
11 Retaining wall in mechanical yard 0.7
12 MS Tower (30%) 8
Total 33.75

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

6.0 EARLY WARNINGS, VARIATIONS & CLAIMS


EARLY WARNINGS

The following issues unless are timely resolved may result in delay and subsequent financial
implications;

 The boundary wall design for wall along the Malal Kas River is being revised. This segment of
the boundary wall will be re-scheduled accordingly.
 Drawings for the domestic water tank and the retaining wall are pending. The tank activity
has been delayed which had been prioritized for completion prior to monsoon rains.
Adjacent structural works in block C (retaining wall and SOG) have been put on hold and
therefore has a subsequent impact on the schedule of this critical area.
 The shop drawings for the MS Tower were submitted on the 2nd of December 2014 and have
been on hold since due to re-design.
 Pending RFI responses marked critical in the RFI log attached in annexure III are holding up
construction activity and will result in delay.
 The following construction drawings have not been issued. Drawings marked critical are
required immediately as they are holding up site activities.

Domestic Water Tank and Mechanical Yard Drawings – Architecture and Structure
(CRITICAL) – ACTIVITY ON HOLD
Storm Channel Detail X-15 and X-15.1 (CRITICAL)
Expansion Joint Details - X-6.81, X-6.82 and X-6.83 (CRITICAL) – ACTIVITY ON HOLD IN
PARKING BASEMENT
MS Tower Revised Drawings – Architecture and Structure.
Roof Details – X7
Wall Type 10 and 11 – X-12.1
Block C Lower Ground Floor Ceiling Plan – A2 003
Block D Lower Ground Floor Ceiling Plan – A2 013
Handicapped Toilet 2 – A8 018
Handicapped Toilet 3 – A8 019
W Series – W-000, W-100, W-200, W-300 and W-400. (5 nos.)
W Series – W22 to W39 (18 nos.)

VARIATIONS & CLAIMS

The following list includes the variations and claims along with status of notification which have
occurred to date.

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

Formal
Time Financial Notification &
S.No. Description of Variation Notice
Impact Impact Early warnings.
Issued
1 Adjustment for change in legislation x  N/A Yes
Inclusion of horizontal groove in UG
2 Parking Columns.   Yes Yes
Addition of Expansion joint in UG
3 Parking   No Yes
Addition of D-Type Column in UG
4 Parking x  No Yes
Incorporation of contraction joint in
5 retaining wall at 18m spacing.  x Yes Yes
RFI Response delay for Staircase in
6 UG Parking  x Yes No
Column size variation in Main office
building at Ground Floor from
7 600mm dia. to 450mm dia.   No Yes
8 UG tank level confirmations  x Yes No
Domestic Water Tank revised and
9 design awaited.  x Yes Yes
10 Boundary Wall design revised.  x Yes Yes
11 Rammed Earth Variations: Yes
- Inclusion of admixtures SBA and
a Crystalline admixture. x  Yes Yes
b - Inclusion of white cement x  Yes Yes
- Variation in mix design with
c inclusion of site soil.  x Yes Yes
Central Vacuum system: GC made
responsible for delivery of detail
design resulting in delays as well as
12 addition power provisions.   Yes Yes
MS Tower revised and design
13 awaited.  x Yes Yes
Boundary wall along Malal Kas river is
revised and design solution is
14 awaited.  x Yes Yes
Construction drawings not issued (50
15 nos.)  x Yes Yes
16 Delayed response to submittals.  x Yes No
17 Delayed response to shop drawings.  x Yes No
18 Delayed response to RFI's  x Yes No
19 Delayed response to BBS.  x Yes No

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

7.0 STATUTORY APPROVALS & SIGNOFF’S

No formal approvals were obtained.

Inspection requests were submitted to IBECH’s for 6 areas along with attachments including
progress status and relevant sketches on the 5th of January 2015. Inspection by the survey team of
IBECHS is awaited.

8.0 RESOURCE DEPLOYMENT

The resource deployment status is attached in Annexure IV.

9.0 SUBMITTALS AND SHOP DRAWINGS SCHEDULE AND RFI LOG

The submittals and shop drawing status is presented in Annexure II. The RFI log is attached in
Annexure III.

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

ANNEXURE I

Construction Schedule with Progress Update

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Construction of Margalla Building, Islamabad648 13-May-14 A 04-Nov-16 13-May-14 12-Sep-16

PRELIMINARIES 838 13-May-14 A 04-Nov-16 13-May-14 03-Jul-16


A1620 45 Mobilization & Layout 20-May-14 A 31-Aug-14 A 20-May-14 01-Jul-14 Mobilization & Layout
A1710 0 Date of Commencement 20-May-14 A 20-May-14 A 20-May-14 20-May-14 Date of Commencement
A1630 0 Contract Agreement 13-May-14 A 13-May-14 Contract Agreement
DELAY EVENTS 24 04-Jul-14 A 12-Sep-14 A 01-Jul-14 25-Jul-14 12-Sep-14 A, DELAY EVENTS
Agreed EOT with Telenor for excusable Delays 24 04-Jul-14 A 12-Sep-14 A 01-Jul-14 25-Jul-14 12-Sep-14 A, Agreed EOT with Telenor for excusable Delays
A8820 0 DELAY START 04-Jul-14 A 01-Jul-14 DELAY START
A8890 24 DELAY IMPACT 04-Jul-14 A 12-Sep-14 A 01-Jul-14 25-Jul-14 DELAY IMPACT
A8810 0 DELAY END 12-Sep-14 A 25-Jul-14 DELAY END
PROJECT MILESTONES 775 20-May-14 A 04-Nov-16 20-May-14 03-Jul-16
MILESTONE # 1 341 20-May-14 A 19-Jul-15 20-May-14 25-Apr-15 19-Jul-15, MILESTONE # 1
A8150 341 Underground Parking grey structure including
20-May-14
waterAproofing
19-Jul-15
and backfill
20-May-14 25-Apr-15 Underground Parking grey structure including water proofing and backfill
MILESTONE # 2 299 20-May-14 A 06-Jul-15 20-May-14 14-Mar-15 06-Jul-15, MILESTONE # 2
A8160 299 Main Office Building up to and including 20-May-14
slab on ground,
A 06-Jul-15
drainage etc. 20-May-14 14-Mar-15 Main Office Building up to and including slab on ground, drainage etc.
MILESTONE # 3 558 20-May-14 A 29-Mar-16 20-May-14 28-Nov-15 29-Mar-16, MILESTONE # 3
A8220 558 Main Office Building grey structure, masonry,
20-May-14
roof water
A 29-Mar-16
proofing, screed
20-May-14 28-Nov-15 Main Office Building grey structu
MILESTONE # 4 671 20-May-14 A 16-Jul-16 20-May-14 20-Mar-16 16-Jul-16, MILE
A8190 671 All MEP Installations, mechanical completion
20-May-14
excluding
A Testing
16-Jul-16
and Commission
20-May-14 20-Mar-16 All MEP Installat
MILESTONE # 5 741 20-May-14 A 25-Sep-16 20-May-14 29-May-16 25-Se
A8200 741 All Outdoor works including retaining walls,
20-May-14
security A
fence,
25-Sep-16
civil works and
20-May-14
lighting etc.29-May-16 All Out
MILESTONE # 6 775 20-May-14 A 04-Nov-16 20-May-14 03-Jul-16
A8210 775 Handover of complete building 20-May-14 A 04-Nov-16 20-May-14 03-Jul-16
GATE WAY ANALYSIS MEETING 475 12-Feb-15 30-Apr-16 18-Sep-14 30-Apr-16 30-Apr-16, GATE WAY ANA
A5190 0 7TH GATE WAY ANALYSIS MEETING 30-Apr-16* 30-Apr-16 7TH GATE WAY ANALYSIS
A5180 0 6TH GATE WAY ANALYSIS MEETING 05-Dec-15* 05-Dec-15 6TH GATE WAY ANALYSIS MEETING
A5170 0 5TH GATE WAY ANALYSIS MEETING 05-Oct-15* 05-Oct-15 5TH GATE WAY ANALYSIS MEETING
A5160 0 4TH GATE WAY ANALYSIS MEETING 03-Jul-15* 03-Jul-15 4TH GATE WAY ANALYSIS MEETING
A5150 0 3RD GATE WAY ANALYSIS MEETING 09-Apr-15* 09-Apr-15 3RD GATE WAY ANALYSIS MEETING
A5140 0 2ND GATE WAY ANALYSIS MEETING 12-Feb-15* 25-Dec-14 2ND GATE WAY ANALYSIS MEETING
A5130 0 1ST GATE WAY ANALYSIS MEETING 12-Feb-15* 18-Sep-14 1ST GATE WAY ANALYSIS MEETING
MOBILIZATION 287 21-May-14 A 12-Feb-15 20-May-14 10-Sep-14 12-Feb-15, MOBILIZATION
BATCHING PLANT 15 05-Jul-14 A 09-Aug-14 A 13-Jun-14 27-Jun-14 09-Aug-14 A, BATCHING PLANT
A1650 15 INSTALLATION 15-Jul-14 A 09-Aug-14 A 13-Jun-14 27-Jun-14 INSTALLATION
A1640 0 ARRIVAL 05-Jul-14 A 13-Jun-14 ARRIVAL
TOWER CRANE 81 01-Oct-14 A 17-Nov-14 A 28-Aug-14 10-Sep-14 17-Nov-14 A, TOWER CRANE
A1670 15 INSTALLATION AND COMMISSIONING
01-Oct-14 A 17-Nov-14 A 28-Aug-14 10-Sep-14 INSTALLATION AND COMMISSIONING
A1660 0 ARRIVAL 01-Oct-14 A 28-Aug-14 ARRIVAL
MOBILE CONCRETE PUMP 0 16-Jun-14 A 16-Jun-14 A 20-May-14 20-May-14 16-Jun-14 A, MOBILE CONCRETE PUMP
A1680 0 ARRIVAL 16-Jun-14 A 20-May-14 ARRIVAL
LOADER 0 21-May-14 A 21-May-14 A 20-May-14 20-May-14 21-May-14 A, LOADER
A1690 0 ARRIVAL 21-May-14 A 20-May-14 ARRIVAL
TRANSIT MIXER 0 12-Feb-15 12-Feb-15 28-Aug-14 28-Aug-14 12-Feb-15, TRANSIT MIXER
A1700 0 ARRIVAL 12-Feb-15 28-Aug-14 ARRIVAL
28-Aug-14 A, ENGINEERING
ENGINEERING 0 21-May-14 A 28-Aug-14 A 28-Aug-14 28-Aug-14

SHOP DRAWINGS 0
SHOP DRAWING SUBMITTAL 0
SHOP DRAWING SUBMITTALS(CIVIL) 0
SHOP DRAWING SUBMITTALS(MEP) 0
SHOP DRAWING APPROVAL 0
SHOP DRAWING APPROVAL (CIVIL) 0
SHOP DRAWING APPROVAL (MEP) 0

Primary Baseline Remaining Work Milestone Page 1 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
ISSUANCE OF IFC DRAWINGS (STRUCTURE) 0 21-May-14 A 28-Aug-14 A 28-Aug-14 28-Aug-14 28-Aug-14 A, ISSUANCE OF IFC DRAWINGS (STRUCTURE)
A7320 0 MAIN BUILDING AND PARKING BUILDING
21-May-14 A 28-Aug-14 MAIN BUILDING AND PARKING BUILDING
A7330 0 EXTERNAL DETAILS 28-Aug-14 A 28-Aug-14 EXTERNAL DETAILS
ISSUANCE OF IFC DRAWINGS (MEP) 0 28-Aug-14 A 28-Aug-14 A 28-Aug-14 28-Aug-14 28-Aug-14 A, ISSUANCE OF IFC DRAWINGS (MEP)
A7380 0 PLUMBING 28-Aug-14 A 28-Aug-14 PLUMBING
A7400 0 HVAC 28-Aug-14 A 28-Aug-14 HVAC
A7420 0 FIRE PROTECTION 28-Aug-14 A 28-Aug-14 FIRE PROTECTION
A7390 0 ELECTRICAL 28-Aug-14 A 28-Aug-14 ELECTRICAL
A7410 0 BMS 28-Aug-14 A 28-Aug-14 BMS
ISSUANCE OF IFC DRAWINGS (ARCHITECURE) 0 28-Aug-14 A 28-Aug-14 A 28-Aug-14 28-Aug-14 28-Aug-14 A, ISSUANCE OF IFC DRAWINGS (ARCHITECURE)
A7340 0 MAIN BUILDING AND PARKING BUILDING
28-Aug-14 A 28-Aug-14 MAIN BUILDING AND PARKING BUILDING
A7370 0 EXTERNAL LANDSCAPE DETAILS 28-Aug-14 A 28-Aug-14 EXTERNAL LANDSCAPE DETAILS
A7350 0 DETAILED SERIES 28-Aug-14 A 28-Aug-14 DETAILED SERIES
A7360 0 ANCILLIARY/SECURITY BUILDING 28-Aug-14 A 28-Aug-14 ANCILLIARY/SECURITY BUILDING

CONSTRUCTION 861 16-Jun-14 A 04-Nov-16 25-Aug-14 12-Sep-16

ADDITIONAL SCOPE OF WORK 58 25-Aug-14 A 02-Dec-14 A 25-Aug-14 17-Oct-14 02-Dec-14 A, ADDITIONAL SCOPE OF WORK
A8240 3 PRE-REQUISITES / MOBILIZATION OF26-Aug-14
EQUIPMENTA 28-Aug-14 A 25-Aug-14 27-Aug-14 PRE-REQUISITES / MOBILIZATION OF EQUIPMENT
A8250 54 PILE CUTTING WORKS (450nos. of Piles)
28-Aug-14 A 02-Dec-14 A 28-Aug-14 17-Oct-14 PILE CUTTING WORKS (450nos. of Piles)
A8230 0 CONTRACT AGREEMENT OF PILE CUTTING
25-Aug-14
WORKS
A 25-Aug-14 CONTRACT AGREEMENT OF PILE CUTTING WORKS
ZONE-1 (PARKING BLOCK) 609 16-Jun-14 A 18-Mar-16 28-Aug-14 02-Mar-16 18-Mar-16, ZONE-1 (PARKING BLOCK)
Strcutural Works 357 16-Jun-14 A 28-Jul-15 28-Aug-14 04-May-15 28-Jul-15, Strcutural Works
Lower Basement 159 16-Jun-14 A 12-Mar-15 28-Aug-14 16-Jan-15 12-Mar-15, Lower Basement
Earth Works 17 16-Jun-14 A 17-Feb-15 28-Aug-14 17-Sep-14 17-Feb-15, Earth Works
A00008 5 Termite Proofing 20-Aug-14 A 17-Feb-15 11-Sep-14 17-Sep-14 Termite Proofing
A00007 13 Excavations 16-Jun-14 A 12-Feb-15 28-Aug-14 12-Sep-14 Excavations
Foundations 58 20-Aug-14 A 27-Feb-15 12-Sep-14 24-Nov-14 27-Feb-15, Foundations
Columns 37 20-Aug-14 A 27-Dec-14 A 12-Sep-14 06-Nov-14 27-Dec-14 A, Columns
A00012 33 Steel Reinforcement Work 24-Aug-14 A 27-Dec-14 A 12-Sep-14 31-Oct-14 Steel Reinforcement Work
A00011 21 Lean Concrete 20-Aug-14 A 26-Dec-14 A 17-Sep-14 23-Oct-14 Lean Concrete
A00013 32 Form Work 25-Aug-14 A 27-Dec-14 A 16-Sep-14 05-Nov-14 Form Work
A00014 25 Concrete in Foundations 26-Aug-14 A 27-Dec-14 A 26-Sep-14 06-Nov-14 Concrete in Foundations
Wall Upto SOG 58 01-Sep-14 A 27-Feb-15 17-Sep-14 24-Nov-14 27-Feb-15, Wall Upto SOG
A00017 30 Water Proofing 04-Sep-14 A 17-Feb-15 18-Sep-14 04-Nov-14 Water Proofing
A00019 31 Steel Reinforcement Work 07-Sep-14 A 23-Feb-15 13-Oct-14 18-Nov-14 Steel Reinforcement Work
A00018 27 Protection of Water Proofing 05-Sep-14 A 19-Feb-15 24-Sep-14 06-Nov-14 Protection of Water Proofing
A00016 26 Lean Concrete 01-Sep-14 A 12-Feb-15 17-Sep-14 29-Oct-14 Lean Concrete
A00020 30 Form Work 24-Sep-14 A 25-Feb-15 15-Oct-14 20-Nov-14 Form Work
A00021 32 Concrete in Foundations 01-Oct-14 A 27-Feb-15 16-Oct-14 24-Nov-14 Concrete in Foundations
Sub Base & SOG 59 29-Oct-14 A 11-Mar-15 16-Oct-14 24-Dec-14 11-Mar-15, Sub Base & SOG
A00026 43 Water Proofing 24-Nov-14 A 27-Feb-15 23-Oct-14 12-Dec-14 Water Proofing
A00028 43 Steel Reinforcement 26-Nov-14 A 06-Mar-15 30-Oct-14 19-Dec-14 Steel Reinforcement
A00024 35 Soling 12-Nov-14 A 19-Feb-15 23-Oct-14 03-Dec-14 Soling
A00027 45 Protection of Water Proofing 25-Nov-14 A 02-Mar-15 23-Oct-14 16-Dec-14 Protection of Water Proofing
A00023 35 Earth Filling 29-Oct-14 A 12-Feb-15 16-Oct-14 27-Nov-14 Earth Filling
A00029 46 Concrete 30-Nov-14 A 11-Mar-15 31-Oct-14 24-Dec-14 Concrete
A00025 44 1:4:8 (75MM) 20-Nov-14 A 20-Feb-15 16-Oct-14 08-Dec-14 1:4:8 (75MM)
Basement Columns 50 24-Oct-14 A 09-Mar-15 06-Nov-14 02-Jan-15 09-Mar-15, Basement Columns
A00031 47 Steel Reinforcement Work 24-Oct-14 A 05-Mar-15 06-Nov-14 31-Dec-14 Steel Reinforcement Work
A00032 45 Form Work 25-Oct-14 A 09-Mar-15 11-Nov-14 02-Jan-15 Form Work
A00033 45 Concrete Pouring 27-Oct-14 A 09-Mar-15 12-Nov-14 02-Jan-15 Concrete Pouring
Basement Walls 110 01-Nov-14 A 19-Feb-15 06-Nov-14 02-Jan-15 19-Feb-15, Basement Walls

Primary Baseline Remaining Work Milestone Page 2 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A00035 46 Steel Reinforcement Work 01-Nov-14 A 16-Feb-15 06-Nov-14 30-Dec-14 Steel Reinforcement Work
A00036 47 Form Work 15-Nov-14 A 18-Feb-15 07-Nov-14 01-Jan-15 Form Work
A00037 48 Concrete Pouring 22-Nov-14 A 19-Feb-15 10-Nov-14 02-Jan-15 Concrete Pouring
Slab & Beams 39 17-Dec-14 A 12-Mar-15 17-Nov-14 16-Jan-15 12-Mar-15, Slab & Beams
Pour -1 33 17-Dec-14 A 29-Jan-15 A 17-Nov-14 12-Dec-14 29-Jan-15 A, Pour -1
A00041 11 Steel Reinforcement 08-Jan-15 A 27-Jan-15 A 01-Dec-14 12-Dec-14 Steel Reinforcement
A00040 12 Form Work 17-Dec-14 A 16-Jan-15 A 17-Nov-14 01-Dec-14 Form Work
A00042 1 Concrete Pouring 27-Jan-15 A 29-Jan-15 A 12-Dec-14 12-Dec-14 Concrete Pouring
Pour -2 31 21-Jan-15 A 18-Feb-15 21-Nov-14 18-Dec-14 18-Feb-15, Pour -2
A00045 11 Steel Reinforcement 23-Jan-15 A 18-Feb-15 05-Dec-14 18-Dec-14 Steel Reinforcement
A00044 12 Form Work 21-Jan-15 A 16-Feb-15 21-Nov-14 05-Dec-14 Form Work
A00046 2 Concrete Pouring 10-Feb-15 A 12-Feb-15 18-Dec-14 18-Dec-14 Concrete Pouring
Pour -3 24 12-Feb-15 11-Mar-15 26-Nov-14 24-Dec-14 11-Mar-15, Pour -3
A00049 11 Steel Reinforcement 26-Feb-15 10-Mar-15 10-Dec-14 23-Dec-14 Steel Reinforcement
A00048 12 Form Work 12-Feb-15 25-Feb-15 26-Nov-14 10-Dec-14 Form Work
A00050 1 Concrete Pouring 11-Mar-15 11-Mar-15 23-Dec-14 24-Dec-14 Concrete Pouring
Pour -4 24 12-Feb-15 12-Mar-15 01-Dec-14 29-Dec-14 12-Mar-15, Pour -4
A00053 11 Steel Reinforcement 26-Feb-15 11-Mar-15 15-Dec-14 26-Dec-14 Steel Reinforcement
A00052 12 Form Work 12-Feb-15 25-Feb-15 01-Dec-14 15-Dec-14 Form Work
A00054 1 Concrete Pouring 11-Mar-15 12-Mar-15 26-Dec-14 29-Dec-14 Concrete Pouring
Pour -5 24 12-Feb-15 11-Mar-15 05-Dec-14 01-Jan-15 11-Mar-15, Pour -5
A00057 11 Steel Reinforcement 26-Feb-15 10-Mar-15 19-Dec-14 01-Jan-15 Steel Reinforcement
A00056 12 Form Work 12-Feb-15 25-Feb-15 05-Dec-14 19-Dec-14 Form Work
A00058 1 Concrete Pouring 11-Mar-15 11-Mar-15 01-Jan-15 01-Jan-15 Concrete Pouring
Pour -6 23 12-Feb-15 10-Mar-15 10-Dec-14 07-Jan-15 10-Mar-15, Pour -6
A00061 10 Steel Reinforcement 26-Feb-15 09-Mar-15 24-Dec-14 05-Jan-15 Steel Reinforcement
A00060 12 Form Work 12-Feb-15 25-Feb-15 10-Dec-14 24-Dec-14 Form Work
A00062 1 Concrete Pouring 10-Mar-15 10-Mar-15 07-Jan-15 07-Jan-15 Concrete Pouring
Pour -7 24 12-Feb-15 11-Mar-15 15-Dec-14 09-Jan-15 11-Mar-15, Pour -7
A00065 11 Steel Reinforcement 26-Feb-15 10-Mar-15 29-Dec-14 09-Jan-15 Steel Reinforcement
A00064 12 Form Work 12-Feb-15 25-Feb-15 15-Dec-14 29-Dec-14 Form Work
A00066 1 Concrete Pouring 11-Mar-15 11-Mar-15 09-Jan-15 09-Jan-15 Concrete Pouring
Pour -8 25 12-Feb-15 12-Mar-15 19-Dec-14 16-Jan-15 12-Mar-15, Pour -8
A00069 12 Steel Reinforcement 26-Feb-15 11-Mar-15 02-Jan-15 16-Jan-15 Steel Reinforcement
A00068 12 Form Work 12-Feb-15 25-Feb-15 19-Dec-14 02-Jan-15 Form Work
A00070 1 Concrete Pouring 12-Mar-15 12-Mar-15 16-Jan-15 16-Jan-15 Concrete Pouring
Upper Basement 128 12-Feb-15 11-Jun-15 15-Dec-14 31-Mar-15 11-Jun-15, Upper Basement
Columns 47 12-Feb-15 07-Apr-15 15-Dec-14 23-Jan-15 07-Apr-15, Columns
Pour -1 7 12-Feb-15 19-Feb-15 15-Dec-14 19-Dec-14 19-Feb-15, Pour -1
A00075 6 Steel Reinforcement Work 12-Feb-15 18-Feb-15 15-Dec-14 19-Dec-14 Steel Reinforcement Work
A00074 3 Form Work 12-Feb-15 16-Feb-15 15-Dec-14 17-Dec-14 Form Work
A00076 6 Concrete Pouring 12-Feb-15 19-Feb-15 15-Dec-14 19-Dec-14 Concrete Pouring
Pour -2 9 13-Feb-15 24-Feb-15 19-Dec-14 30-Dec-14 24-Feb-15, Pour -2
A00079 8 Steel Reinforcement Work 13-Feb-15 23-Feb-15 19-Dec-14 29-Dec-14 Steel Reinforcement Work
A00078 4 Form Work 16-Feb-15 20-Feb-15 22-Dec-14 26-Dec-14 Form Work
A00080 7 Concrete Pouring 16-Feb-15 24-Feb-15 22-Dec-14 30-Dec-14 Concrete Pouring
Pour -3 6 13-Mar-15 20-Mar-15 25-Dec-14 05-Jan-15 20-Mar-15, Pour -3
A00082 4 Steel Reinforcement Work 13-Mar-15 18-Mar-15 25-Dec-14 31-Dec-14 Steel Reinforcement Work
A00083 4 Form Work 16-Mar-15 20-Mar-15 29-Dec-14 02-Jan-15 Form Work
A00084 4 Concrete Pouring 16-Mar-15 20-Mar-15 30-Dec-14 05-Jan-15 Concrete Pouring
Pour -4 9 16-Mar-15 25-Mar-15 31-Dec-14 12-Jan-15 25-Mar-15, Pour -4
A00086 3 Steel Reinforcement Work 16-Mar-15 19-Mar-15 31-Dec-14 05-Jan-15 Steel Reinforcement Work

Primary Baseline Remaining Work Milestone Page 3 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A00087 5 Form Work 16-Mar-15 20-Mar-15 02-Jan-15 09-Jan-15 Form Work
A00088 5 Concrete Pouring 20-Mar-15 25-Mar-15 07-Jan-15 12-Jan-15 Concrete Pouring
Pour -5 13 13-Mar-15 27-Mar-15 07-Jan-15 15-Jan-15 27-Mar-15, Pour -5
A00090 3 Steel Reinforcement Work 13-Mar-15 17-Mar-15 07-Jan-15 09-Jan-15 Steel Reinforcement Work
A00091 5 Form Work 13-Mar-15 20-Mar-15 07-Jan-15 13-Jan-15 Form Work
A00092 4 Concrete Pouring 23-Mar-15 27-Mar-15 09-Jan-15 15-Jan-15 Concrete Pouring
Pour -6 21 12-Mar-15 06-Apr-15 09-Jan-15 23-Jan-15 06-Apr-15, Pour -6
A00094 5 Steel Reinforcement Work 12-Mar-15 18-Mar-15 09-Jan-15 15-Jan-15 Steel Reinforcement Work
A00095 5 Form Work 16-Mar-15 20-Mar-15 12-Jan-15 16-Jan-15 Form Work
A00096 6 Concrete Pouring 30-Mar-15 06-Apr-15 16-Jan-15 23-Jan-15 Concrete Pouring
Pour -7 21 13-Mar-15 06-Apr-15 12-Jan-15 23-Jan-15 06-Apr-15, Pour -7
A00098 5 Steel Reinforcement Work 13-Mar-15 19-Mar-15 12-Jan-15 16-Jan-15 Steel Reinforcement Work
A00099 5 Form Work 16-Mar-15 20-Mar-15 13-Jan-15 19-Jan-15 Form Work
A00100 5 Concrete Pouring 31-Mar-15 06-Apr-15 19-Jan-15 23-Jan-15 Concrete Pouring
Pour -8 20 16-Mar-15 07-Apr-15 19-Jan-15 23-Jan-15 07-Apr-15, Pour -8
A00102 2 Steel Reinforcement Work 16-Mar-15 18-Mar-15 19-Jan-15 21-Jan-15 Steel Reinforcement Work
A00103 4 Form Work 16-Mar-15 20-Mar-15 19-Jan-15 23-Jan-15 Form Work
A00104 6 Concrete Pouring 31-Mar-15 07-Apr-15 19-Jan-15 23-Jan-15 Concrete Pouring
Walls 75 12-Feb-15 22-Apr-15 15-Dec-14 10-Feb-15 22-Apr-15, Walls
Pour -1 8 12-Feb-15 20-Feb-15 15-Dec-14 23-Dec-14 20-Feb-15, Pour -1
A00107 6 Steel Reinforcement Work 12-Feb-15 18-Feb-15 15-Dec-14 19-Dec-14 Steel Reinforcement Work
A00108 2 Form Work 18-Feb-15 20-Feb-15 18-Dec-14 22-Dec-14 Form Work
A00109 3 Concrete Pouring 18-Feb-15 20-Feb-15 18-Dec-14 23-Dec-14 Concrete Pouring
Pour -2 5 23-Feb-15 27-Feb-15 29-Dec-14 02-Jan-15 27-Feb-15, Pour -2
A00111 3 Steel Reinforcement Work 23-Feb-15 25-Feb-15 30-Dec-14 01-Jan-15 Steel Reinforcement Work
A00112 4 Form Work 23-Feb-15 27-Feb-15 29-Dec-14 02-Jan-15 Form Work
A00113 4 Concrete Pouring 24-Feb-15 27-Feb-15 30-Dec-14 02-Jan-15 Concrete Pouring
Pour -3 5 23-Mar-15 27-Mar-15 07-Jan-15 09-Jan-15 27-Mar-15, Pour -3
A00115 2 Steel Reinforcement Work 23-Mar-15 25-Mar-15 07-Jan-15 09-Jan-15 Steel Reinforcement Work
A00116 3 Form Work 24-Mar-15 26-Mar-15 07-Jan-15 09-Jan-15 Form Work
A00117 3 Concrete Pouring 24-Mar-15 27-Mar-15 07-Jan-15 09-Jan-15 Concrete Pouring
Pour -4 9 23-Mar-15 01-Apr-15 12-Jan-15 16-Jan-15 01-Apr-15, Pour -4
A00119 4 Steel Reinforcement Work 23-Mar-15 27-Mar-15 12-Jan-15 16-Jan-15 Steel Reinforcement Work
A00120 3 Form Work 24-Mar-15 27-Mar-15 13-Jan-15 16-Jan-15 Form Work
A00121 4 Concrete Pouring 27-Mar-15 01-Apr-15 13-Jan-15 16-Jan-15 Concrete Pouring
Pour -5 14 23-Mar-15 08-Apr-15 14-Jan-15 26-Jan-15 08-Apr-15, Pour -5
A00123 6 Steel Reinforcement Work 23-Mar-15 30-Mar-15 14-Jan-15 22-Jan-15 Steel Reinforcement Work
A00124 6 Form Work 24-Mar-15 31-Mar-15 16-Jan-15 23-Jan-15 Form Work
A00125 6 Concrete Pouring 01-Apr-15 08-Apr-15 19-Jan-15 26-Jan-15 Concrete Pouring
Pour -6 23 20-Mar-15 16-Apr-15 19-Jan-15 03-Feb-15 16-Apr-15, Pour -6
A00127 6 Steel Reinforcement Work 20-Mar-15 27-Mar-15 19-Jan-15 23-Jan-15 Steel Reinforcement Work
A00128 4 Form Work 25-Mar-15 30-Mar-15 21-Jan-15 26-Jan-15 Form Work
A00129 3 Concrete Pouring 13-Apr-15 16-Apr-15 29-Jan-15 03-Feb-15 Concrete Pouring
Pour -7 32 23-Mar-15 21-Apr-15 20-Jan-15 07-Feb-15 21-Apr-15, Pour -7
A00131 5 Steel Reinforcement Work 23-Mar-15 27-Mar-15 20-Jan-15 27-Jan-15 Steel Reinforcement Work
A00132 3 Form Work 26-Mar-15 30-Mar-15 27-Jan-15 28-Jan-15 Form Work
A00172 5 Concrete Pouring 16-Apr-15 21-Apr-15 03-Feb-15 07-Feb-15 Concrete Pouring
Pour -8 29 20-Mar-15 22-Apr-15 26-Jan-15 10-Feb-15 22-Apr-15, Pour -8
A00135 5 Steel Reinforcement Work 20-Mar-15 26-Mar-15 26-Jan-15 30-Jan-15 Steel Reinforcement Work
A00136 4 Form Work 24-Mar-15 27-Mar-15 27-Jan-15 30-Jan-15 Form Work
A00137 5 Concrete Pouring 16-Apr-15 22-Apr-15 03-Feb-15 10-Feb-15 Concrete Pouring
Slab & Beams 62 31-Mar-15 11-Jun-15 20-Jan-15 31-Mar-15 11-Jun-15, Slab & Beams

Primary Baseline Remaining Work Milestone Page 4 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Pour -1 17 01-Apr-15 20-Apr-15 20-Jan-15 06-Feb-15 20-Apr-15, Pour -1
A00141 2 Steel Reinforcement 15-Apr-15 17-Apr-15 03-Feb-15 05-Feb-15 Steel Reinforcement
A00140 12 Form Work 01-Apr-15 15-Apr-15 20-Jan-15 03-Feb-15 Form Work
A00142 2 Concrete Pouring 17-Apr-15 20-Apr-15 05-Feb-15 06-Feb-15 Concrete Pouring
Pour -2 23 31-Mar-15 27-Apr-15 23-Jan-15 13-Feb-15 27-Apr-15, Pour -2
A00145 5 Steel Reinforcement 14-Apr-15 20-Apr-15 06-Feb-15 12-Feb-15 Steel Reinforcement
A00144 11 Form Work 31-Mar-15 13-Apr-15 23-Jan-15 06-Feb-15 Form Work
A00146 2 Concrete Pouring 24-Apr-15 27-Apr-15 12-Feb-15 13-Feb-15 Concrete Pouring
Pour -3 21 07-Apr-15 01-May-15 27-Jan-15 18-Feb-15 01-May-15, Pour -3
A00149 3 Steel Reinforcement 21-Apr-15 24-Apr-15 10-Feb-15 16-Feb-15 Steel Reinforcement
A00148 12 Form Work 07-Apr-15 21-Apr-15 27-Jan-15 10-Feb-15 Form Work
A00150 1 Concrete Pouring 30-Apr-15 01-May-15 17-Feb-15 18-Feb-15 Concrete Pouring
Pour -4 18 13-Apr-15 04-May-15 29-Jan-15 19-Feb-15 04-May-15, Pour -4
A00153 3 Steel Reinforcement 27-Apr-15 29-Apr-15 13-Feb-15 17-Feb-15 Steel Reinforcement
A00152 12 Form Work 13-Apr-15 27-Apr-15 29-Jan-15 12-Feb-15 Form Work
A00154 2 Concrete Pouring 01-May-15 04-May-15 18-Feb-15 19-Feb-15 Concrete Pouring
Pour -5 21 14-Apr-15 08-May-15 05-Feb-15 26-Feb-15 08-May-15, Pour -5
A00157 5 Steel Reinforcement 28-Apr-15 04-May-15 20-Feb-15 26-Feb-15 Steel Reinforcement
A00156 12 Form Work 14-Apr-15 28-Apr-15 05-Feb-15 20-Feb-15 Form Work
A00158 0 Concrete Pouring 08-May-15 08-May-15 26-Feb-15 26-Feb-15 Concrete Pouring
Pour -6 16 11-May-15 28-May-15 26-Feb-15 18-Mar-15 28-May-15, Pour -6
A00161 4 Steel Reinforcement 25-May-15 28-May-15 12-Mar-15 18-Mar-15 Steel Reinforcement
A00160 11 Form Work 11-May-15 22-May-15 26-Feb-15 12-Mar-15 Form Work
A00162 0 Concrete Pouring 28-May-15 28-May-15 18-Mar-15 18-Mar-15 Concrete Pouring
Pour -7 19 18-May-15 08-Jun-15 05-Mar-15 26-Mar-15 08-Jun-15, Pour -7
A00165 4 Steel Reinforcement 01-Jun-15 05-Jun-15 19-Mar-15 25-Mar-15 Steel Reinforcement
A00164 12 Form Work 18-May-15 01-Jun-15 05-Mar-15 19-Mar-15 Form Work
A00166 2 Concrete Pouring 05-Jun-15 08-Jun-15 25-Mar-15 26-Mar-15 Concrete Pouring
Pour -8 18 21-May-15 11-Jun-15 10-Mar-15 31-Mar-15 11-Jun-15, Pour -8
A00169 2 Steel Reinforcement 08-Jun-15 10-Jun-15 26-Mar-15 30-Mar-15 Steel Reinforcement
A00168 15 Form Work 21-May-15 08-Jun-15 10-Mar-15 26-Mar-15 Form Work
A00170 1 Concrete Pouring 10-Jun-15 11-Jun-15 30-Mar-15 31-Mar-15 Concrete Pouring
Surface Parking Level 32 11-Jun-15 28-Jul-15 31-Mar-15 04-May-15 28-Jul-15, Surface Parking Level
Columns 12 11-Jun-15 25-Jun-15 31-Mar-15 10-Apr-15 25-Jun-15, Columns
A00173 9 Steel Reinforcement Work 11-Jun-15 22-Jun-15 31-Mar-15 09-Apr-15 Steel Reinforcement Work
A00174 8 Form Work 15-Jun-15 24-Jun-15 02-Apr-15 10-Apr-15 Form Work
A00175 8 Concrete Pouring 16-Jun-15 25-Jun-15 02-Apr-15 10-Apr-15 Concrete Pouring
Slab & Beams 20 25-Jun-15 28-Jul-15 13-Apr-15 04-May-15 28-Jul-15, Slab & Beams
A00178 5 Steel Reinforcement 09-Jul-15 15-Jul-15 27-Apr-15 01-May-15 Steel Reinforcement
A00177 12 Form Work 25-Jun-15 09-Jul-15 13-Apr-15 24-Apr-15 Form Work
A00179 4 Concrete Pouring 24-Jul-15 28-Jul-15 30-Apr-15 04-May-15 Concrete Pouring
First Milestone as per contract 0 01-May-15 01-May-15 01-May-15 01-May-15 01-May-15, First Milestone as per contract
A7650 0 Completion of Grey Structure 01-May-15* 01-May-15 Completion of Grey Structure
Finishing 190 31-Mar-15 27-Nov-15 05-Feb-15 14-Sep-15 27-Nov-15, Finishing
Lower Basement 97 31-Mar-15 31-Jul-15 05-Feb-15 28-May-15 31-Jul-15, Lower Basement
A00183 37 Plaster 14-Apr-15 27-May-15 19-Feb-15 02-Apr-15 Plaster
A00186 37 Paint 26-May-15 08-Jul-15 02-Apr-15 14-May-15 Paint
A00187 17 Metal works 03-Jul-15 31-Jul-15 30-Apr-15 28-May-15 Metal works
A00185 37 Flooring 12-May-15 24-Jun-15 19-Mar-15 30-Apr-15 Flooring
A00184 37 Ceiling 28-Apr-15 10-Jun-15 05-Mar-15 16-Apr-15 Ceiling
A00182 37 Block masonry 31-Mar-15 13-May-15 05-Feb-15 19-Mar-15 Block masonry
Upper Basement 88 30-Jun-15 30-Oct-15 20-Apr-15 21-Aug-15 30-Oct-15, Upper Basement

Primary Baseline Remaining Work Milestone Page 5 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A00190 28 Plaster 14-Jul-15 25-Aug-15 04-May-15 12-Jun-15 Plaster
A00193 29 Paint 02-Sep-15 14-Oct-15 23-Jun-15 03-Aug-15 Paint
A00194 23 Metal works 01-Oct-15 30-Oct-15 24-Jul-15 21-Aug-15 Metal works
A00192 36 Flooring 11-Aug-15 22-Sep-15 29-May-15 10-Jul-15 Flooring
A00191 37 Ceiling 27-Jul-15 08-Sep-15 15-May-15 26-Jun-15 Ceiling
A00189 28 Block masonry 30-Jun-15 11-Aug-15 20-Apr-15 29-May-15 Block masonry
Surface Parking level 112 30-Jun-15 27-Nov-15 20-Apr-15 14-Sep-15 27-Nov-15, Surface Parking level
A00202 40 Roof Screeding and Water Proofing 30-Jun-15 25-Aug-15 20-Apr-15 12-Jun-15 Roof Screeding and Water Proofing
A00197 18 Plaster 07-Sep-15 06-Oct-15 09-Jun-15 08-Jul-15 Plaster
A00200 23 Paint 21-Oct-15 19-Nov-15 06-Aug-15 04-Sep-15 Paint
A00201 16 Metal works 10-Nov-15 27-Nov-15 25-Aug-15 14-Sep-15 Metal works
A00199 22 Flooring 08-Oct-15 05-Nov-15 24-Jul-15 21-Aug-15 Flooring
A00198 18 Ceiling 22-Sep-15 20-Oct-15 03-Jul-15 31-Jul-15 Ceiling
A00196 25 Block masonry 17-Aug-15 14-Sep-15 27-May-15 24-Jun-15 Block masonry
MEP WORKS 430 12-Feb-15 18-Mar-16 15-Oct-14 02-Mar-16 18-Mar-16, MEP WORKS
ZONE-2 (BLOCK- A AND BLOCK- B) 606 01-Sep-14 A 18-Mar-16 31-Oct-14 02-Mar-16 18-Mar-16, ZONE-2 (BLOCK- A A
BLOCK- A 606 01-Sep-14 A 18-Mar-16 31-Oct-14 02-Mar-16 18-Mar-16, BLOCK- A
Earth Works 144 01-Sep-14 A 24-Dec-14 A 31-Oct-14 04-Dec-14 24-Dec-14 A, Earth Works
A00261 27 Termite Proofing 17-Sep-14 A 24-Dec-14 A 04-Nov-14 04-Dec-14 Termite Proofing
A00260 23 Excavations 01-Sep-14 A 03-Nov-14 A 31-Oct-14 28-Nov-14 Excavations
Strcutural Works 265 18-Sep-14 A 18-Aug-15 31-Oct-14 14-Jul-15 18-Aug-15, Strcutural Works
Ground Floor 167 18-Sep-14 A 16-Apr-15 31-Oct-14 27-Mar-15 16-Apr-15, Ground Floor
Pile Caps 41 18-Sep-14 A 23-Jan-15 A 31-Oct-14 15-Dec-14 23-Jan-15 A, Pile Caps
A00266 22 Steel Reinforcement Work 25-Sep-14 A 23-Jan-15 A 04-Nov-14 10-Dec-14 Steel Reinforcement Work
A00265 20 Lean Concrete 18-Sep-14 A 22-Jan-15 A 31-Oct-14 05-Dec-14 Lean Concrete
A00267 20 Form Work 29-Sep-14 A 23-Jan-15 A 07-Nov-14 12-Dec-14 Form Work
A00268 30 Concrete in Pile Caps 01-Oct-14 A 23-Jan-15 A 07-Nov-14 15-Dec-14 Concrete in Pile Caps
Sub Base, Ground Beams & SOG 121 08-Nov-14 A 10-Apr-15 17-Nov-14 16-Feb-15 10-Apr-15, Sub Base, Ground Beams & SOG
A00273 22 Water Proofing 12-Dec-14 A 05-Mar-15 12-Dec-14 09-Jan-15 Water Proofing
A00275 24 Steel Reinforcement 09-Dec-14 A 11-Mar-15 19-Dec-14 16-Jan-15 Steel Reinforcement
A00271 33 Soling 08-Dec-14 A 24-Feb-15 20-Nov-14 29-Dec-14 Soling
A00274 21 Protection of Water Proofing 15-Dec-14 A 06-Mar-15 15-Dec-14 12-Jan-15 Protection of Water Proofing
A00270 31 Earth Filling 08-Nov-14 A 16-Feb-15 17-Nov-14 22-Dec-14 Earth Filling
A00276 25 Concrete 27-Dec-14 A 10-Apr-15 16-Jan-15 16-Feb-15 Concrete
A00272 31 1:4:8 10-Dec-14 A 26-Feb-15 25-Nov-14 31-Dec-14 1:4:8
Columns 48 05-Jan-15 A 26-Mar-15 21-Jan-15 06-Mar-15 26-Mar-15, Columns
A00278 35 Steel Reinforcement Work 05-Jan-15 A 23-Mar-15 21-Jan-15 03-Mar-15 Steel Reinforcement Work
A00279 34 Form Work 09-Jan-15 A 25-Mar-15 26-Jan-15 05-Mar-15 Form Work
A00280 35 Concrete in Columns 13-Feb-15 26-Mar-15 27-Jan-15 06-Mar-15 Concrete in Columns
Shear Walls 77 01-Jan-15 A 19-Mar-15 21-Jan-15 26-Feb-15 19-Mar-15, Shear Walls
A00282 28 Steel Reinforcement Work 01-Jan-15 A 16-Mar-15 21-Jan-15 23-Feb-15 Steel Reinforcement Work
A00283 24 Form Work 02-Jan-15 A 18-Mar-15 27-Jan-15 26-Feb-15 Form Work
A00284 25 Concrete in Walls 05-Jan-15 A 19-Mar-15 28-Jan-15 26-Feb-15 Concrete in Walls
Slab & Beams 41 27-Feb-15 16-Apr-15 11-Feb-15 27-Mar-15 16-Apr-15, Slab & Beams
Pour -1 28 27-Feb-15 01-Apr-15 11-Feb-15 13-Mar-15 01-Apr-15, Pour -1
A00288 4 Steel Reinforcement 26-Mar-15 31-Mar-15 10-Mar-15 13-Mar-15 Steel Reinforcement
A00287 23 Form Work 27-Feb-15 26-Mar-15 11-Feb-15 10-Mar-15 Form Work
A00289 1 Concrete Pouring 31-Mar-15 01-Apr-15 13-Mar-15 13-Mar-15 Concrete Pouring
Pour -2 18 26-Mar-15 16-Apr-15 09-Mar-15 27-Mar-15 16-Apr-15, Pour -2
A00292 5 Steel Reinforcement 10-Apr-15 16-Apr-15 23-Mar-15 27-Mar-15 Steel Reinforcement
A00291 13 Form Work 26-Mar-15 10-Apr-15 09-Mar-15 23-Mar-15 Form Work
A00293 0 Concrete Pouring 16-Apr-15 16-Apr-15 27-Mar-15 27-Mar-15 Concrete Pouring

Primary Baseline Remaining Work Milestone Page 6 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
First Floor 45 03-Apr-15 25-May-15 16-Mar-15 06-May-15 25-May-15, First Floor
Columns 19 03-Apr-15 24-Apr-15 16-Mar-15 10-Apr-15 24-Apr-15, Columns
Pour - 1 8 03-Apr-15 13-Apr-15 16-Mar-15 26-Mar-15 13-Apr-15, Pour - 1
A00297 5 Steel Reinforcement Work 03-Apr-15 08-Apr-15 16-Mar-15 20-Mar-15 Steel Reinforcement Work
A00298 4 Form Work 06-Apr-15 10-Apr-15 19-Mar-15 25-Mar-15 Form Work
A00299 5 Concrete in Columns 07-Apr-15 13-Apr-15 20-Mar-15 26-Mar-15 Concrete in Columns
Pour - 2 6 17-Apr-15 24-Apr-15 02-Apr-15 10-Apr-15 24-Apr-15, Pour - 2
A00301 3 Steel Reinforcement Work 20-Apr-15 23-Apr-15 02-Apr-15 07-Apr-15 Steel Reinforcement Work
A00302 6 Form Work 17-Apr-15 24-Apr-15 02-Apr-15 09-Apr-15 Form Work
A00303 6 Concrete in Columns 17-Apr-15 24-Apr-15 03-Apr-15 10-Apr-15 Concrete in Columns
Shear Walls 21 03-Apr-15 28-Apr-15 16-Mar-15 08-Apr-15 28-Apr-15, Shear Walls
Pour -1 7 03-Apr-15 10-Apr-15 16-Mar-15 24-Mar-15 10-Apr-15, Pour -1
A00306 5 Steel Reinforcement Work 03-Apr-15 08-Apr-15 16-Mar-15 20-Mar-15 Steel Reinforcement Work
A00307 4 Form Work 06-Apr-15 10-Apr-15 17-Mar-15 23-Mar-15 Form Work
A00308 4 Concrete in Walls 06-Apr-15 10-Apr-15 18-Mar-15 24-Mar-15 Concrete in Walls
Pour -2 7 20-Apr-15 28-Apr-15 30-Mar-15 08-Apr-15 28-Apr-15, Pour -2
A00310 4 Steel Reinforcement Work 20-Apr-15 24-Apr-15 30-Mar-15 03-Apr-15 Steel Reinforcement Work
A00311 6 Form Work 20-Apr-15 27-Apr-15 30-Mar-15 06-Apr-15 Form Work
A00312 6 Concrete in Walls 21-Apr-15 28-Apr-15 31-Mar-15 08-Apr-15 Concrete in Walls
Slab & Beams 30 21-Apr-15 25-May-15 02-Apr-15 06-May-15 25-May-15, Slab & Beams
Pour -1 16 21-Apr-15 08-May-15 02-Apr-15 22-Apr-15 08-May-15, Pour -1
A00316 2 Steel Reinforcement 05-May-15 07-May-15 17-Apr-15 21-Apr-15 Steel Reinforcement
A00315 12 Form Work 21-Apr-15 05-May-15 02-Apr-15 17-Apr-15 Form Work
A00317 1 Concrete Pouring 07-May-15 08-May-15 21-Apr-15 22-Apr-15 Concrete Pouring
Pour -2 16 06-May-15 25-May-15 16-Apr-15 06-May-15 25-May-15, Pour -2
A00320 3 Steel Reinforcement 19-May-15 22-May-15 29-Apr-15 05-May-15 Steel Reinforcement
A00319 11 Form Work 06-May-15 19-May-15 16-Apr-15 29-Apr-15 Form Work
A00321 2 Concrete Pouring 22-May-15 25-May-15 05-May-15 06-May-15 Concrete Pouring
Second Floor 48 11-May-15 06-Jul-15 24-Apr-15 16-Jun-15 06-Jul-15, Second Floor
Columns 19 11-May-15 02-Jun-15 24-Apr-15 15-May-15 02-Jun-15, Columns
Pour -1 5 11-May-15 15-May-15 24-Apr-15 01-May-15 15-May-15, Pour -1
A00325 2 Steel Reinforcement Work 11-May-15 13-May-15 24-Apr-15 28-Apr-15 Steel Reinforcement Work
A00326 4 Form Work 11-May-15 15-May-15 24-Apr-15 30-Apr-15 Form Work
A00327 4 Concrete in Walls 11-May-15 15-May-15 27-Apr-15 01-May-15 Concrete in Walls
Pour -2 6 26-May-15 02-Jun-15 08-May-15 15-May-15 02-Jun-15, Pour -2
A00329 2 Steel Reinforcement Work 27-May-15 29-May-15 08-May-15 12-May-15 Steel Reinforcement Work
A00330 5 Form Work 26-May-15 01-Jun-15 08-May-15 14-May-15 Form Work
A00331 6 Concrete in Walls 26-May-15 02-Jun-15 11-May-15 15-May-15 Concrete in Walls
Shear Walls 19 11-May-15 02-Jun-15 24-Apr-15 15-May-15 02-Jun-15, Shear Walls
Pour -1 5 11-May-15 15-May-15 24-Apr-15 01-May-15 15-May-15, Pour -1
A00334 2 Steel Reinforcement Work 11-May-15 13-May-15 24-Apr-15 28-Apr-15 Steel Reinforcement Work
A00335 4 Form Work 11-May-15 15-May-15 24-Apr-15 30-Apr-15 Form Work
A00336 4 Concrete in Walls 11-May-15 15-May-15 27-Apr-15 01-May-15 Concrete in Walls
Pour -2 6 26-May-15 02-Jun-15 08-May-15 15-May-15 02-Jun-15, Pour -2
A00338 2 Steel Reinforcement Work 27-May-15 29-May-15 08-May-15 12-May-15 Steel Reinforcement Work
A00339 5 Form Work 26-May-15 01-Jun-15 08-May-15 14-May-15 Form Work
A00340 6 Concrete in Walls 26-May-15 02-Jun-15 11-May-15 15-May-15 Concrete in Walls
Slab & Beams 33 28-May-15 06-Jul-15 12-May-15 16-Jun-15 06-Jul-15, Slab & Beams
Pour -1 17 28-May-15 17-Jun-15 12-May-15 01-Jun-15 17-Jun-15, Pour -1
A00344 5 Steel Reinforcement 11-Jun-15 17-Jun-15 26-May-15 29-May-15 Steel Reinforcement
A00343 12 Form Work 28-May-15 11-Jun-15 12-May-15 26-May-15 Form Work
A00345 1 Concrete Pouring 17-Jun-15 17-Jun-15 29-May-15 01-Jun-15 Concrete Pouring
Pour -2 18 15-Jun-15 06-Jul-15 26-May-15 16-Jun-15 06-Jul-15, Pour -2

Primary Baseline Remaining Work Milestone Page 7 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A00348 5 Steel Reinforcement 29-Jun-15 03-Jul-15 09-Jun-15 16-Jun-15 Steel Reinforcement
A00347 12 Form Work 15-Jun-15 29-Jun-15 26-May-15 09-Jun-15 Form Work
A00349 0 Concrete Pouring 06-Jul-15 06-Jul-15 16-Jun-15 16-Jun-15 Concrete Pouring
Roof 28 07-Jul-15 18-Aug-15 17-Jun-15 14-Jul-15 18-Aug-15, Roof
Columns 13 07-Jul-15 31-Jul-15 17-Jun-15 26-Jun-15 31-Jul-15, Columns
A00352 6 Steel Reinforcement Work 07-Jul-15 14-Jul-15 17-Jun-15 24-Jun-15 Steel Reinforcement Work
A00353 6 Form Work 24-Jul-15 31-Jul-15 19-Jun-15 26-Jun-15 Form Work
A00354 6 Concrete in Columns 24-Jul-15 31-Jul-15 19-Jun-15 26-Jun-15 Concrete in Columns
Shear Walls 13 07-Jul-15 31-Jul-15 17-Jun-15 26-Jun-15 31-Jul-15, Shear Walls
A00356 6 Steel Reinforcement Work 07-Jul-15 14-Jul-15 17-Jun-15 24-Jun-15 Steel Reinforcement Work
A00357 6 Form Work 24-Jul-15 31-Jul-15 19-Jun-15 26-Jun-15 Form Work
A00358 6 Concrete in Columns 24-Jul-15 31-Jul-15 19-Jun-15 26-Jun-15 Concrete in Columns
Slab & Beams 13 03-Aug-15 18-Aug-15 29-Jun-15 14-Jul-15 18-Aug-15, Slab & Beams
A00361 5 Steel Reinforcement 11-Aug-15 17-Aug-15 07-Jul-15 13-Jul-15 Steel Reinforcement
A00360 8 Form Work 03-Aug-15 11-Aug-15 29-Jun-15 07-Jul-15 Form Work
A00362 1 Concrete Pouring 17-Aug-15 18-Aug-15 13-Jul-15 14-Jul-15 Concrete Pouring
Finishing 240 12-May-15 09-Mar-16 23-Apr-15 23-Feb-16 09-Mar-16, Finishing
Ground Floor 178 12-May-15 28-Dec-15 23-Apr-15 27-Nov-15 28-Dec-15, Ground Floor
A00366 41 Plaster 18-Jun-15 14-Aug-15 01-Jun-15 29-Jul-15 Plaster
A00369 47 Paint 01-Oct-15 27-Nov-15 03-Sep-15 30-Oct-15 Paint
A00368 41 Flooring works 01-Sep-15 29-Oct-15 04-Aug-15 01-Oct-15 Flooring works
A00370 24 Doors & Windows fixing 27-Nov-15 28-Dec-15 30-Oct-15 27-Nov-15 Doors & Windows fixing
A00367 50 Ceiling works 24-Jul-15 21-Sep-15 30-Jun-15 26-Aug-15 Ceiling works
A00365 50 Block Masonry 12-May-15 09-Jul-15 23-Apr-15 22-Jun-15 Block Masonry
First Floor 175 22-Jun-15 03-Feb-16 03-Jun-15 07-Jan-16 03-Feb-16, First Floor
A00373 48 Plaster 27-Jul-15 21-Sep-15 02-Jul-15 27-Aug-15 Plaster
A00376 47 Paint 05-Nov-15 01-Jan-16 09-Oct-15 08-Dec-15 Paint
A00375 47 Flooring works 07-Oct-15 03-Dec-15 04-Sep-15 02-Nov-15 Flooring works
A00377 32 Doors & Windows fixing 28-Dec-15 03-Feb-16 01-Dec-15 07-Jan-16 Doors & Windows fixing
A00374 41 Ceiling works 01-Sep-15 29-Oct-15 06-Aug-15 02-Oct-15 Ceiling works
A00372 41 Block Masonry 22-Jun-15 18-Aug-15 03-Jun-15 30-Jul-15 Block Masonry
Second Floor 170 12-Aug-15 09-Mar-16 14-Jul-15 23-Feb-16 09-Mar-16, Second Floor
A00380 40 Plaster 10-Sep-15 06-Nov-15 18-Aug-15 14-Oct-15 Plaster
A00383 55 Paint 03-Dec-15 08-Feb-16 09-Nov-15 13-Jan-16 Paint
A00382 48 Flooring works 06-Nov-15 04-Jan-16 15-Oct-15 11-Dec-15 Flooring works
A00384 32 Doors & Windows fixing 02-Feb-16 09-Mar-16 18-Jan-16 23-Feb-16 Doors & Windows fixing
A00381 47 Ceiling works 08-Oct-15 04-Dec-15 17-Sep-15 13-Nov-15 Ceiling works
A00379 42 Block Masonry 12-Aug-15 07-Oct-15 14-Jul-15 08-Sep-15 Block Masonry
Mechanical Floor 105 27-Aug-15 08-Jan-16 03-Aug-15 21-Dec-15 08-Jan-16, Mechanical Floor
A00392 1 Roof Screeding and Water Proofing 27-Aug-15 28-Aug-15 03-Aug-15 03-Aug-15 Roof Screeding and Water Proofing
A00387 23 Plaster 01-Oct-15 29-Oct-15 11-Sep-15 09-Oct-15 Plaster
A00390 24 Paint 25-Nov-15 23-Dec-15 09-Nov-15 07-Dec-15 Paint
A00389 24 Flooring works 06-Nov-15 04-Dec-15 21-Oct-15 18-Nov-15 Flooring works
A00391 11 Doors & Windows fixing 28-Dec-15 08-Jan-16 08-Dec-15 21-Dec-15 Doors & Windows fixing
A00388 23 Ceiling Works 20-Oct-15 17-Nov-15 02-Oct-15 30-Oct-15 Ceiling Works
A00386 18 Block Masonry 10-Sep-15 08-Oct-15 17-Aug-15 14-Sep-15 Block Masonry
MEP WORKS 430 12-Feb-15 18-Mar-16 22-Dec-14 02-Mar-16 18-Mar-16, MEP WORKS
BLOCK- B 507 13-Oct-14 A 28-Jan-16 20-Nov-14 28-Jan-16 28-Jan-16, BLOCK- B
Earth Works 31 13-Oct-14 A 27-Jan-15 A 20-Nov-14 29-Dec-14 27-Jan-15 A, Earth Works
A00503 28 Termite Proofing 16-Oct-14 A 27-Jan-15 A 25-Nov-14 29-Dec-14 Termite Proofing
A00502 27 Excavations 13-Oct-14 A 12-Nov-14 A 20-Nov-14 24-Dec-14 Excavations
Strcutural Works 223 16-Oct-14 A 07-Jul-15 15-Dec-14 07-Jul-15 07-Jul-15, Strcutural Works

Primary Baseline Remaining Work Milestone Page 8 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Ground Floor 144 16-Oct-14 A 13-Mar-15 15-Dec-14 13-Mar-15 13-Mar-15, Ground Floor
Pile Caps 128 16-Oct-14 A 20-Feb-15 15-Dec-14 09-Jan-15 20-Feb-15, Pile Caps
A00508 11 Steel Reinforcement Work 22-Oct-14 A 17-Feb-15 19-Dec-14 02-Jan-15 Steel Reinforcement Work
A00507 12 Lean Concrete 16-Oct-14 A 12-Feb-15 15-Dec-14 29-Dec-14 Lean Concrete
A00509 12 Form Work 27-Oct-14 A 19-Feb-15 25-Dec-14 08-Jan-15 Form Work
A00510 12 Concrete in Pile Caps 28-Oct-14 A 20-Feb-15 29-Dec-14 09-Jan-15 Concrete in Pile Caps
Sub Base, Ground Beams & SOG 86 21-Nov-14 A 11-Mar-15 08-Jan-15 18-Feb-15 11-Mar-15, Sub Base, Ground Beams & SOG
A00515 17 Water Proofing 14-Dec-14 A 27-Feb-15 15-Jan-15 06-Feb-15 Water Proofing
A00517 18 Steel Reinforcement 19-Dec-14 A 06-Mar-15 21-Jan-15 13-Feb-15 Steel Reinforcement
A00513 12 Soling 10-Dec-14 A 19-Feb-15 15-Jan-15 29-Jan-15 Soling
A00516 20 Protection of Water Proofing 15-Dec-14 A 03-Mar-15 15-Jan-15 10-Feb-15 Protection of Water Proofing
A00512 12 Earth Filling 21-Nov-14 A 13-Feb-15 08-Jan-15 23-Jan-15 Earth Filling
A00518 12 Concrete 24-Dec-14 A 11-Mar-15 05-Feb-15 18-Feb-15 Concrete
A00514 14 1:4:8 12-Dec-14 A 23-Feb-15 16-Jan-15 02-Feb-15 1:4:8
Columns 14 12-Feb-15 27-Feb-15 10-Feb-15 27-Feb-15 27-Feb-15, Columns
A00520 12 Steel Reinforcement Work 12-Feb-15 26-Feb-15 10-Feb-15 24-Feb-15 Steel Reinforcement Work
A00521 13 Form Work 12-Feb-15 27-Feb-15 11-Feb-15 26-Feb-15 Form Work
A00522 13 Concrete in Columns 12-Feb-15 27-Feb-15 12-Feb-15 27-Feb-15 Concrete in Columns
Shear Walls 17 09-Feb-15 A 27-Feb-15 10-Feb-15 27-Feb-15 27-Feb-15, Shear Walls
A00524 12 Steel Reinforcement Work 09-Feb-15 A 25-Feb-15 10-Feb-15 24-Feb-15 Steel Reinforcement Work
A00525 13 Form Work 12-Feb-15 27-Feb-15 11-Feb-15 26-Feb-15 Form Work
A00526 13 Concrete in Columns 12-Feb-15 27-Feb-15 12-Feb-15 27-Feb-15 Concrete in Columns
Slab & Beams 21 17-Feb-15 13-Mar-15 17-Feb-15 13-Mar-15 13-Mar-15, Slab & Beams
A00529 5 Steel Reinforcement 06-Mar-15 12-Mar-15 06-Mar-15 12-Mar-15 Steel Reinforcement
A00528 15 Form Work 17-Feb-15 06-Mar-15 17-Feb-15 06-Mar-15 Form Work
A00530 1 Concrete Pouring 13-Mar-15 13-Mar-15 12-Mar-15 13-Mar-15 Concrete Pouring
First Floor 32 16-Mar-15 22-Apr-15 16-Mar-15 21-Apr-15 22-Apr-15, First Floor
Columns 8 16-Mar-15 24-Mar-15 16-Mar-15 24-Mar-15 24-Mar-15, Columns
A00533 4 Steel Reinforcement Work 16-Mar-15 20-Mar-15 16-Mar-15 20-Mar-15 Steel Reinforcement Work
A00534 6 Form Work 16-Mar-15 23-Mar-15 16-Mar-15 23-Mar-15 Form Work
A00535 6 Concrete in Columns 17-Mar-15 24-Mar-15 17-Mar-15 24-Mar-15 Concrete in Columns
Shear Walls 8 16-Mar-15 24-Mar-15 16-Mar-15 24-Mar-15 24-Mar-15, Shear Walls
A00537 4 Steel Reinforcement Work 16-Mar-15 20-Mar-15 16-Mar-15 20-Mar-15 Steel Reinforcement Work
A00538 6 Form Work 16-Mar-15 23-Mar-15 16-Mar-15 23-Mar-15 Form Work
A00539 6 Concrete in Walls 17-Mar-15 24-Mar-15 17-Mar-15 24-Mar-15 Concrete in Walls
Slab & Beams 17 02-Apr-15 22-Apr-15 02-Apr-15 21-Apr-15 22-Apr-15, Slab & Beams
A00542 5 Steel Reinforcement 15-Apr-15 21-Apr-15 15-Apr-15 20-Apr-15 Steel Reinforcement
A00541 11 Form Work 02-Apr-15 15-Apr-15 02-Apr-15 15-Apr-15 Form Work
A00543 1 Concrete Pouring 21-Apr-15 22-Apr-15 21-Apr-15 21-Apr-15 Concrete Pouring
Second Floor 34 24-Apr-15 02-Jun-15 23-Apr-15 02-Jun-15 02-Jun-15, Second Floor
Columns 7 24-Apr-15 01-May-15 23-Apr-15 30-Apr-15 01-May-15, Columns
A00546 3 Steel Reinforcement Work 24-Apr-15 28-Apr-15 23-Apr-15 27-Apr-15 Steel Reinforcement Work
A00547 5 Form Work 24-Apr-15 30-Apr-15 23-Apr-15 30-Apr-15 Form Work
A00548 4 Concrete in Columns 27-Apr-15 01-May-15 24-Apr-15 30-Apr-15 Concrete in Columns
Shear Walls 7 24-Apr-15 01-May-15 23-Apr-15 30-Apr-15 01-May-15, Shear Walls
A00550 3 Steel Reinforcement Work 24-Apr-15 28-Apr-15 23-Apr-15 27-Apr-15 Steel Reinforcement Work
A00551 5 Form Work 24-Apr-15 30-Apr-15 23-Apr-15 30-Apr-15 Form Work
A00552 4 Concrete in Walls 27-Apr-15 01-May-15 24-Apr-15 30-Apr-15 Concrete in Walls
Slab & Beams 19 12-May-15 02-Jun-15 11-May-15 02-Jun-15 02-Jun-15, Slab & Beams
A00555 4 Steel Reinforcement 27-May-15 01-Jun-15 27-May-15 01-Jun-15 Steel Reinforcement
A00554 13 Form Work 12-May-15 27-May-15 11-May-15 27-May-15 Form Work
A00556 1 Concrete Pouring 01-Jun-15 02-Jun-15 01-Jun-15 02-Jun-15 Concrete Pouring

Primary Baseline Remaining Work Milestone Page 9 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Roof 28 04-Jun-15 07-Jul-15 04-Jun-15 07-Jul-15 07-Jul-15, Roof
Columns 8 04-Jun-15 12-Jun-15 04-Jun-15 12-Jun-15 12-Jun-15, Columns
A00559 4 Steel Reinforcement Work 04-Jun-15 09-Jun-15 04-Jun-15 09-Jun-15 Steel Reinforcement Work
A00560 6 Form Work 05-Jun-15 11-Jun-15 04-Jun-15 11-Jun-15 Form Work
A00561 6 Concrete in Columns 05-Jun-15 12-Jun-15 05-Jun-15 12-Jun-15 Concrete in Columns
Shear Walls 8 04-Jun-15 12-Jun-15 04-Jun-15 12-Jun-15 12-Jun-15, Shear Walls
A00563 4 Steel Reinforcement Work 04-Jun-15 09-Jun-15 04-Jun-15 09-Jun-15 Steel Reinforcement Work
A00564 6 Form Work 05-Jun-15 11-Jun-15 04-Jun-15 11-Jun-15 Form Work
A00565 6 Concrete in Columns 05-Jun-15 12-Jun-15 05-Jun-15 12-Jun-15 Concrete in Columns
Slab & Beams 13 22-Jun-15 07-Jul-15 22-Jun-15 07-Jul-15 07-Jul-15, Slab & Beams
A00568 4 Steel Reinforcement 01-Jul-15 06-Jul-15 01-Jul-15 06-Jul-15 Steel Reinforcement
A00567 8 Form Work 22-Jun-15 01-Jul-15 22-Jun-15 30-Jun-15 Form Work
A00569 1 Concrete Pouring 06-Jul-15 07-Jul-15 06-Jul-15 07-Jul-15 Concrete Pouring
Finishing 232 10-Apr-15 28-Jan-16 10-Apr-15 28-Jan-16 28-Jan-16, Finishing
Ground Floor 157 10-Apr-15 30-Oct-15 10-Apr-15 30-Oct-15 30-Oct-15, Ground Floor
A00573 38 Plaster 08-May-15 22-Jun-15 08-May-15 22-Jun-15 Plaster
A00576 30 Paint 19-Aug-15 01-Oct-15 19-Aug-15 01-Oct-15 Paint
A00575 29 Flooring works 14-Jul-15 26-Aug-15 14-Jul-15 26-Aug-15 Flooring works
A00577 23 Doors & Windows fixing 02-Oct-15 30-Oct-15 02-Oct-15 30-Oct-15 Doors & Windows fixing
A00574 29 Ceiling works 16-Jun-15 29-Jul-15 16-Jun-15 29-Jul-15 Ceiling works
A00572 38 Block Masonry 10-Apr-15 25-May-15 10-Apr-15 25-May-15 Block Masonry
First Floor 158 20-May-15 09-Dec-15 19-May-15 09-Dec-15 09-Dec-15, First Floor
A00580 29 Plaster 26-Jun-15 07-Aug-15 25-Jun-15 07-Aug-15 Plaster
A00583 34 Paint 01-Oct-15 11-Nov-15 01-Oct-15 11-Nov-15 Paint
A00582 30 Flooring works 28-Aug-15 09-Oct-15 28-Aug-15 09-Oct-15 Flooring works
A00584 30 Doors & Windows fixing 04-Nov-15 09-Dec-15 04-Nov-15 09-Dec-15 Doors & Windows fixing
A00581 37 Ceiling works 24-Jul-15 04-Sep-15 24-Jul-15 04-Sep-15 Ceiling works
A00579 37 Block Masonry 20-May-15 02-Jul-15 19-May-15 01-Jul-15 Block Masonry
Second Floor 163 30-Jun-15 28-Jan-16 30-Jun-15 28-Jan-16 28-Jan-16, Second Floor
A00587 36 Plaster 28-Jul-15 08-Sep-15 28-Jul-15 08-Sep-15 Plaster
A00590 43 Paint 26-Oct-15 14-Dec-15 26-Oct-15 14-Dec-15 Paint
A00589 35 Flooring works 01-Oct-15 13-Nov-15 01-Oct-15 13-Nov-15 Flooring works
A00591 24 Doors & Windows fixing 31-Dec-15 28-Jan-16 31-Dec-15 28-Jan-16 Doors & Windows fixing
A00588 30 Ceiling works 01-Sep-15 14-Oct-15 01-Sep-15 14-Oct-15 Ceiling works
A00586 28 Block Masonry 30-Jun-15 11-Aug-15 30-Jun-15 11-Aug-15 Block Masonry
Mechanical Floor 108 30-Jul-15 14-Dec-15 30-Jul-15 14-Dec-15 14-Dec-15, Mechanical Floor
A00599 37 Roof Screeding and Water Proofing 30-Jul-15 11-Sep-15 30-Jul-15 11-Sep-15 Roof Screeding and Water Proofing
A00594 14 Plaster 08-Sep-15 02-Oct-15 08-Sep-15 02-Oct-15 Plaster
A00597 22 Paint 04-Nov-15 30-Nov-15 04-Nov-15 30-Nov-15 Paint
A00596 18 Flooring works 20-Oct-15 11-Nov-15 20-Oct-15 11-Nov-15 Flooring works
A00598 12 Doors & Windows fixing 30-Nov-15 14-Dec-15 30-Nov-15 14-Dec-15 Doors & Windows fixing
A00595 18 Ceiling Works 01-Oct-15 23-Oct-15 01-Oct-15 23-Oct-15 Ceiling Works
A00593 21 Block Masonry 13-Aug-15 07-Sep-15 13-Aug-15 07-Sep-15 Block Masonry
MEP WORKS 302 12-Feb-15 20-Nov-15 23-Jan-15 20-Oct-15 20-Nov-15, MEP WORKS
Water Body Struc ture Works 111 06-Nov-14 A 10-Apr-15 31-Oct-14 27-Feb-15 10-Apr-15, Water Body Structure Works
WB-Part 1 106 06-Nov-14 A 10-Apr-15 31-Oct-14 16-Feb-15 10-Apr-15, WB-Part 1
A7850 20 Waterproofing 15-Jan-15 A 22-Jan-15 A 22-Nov-14 11-Dec-14 Waterproofing
A7960 10 Water Proofing 09-Mar-15 18-Mar-15 14-Jan-15 23-Jan-15 Water Proofing
A7930 20 Wall Reinforcement 25-Feb-15 16-Mar-15 02-Jan-15 21-Jan-15 Wall Reinforcement
A7940 20 Wall Form Work 02-Mar-15 20-Mar-15 07-Jan-15 26-Jan-15 Wall Form Work
A7950 20 Wall Concrete 04-Mar-15 23-Mar-15 09-Jan-15 28-Jan-15 Wall Concrete
A7830 25 Termite Proofing 15-Nov-14 A 20-Jan-15 A 14-Nov-14 08-Dec-14 Termite Proofing

Primary Baseline Remaining Work Milestone Page 10 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A7900 25 Reinforcement Slab 14-Jan-15 A 12-Feb-15 18-Dec-14 10-Jan-15 Reinforcement Slab
A7860 20 Reinforcement Beams 30-Dec-14 A 06-Feb-15 A 27-Nov-14 16-Dec-14 Reinforcement Beams
A7840 20 Lean Concrete 15-Nov-14 A 20-Jan-15 A 20-Nov-14 09-Dec-14 Lean Concrete
A7891 20 Lean and Water Proofing 10-Jan-15 A 21-Feb-15 A 09-Dec-14 27-Dec-14 Lean and Water Proofing
A7910 25 FormWork Slab 12-Feb-15 06-Mar-15 20-Dec-14 12-Jan-15 FormWork Slab
A7870 20 FormWork Beams 17-Jan-15 A 06-Feb-15 A 02-Dec-14 20-Dec-14 FormWork Beams
A7820 25 Excavation 06-Nov-14 A 17-Nov-14 A 31-Oct-14 24-Nov-14 Excavation
A7890 20 Earth filling 02-Dec-14 A 19-Jan-15 A 06-Dec-14 24-Dec-14 Earth filling
A7970 25 Connecting Slabs 18-Mar-15 10-Apr-15 23-Jan-15 16-Feb-15 Connecting Slabs
A7920 25 Concrete Slab 13-Feb-15 09-Mar-15 22-Dec-14 14-Jan-15 Concrete Slab
A7880 20 Concrete Beams 19-Jan-15 A 06-Feb-15 A 03-Dec-14 22-Dec-14 Concrete Beams
WB-Part 2 111 06-Nov-14 A 10-Apr-15 12-Nov-14 27-Feb-15 10-Apr-15, WB-Part 2
A8010 20 Waterproofing 21-Jan-15 A 02-Feb-15 A 04-Dec-14 23-Dec-14 Waterproofing
A8130 10 Water Proofing 09-Mar-15 18-Mar-15 26-Jan-15 04-Feb-15 Water Proofing
A8100 20 Wall Reinforcement 25-Feb-15 16-Mar-15 13-Jan-15 31-Jan-15 Wall Reinforcement
A8110 20 Wall Form Work 02-Mar-15 20-Mar-15 17-Jan-15 05-Feb-15 Wall Form Work
A8120 20 Wall Concrete 04-Mar-15 23-Mar-15 21-Jan-15 09-Feb-15 Wall Concrete
A7990 25 Termite Proofing 06-Nov-14 A 01-Feb-15 A 26-Nov-14 19-Dec-14 Termite Proofing
A8070 25 Reinforcement Slab 04-Feb-15 A 28-Feb-15 30-Dec-14 21-Jan-15 Reinforcement Slab
A8020 20 Reinforcement Beams 18-Dec-14 A 04-Feb-15 A 09-Dec-14 27-Dec-14 Reinforcement Beams
A8000 21 Lean Concrete 06-Nov-14 A 01-Feb-15 A 02-Dec-14 20-Dec-14 Lean Concrete
A8060 20 Lean and Water Proofing 02-Feb-15 A 16-Feb-15 20-Dec-14 07-Jan-15 Lean and Water Proofing
A8080 25 FormWork Slab 12-Feb-15 06-Mar-15 31-Dec-14 23-Jan-15 FormWork Slab
A8030 20 FormWork Beams 21-Jan-15 A 04-Feb-15 A 13-Dec-14 01-Jan-15 FormWork Beams
A7980 25 Excavation 06-Nov-14 A 30-Nov-14 A 12-Nov-14 05-Dec-14 Excavation
A8050 20 Earth filling 17-Dec-14 A 17-Feb-15 17-Dec-14 05-Jan-15 Earth filling
A8140 25 Connecting Slabs 18-Mar-15 10-Apr-15 04-Feb-15 27-Feb-15 Connecting Slabs
A8090 25 Concrete Slab 13-Feb-15 09-Mar-15 02-Jan-15 26-Jan-15 Concrete Slab
A8040 20 Concrete Beams 28-Jan-15 A 06-Feb-15 A 15-Dec-14 02-Jan-15 Concrete Beams
ZONE-3 (BLOCK- C AND BLOCK- F) 491 01-Sep-14 A 18-Mar-16 09-Sep-14 02-Mar-16 18-Mar-16, ZONE-3 (BLOCK- C
BLOCK- C 436 01-Sep-14 A 27-Jan-16 09-Sep-14 30-Dec-15 27-Jan-16, BLOCK- C
Earth Works 25 01-Sep-14 A 13-Nov-14 A 09-Sep-14 16-Oct-14 13-Nov-14 A, Earth Works
A00711 21 Termite Proofing 18-Sep-14 A 13-Nov-14 A 19-Sep-14 16-Oct-14 Termite Proofing
A00710 22 Excavations 01-Sep-14 A 24-Oct-14 A 09-Sep-14 06-Oct-14 Excavations
Strcutural Works 200 18-Sep-14 A 24-Aug-15 22-Sep-14 10-Jul-15 24-Aug-15, Strcutural Works
Lower Ground Floor 97 18-Sep-14 A 16-Apr-15 22-Sep-14 09-Mar-15 16-Apr-15, Lower Ground Floor
Pile Caps 37 18-Sep-14 A 16-Feb-15 22-Sep-14 11-Nov-14 16-Feb-15, Pile Caps
A00716 30 Steel Reinforcement Work 25-Sep-14 A 12-Feb-15 23-Sep-14 30-Oct-14 Steel Reinforcement Work
A00715 22 Lean Concrete 18-Sep-14 A 13-Nov-14 A 22-Sep-14 17-Oct-14 Lean Concrete
A00717 31 Form Work 27-Sep-14 A 13-Feb-15 26-Sep-14 04-Nov-14 Form Work
A00718 26 Concrete in Pile Caps 30-Sep-14 A 16-Feb-15 13-Oct-14 11-Nov-14 Concrete in Pile Caps
Sub Base, Ground Beams & SOG 53 28-Oct-14 A 16-Mar-15 21-Oct-14 26-Dec-14 16-Mar-15, Sub Base, Ground Beams & SOG
A00723 24 Water Proofing 06-Dec-14 A 04-Mar-15 14-Nov-14 15-Dec-14 Water Proofing
A00725 25 Steel Reinforcement 13-Dec-14 A 11-Mar-15 21-Nov-14 22-Dec-14 Steel Reinforcement
A00721 33 Soling 24-Nov-14 A 23-Feb-15 27-Oct-14 05-Dec-14 Soling
A00724 26 Protection of Water Proofing 08-Dec-14 A 06-Mar-15 19-Nov-14 17-Dec-14 Protection of Water Proofing
A00720 33 Earth Filling 28-Oct-14 A 16-Feb-15 21-Oct-14 28-Nov-14 Earth Filling
A00726 23 Concrete 25-Dec-14 A 16-Mar-15 27-Nov-14 26-Dec-14 Concrete
A00722 26 1:4:8 04-Dec-14 A 25-Feb-15 07-Nov-14 08-Dec-14 1:4:8
Columns 45 07-Jan-15 A 25-Feb-15 25-Nov-14 16-Jan-15 25-Feb-15, Columns
A00728 40 Steel Reinforcement Work 07-Jan-15 A 24-Feb-15 25-Nov-14 12-Jan-15 Steel Reinforcement Work

Primary Baseline Remaining Work Milestone Page 11 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A00729 41 Form Work 16-Jan-15 A 25-Feb-15 27-Nov-14 14-Jan-15 Form Work
A00730 42 Concrete in Columns 17-Jan-15 A 25-Feb-15 28-Nov-14 16-Jan-15 Concrete in Columns
Shear Walls 45 20-Jan-15 A 01-Apr-15 26-Nov-14 16-Jan-15 01-Apr-15, Shear Walls
A00732 40 Steel Reinforcement Work 20-Jan-15 A 27-Mar-15 26-Nov-14 12-Jan-15 Steel Reinforcement Work
A00733 42 Form Work 30-Jan-15 A 30-Mar-15 28-Nov-14 16-Jan-15 Form Work
A00734 42 Concrete in shear Walls 12-Feb-15 01-Apr-15 01-Dec-14 16-Jan-15 Concrete in shear Walls
Retaining Wall 51 01-Dec-14 A 10-Apr-15 25-Nov-14 27-Feb-15 10-Apr-15, Retaining Wall
A00736 50 Steel Reinforcement Work 01-Dec-14 A 24-Mar-15 25-Nov-14 20-Jan-15 Steel Reinforcement Work
A00737 49 Form Work 10-Dec-14 A 23-Mar-15 27-Nov-14 23-Jan-15 Form Work
A00738 48 Concrete in Wall 13-Jan-15 A 10-Apr-15 01-Jan-15 27-Feb-15 Concrete in Wall
Slab & Beams 43 26-Feb-15 16-Apr-15 19-Jan-15 09-Mar-15 16-Apr-15, Slab & Beams
Pour -1 Block C area 28 26-Feb-15 30-Mar-15 19-Jan-15 19-Feb-15 30-Mar-15, Pour -1 Block C area
A00741 6 Steel Reinforcement 19-Mar-15 26-Mar-15 09-Feb-15 16-Feb-15 Steel Reinforcement
A00740 19 Form Work 26-Feb-15 19-Mar-15 19-Jan-15 09-Feb-15 Form Work
A00742 1 Concrete Pouring 30-Mar-15 30-Mar-15 19-Feb-15 19-Feb-15 Concrete Pouring
Pour - 2 Block D Area 28 16-Mar-15 16-Apr-15 04-Feb-15 09-Mar-15 16-Apr-15, Pour - 2 Block D Area
A7670 6 Steel Reinforcement 06-Apr-15 13-Apr-15 26-Feb-15 05-Mar-15 Steel Reinforcement
A7660 19 Form Work 16-Mar-15 06-Apr-15 04-Feb-15 26-Feb-15 Form Work
A7680 1 Concrete Pouring 16-Apr-15 16-Apr-15 09-Mar-15 09-Mar-15 Concrete Pouring
Ground Floor 34 01-Apr-15 11-May-15 23-Feb-15 03-Apr-15 11-May-15, Ground Floor
Columns 13 01-Apr-15 16-Apr-15 23-Feb-15 06-Mar-15 16-Apr-15, Columns
A00745 10 Steel Reinforcement Work 01-Apr-15 13-Apr-15 23-Feb-15 05-Mar-15 Steel Reinforcement Work
A00746 12 Form Work 02-Apr-15 15-Apr-15 23-Feb-15 06-Mar-15 Form Work
A00747 11 Concrete in Columns 03-Apr-15 16-Apr-15 24-Feb-15 06-Mar-15 Concrete in Columns
Shear Walls 13 01-Apr-15 16-Apr-15 23-Feb-15 09-Mar-15 16-Apr-15, Shear Walls
A00749 10 Steel Reinforcement Work 01-Apr-15 13-Apr-15 23-Feb-15 05-Mar-15 Steel Reinforcement Work
A00750 12 Form Work 02-Apr-15 15-Apr-15 23-Feb-15 06-Mar-15 Form Work
A00751 11 Concrete in Walls 03-Apr-15 16-Apr-15 24-Feb-15 09-Mar-15 Concrete in Walls
Slab & Beams 18 20-Apr-15 11-May-15 11-Mar-15 03-Apr-15 11-May-15, Slab & Beams
A00754 5 Steel Reinforcement 04-May-15 08-May-15 26-Mar-15 02-Apr-15 Steel Reinforcement
A00753 11 Form Work 20-Apr-15 01-May-15 11-Mar-15 25-Mar-15 Form Work
A00755 0 Concrete Pouring 11-May-15 11-May-15 03-Apr-15 03-Apr-15 Concrete Pouring
First Floor 33 13-May-15 19-Jun-15 06-Apr-15 13-May-15 19-Jun-15, First Floor
Columns 7 13-May-15 21-May-15 06-Apr-15 14-Apr-15 21-May-15, Columns
A00758 5 Steel Reinforcement Work 13-May-15 19-May-15 06-Apr-15 10-Apr-15 Steel Reinforcement Work
A00759 6 Form Work 14-May-15 20-May-15 07-Apr-15 13-Apr-15 Form Work
A00760 5 Concrete in Columns 15-May-15 21-May-15 08-Apr-15 14-Apr-15 Concrete in Columns
Shear Walls 7 13-May-15 21-May-15 06-Apr-15 14-Apr-15 21-May-15, Shear Walls
A00762 5 Steel Reinforcement Work 13-May-15 19-May-15 06-Apr-15 10-Apr-15 Steel Reinforcement Work
A00763 6 Form Work 14-May-15 21-May-15 07-Apr-15 14-Apr-15 Form Work
A00764 5 Concrete in Walls 15-May-15 21-May-15 08-Apr-15 14-Apr-15 Concrete in Walls
Slab & Beams 17 01-Jun-15 19-Jun-15 23-Apr-15 13-May-15 19-Jun-15, Slab & Beams
A00767 6 Steel Reinforcement 11-Jun-15 17-Jun-15 05-May-15 12-May-15 Steel Reinforcement
A00766 9 Form Work 01-Jun-15 10-Jun-15 23-Apr-15 05-May-15 Form Work
A00768 1 Concrete Pouring 18-Jun-15 19-Jun-15 13-May-15 13-May-15 Concrete Pouring
Second Floor 24 19-Jun-15 27-Jul-15 14-May-15 11-Jun-15 27-Jul-15, Second Floor
Columns 8 19-Jun-15 29-Jun-15 14-May-15 22-May-15 29-Jun-15, Columns
A8930 6 Steel Reinforcement Work 19-Jun-15 26-Jun-15 14-May-15 20-May-15 Steel Reinforcement Work
A8940 5 Form Work 22-Jun-15 26-Jun-15 15-May-15 21-May-15 Form Work
A8950 5 Concrete in Columns 23-Jun-15 29-Jun-15 18-May-15 22-May-15 Concrete in Columns
Shear Walls 8 19-Jun-15 29-Jun-15 14-May-15 22-May-15 29-Jun-15, Shear Walls
A8960 6 Steel Reinforcement Work 19-Jun-15 26-Jun-15 14-May-15 20-May-15 Steel Reinforcement Work

Primary Baseline Remaining Work Milestone Page 12 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A8970 6 Form Work 22-Jun-15 29-Jun-15 15-May-15 22-May-15 Form Work
A8980 5 Concrete in Walls 23-Jun-15 29-Jun-15 18-May-15 22-May-15 Concrete in Walls
Slab & Beams 17 29-Jun-15 27-Jul-15 22-May-15 11-Jun-15 27-Jul-15, Slab & Beams
A9000 5 Steel Reinforcement 09-Jul-15 16-Jul-15 03-Jun-15 10-Jun-15 Steel Reinforcement
A8990 9 Form Work 29-Jun-15 09-Jul-15 22-May-15 03-Jun-15 Form Work
A9010 2 Concrete Pouring 24-Jul-15 27-Jul-15 11-Jun-15 11-Jun-15 Concrete Pouring
Roof 24 27-Jul-15 24-Aug-15 12-Jun-15 10-Jul-15 24-Aug-15, Roof
Columns 7 27-Jul-15 04-Aug-15 12-Jun-15 22-Jun-15 04-Aug-15, Columns
A9020 6 Steel Reinforcement Work 27-Jul-15 03-Aug-15 12-Jun-15 18-Jun-15 Steel Reinforcement Work
A9030 6 Form Work 28-Jul-15 04-Aug-15 15-Jun-15 19-Jun-15 Form Work
A9040 5 Concrete in Columns 29-Jul-15 04-Aug-15 16-Jun-15 22-Jun-15 Concrete in Columns
Shear Walls 7 27-Jul-15 04-Aug-15 12-Jun-15 22-Jun-15 04-Aug-15, Shear Walls
A9050 6 Steel Reinforcement Work 27-Jul-15 03-Aug-15 12-Jun-15 18-Jun-15 Steel Reinforcement Work
A9060 6 Form Work 28-Jul-15 04-Aug-15 15-Jun-15 22-Jun-15 Form Work
A9070 5 Concrete in Walls 29-Jul-15 04-Aug-15 16-Jun-15 22-Jun-15 Concrete in Walls
Slab & Beams 17 04-Aug-15 24-Aug-15 22-Jun-15 10-Jul-15 24-Aug-15, Slab & Beams
A9090 6 Steel Reinforcement 14-Aug-15 21-Aug-15 02-Jul-15 09-Jul-15 Steel Reinforcement
A9080 9 Form Work 04-Aug-15 14-Aug-15 22-Jun-15 02-Jul-15 Form Work
A9100 1 Concrete Pouring 24-Aug-15 24-Aug-15 10-Jul-15 10-Jul-15 Concrete Pouring
Finishing 217 28-Apr-15 27-Jan-16 20-Mar-15 30-Dec-15 27-Jan-16, Finishing
Lower Ground Floor 108 28-Apr-15 09-Sep-15 20-Mar-15 27-Jul-15 09-Sep-15, Lower Ground Floor
A00772 25 Plaster 15-May-15 12-Jun-15 07-Apr-15 05-May-15 Plaster
A00775 25 Paint 24-Jul-15 21-Aug-15 01-Jun-15 29-Jun-15 Paint
A00774 17 Flooring works 01-Jul-15 29-Jul-15 13-May-15 10-Jun-15 Flooring works
A00776 16 Doors & Windows fixing 21-Aug-15 09-Sep-15 09-Jul-15 27-Jul-15 Doors & Windows fixing
A00773 24 Ceiling works 03-Jun-15 01-Jul-15 24-Apr-15 22-May-15 Ceiling works
A00771 24 Block Masonry 28-Apr-15 25-May-15 20-Mar-15 16-Apr-15 Block Masonry
Ground Floor 106 08-Jun-15 29-Oct-15 01-May-15 09-Sep-15 29-Oct-15, Ground Floor
A00779 16 Plaster 06-Jul-15 03-Aug-15 20-May-15 17-Jun-15 Plaster
A00782 17 Paint 08-Sep-15 06-Oct-15 24-Jul-15 21-Aug-15 Paint
A00781 24 Flooring works 12-Aug-15 09-Sep-15 06-Jul-15 03-Aug-15 Flooring works
A00783 22 Doors & Windows fixing 01-Oct-15 29-Oct-15 12-Aug-15 09-Sep-15 Doors & Windows fixing
A00780 25 Ceiling works 24-Jul-15 21-Aug-15 05-Jun-15 06-Jul-15 Ceiling works
A00778 24 Block Masonry 08-Jun-15 06-Jul-15 01-May-15 29-May-15 Block Masonry
First Floor 115 03-Jul-15 04-Dec-15 28-May-15 30-Oct-15 04-Dec-15, First Floor
A00791 30 Roof Screeding and Water Proofing 03-Jul-15 17-Aug-15 28-May-15 09-Jul-15 Roof Screeding and Water Proofing
A00786 25 Plaster 14-Aug-15 11-Sep-15 08-Jul-15 06-Aug-15 Plaster
A00789 28 Paint 13-Oct-15 17-Nov-15 04-Sep-15 09-Oct-15 Paint
A00788 22 Flooring works 02-Oct-15 29-Oct-15 17-Aug-15 14-Sep-15 Flooring works
A00790 16 Doors & Windows fixing 17-Nov-15 04-Dec-15 13-Oct-15 30-Oct-15 Doors & Windows fixing
A00787 18 Ceiling works 10-Sep-15 08-Oct-15 29-Jul-15 26-Aug-15 Ceiling works
A00785 25 Block Masonry 27-Jul-15 25-Aug-15 11-Jun-15 09-Jul-15 Block Masonry
Second Floor 107 10-Aug-15 23-Dec-15 26-Jun-15 05-Nov-15 23-Dec-15, Second Floor
A9120 19 Plaster 04-Sep-15 05-Oct-15 14-Jul-15 12-Aug-15 Plaster
A9150 30 Paint 30-Oct-15 04-Dec-15 10-Sep-15 15-Oct-15 Paint
A9140 22 Flooring works 20-Oct-15 17-Nov-15 21-Aug-15 18-Sep-15 Flooring works
A9160 17 Doors & Windows fixing 04-Dec-15 23-Dec-15 16-Oct-15 05-Nov-15 Doors & Windows fixing
A9130 23 Ceiling works 01-Oct-15 29-Oct-15 03-Aug-15 31-Aug-15 Ceiling works
A9110 25 Block Masonry 10-Aug-15 08-Sep-15 26-Jun-15 24-Jul-15 Block Masonry
Roof Floor 111 08-Sep-15 27-Jan-16 04-Aug-15 30-Dec-15 27-Jan-16, Roof Floor
A9240 30 Roof Screeding and Water Proofing 08-Sep-15 20-Oct-15 04-Aug-15 15-Sep-15 Roof Screeding and Water Proofing
A9190 23 Plaster 01-Oct-15 29-Oct-15 21-Aug-15 18-Sep-15 Plaster

Primary Baseline Remaining Work Milestone Page 13 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A9220 28 Paint 04-Dec-15 08-Jan-16 04-Nov-15 09-Dec-15 Paint
A9210 24 Flooring works 20-Nov-15 18-Dec-15 26-Oct-15 20-Nov-15 Flooring works
A9230 17 Doors & Windows fixing 07-Jan-16 27-Jan-16 11-Dec-15 30-Dec-15 Doors & Windows fixing
A9200 25 Ceiling works 02-Nov-15 30-Nov-15 05-Oct-15 02-Nov-15 Ceiling works
A9180 18 Block Masonry 08-Sep-15 06-Oct-15 04-Aug-15 01-Sep-15 Block Masonry
MEP WORKS 374 12-Feb-15 27-Jan-16 19-Sep-14 11-Dec-15 27-Jan-16, MEP WORKS
BLOCK- F 488 06-Nov-14 A 18-Mar-16 27-Nov-14 02-Mar-16 18-Mar-16, BLOCK- F
Earth Works 16 06-Nov-14 A 12-Feb-15 27-Nov-14 16-Dec-14 12-Feb-15, Earth Works
A00902 12 Termite Proofing 14-Nov-14 A 12-Feb-15 02-Dec-14 16-Dec-14 Termite Proofing
A00901 12 Excavations 06-Nov-14 A 29-Dec-14 A 27-Nov-14 11-Dec-14 Excavations
Strcutural Works 130 14-Nov-14 A 22-May-15 27-Nov-14 27-Mar-15 22-May-15, Strcutural Works
Ground Floor 96 14-Nov-14 A 14-Apr-15 27-Nov-14 17-Feb-15 14-Apr-15, Ground Floor
Pile Caps 23 14-Nov-14 A 20-Feb-15 27-Nov-14 24-Dec-14 20-Feb-15, Pile Caps
A00907 19 Steel Reinforcement Work 18-Nov-14 A 17-Feb-15 27-Nov-14 19-Dec-14 Steel Reinforcement Work
A00906 12 Lean Concrete 14-Nov-14 A 12-Feb-15 02-Dec-14 16-Dec-14 Lean Concrete
A00908 21 Form Work 22-Nov-14 A 19-Feb-15 27-Nov-14 23-Dec-14 Form Work
A00909 23 Concrete in Pile Caps 24-Nov-14 A 20-Feb-15 28-Nov-14 24-Dec-14 Concrete in Pile Caps
Sub Base, Ground Beams & SOG 72 08-Dec-14 A 16-Mar-15 06-Dec-14 21-Jan-15 16-Mar-15, Sub Base, Ground Beams & SOG
A00914 12 Water Proofing 30-Dec-14 A 04-Mar-15 23-Dec-14 08-Jan-15 Water Proofing
A00916 10 Steel Reinforcement 01-Jan-15 A 11-Mar-15 02-Jan-15 15-Jan-15 Steel Reinforcement
A00912 12 Soling 28-Dec-14 A 23-Feb-15 13-Dec-14 27-Dec-14 Soling
A00915 12 Protection of Water Proofing 31-Dec-14 A 06-Mar-15 25-Dec-14 10-Jan-15 Protection of Water Proofing
A00911 12 Earth Filling 08-Dec-14 A 16-Feb-15 06-Dec-14 20-Dec-14 Earth Filling
A00917 12 Concrete 02-Mar-15 16-Mar-15 07-Jan-15 21-Jan-15 Concrete
A00913 12 1:4:8 29-Jan-15 A 25-Feb-15 16-Dec-14 30-Dec-14 1:4:8
Columns 15 06-Mar-15 24-Mar-15 12-Jan-15 27-Jan-15 24-Mar-15, Columns
A00919 12 Steel Reinforcement Work 06-Mar-15 20-Mar-15 12-Jan-15 23-Jan-15 Steel Reinforcement Work
A00920 12 Form Work 09-Mar-15 23-Mar-15 13-Jan-15 27-Jan-15 Form Work
A00921 12 Concrete in Columns 10-Mar-15 24-Mar-15 13-Jan-15 27-Jan-15 Concrete in Columns
Shear Walls 16 06-Mar-15 25-Mar-15 12-Jan-15 28-Jan-15 25-Mar-15, Shear Walls
A00923 12 Steel Reinforcement Work 06-Mar-15 20-Mar-15 12-Jan-15 23-Jan-15 Steel Reinforcement Work
A00924 12 Form Work 09-Mar-15 23-Mar-15 13-Jan-15 27-Jan-15 Form Work
A00925 12 Concrete in Columns 11-Mar-15 25-Mar-15 14-Jan-15 28-Jan-15 Concrete in Columns
Slab & Beams 17 25-Mar-15 14-Apr-15 28-Jan-15 17-Feb-15 14-Apr-15, Slab & Beams
A00928 4 Steel Reinforcement 08-Apr-15 13-Apr-15 12-Feb-15 16-Feb-15 Steel Reinforcement
A00927 12 Form Work 25-Mar-15 08-Apr-15 28-Jan-15 12-Feb-15 Form Work
A00929 1 Concrete Pouring 13-Apr-15 14-Apr-15 16-Feb-15 17-Feb-15 Concrete Pouring
First Floor 31 16-Apr-15 22-May-15 19-Feb-15 27-Mar-15 22-May-15, First Floor
Columns 7 16-Apr-15 24-Apr-15 19-Feb-15 27-Feb-15 24-Apr-15, Columns
A00932 4 Steel Reinforcement Work 16-Apr-15 21-Apr-15 19-Feb-15 24-Feb-15 Steel Reinforcement Work
A00933 6 Form Work 16-Apr-15 23-Apr-15 19-Feb-15 26-Feb-15 Form Work
A00934 6 Concrete in Columns 17-Apr-15 24-Apr-15 20-Feb-15 27-Feb-15 Concrete in Columns
Shear Walls 7 16-Apr-15 24-Apr-15 19-Feb-15 27-Feb-15 24-Apr-15, Shear Walls
A00936 4 Steel Reinforcement Work 16-Apr-15 21-Apr-15 19-Feb-15 24-Feb-15 Steel Reinforcement Work
A00937 6 Form Work 16-Apr-15 23-Apr-15 19-Feb-15 26-Feb-15 Form Work
A00938 6 Concrete in Columns 17-Apr-15 24-Apr-15 20-Feb-15 27-Feb-15 Concrete in Columns
Slab & Beams 16 04-May-15 22-May-15 09-Mar-15 27-Mar-15 22-May-15, Slab & Beams
A00941 3 Steel Reinforcement 18-May-15 21-May-15 23-Mar-15 27-Mar-15 Steel Reinforcement
A00940 12 Form Work 04-May-15 18-May-15 09-Mar-15 23-Mar-15 Form Work
A00942 1 Concrete Pouring 21-May-15 22-May-15 27-Mar-15 27-Mar-15 Concrete Pouring
Finishing 135 12-May-15 04-Nov-15 17-Mar-15 02-Sep-15 04-Nov-15, Finishing
Ground Floor 104 12-May-15 18-Sep-15 17-Mar-15 27-Jul-15 18-Sep-15, Ground Floor

Primary Baseline Remaining Work Milestone Page 14 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A00946 25 Plaster 29-May-15 26-Jun-15 03-Apr-15 04-May-15 Plaster
A00949 24 Paint 03-Aug-15 31-Aug-15 01-Jun-15 29-Jun-15 Paint
A00948 24 Flooring works 06-Jul-15 12-Aug-15 13-May-15 10-Jun-15 Flooring works
A00950 16 Doors & Windows fixing 31-Aug-15 18-Sep-15 29-Jun-15 27-Jul-15 Doors & Windows fixing
A00947 24 Ceiling works 17-Jun-15 24-Jul-15 24-Apr-15 22-May-15 Ceiling works
A00945 25 Block Masonry 12-May-15 09-Jun-15 17-Mar-15 15-Apr-15 Block Masonry
First Floor 113 05-Jun-15 04-Nov-15 10-Apr-15 02-Sep-15 04-Nov-15, First Floor
A00958 24 Roof Screeding and Water Proofing 05-Jun-15 03-Jul-15 10-Apr-15 08-May-15 Roof Screeding and Water Proofing
A00953 16 Plaster 14-Jul-15 11-Aug-15 13-May-15 10-Jun-15 Plaster
A00956 24 Paint 08-Sep-15 14-Oct-15 08-Jul-15 14-Aug-15 Paint
A00955 24 Flooring works 20-Aug-15 17-Sep-15 19-Jun-15 27-Jul-15 Flooring works
A00957 16 Doors & Windows fixing 14-Oct-15 04-Nov-15 14-Aug-15 02-Sep-15 Doors & Windows fixing
A00954 24 Ceiling works 01-Aug-15 29-Aug-15 01-Jun-15 29-Jun-15 Ceiling works
A00952 22 Block Masonry 19-Jun-15 17-Jul-15 27-Apr-15 22-May-15 Block Masonry
MEP WORKS 430 12-Feb-15 18-Mar-16 05-Jan-15 02-Mar-16 18-Mar-16, MEP WORKS
ZONE-4 (BLOCK- D AND BLOCK- E) 572 01-Sep-14 A 31-May-16 20-Oct-14 13-Apr-16 31-May-16, ZONE-4 (B
BLOCK- D 570 01-Sep-14 A 31-May-16 20-Oct-14 13-Apr-16 31-May-16, BLOCK- D
Earth Works 47 01-Sep-14 A 25-Dec-14 A 20-Oct-14 15-Dec-14 25-Dec-14 A, Earth Works
A01037 46 Termite Proofing 02-Oct-14 A 25-Dec-14 A 21-Oct-14 15-Dec-14 Termite Proofing
A01036 43 Excavations 01-Sep-14 A 11-Dec-14 A 20-Oct-14 10-Dec-14 Excavations
Strcutural Works 298 02-Oct-14 A 22-Dec-15 21-Oct-14 05-Nov-15 22-Dec-15, Strcutural Works
Lower Ground Floor 150 02-Oct-14 A 12-Jun-15 21-Oct-14 05-May-15 12-Jun-15, Lower Ground Floor
Pile Caps 54 02-Oct-14 A 28-Dec-14 A 21-Oct-14 24-Dec-14 28-Dec-14 A, Pile Caps
A01042 37 Steel Reinforcement Work 07-Nov-14 A 27-Dec-14 A 06-Nov-14 19-Dec-14 Steel Reinforcement Work
A01041 46 Lean Concrete 02-Oct-14 A 25-Dec-14 A 21-Oct-14 15-Dec-14 Lean Concrete
A01043 37 Form Work 10-Nov-14 A 28-Dec-14 A 10-Nov-14 23-Dec-14 Form Work
A01044 25 Concrete in Pile Caps 08-Nov-14 A 28-Dec-14 A 26-Nov-14 24-Dec-14 Concrete in Pile Caps
Sub Base, Ground Beams & SOG 74 01-Dec-14 A 25-Mar-15 04-Dec-14 11-Feb-15 25-Mar-15, Sub Base, Ground Beams & SOG
A01049 36 Water Proofing 17-Dec-14 A 13-Mar-15 17-Dec-14 30-Jan-15 Water Proofing
A01051 37 Steel Reinforcement 19-Dec-14 A 20-Mar-15 26-Dec-14 06-Feb-15 Steel Reinforcement
A01047 37 Soling 10-Dec-14 A 05-Mar-15 10-Dec-14 22-Jan-15 Soling
A01050 34 Protection of Water Proofing 18-Dec-14 A 16-Mar-15 22-Dec-14 02-Feb-15 Protection of Water Proofing
A01046 35 Earth Filling 01-Dec-14 A 20-Feb-15 04-Dec-14 15-Jan-15 Earth Filling
A01052 38 Concrete 06-Jan-15 A 25-Mar-15 30-Dec-14 11-Feb-15 Concrete
A01048 37 1:4:8 15-Dec-14 A 06-Mar-15 12-Dec-14 23-Jan-15 1:4:8
Columns 28 03-Feb-15 A 11-Mar-15 07-Jan-15 06-Feb-15 11-Mar-15, Columns
A01054 26 Steel Reinforcement Work 03-Feb-15 A 06-Mar-15 07-Jan-15 05-Feb-15 Steel Reinforcement Work
A01055 26 Form Work 04-Feb-15 A 11-Mar-15 07-Jan-15 06-Feb-15 Form Work
A01056 26 Concrete in Columns 05-Feb-15 A 11-Mar-15 07-Jan-15 06-Feb-15 Concrete in Columns
Shear Walls 30 06-Feb-15 A 13-Mar-15 07-Jan-15 09-Feb-15 13-Mar-15, Shear Walls
A01058 26 Steel Reinforcement Work 06-Feb-15 A 12-Mar-15 07-Jan-15 05-Feb-15 Steel Reinforcement Work
A01059 26 Form Work 07-Feb-15 A 13-Mar-15 07-Jan-15 06-Feb-15 Form Work
A01060 26 Concrete in Walls 08-Feb-15 A 13-Mar-15 09-Jan-15 09-Feb-15 Concrete in Walls
Retaining Wall 29 12-Feb-15 17-Mar-15 07-Jan-15 06-Feb-15 17-Mar-15, Retaining Wall
A01062 26 Steel Reinforcement Work 12-Feb-15 13-Mar-15 07-Jan-15 05-Feb-15 Steel Reinforcement Work
A01063 27 Form Work 13-Feb-15 17-Mar-15 07-Jan-15 06-Feb-15 Form Work
A01064 25 Concrete in Columns 16-Feb-15 17-Mar-15 08-Jan-15 06-Feb-15 Concrete in Columns
Slab & Beams 32 06-May-15 12-Jun-15 30-Mar-15 05-May-15 12-Jun-15, Slab & Beams
A01067 7 Steel Reinforcement 03-Jun-15 11-Jun-15 24-Apr-15 04-May-15 Steel Reinforcement
A01066 24 Form Work 06-May-15 03-Jun-15 30-Mar-15 24-Apr-15 Form Work
A01068 1 Concrete Pouring 11-Jun-15 12-Jun-15 05-May-15 05-May-15 Concrete Pouring
Ground Floor 41 15-Jun-15 11-Aug-15 07-May-15 26-Jun-15 11-Aug-15, Ground Floor

Primary Baseline Remaining Work Milestone Page 15 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Columns 16 15-Jun-15 03-Jul-15 07-May-15 26-May-15 03-Jul-15, Columns
Pour - 1 7 15-Jun-15 23-Jun-15 07-May-15 18-May-15 23-Jun-15, Pour - 1
A01072 4 Steel Reinforcement Work 15-Jun-15 19-Jun-15 07-May-15 13-May-15 Steel Reinforcement Work
A01073 6 Form Work 16-Jun-15 22-Jun-15 11-May-15 15-May-15 Form Work
A01074 5 Concrete in Columns 17-Jun-15 23-Jun-15 12-May-15 18-May-15 Concrete in Columns
Pour - 2 8 24-Jun-15 03-Jul-15 18-May-15 26-May-15 03-Jul-15, Pour - 2
A01076 5 Steel Reinforcement Work 24-Jun-15 30-Jun-15 18-May-15 22-May-15 Steel Reinforcement Work
A01077 5 Form Work 26-Jun-15 02-Jul-15 19-May-15 25-May-15 Form Work
A01078 4 Concrete in Columns 29-Jun-15 03-Jul-15 20-May-15 26-May-15 Concrete in Columns
Shear Walls 16 15-Jun-15 03-Jul-15 07-May-15 26-May-15 03-Jul-15, Shear Walls
Pour -1 7 15-Jun-15 23-Jun-15 07-May-15 15-May-15 23-Jun-15, Pour -1
A01081 4 Steel Reinforcement Work 15-Jun-15 19-Jun-15 07-May-15 13-May-15 Steel Reinforcement Work
A01082 6 Form Work 16-Jun-15 22-Jun-15 11-May-15 15-May-15 Form Work
A01083 5 Concrete in Walls 17-Jun-15 23-Jun-15 11-May-15 15-May-15 Concrete in Walls
Pour -2 8 24-Jun-15 03-Jul-15 18-May-15 26-May-15 03-Jul-15, Pour -2
A01085 5 Steel Reinforcement Work 24-Jun-15 30-Jun-15 18-May-15 22-May-15 Steel Reinforcement Work
A01086 5 Form Work 26-Jun-15 02-Jul-15 19-May-15 25-May-15 Form Work
A01087 4 Concrete in Walls 29-Jun-15 03-Jul-15 20-May-15 26-May-15 Concrete in Walls
Slab & Beams 26 02-Jul-15 11-Aug-15 25-May-15 26-Jun-15 11-Aug-15, Slab & Beams
Pour -1 16 02-Jul-15 30-Jul-15 25-May-15 15-Jun-15 30-Jul-15, Pour -1
A01091 5 Steel Reinforcement 24-Jul-15 30-Jul-15 09-Jun-15 15-Jun-15 Steel Reinforcement
A01090 11 Form Work 02-Jul-15 16-Jul-15 25-May-15 09-Jun-15 Form Work
A01092 0 Concrete Pouring 30-Jul-15 30-Jul-15 15-Jun-15 15-Jun-15 Concrete Pouring
Pour -2 25 03-Jul-15 11-Aug-15 26-May-15 26-Jun-15 11-Aug-15, Pour -2
A01095 4 Steel Reinforcement 24-Jul-15 29-Jul-15 09-Jun-15 15-Jun-15 Steel Reinforcement
A01094 9 Form Work 03-Jul-15 17-Jul-15 26-May-15 09-Jun-15 Form Work
A01096 1 Concrete Pouring 10-Aug-15 11-Aug-15 25-Jun-15 26-Jun-15 Concrete Pouring
First Floor 51 30-Jul-15 05-Oct-15 15-Jun-15 18-Aug-15 05-Oct-15, First Floor
Columns 21 30-Jul-15 24-Aug-15 15-Jun-15 08-Jul-15 24-Aug-15, Columns
Pour - 1 9 30-Jul-15 10-Aug-15 15-Jun-15 24-Jun-15 10-Aug-15, Pour - 1
A01100 5 Steel Reinforcement Work 30-Jul-15 05-Aug-15 15-Jun-15 19-Jun-15 Steel Reinforcement Work
A01101 4 Form Work 03-Aug-15 07-Aug-15 17-Jun-15 23-Jun-15 Form Work
A01102 5 Concrete in Columns 04-Aug-15 10-Aug-15 18-Jun-15 24-Jun-15 Concrete in Columns
Pour - 2 9 13-Aug-15 24-Aug-15 29-Jun-15 08-Jul-15 24-Aug-15, Pour - 2
A01104 5 Steel Reinforcement Work 13-Aug-15 19-Aug-15 29-Jun-15 03-Jul-15 Steel Reinforcement Work
A01105 5 Form Work 14-Aug-15 20-Aug-15 30-Jun-15 06-Jul-15 Form Work
A01106 6 Concrete in Columns 17-Aug-15 24-Aug-15 01-Jul-15 08-Jul-15 Concrete in Columns
Shear Walls 19 30-Jul-15 20-Aug-15 15-Jun-15 07-Jul-15 20-Aug-15, Shear Walls
Pour -1 7 30-Jul-15 07-Aug-15 15-Jun-15 23-Jun-15 07-Aug-15, Pour -1
A01109 5 Steel Reinforcement Work 30-Jul-15 05-Aug-15 15-Jun-15 19-Jun-15 Steel Reinforcement Work
A01110 5 Form Work 31-Jul-15 06-Aug-15 16-Jun-15 22-Jun-15 Form Work
A01111 4 Concrete in Walls 03-Aug-15 07-Aug-15 17-Jun-15 23-Jun-15 Concrete in Walls
Pour -2 7 13-Aug-15 20-Aug-15 29-Jun-15 07-Jul-15 20-Aug-15, Pour -2
A01113 3 Steel Reinforcement Work 13-Aug-15 17-Aug-15 29-Jun-15 01-Jul-15 Steel Reinforcement Work
A01114 5 Form Work 13-Aug-15 19-Aug-15 29-Jun-15 03-Jul-15 Form Work
A01115 4 Concrete in Walls 17-Aug-15 20-Aug-15 01-Jul-15 07-Jul-15 Concrete in Walls
Slab & Beams 34 19-Aug-15 05-Oct-15 06-Jul-15 18-Aug-15 05-Oct-15, Slab & Beams
Pour -1 17 19-Aug-15 08-Sep-15 06-Jul-15 30-Jul-15 08-Sep-15, Pour -1
A01119 4 Steel Reinforcement 02-Sep-15 07-Sep-15 24-Jul-15 29-Jul-15 Steel Reinforcement
A01118 12 Form Work 19-Aug-15 02-Sep-15 06-Jul-15 20-Jul-15 Form Work
A01120 1 Concrete Pouring 07-Sep-15 08-Sep-15 29-Jul-15 30-Jul-15 Concrete Pouring
Pour -2 17 08-Sep-15 05-Oct-15 30-Jul-15 18-Aug-15 05-Oct-15, Pour -2
A01123 0 Steel Reinforcement 22-Sep-15 24-Sep-15 13-Aug-15 17-Aug-15 Steel Reinforcement

Primary Baseline Remaining Work Milestone Page 16 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A01122 12 Form Work 08-Sep-15 22-Sep-15 30-Jul-15 13-Aug-15 Form Work
A01124 1 Concrete Pouring 05-Oct-15 05-Oct-15 17-Aug-15 18-Aug-15 Concrete Pouring
Second Floor 50 10-Sep-15 17-Nov-15 03-Aug-15 07-Oct-15 17-Nov-15, Second Floor
Columns 28 10-Sep-15 20-Oct-15 03-Aug-15 03-Sep-15 20-Oct-15, Columns
Pour - 1 10 10-Sep-15 21-Sep-15 03-Aug-15 13-Aug-15 21-Sep-15, Pour - 1
A01128 6 Steel Reinforcement Work 10-Sep-15 16-Sep-15 03-Aug-15 07-Aug-15 Steel Reinforcement Work
A01129 4 Form Work 14-Sep-15 18-Sep-15 05-Aug-15 11-Aug-15 Form Work
A01130 6 Concrete in Columns 15-Sep-15 21-Sep-15 06-Aug-15 13-Aug-15 Concrete in Columns
Pour - 2 10 09-Oct-15 20-Oct-15 24-Aug-15 03-Sep-15 20-Oct-15, Pour - 2
A01132 5 Steel Reinforcement Work 09-Oct-15 15-Oct-15 24-Aug-15 28-Aug-15 Steel Reinforcement Work
A01133 6 Form Work 12-Oct-15 19-Oct-15 26-Aug-15 02-Sep-15 Form Work
A01134 6 Concrete in Columns 13-Oct-15 20-Oct-15 27-Aug-15 03-Sep-15 Concrete in Columns
Shear Walls 25 10-Sep-15 16-Oct-15 03-Aug-15 01-Sep-15 16-Oct-15, Shear Walls
Pour -1 7 10-Sep-15 17-Sep-15 03-Aug-15 07-Aug-15 17-Sep-15, Pour -1
A01137 4 Steel Reinforcement Work 10-Sep-15 14-Sep-15 03-Aug-15 05-Aug-15 Steel Reinforcement Work
A01138 5 Form Work 10-Sep-15 16-Sep-15 03-Aug-15 07-Aug-15 Form Work
A01139 6 Concrete in Walls 10-Sep-15 17-Sep-15 03-Aug-15 07-Aug-15 Concrete in Walls
Pour -2 7 09-Oct-15 16-Oct-15 24-Aug-15 01-Sep-15 16-Oct-15, Pour -2
A01141 5 Steel Reinforcement Work 09-Oct-15 15-Oct-15 24-Aug-15 28-Aug-15 Steel Reinforcement Work
A01142 6 Form Work 09-Oct-15 16-Oct-15 24-Aug-15 31-Aug-15 Form Work
A01143 6 Concrete in Walls 09-Oct-15 16-Oct-15 25-Aug-15 01-Sep-15 Concrete in Walls
Slab & Beams 35 06-Oct-15 17-Nov-15 19-Aug-15 07-Oct-15 17-Nov-15, Slab & Beams
Pour -1 16 06-Oct-15 27-Oct-15 19-Aug-15 08-Sep-15 27-Oct-15, Pour -1
A01147 3 Steel Reinforcement 20-Oct-15 26-Oct-15 02-Sep-15 07-Sep-15 Steel Reinforcement
A01146 12 Form Work 06-Oct-15 20-Oct-15 19-Aug-15 01-Sep-15 Form Work
A01148 1 Concrete Pouring 26-Oct-15 27-Oct-15 08-Sep-15 08-Sep-15 Concrete Pouring
Pour -2 18 27-Oct-15 17-Nov-15 09-Sep-15 07-Oct-15 17-Nov-15, Pour -2
A01151 6 Steel Reinforcement 10-Nov-15 17-Nov-15 01-Oct-15 07-Oct-15 Steel Reinforcement
A01150 12 Form Work 27-Oct-15 10-Nov-15 09-Sep-15 22-Sep-15 Form Work
A01152 0 Concrete Pouring 17-Nov-15 17-Nov-15 01-Oct-15 01-Oct-15 Concrete Pouring
Roof 28 19-Nov-15 22-Dec-15 05-Oct-15 05-Nov-15 22-Dec-15, Roof
Columns 8 19-Nov-15 27-Nov-15 05-Oct-15 12-Oct-15 27-Nov-15, Columns
A01155 5 Steel Reinforcement Work 19-Nov-15 25-Nov-15 05-Oct-15 08-Oct-15 Steel Reinforcement Work
A01156 4 Form Work 23-Nov-15 27-Nov-15 05-Oct-15 12-Oct-15 Form Work
A01157 4 Concrete in Columns 23-Nov-15 27-Nov-15 06-Oct-15 12-Oct-15 Concrete in Columns
Shear Walls 8 19-Nov-15 27-Nov-15 05-Oct-15 12-Oct-15 27-Nov-15, Shear Walls
A01159 5 Steel Reinforcement Work 19-Nov-15 25-Nov-15 05-Oct-15 08-Oct-15 Steel Reinforcement Work
A01160 4 Form Work 23-Nov-15 27-Nov-15 05-Oct-15 12-Oct-15 Form Work
A01161 4 Concrete in Columns 23-Nov-15 27-Nov-15 06-Oct-15 12-Oct-15 Concrete in Columns
Slab & Beams 13 07-Dec-15 22-Dec-15 21-Oct-15 05-Nov-15 22-Dec-15, Slab & Beams
A01164 3 Steel Reinforcement 17-Dec-15 21-Dec-15 02-Nov-15 04-Nov-15 Steel Reinforcement
A01163 9 Form Work 07-Dec-15 17-Dec-15 21-Oct-15 02-Nov-15 Form Work
A01165 1 Concrete Pouring 21-Dec-15 22-Dec-15 04-Nov-15 05-Nov-15 Concrete Pouring
Finishing 260 10-Jul-15 31-May-16 03-Jun-15 13-Apr-16 31-May-16, Finishing
Lower Ground Floor 127 10-Jul-15 28-Dec-15 03-Jun-15 24-Nov-15 28-Dec-15, Lower Ground Floor
A01169 37 Plaster 04-Aug-15 16-Sep-15 03-Jul-15 14-Aug-15 Plaster
A01172 41 Paint 16-Oct-15 04-Dec-15 15-Sep-15 03-Nov-15 Paint
A01171 34 Flooring works 01-Oct-15 11-Nov-15 28-Aug-15 08-Oct-15 Flooring works
A01173 23 Doors & Windows fixing 30-Nov-15 28-Dec-15 27-Oct-15 24-Nov-15 Doors & Windows fixing
A01170 30 Ceiling works 04-Sep-15 16-Oct-15 27-Jul-15 07-Sep-15 Ceiling works
A01168 30 Block Masonry 10-Jul-15 24-Aug-15 03-Jun-15 15-Jul-15 Block Masonry
Ground Floor 141 08-Sep-15 02-Mar-16 03-Aug-15 05-Feb-16 02-Mar-16, Ground Floor

Primary Baseline Remaining Work Milestone Page 17 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A01176 47 Plaster 01-Oct-15 27-Nov-15 28-Aug-15 26-Oct-15 Plaster
A01179 43 Paint 18-Dec-15 08-Feb-16 24-Nov-15 13-Jan-16 Paint
A01178 53 Flooring works 12-Nov-15 15-Jan-16 15-Oct-15 18-Dec-15 Flooring works
A01180 25 Doors & Windows fixing 03-Feb-16 02-Mar-16 08-Jan-16 05-Feb-16 Doors & Windows fixing
A01177 49 Ceiling works 26-Oct-15 21-Dec-15 01-Oct-15 26-Nov-15 Ceiling works
A01175 40 Block Masonry 08-Sep-15 04-Nov-15 03-Aug-15 29-Sep-15 Block Masonry
First Floor 147 02-Nov-15 22-Apr-16 11-Sep-15 09-Mar-16 22-Apr-16, First Floor
A01183 53 Plaster 18-Nov-15 21-Jan-16 01-Oct-15 03-Dec-15 Plaster
A01186 49 Paint 03-Feb-16 30-Mar-16 18-Dec-15 15-Feb-16 Paint
A01185 55 Flooring works 04-Jan-16 07-Mar-16 19-Nov-15 22-Jan-16 Flooring works
A01187 25 Doors & Windows fixing 25-Mar-16 22-Apr-16 09-Feb-16 09-Mar-16 Doors & Windows fixing
A01184 54 Ceiling works 09-Dec-15 12-Feb-16 26-Oct-15 30-Dec-15 Ceiling works
A01182 47 Block Masonry 02-Nov-15 29-Dec-15 11-Sep-15 09-Nov-15 Block Masonry
Second Floor 148 08-Dec-15 31-May-16 26-Oct-15 13-Apr-16 31-May-16, Second Floor
A01190 56 Plaster 31-Dec-15 04-Mar-16 17-Nov-15 21-Jan-16 Plaster
A01193 47 Paint 21-Mar-16 13-May-16 04-Feb-16 30-Mar-16 Paint
A01192 55 Flooring works 17-Feb-16 20-Apr-16 04-Jan-16 07-Mar-16 Flooring works
A01194 25 Doors & Windows fixing 02-May-16 31-May-16 16-Mar-16 13-Apr-16 Doors & Windows fixing
A01191 51 Ceiling Works 29-Jan-16 28-Mar-16 17-Dec-15 12-Feb-16 Ceiling Works
A01189 54 Block Masonry 08-Dec-15 11-Feb-16 26-Oct-15 29-Dec-15 Block Masonry
Mechanical Floor 115 04-Jan-16 16-May-16 16-Nov-15 28-Mar-16 16-May-16, Mechanical Floor
A01202 47 Roof Screeding and Water Proofing 04-Jan-16 26-Feb-16 16-Nov-15 08-Jan-16 Roof Screeding and Water Proofing
A01197 24 Plaster 08-Feb-16 07-Mar-16 21-Dec-15 18-Jan-16 Plaster
A01200 27 Paint 01-Apr-16 02-May-16 11-Feb-16 14-Mar-16 Paint
A01199 30 Flooring works 09-Mar-16 13-Apr-16 20-Jan-16 24-Feb-16 Flooring works
A01201 12 Doors & Windows fixing 02-May-16 16-May-16 14-Mar-16 28-Mar-16 Doors & Windows fixing
A01198 25 Ceiling Works 26-Feb-16 25-Mar-16 07-Jan-16 05-Feb-16 Ceiling Works
A01196 31 Block Masonry 12-Jan-16 17-Feb-16 24-Nov-15 30-Dec-15 Block Masonry
MEP WORKS 472 12-Feb-15 27-Apr-16 27-Dec-14 09-Mar-16 27-Apr-16, MEP WORKS
LOWER GROUND FLOOR 268 12-Feb-15 19-Oct-15 27-Dec-14 03-Sep-15 19-Oct-15, LOWER GROUND FLOOR
Electrical Works 268 12-Feb-15 19-Oct-15 27-Dec-14 03-Sep-15 19-Oct-15, Electrical Works
Conduit Works 125 12-Feb-15 08-Jun-15 27-Dec-14 29-Apr-15 08-Jun-15, Conduit Works
A6410 25 Conduiting for Lighting Protection at Shear
12-Feb-15
Walls 06-Mar-15 09-Jan-15 02-Feb-15 Conduiting for Lighting Protection at Shear Walls
A6420 4 Conduiting Electrical System of all system
04-Jun-15
at Slab and Beams
08-Jun-15 25-Apr-15 29-Apr-15 Conduiting Electrical System of all system at Slab and Beams
A6490 39 Conduiting & Cable Trunking at Sub base
12-Feb-15
and SOG 20-Mar-15 27-Dec-14 02-Feb-15 Conduiting & Cable Trunking at Sub base and SOG
Electrical Works 118 01-Jul-15 19-Oct-15 23-May-15 03-Sep-15 19-Oct-15, Electrical Works
A6430 50 Wiring for Lighting Power & ELV system01-Jul-15 17-Aug-15 23-May-15 09-Jul-15 Wiring for Lighting Power & ELV system
A6400 16 Testing & Commissioning 01-Oct-15 19-Oct-15 15-Aug-15 03-Sep-15 Testing & Commissioning
A6460 30 Laying of Power Cable 19-Aug-15 16-Sep-15 11-Jul-15 08-Aug-15 Laying of Power Cable
A6470 45 Installation of ELV System 10-Jul-15 21-Aug-15 02-Jun-15 14-Jul-15 Installation of ELV System
A6450 50 Installation of D.Bs Panels 03-Jul-15 19-Aug-15 26-May-15 11-Jul-15 Installation of D.Bs Panels
A6480 40 Fixing of Devices 17-Aug-15 23-Sep-15 09-Jul-15 15-Aug-15 Fixing of Devices
A6440 50 Fixing of Cable Tray 02-Jul-15 18-Aug-15 25-May-15 10-Jul-15 Fixing of Cable Tray
HVAC Works 56 03-Aug-15 24-Sep-15 16-Jun-15 19-Aug-15 24-Sep-15, HVAC Works
PIPING WORKS 44 03-Aug-15 14-Sep-15 16-Jun-15 19-Aug-15 14-Sep-15, PIPING WORKS
A3800 2 TESTING 26-Aug-15 28-Aug-15 09-Jul-15 11-Jul-15 TESTING
A3700 5 SUPPORTING MATERIALS (PIPE HANGERS
03-Aug-15
AND SUPPORTS)
07-Aug-15 16-Jun-15 20-Jun-15 SUPPORTING MATERIALS (PIPE HANGERS AND SUPPORTS)
A3710 20 PIPING FOR CHILLED AND CONDENSATE
07-Aug-15
WATER 26-Aug-15 20-Jun-15 09-Jul-15 PIPING FOR CHILLED AND CONDENSATE WATER
A3720 15 PIPE INSULATION 28-Aug-15 11-Sep-15 11-Jul-15 25-Jul-15 PIPE INSULATION
A4960 15 CENTRALIZED VACCUM SYSTEM 31-Aug-15 14-Sep-15 05-Aug-15 19-Aug-15 CENTRALIZED VACCUM SYSTEM
DUCTING WORKS 22 07-Aug-15 28-Aug-15 20-Jun-15 11-Jul-15 28-Aug-15, DUCTING WORKS
A3820 2 TESTING 26-Aug-15 28-Aug-15 09-Jul-15 11-Jul-15 TESTING

Primary Baseline Remaining Work Milestone Page 18 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A3810 5 SUPPORTING MATERIALS (DUCT HANGERS
07-Aug-15
AND SUPPORTS)
12-Aug-15 20-Jun-15 25-Jun-15 SUPPORTING MATERIALS (DUCT HANGERS AND SUPPORTS)
A3750 10 INSULATION OF DUCT 12-Aug-15 21-Aug-15 25-Jun-15 04-Jul-15 INSULATION OF DUCT
A3830 3 INSTALLATION OF VENTILATION DUCT
12-Aug-15
IN TOILET 15-Aug-15 25-Jun-15 29-Jun-15 INSTALLATION OF VENTILATION DUCT IN TOILET
A3730 15 INSTALLATION OF DUCT 12-Aug-15 26-Aug-15 25-Jun-15 09-Jul-15 INSTALLATION OF DUCT
UNIT INSTALLATION / BMS 23 26-Aug-15 17-Sep-15 09-Jul-15 31-Jul-15 17-Sep-15, UNIT INSTALLATION / BMS
A3780 8 INSTALLATION OF VENTILATION FAN26-Aug-15
IN TOILET AREA
03-Sep-15 09-Jul-15 17-Jul-15 INSTALLATION OF VENTILATION FAN IN TOILET AREA
A3740 10 INSTALLATION OF AHU UNITS 03-Sep-15 12-Sep-15 17-Jul-15 27-Jul-15 INSTALLATION OF AHU UNITS
A3770 5 BMS (BUILDING MANAGEMENT SYSTEM)
12-Sep-15 17-Sep-15 27-Jul-15 31-Jul-15 BMS (BUILDING MANAGEMENT SYSTEM)
PAINTING & IDENTIFICATION WORKS / AIR DEVICES
8 17-Sep-15 24-Sep-15 01-Aug-15 10-Aug-15 24-Sep-15, PAINTING & IDENTIFICATION WORKS / AIR DEVICES
A3790 2 PAINTING & INDENTIFICATION 18-Sep-15 21-Sep-15 05-Aug-15 06-Aug-15 PAINTING & INDENTIFICATION
A3760 8 INSTALLATION OF AIR DEVICES 17-Sep-15 24-Sep-15 01-Aug-15 10-Aug-15 INSTALLATION OF AIR DEVICES
Fire Protection Works 42 01-Jul-15 28-Aug-15 23-May-15 11-Jul-15 28-Aug-15, Fire Protection Works
A01230 12 Testing and Commisioning 14-Aug-15 28-Aug-15 27-Jun-15 11-Jul-15 Testing and Commisioning
A01227 28 Installation of MS Pipes 01-Jul-15 12-Aug-15 23-May-15 25-Jun-15 Installation of MS Pipes
A01229 24 Installation of miscellaneous Fittings 07-Jul-15 13-Aug-15 29-May-15 26-Jun-15 Installation of miscellaneous Fittings
A01228 24 Fitting and Fixing of Sprinklers 08-Jul-15 14-Aug-15 30-May-15 27-Jun-15 Fitting and Fixing of Sprinklers
Plumbing Works 52 01-Jul-15 09-Sep-15 23-May-15 01-Aug-15 09-Sep-15, Plumbing Works
A01232 24 Water supply conduiting 01-Jul-15 07-Aug-15 23-May-15 20-Jun-15 Water supply conduiting
A01236 12 Testing and Commisioning 26-Aug-15 09-Sep-15 09-Jul-15 01-Aug-15 Testing and Commisioning
A01234 24 Soil and Waste Water Pipes 29-Jul-15 26-Aug-15 11-Jun-15 09-Jul-15 Soil and Waste Water Pipes
A01235 16 Installation of Gully traps, Cleanouts and01-Aug-15
Misce 20-Aug-15 16-Jun-15 04-Jul-15 Installation of Gully traps, Cleanouts and Misce
A01233 12 Drainage Pipes 10-Jul-15 03-Aug-15 02-Jun-15 16-Jun-15 Drainage Pipes
GROUND FLOOR 204 16-Jun-15 24-Dec-15 12-May-15 18-Nov-15 24-Dec-15, GROUND FLOOR
Electrical Works 189 16-Jun-15 10-Dec-15 12-May-15 06-Nov-15 10-Dec-15, Electrical Works
Conduit Works 58 16-Jun-15 10-Aug-15 12-May-15 25-Jun-15 10-Aug-15, Conduit Works
A6610 18 Conduiting for Lighting Protection at Shear
16-Jun-15
Walls 03-Jul-15 12-May-15 28-May-15 Conduiting for Lighting Protection at Shear Walls
A6620 17 Conduiting Electrical System of all system
24-Jul-15
at Slab and Beams
10-Aug-15 10-Jun-15 25-Jun-15 Conduiting Electrical System of all system at Slab and Beams
Electrical Works 110 29-Aug-15 10-Dec-15 24-Jul-15 06-Nov-15 10-Dec-15, Electrical Works
A6630 50 Wiring for Lighting Power & ELV system29-Aug-15 15-Oct-15 24-Jul-15 09-Sep-15 Wiring for Lighting Power & ELV system
A6600 16 Testing & Commissioning 21-Nov-15 10-Dec-15 16-Oct-15 06-Nov-15 Testing & Commissioning
A6660 30 Laying of Power Cable 17-Oct-15 13-Nov-15 11-Sep-15 09-Oct-15 Laying of Power Cable
A6670 45 Installation of ELV System 08-Sep-15 20-Oct-15 03-Aug-15 14-Sep-15 Installation of ELV System
A6650 50 Installation of D.Bs Panels 01-Sep-15 16-Oct-15 27-Jul-15 11-Sep-15 Installation of D.Bs Panels
A6680 40 Fixing of Devices 15-Oct-15 21-Nov-15 09-Sep-15 16-Oct-15 Fixing of Devices
A6640 50 Fixing of Cable Tray 31-Aug-15 16-Oct-15 25-Jul-15 10-Sep-15 Fixing of Cable Tray
HVAC Works 100 22-Sep-15 24-Dec-15 17-Aug-15 18-Nov-15 24-Dec-15, HVAC Works
PIPING WORKS 62 22-Sep-15 18-Nov-15 17-Aug-15 14-Oct-15 18-Nov-15, PIPING WORKS
A3940 2 TESTING 24-Oct-15 26-Oct-15 18-Sep-15 21-Sep-15 TESTING
A3840 5 SUPPORTING MATERIALS (PIPE HANGERS
22-Sep-15
AND SUPPORTS)
26-Sep-15 17-Aug-15 21-Aug-15 SUPPORTING MATERIALS (PIPE HANGERS AND SUPPORTS)
A3850 30 PIPING FOR CHILLED AND CONDENSATE
26-Sep-15
WATER 24-Oct-15 21-Aug-15 18-Sep-15 PIPING FOR CHILLED AND CONDENSATE WATER
A3860 25 PIPE INSULATION 27-Oct-15 18-Nov-15 21-Sep-15 14-Oct-15 PIPE INSULATION
A5070 15 CENTRALIZED VACCUM SYSTEM 17-Oct-15 31-Oct-15 14-Sep-15 28-Sep-15 CENTRALIZED VACCUM SYSTEM
DUCTING WORKS 27 26-Sep-15 21-Oct-15 21-Aug-15 16-Sep-15 21-Oct-15, DUCTING WORKS
A3960 2 TESTING 20-Oct-15 21-Oct-15 14-Sep-15 16-Sep-15 TESTING
A3950 5 SUPPORTING MATERIALS (DUCT HANGERS
26-Sep-15
AND SUPPORTS)
01-Oct-15 21-Aug-15 26-Aug-15 SUPPORTING MATERIALS (DUCT HANGERS AND SUPPORTS)
A3890 15 INSULATION OF DUCT 01-Oct-15 15-Oct-15 26-Aug-15 09-Sep-15 INSULATION OF DUCT
A3970 3 INSTALLATION OF VENTILATION DUCT
01-Oct-15
IN TOILET 03-Oct-15 26-Aug-15 28-Aug-15 INSTALLATION OF VENTILATION DUCT IN TOILET
A3870 20 INSTALLATION OF DUCT 01-Oct-15 20-Oct-15 26-Aug-15 14-Sep-15 INSTALLATION OF DUCT
UNIT INSTALLATION / BMS 55 20-Oct-15 10-Dec-15 14-Sep-15 04-Nov-15 10-Dec-15, UNIT INSTALLATION / BMS
A3920 15 INSTALLATION OF VENTILATION FAN20-Oct-15
IN TOILET AREA
03-Nov-15 14-Sep-15 28-Sep-15 INSTALLATION OF VENTILATION FAN IN TOILET AREA
A3880 25 INSTALLATION OF AHU UNITS 03-Nov-15 26-Nov-15 28-Sep-15 21-Oct-15 INSTALLATION OF AHU UNITS
A3910 15 BMS (BUILDING MANAGEMENT SYSTEM)
26-Nov-15 10-Dec-15 21-Oct-15 04-Nov-15 BMS (BUILDING MANAGEMENT SYSTEM)

Primary Baseline Remaining Work Milestone Page 19 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
PAINTING & IDENTIFICATION WORKS / AIR DEVICES
15 10-Dec-15 24-Dec-15 04-Nov-15 18-Nov-15 24-Dec-15, PAINTING & IDENTIFICATION W
A3930 2 PAINTING & INDENTIFICATION 10-Dec-15 11-Dec-15 04-Nov-15 06-Nov-15 PAINTING & INDENTIFICATION
A3900 15 INSTALLATION OF AIR DEVICES 10-Dec-15 24-Dec-15 04-Nov-15 18-Nov-15 INSTALLATION OF AIR DEVICES
Fire Protection Works 54 29-Aug-15 11-Nov-15 24-Jul-15 03-Oct-15 11-Nov-15, Fire Protection Works
A01263 16 Testing and Commisioning 21-Oct-15 11-Nov-15 07-Sep-15 03-Oct-15 Testing and Commisioning
A01260 36 Installation of MS Pipes 29-Aug-15 19-Oct-15 24-Jul-15 04-Sep-15 Installation of MS Pipes
A01262 32 Installation of miscellaneous Fittings 04-Sep-15 20-Oct-15 30-Jul-15 05-Sep-15 Installation of miscellaneous Fittings
A01261 32 Fitting and Fixing of Sprinklers 05-Sep-15 21-Oct-15 31-Jul-15 07-Sep-15 Fitting and Fixing of Sprinklers
Plumbing Works 57 29-Aug-15 14-Nov-15 24-Jul-15 07-Oct-15 14-Nov-15, Plumbing Works
A01265 32 Water supply conduiting 29-Aug-15 14-Oct-15 24-Jul-15 31-Aug-15 Water supply conduiting
A01269 16 Testing and Commisioning 27-Oct-15 14-Nov-15 10-Sep-15 07-Oct-15 Testing and Commisioning
A01267 24 Soil and Waste Water Pipes 17-Sep-15 26-Oct-15 12-Aug-15 09-Sep-15 Soil and Waste Water Pipes
A01268 16 Installation of Gully traps, Cleanouts and21-Sep-15
Misce 17-Oct-15 15-Aug-15 03-Sep-15 Installation of Gully traps, Cleanouts and Misce
A01266 16 Drainage Pipes 08-Sep-15 05-Oct-15 03-Aug-15 21-Aug-15 Drainage Pipes
FIRST FLOOR 222 01-Aug-15 24-Feb-16 17-Jun-15 13-Jan-16 24-Feb-16, FIRST FLOOR
Electrical Works 214 01-Aug-15 17-Feb-16 17-Jun-15 31-Dec-15 17-Feb-16, Electrical Works
Conduit Works 68 01-Aug-15 03-Oct-15 17-Jun-15 17-Aug-15 03-Oct-15, Conduit Works
A6970 15 Conduiting for Lighting Protection at Shear
01-Aug-15
Walls 15-Aug-15 17-Jun-15 01-Jul-15 Conduiting for Lighting Protection at Shear Walls
A6980 3 Conduiting Electrical System of all system
01-Oct-15
at Slab and Beams
03-Oct-15 14-Aug-15 17-Aug-15 Conduiting Electrical System of all system at Slab and Beams
Electrical Works 122 26-Oct-15 17-Feb-16 05-Sep-15 31-Dec-15 17-Feb-16, Electrical Works
A6990 50 Wiring for Lighting Power & ELV system26-Oct-15 11-Dec-15 05-Sep-15 22-Oct-15 Wiring for Lighting Power & ELV system
A6960 16 Testing & Commissioning 29-Jan-16 17-Feb-16 10-Dec-15 31-Dec-15 Testing & Commissioning
A7020 30 Laying of Power Cable 14-Dec-15 11-Jan-16 24-Oct-15 21-Nov-15 Laying of Power Cable
A7030 45 Installation of ELV System 04-Nov-15 16-Dec-15 15-Sep-15 27-Oct-15 Installation of ELV System
A7010 50 Installation of D.Bs Panels 28-Oct-15 14-Dec-15 08-Sep-15 24-Oct-15 Installation of D.Bs Panels
A7040 40 Fixing of Devices 11-Dec-15 18-Jan-16 22-Oct-15 28-Nov-15 Fixing of Devices
A7000 50 Fixing of Cable Tray 27-Oct-15 12-Dec-15 07-Sep-15 23-Oct-15 Fixing of Cable Tray
HVAC Works 105 18-Nov-15 24-Feb-16 07-Oct-15 13-Jan-16 24-Feb-16, HVAC Works
PIPING WORKS 62 18-Nov-15 15-Jan-16 07-Oct-15 04-Dec-15 15-Jan-16, PIPING WORKS
A4080 2 TESTING 21-Dec-15 23-Dec-15 09-Nov-15 11-Nov-15 TESTING
A3980 5 SUPPORTING MATERIALS (PIPE HANGERS
18-Nov-15
AND SUPPORTS)
23-Nov-15 07-Oct-15 12-Oct-15 SUPPORTING MATERIALS (PIPE HANGERS AN
A3990 30 PIPING FOR CHILLED AND CONDENSATE
23-Nov-15
WATER 21-Dec-15 12-Oct-15 09-Nov-15 PIPING FOR CHILLED AND CONDENSATE WATER
A4000 25 PIPE INSULATION 23-Dec-15 15-Jan-16 11-Nov-15 04-Dec-15 PIPE INSULATION
A5080 15 CENTRALIZED VACCUM SYSTEM 09-Dec-15 23-Dec-15 27-Oct-15 10-Nov-15 CENTRALIZED VACCUM SYSTEM
DUCTING WORKS 27 23-Nov-15 18-Dec-15 12-Oct-15 06-Nov-15 18-Dec-15, DUCTING WORKS
A4100 2 TESTING 16-Dec-15 18-Dec-15 04-Nov-15 06-Nov-15 TESTING
A4090 5 SUPPORTING MATERIALS (DUCT HANGERS
23-Nov-15
AND SUPPORTS)
27-Nov-15 12-Oct-15 16-Oct-15 SUPPORTING MATERIALS (DUCT HANGERS A
A4030 15 INSULATION OF DUCT 27-Nov-15 11-Dec-15 16-Oct-15 30-Oct-15 INSULATION OF DUCT
A4110 3 INSTALLATION OF VENTILATION DUCT
27-Nov-15
IN TOILET 01-Dec-15 16-Oct-15 20-Oct-15 INSTALLATION OF VENTILATION DUCT IN TOILET
A4010 20 INSTALLATION OF DUCT 27-Nov-15 16-Dec-15 16-Oct-15 04-Nov-15 INSTALLATION OF DUCT
UNIT INSTALLATION / BMS 60 16-Dec-15 10-Feb-16 04-Nov-15 30-Dec-15 10-Feb-16, UNIT INSTALLATION / BMS
A4060 15 INSTALLATION OF VENTILATION FAN16-Dec-15
IN TOILET AREA
30-Dec-15 04-Nov-15 18-Nov-15 INSTALLATION OF VENTILATION FAN IN T
A4020 25 INSTALLATION OF AHU UNITS 30-Dec-15 22-Jan-16 18-Nov-15 11-Dec-15 INSTALLATION OF AHU UNITS
A4050 20 BMS (BUILDING MANAGEMENT SYSTEM)
22-Jan-16 10-Feb-16 11-Dec-15 30-Dec-15 BMS (BUILDING MANAGEMENT SYSTEM)
PAINTING & IDENTIFICATION WORKS / AIR DEVICES
15 10-Feb-16 24-Feb-16 30-Dec-15 13-Jan-16 24-Feb-16, PAINTING & IDENTIFIC
A4070 2 PAINTING & INDENTIFICATION 10-Feb-16 12-Feb-16 30-Dec-15 01-Jan-16 PAINTING & INDENTIFICATION
A4040 15 INSTALLATION OF AIR DEVICES 10-Feb-16 24-Feb-16 30-Dec-15 13-Jan-16 INSTALLATION OF AIR DEVICES
Fire Protection Works 54 26-Oct-15 30-Dec-15 05-Sep-15 18-Nov-15 30-Dec-15, Fire Protection Works
A01296 16 Testing and Commisioning 09-Dec-15 30-Dec-15 30-Oct-15 18-Nov-15 Testing and Commisioning
A01293 36 Installation of MS Pipes 26-Oct-15 07-Dec-15 05-Sep-15 28-Oct-15 Installation of MS Pipes
A01295 32 Installation of miscellaneous Fittings 31-Oct-15 08-Dec-15 11-Sep-15 29-Oct-15 Installation of miscellaneous Fittings
A01294 32 Fitting and Fixing of Sprinklers 02-Nov-15 09-Dec-15 12-Sep-15 30-Oct-15 Fitting and Fixing of Sprinklers

Primary Baseline Remaining Work Milestone Page 20 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Plumbing Works 56 26-Oct-15 02-Jan-16 05-Sep-15 25-Nov-15 02-Jan-16, Plumbing Works
A01298 32 Water supply conduiting 26-Oct-15 02-Dec-15 05-Sep-15 21-Oct-15 Water supply conduiting
A01302 16 Testing and Commisioning 12-Dec-15 02-Jan-16 06-Nov-15 25-Nov-15 Testing and Commisioning
A01300 24 Soil and Waste Water Pipes 14-Nov-15 12-Dec-15 07-Oct-15 06-Nov-15 Soil and Waste Water Pipes
A01301 16 Installation of Gully traps, Cleanouts and18-Nov-15
Misce 07-Dec-15 10-Oct-15 31-Oct-15 Installation of Gully traps, Cleanouts and Misce
A01299 16 Drainage Pipes 04-Nov-15 23-Nov-15 15-Sep-15 12-Oct-15 Drainage Pipes
SECOND FLOOR 250 18-Aug-15 07-Apr-16 01-Jul-15 20-Feb-16 07-Apr-16, SECOND FLOOR
Electrical Works 232 18-Aug-15 21-Mar-16 01-Jul-15 03-Feb-16 21-Mar-16, Electrical Works
Conduit Works 67 18-Aug-15 20-Oct-15 01-Jul-15 02-Sep-15 20-Oct-15, Conduit Works
A6700 20 Conduiting for Lighting Protection at Shear
18-Aug-15
Walls 05-Sep-15 01-Jul-15 20-Jul-15 Conduiting for Lighting Protection at Shear Walls
A6710 15 Conduiting Electrical System of all system
06-Oct-15
at Slab and Beams
20-Oct-15 19-Aug-15 02-Sep-15 Conduiting Electrical System of all system at Slab and Beams
Electrical Works 114 05-Dec-15 21-Mar-16 20-Oct-15 03-Feb-16 21-Mar-16, Electrical Works
A6720 50 Wiring for Lighting Power & ELV system05-Dec-15 21-Jan-16 20-Oct-15 05-Dec-15 Wiring for Lighting Power & ELV system
A6690 16 Testing & Commissioning 02-Mar-16 21-Mar-16 15-Jan-16 03-Feb-16 Testing & Commissioning
A6750 30 Laying of Power Cable 23-Jan-16 20-Feb-16 08-Dec-15 05-Jan-16 Laying of Power Cable
A6760 45 Installation of ELV System 15-Dec-15 26-Jan-16 29-Oct-15 10-Dec-15 Installation of ELV System
A6740 50 Installation of D.Bs Panels 08-Dec-15 23-Jan-16 22-Oct-15 08-Dec-15 Installation of D.Bs Panels
A6770 40 Fixing of Devices 21-Jan-16 27-Feb-16 05-Dec-15 12-Jan-16 Fixing of Devices
A6730 50 Fixing of Cable Tray 07-Dec-15 22-Jan-16 21-Oct-15 07-Dec-15 Fixing of Cable Tray
HVAC Works 105 31-Dec-15 07-Apr-16 14-Nov-15 20-Feb-16 07-Apr-16, HVAC Works
PIPING WORKS 62 31-Dec-15 27-Feb-16 14-Nov-15 12-Jan-16 27-Feb-16, PIPING WORKS
A4220 2 TESTING 02-Feb-16 04-Feb-16 17-Dec-15 19-Dec-15 TESTING
A4120 5 SUPPORTING MATERIALS (PIPE HANGERS
31-Dec-15
AND SUPPORTS)
05-Jan-16 14-Nov-15 19-Nov-15 SUPPORTING MATERIALS (PIPE HANGE
A4130 30 PIPING FOR CHILLED AND CONDENSATE
05-Jan-16
WATER 02-Feb-16 19-Nov-15 17-Dec-15 PIPING FOR CHILLED AND CONDENS
A4140 25 PIPE INSULATION 04-Feb-16 27-Feb-16 19-Dec-15 12-Jan-16 PIPE INSULATION
A5090 15 CENTRALIZED VACCUM SYSTEM 25-Jan-16 08-Feb-16 09-Dec-15 23-Dec-15 CENTRALIZED VACCUM SYSTEM
DUCTING WORKS 22 05-Jan-16 26-Jan-16 19-Nov-15 10-Dec-15 26-Jan-16, DUCTING WORKS
A4240 2 TESTING 23-Jan-16 26-Jan-16 08-Dec-15 10-Dec-15 TESTING
A4230 5 SUPPORTING MATERIALS (DUCT HANGERS
05-Jan-16
AND SUPPORTS)
09-Jan-16 19-Nov-15 24-Nov-15 SUPPORTING MATERIALS (DUCT HANG
A4170 10 INSULATION OF DUCT 09-Jan-16 19-Jan-16 24-Nov-15 03-Dec-15 INSULATION OF DUCT
A4250 3 INSTALLATION OF VENTILATION DUCT
09-Jan-16
IN TOILET 13-Jan-16 24-Nov-15 26-Nov-15 INSTALLATION OF VENTILATION DUCT
A4150 15 INSTALLATION OF DUCT 09-Jan-16 23-Jan-16 24-Nov-15 08-Dec-15 INSTALLATION OF DUCT
UNIT INSTALLATION / BMS 70 19-Jan-16 24-Mar-16 03-Dec-15 06-Feb-16 24-Mar-16, UNIT INSTALLATION / BMS
A4200 20 INSTALLATION OF VENTILATION FAN19-Jan-16
IN TOILET AREA
06-Feb-16 03-Dec-15 22-Dec-15 INSTALLATION OF VENTILATION FAN
A4160 30 INSTALLATION OF AHU UNITS 06-Feb-16 05-Mar-16 22-Dec-15 19-Jan-16 INSTALLATION OF AHU UNITS
A4190 20 BMS (BUILDING MANAGEMENT SYSTEM)
05-Mar-16 24-Mar-16 19-Jan-16 06-Feb-16 BMS (BUILDING MANAGEMEN
PAINTING & IDENTIFICATION WORKS / AIR DEVICES
15 24-Mar-16 07-Apr-16 06-Feb-16 20-Feb-16 07-Apr-16, PAINTING & IDEN
A4210 2 PAINTING & INDENTIFICATION 24-Mar-16 26-Mar-16 06-Feb-16 09-Feb-16 PAINTING & INDENTIFICATION
A4180 15 INSTALLATION OF AIR DEVICES 24-Mar-16 07-Apr-16 06-Feb-16 20-Feb-16 INSTALLATION OF AIR DEVICES
Fire Protection Works 60 05-Dec-15 16-Feb-16 20-Oct-15 02-Jan-16 16-Feb-16, Fire Protection Works
A01329 16 Testing and Commisioning 28-Jan-16 16-Feb-16 12-Dec-15 02-Jan-16 Testing and Commisioning
A01326 36 Installation of MS Pipes 05-Dec-15 19-Jan-16 20-Oct-15 03-Dec-15 Installation of MS Pipes
A01328 32 Installation of miscellaneous Fittings 11-Dec-15 20-Jan-16 28-Oct-15 04-Dec-15 Installation of miscellaneous Fittings
A01327 32 Fitting and Fixing of Sprinklers 12-Dec-15 21-Jan-16 29-Oct-15 05-Dec-15 Fitting and Fixing of Sprinklers
Plumbing Works 56 05-Dec-15 11-Feb-16 20-Oct-15 29-Dec-15 11-Feb-16, Plumbing Works
A01331 32 Water supply conduiting 05-Dec-15 14-Jan-16 20-Oct-15 28-Nov-15 Water supply conduiting
A01335 16 Testing and Commisioning 23-Jan-16 11-Feb-16 08-Dec-15 29-Dec-15 Testing and Commisioning
A01333 24 Soil and Waste Water Pipes 26-Dec-15 23-Jan-16 10-Nov-15 08-Dec-15 Soil and Waste Water Pipes
A01334 16 Installation of Gully traps, Cleanouts and30-Dec-15
Misce 18-Jan-16 13-Nov-15 02-Dec-15 Installation of Gully traps, Cleanouts and Misce
A01332 16 Drainage Pipes 15-Dec-15 05-Jan-16 31-Oct-15 19-Nov-15 Drainage Pipes
ROOF FLOOR 188 04-Nov-15 27-Apr-16 08-Sep-15 09-Mar-16 27-Apr-16, ROOF FLOOR
HVAC Works 89 04-Feb-16 27-Apr-16 17-Dec-15 09-Mar-16 27-Apr-16, HVAC Works

Primary Baseline Remaining Work Milestone Page 21 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
PIPING WORKS 67 04-Feb-16 07-Apr-16 17-Dec-15 18-Feb-16 07-Apr-16, PIPING WORKS
A4360 2 TESTING 12-Mar-16 15-Mar-16 23-Jan-16 26-Jan-16 TESTING
A4260 5 SUPPORTING MATERIALS (PIPE HANGERS
04-Feb-16
AND SUPPORTS)
09-Feb-16 17-Dec-15 22-Dec-15 SUPPORTING MATERIALS (PIPE HA
A4270 35 PIPING FOR CHILLED AND CONDENSATE
09-Feb-16
WATER 12-Mar-16 22-Dec-15 23-Jan-16 PIPING FOR CHILLED AND CON
A4280 25 PIPE INSULATION 15-Mar-16 07-Apr-16 26-Jan-16 18-Feb-16 PIPE INSULATION
DUCTING WORKS 27 09-Feb-16 05-Mar-16 22-Dec-15 16-Jan-16 05-Mar-16, DUCTING WORKS
A4380 2 TESTING 03-Mar-16 05-Mar-16 14-Jan-16 16-Jan-16 TESTING
A4370 5 SUPPORTING MATERIALS (DUCT HANGERS
09-Feb-16
AND SUPPORTS)
13-Feb-16 22-Dec-15 26-Dec-15 SUPPORTING MATERIALS (DUCT H
A4310 10 INSULATION OF DUCT 13-Feb-16 23-Feb-16 26-Dec-15 05-Jan-16 INSULATION OF DUCT
A4390 3 INSTALLATION OF VENTILATION DUCT
13-Feb-16
IN TOILET 17-Feb-16 26-Dec-15 29-Dec-15 INSTALLATION OF VENTILATION D
A4290 20 INSTALLATION OF DUCT 13-Feb-16 03-Mar-16 26-Dec-15 14-Jan-16 INSTALLATION OF DUCT
UNIT INSTALLATION / BMS 52 03-Mar-16 21-Apr-16 14-Jan-16 03-Mar-16 21-Apr-16, UNIT INSTALLAT
A4340 7 INSTALLATION OF VENTILATION FAN03-Mar-16
IN TOILET AREA
10-Mar-16 14-Jan-16 21-Jan-16 INSTALLATION OF VENTILATION
A4300 30 INSTALLATION OF AHU UNITS 10-Mar-16 07-Apr-16 21-Jan-16 18-Feb-16 INSTALLATION OF AHU UNITS
A4330 15 BMS (BUILDING MANAGEMENT SYSTEM)
07-Apr-16 21-Apr-16 18-Feb-16 03-Mar-16 BMS (BUILDING MANAGEM
PAINTING & IDENTIFICATION WORKS / AIR DEVICES
7 21-Apr-16 27-Apr-16 03-Mar-16 09-Mar-16 27-Apr-16, PAINTING & IDE
A4350 2 PAINTING & INDENTIFICATION 21-Apr-16 22-Apr-16 03-Mar-16 04-Mar-16 PAINTING & INDENTIFICATION
A4320 7 INSTALLATION OF AIR DEVICES 21-Apr-16 27-Apr-16 03-Mar-16 09-Mar-16 INSTALLATION OF AIR DEVICES
Electrical Works 160 04-Nov-15 01-Apr-16 08-Sep-15 02-Mar-16 01-Apr-16, Electrical Works
Conduit Works 41 04-Nov-15 12-Dec-15 08-Sep-15 26-Oct-15 12-Dec-15, Conduit Works
A6790 20 Conduiting for Lighting Protection at Shear
04-Nov-15
Walls 23-Nov-15 08-Sep-15 26-Sep-15 Conduiting for Lighting Protection at Shear Walls
A6800 15 Conduiting Electrical System of all system
28-Nov-15
at Slab and Beams
12-Dec-15 12-Oct-15 26-Oct-15 Conduiting Electrical System of all system at Sla
Electrical Works 86 12-Jan-16 01-Apr-16 24-Nov-15 02-Mar-16 01-Apr-16, Electrical Works
A6810 30 Wiring for Lighting Power & ELV system12-Jan-16 09-Feb-16 24-Nov-15 22-Dec-15 Wiring for Lighting Power & ELV system
A6780 16 Testing & Commissioning 14-Mar-16 01-Apr-16 27-Jan-16 15-Feb-16 Testing & Commissioning
A6840 20 Laying of Power Cable 26-Jan-16 13-Feb-16 08-Dec-15 26-Dec-15 Laying of Power Cable
A6860 30 Fixing of Devices 04-Feb-16 03-Mar-16 17-Dec-15 14-Jan-16 Fixing of Devices
A7510 60 Elevators 22-Jan-16 18-Mar-16 06-Jan-16 02-Mar-16 Elevators
Installation of Solar Pannels and lightning Protection
56 04-Jan-16 09-Mar-16 16-Nov-15 22-Jan-16 09-Mar-16, Installation of Solar Pa
A01342 8 Testing & Commissioning 29-Feb-16 09-Mar-16 13-Jan-16 22-Jan-16 Testing & Commissioning
A01338 24 Lightning protection 04-Jan-16 01-Feb-16 16-Nov-15 14-Dec-15 Lightning protection
A01341 32 Laying of Cables 22-Jan-16 29-Feb-16 04-Dec-15 13-Jan-16 Laying of Cables
A01339 28 Installation of Pv Pannels 13-Jan-16 15-Feb-16 25-Nov-15 30-Dec-15 Installation of Pv Pannels
A01340 24 Installation of Grid Invertors and System27-Jan-16 24-Feb-16 09-Dec-15 08-Jan-16 Installation of Grid Invertors and System
BLOCK- E 518 20-Sep-14 A 11-Apr-16 31-Oct-14 25-Mar-16 11-Apr-16, BLOCK- E
Earth Works 19 20-Sep-14 A 14-Jan-15 A 31-Oct-14 25-Nov-14 14-Jan-15 A, Earth Works
A01346 9 Termite Proofing 23-Sep-14 A 14-Jan-15 A 11-Nov-14 25-Nov-14 Termite Proofing
A01345 16 Excavations 20-Sep-14 A 12-Nov-14 A 31-Oct-14 20-Nov-14 Excavations
Strcutural Works 232 23-Sep-14 A 01-Oct-15 11-Nov-14 30-Jul-15 01-Oct-15, Strcutural Works
Ground Floor 138 23-Sep-14 A 26-May-15 11-Nov-14 02-Apr-15 26-May-15, Ground Floor
Pile Caps 19 23-Sep-14 A 16-Jan-15 A 11-Nov-14 03-Dec-14 16-Jan-15 A, Pile Caps
A01351 10 Steel Reinforcement Work 31-Oct-14 A 15-Jan-15 A 14-Nov-14 28-Nov-14 Steel Reinforcement Work
A01350 9 Lean Concrete 23-Sep-14 A 14-Jan-15 A 11-Nov-14 25-Nov-14 Lean Concrete
A01352 11 Form Work 05-Nov-14 A 16-Jan-15 A 19-Nov-14 02-Dec-14 Form Work
A01353 11 Concrete in Pile Caps 06-Nov-14 A 16-Jan-15 A 20-Nov-14 03-Dec-14 Concrete in Pile Caps
Sub Base, Ground Beams & SOG 69 25-Nov-14 A 10-Apr-15 28-Nov-14 16-Feb-15 10-Apr-15, Sub Base, Ground Beams & SOG
A01358 10 Water Proofing 10-Dec-14 A 05-Mar-15 29-Dec-14 09-Jan-15 Water Proofing
A01360 12 Steel Reinforcement 14-Dec-14 A 13-Mar-15 07-Jan-15 20-Jan-15 Steel Reinforcement
A01356 20 Soling 08-Dec-14 A 24-Feb-15 05-Dec-14 29-Dec-14 Soling
A01359 12 Protection of Water Proofing 13-Dec-14 A 09-Mar-15 29-Dec-14 13-Jan-15 Protection of Water Proofing
A01355 21 Earth Filling 25-Nov-14 A 18-Feb-15 28-Nov-14 23-Dec-14 Earth Filling
A01361 12 Concrete 18-Dec-14 A 10-Apr-15 02-Feb-15 16-Feb-15 Concrete

Primary Baseline Remaining Work Milestone Page 22 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A01357 19 1:4:8 09-Dec-14 A 27-Feb-15 09-Dec-14 01-Jan-15 1:4:8
Columns 15 10-Apr-15 28-Apr-15 16-Feb-15 05-Mar-15 28-Apr-15, Columns
A01363 12 Steel Reinforcement Work 10-Apr-15 24-Apr-15 16-Feb-15 02-Mar-15 Steel Reinforcement Work
A01364 12 Form Work 14-Apr-15 28-Apr-15 19-Feb-15 05-Mar-15 Form Work
A01365 12 Concrete in Columns 14-Apr-15 28-Apr-15 19-Feb-15 05-Mar-15 Concrete in Columns
Shear Walls 15 10-Apr-15 28-Apr-15 16-Feb-15 05-Mar-15 28-Apr-15, Shear Walls
A01367 12 Steel Reinforcement Work 10-Apr-15 24-Apr-15 16-Feb-15 02-Mar-15 Steel Reinforcement Work
A01368 11 Form Work 14-Apr-15 27-Apr-15 19-Feb-15 04-Mar-15 Form Work
A01369 12 Concrete in walls 15-Apr-15 28-Apr-15 20-Feb-15 05-Mar-15 Concrete in walls
Slab & Beams 18 06-May-15 26-May-15 13-Mar-15 02-Apr-15 26-May-15, Slab & Beams
A01372 4 Steel Reinforcement 21-May-15 26-May-15 30-Mar-15 02-Apr-15 Steel Reinforcement
A01371 13 Form Work 06-May-15 21-May-15 13-Mar-15 30-Mar-15 Form Work
A01373 1 Concrete Pouring 26-May-15 26-May-15 02-Apr-15 02-Apr-15 Concrete Pouring
First Floor 33 28-May-15 06-Jul-15 06-Apr-15 13-May-15 06-Jul-15, First Floor
Columns 8 28-May-15 05-Jun-15 06-Apr-15 13-Apr-15 05-Jun-15, Columns
A01376 5 Steel Reinforcement Work 28-May-15 03-Jun-15 06-Apr-15 09-Apr-15 Steel Reinforcement Work
A01377 5 Form Work 01-Jun-15 05-Jun-15 06-Apr-15 13-Apr-15 Form Work
A01378 4 Concrete in Columns 01-Jun-15 05-Jun-15 07-Apr-15 13-Apr-15 Concrete in Columns
Shear Walls 10 28-May-15 09-Jun-15 06-Apr-15 14-Apr-15 09-Jun-15, Shear Walls
A01380 5 Steel Reinforcement Work 28-May-15 03-Jun-15 06-Apr-15 09-Apr-15 Steel Reinforcement Work
A01381 5 Form Work 01-Jun-15 05-Jun-15 06-Apr-15 13-Apr-15 Form Work
A01382 5 Concrete in Columns 02-Jun-15 09-Jun-15 08-Apr-15 14-Apr-15 Concrete in Columns
Slab & Beams 18 15-Jun-15 06-Jul-15 22-Apr-15 13-May-15 06-Jul-15, Slab & Beams
A01385 5 Steel Reinforcement 30-Jun-15 06-Jul-15 07-May-15 13-May-15 Steel Reinforcement
A01384 13 Form Work 15-Jun-15 30-Jun-15 22-Apr-15 07-May-15 Form Work
A01386 0 Concrete Pouring 06-Jul-15 06-Jul-15 13-May-15 13-May-15 Concrete Pouring
Second Floor 32 08-Jul-15 24-Aug-15 15-May-15 22-Jun-15 24-Aug-15, Second Floor
Columns 11 08-Jul-15 30-Jul-15 15-May-15 22-May-15 30-Jul-15, Columns
A01389 3 Steel Reinforcement Work 08-Jul-15 10-Jul-15 15-May-15 19-May-15 Steel Reinforcement Work
A01390 5 Form Work 08-Jul-15 14-Jul-15 18-May-15 22-May-15 Form Work
A01391 5 Concrete in Columns 24-Jul-15 30-Jul-15 18-May-15 22-May-15 Concrete in Columns
Shear Walls 11 08-Jul-15 30-Jul-15 15-May-15 25-May-15 30-Jul-15, Shear Walls
A01393 3 Steel Reinforcement Work 08-Jul-15 10-Jul-15 15-May-15 19-May-15 Steel Reinforcement Work
A01394 5 Form Work 08-Jul-15 14-Jul-15 18-May-15 22-May-15 Form Work
A01395 5 Concrete in Columns 24-Jul-15 30-Jul-15 19-May-15 25-May-15 Concrete in Columns
Slab & Beams 17 04-Aug-15 24-Aug-15 02-Jun-15 22-Jun-15 24-Aug-15, Slab & Beams
A01398 3 Steel Reinforcement 18-Aug-15 21-Aug-15 16-Jun-15 19-Jun-15 Steel Reinforcement
A01397 12 Form Work 04-Aug-15 18-Aug-15 02-Jun-15 16-Jun-15 Form Work
A01399 2 Concrete Pouring 21-Aug-15 24-Aug-15 19-Jun-15 22-Jun-15 Concrete Pouring
Roof 25 25-Aug-15 01-Oct-15 23-Jun-15 30-Jul-15 01-Oct-15, Roof
Columns 6 25-Aug-15 01-Sep-15 23-Jun-15 30-Jun-15 01-Sep-15, Columns
A01402 3 Steel Reinforcement Work 26-Aug-15 28-Aug-15 24-Jun-15 26-Jun-15 Steel Reinforcement Work
A01403 5 Form Work 25-Aug-15 31-Aug-15 23-Jun-15 29-Jun-15 Form Work
A01404 6 Concrete in Columns 25-Aug-15 01-Sep-15 23-Jun-15 30-Jun-15 Concrete in Columns
Shear Walls 7 25-Aug-15 02-Sep-15 23-Jun-15 01-Jul-15 02-Sep-15, Shear Walls
A01406 3 Steel Reinforcement Work 26-Aug-15 28-Aug-15 24-Jun-15 26-Jun-15 Steel Reinforcement Work
A01407 5 Form Work 25-Aug-15 31-Aug-15 23-Jun-15 29-Jun-15 Form Work
A01408 6 Concrete in Columns 26-Aug-15 02-Sep-15 24-Jun-15 01-Jul-15 Concrete in Columns
Slab & Beams 8 14-Sep-15 01-Oct-15 13-Jul-15 30-Jul-15 01-Oct-15, Slab & Beams
A01411 1 Steel Reinforcement 22-Sep-15 25-Sep-15 24-Jul-15 29-Jul-15 Steel Reinforcement
A01410 7 Form Work 14-Sep-15 22-Sep-15 13-Jul-15 21-Jul-15 Form Work
A01412 0 Concrete Pouring 01-Oct-15 01-Oct-15 29-Jul-15 30-Jul-15 Concrete Pouring

Primary Baseline Remaining Work Milestone Page 23 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Finishing 232 23-Jun-15 11-Apr-16 30-Apr-15 25-Mar-16 11-Apr-16, Finishing
Ground Floor 218 23-Jun-15 25-Mar-16 30-Apr-15 25-Mar-16 25-Mar-16, Ground Floor
A01416 36 Plaster 24-Jul-15 03-Sep-15 29-May-15 10-Jul-15 Plaster
A01419 35 Paint 10-Dec-15 22-Jan-16 20-Oct-15 02-Dec-15 Paint
A01418 34 Flooring works 01-Oct-15 12-Nov-15 03-Aug-15 14-Sep-15 Flooring works
A01420 30 Doors & Windows fixing 19-Feb-16 25-Mar-16 19-Feb-16 25-Mar-16 Doors & Windows fixing
A01417 29 Ceiling works 28-Aug-15 09-Oct-15 06-Jul-15 17-Aug-15 Ceiling works
A01415 29 Block Masonry 23-Jun-15 05-Aug-15 30-Apr-15 12-Jun-15 Block Masonry
First Floor 156 12-Aug-15 22-Feb-16 10-Jun-15 21-Dec-15 22-Feb-16, First Floor
A01423 28 Plaster 18-Sep-15 30-Oct-15 09-Jul-15 20-Aug-15 Plaster
A01426 43 Paint 04-Dec-15 25-Jan-16 02-Oct-15 23-Nov-15 Paint
A01425 41 Flooring works 09-Nov-15 28-Dec-15 07-Sep-15 26-Oct-15 Flooring works
A01427 32 Doors & Windows fixing 15-Jan-16 22-Feb-16 13-Nov-15 21-Dec-15 Doors & Windows fixing
A01424 35 Ceiling works 16-Oct-15 27-Nov-15 06-Aug-15 17-Sep-15 Ceiling works
A01422 36 Block Masonry 12-Aug-15 24-Sep-15 10-Jun-15 23-Jul-15 Block Masonry
Second Floor 163 21-Sep-15 11-Apr-16 29-Jul-15 18-Mar-16 11-Apr-16, Second Floor
A01430 35 Plaster 19-Oct-15 01-Dec-15 03-Sep-15 16-Oct-15 Plaster
A01433 44 Paint 05-Jan-16 25-Feb-16 26-Nov-15 15-Jan-16 Paint
A01432 42 Flooring works 08-Dec-15 28-Jan-16 28-Oct-15 17-Dec-15 Flooring works
A01434 24 Doors & Windows fixing 14-Mar-16 11-Apr-16 19-Feb-16 18-Mar-16 Doors & Windows fixing
A01431 41 Ceiling works 11-Nov-15 31-Dec-15 01-Oct-15 19-Nov-15 Ceiling works
A01429 28 Block Masonry 21-Sep-15 03-Nov-15 29-Jul-15 10-Sep-15 Block Masonry
Mechanical Floor 109 15-Oct-15 24-Feb-16 13-Aug-15 06-Jan-16 24-Feb-16, Mechanical Floor
A01442 35 Roof Screeding and Water Proofing 15-Oct-15 27-Nov-15 13-Aug-15 25-Sep-15 Roof Screeding and Water Proofing
A01437 21 Plaster 19-Nov-15 14-Dec-15 01-Oct-15 26-Oct-15 Plaster
A01440 22 Paint 15-Jan-16 10-Feb-16 25-Nov-15 21-Dec-15 Paint
A01439 24 Flooring works 23-Dec-15 22-Jan-16 02-Nov-15 02-Dec-15 Flooring works
A01441 12 Doors & Windows fixing 10-Feb-16 24-Feb-16 23-Dec-15 06-Jan-16 Doors & Windows fixing
A01438 16 Ceiling Works 14-Dec-15 04-Jan-16 26-Oct-15 13-Nov-15 Ceiling Works
A01436 20 Block Masonry 02-Nov-15 25-Nov-15 27-Aug-15 21-Sep-15 Block Masonry
MEP WORKS 314 15-Apr-15 02-Feb-16 20-Feb-15 28-Nov-15 02-Feb-16, MEP WORKS
EXTERNAL FINISHES (Façade - RAMMED EARTH) 666 12-Feb-15 25-Oct-16 23-Sep-14 31-Aug-16 25
PHASE-01 (DESIGN MIX AND APPROVAL) 150 12-Feb-15 01-Jul-15 23-Sep-14 10-Feb-15 01-Jul-15, PHASE-01 (DESIGN MIX AND APPROVAL)
A7610 25 RECTIFICATION (IF ANY) 16-May-15 08-Jun-15 25-Dec-14 17-Jan-15 RECTIFICATION (IF ANY)
A7600 25 ON SITE MOCKUP (CASTING) 23-Apr-15 15-May-15 02-Dec-14 25-Dec-14 ON SITE MOCKUP (CASTING)
A7590 25 FORMWORK DESIGN 31-Mar-15 22-Apr-15 08-Nov-14 02-Dec-14 FORMWORK DESIGN
A7620 25 FINAL DESIGN DRAWING 09-Jun-15 01-Jul-15 17-Jan-15 10-Feb-15 FINAL DESIGN DRAWING
A7580 25 FINAL DESIGN 07-Mar-15 30-Mar-15 16-Oct-14 08-Nov-14 FINAL DESIGN
A7570 25 DESIGN MIX 12-Feb-15 06-Mar-15 23-Sep-14 16-Oct-14 DESIGN MIX
PHASE-02 (STARTUP AND EXECUTION) 30 24-Apr-15 22-May-15 27-Feb-15 27-Mar-15 22-May-15, PHASE-02 (STARTUP AND EXECUTION)
A7630 15 ON SITE CASTING OF RAMMED WALL
24-Apr-15 08-May-15 27-Feb-15 13-Mar-15 ON SITE CASTING OF RAMMED WALL
A7640 15 INSPECTION AND RECTIFICATION (IF
08-May-15
REQUIRED) 22-May-15 13-Mar-15 27-Mar-15 INSPECTION AND RECTIFICATION (IF REQUIRED)
PHASE-03 (FINAL EXECUTION) 416 27-May-15 25-Oct-16 01-Apr-15 31-Aug-16 25
BLOCK-F (226.35M) 45 27-May-15 28-Jul-15 01-Apr-15 23-May-15 28-Jul-15, BLOCK-F (226.35M)
A01551 45 Rammed Earth Wall Cladding 27-May-15 28-Jul-15 01-Apr-15 23-May-15 Rammed Earth Wall Cladding
A01553 45 Rammed Earth Jali 27-May-15 28-Jul-15 01-Apr-15 23-May-15 Rammed Earth Jali
A01552 45 Curtain Wall / Aluminium Works 27-May-15 28-Jul-15 01-Apr-15 23-May-15 Curtain Wall / Aluminium Works
BLOCK-B (233.06M) 46 28-Jul-15 19-Sep-15 23-May-15 25-Jul-15 19-Sep-15, BLOCK-B (233.06M)
A9280 46 Rammed Earth Wall Cladding 28-Jul-15 19-Sep-15 23-May-15 25-Jul-15 Rammed Earth Wall Cladding
A9300 46 Rammed Earth Jali 28-Jul-15 19-Sep-15 23-May-15 25-Jul-15 Rammed Earth Jali
A9290 46 Curtain Wall / Aluminium Works 28-Jul-15 19-Sep-15 23-May-15 25-Jul-15 Curtain Wall / Aluminium Works
BLOCK-C (555.26M) 110 01-Oct-15 11-Feb-16 30-Jul-15 16-Dec-15 11-Feb-16, BLOCK-C (555.26M)

Primary Baseline Remaining Work Milestone Page 24 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A9310 110 Rammed Earth Wall Cladding 01-Oct-15 11-Feb-16 30-Jul-15 16-Dec-15 Rammed Earth Wall Cladding
A9330 110 Rammed Earth Jali 01-Oct-15 11-Feb-16 30-Jul-15 16-Dec-15 Rammed Earth Jali
A9320 110 Curtain Wall / Aluminium Works 01-Oct-15 11-Feb-16 30-Jul-15 16-Dec-15 Curtain Wall / Aluminium Works
BLOCK-A (379.96M) 75 11-Feb-16 09-May-16 16-Dec-15 15-Mar-16 09-May-16, BLOCK-A (379.96M)
A9340 75 Rammed Earth Wall Cladding 11-Feb-16 09-May-16 16-Dec-15 15-Mar-16 Rammed Earth Wall Cladding
A9360 75 Rammed Earth Jali 11-Feb-16 09-May-16 16-Dec-15 15-Mar-16 Rammed Earth Jali
A9350 75 Curtain Wall / Aluminium Works 11-Feb-16 09-May-16 16-Dec-15 15-Mar-16 Curtain Wall / Aluminium Works
BLOCK-E (334.7M) 66 09-May-16 03-Aug-16 15-Mar-16 31-May-16 03-Aug-16, B
A9370 66 Rammed Earth Wall Cladding 09-May-16 03-Aug-16 15-Mar-16 31-May-16 Rammed Ear
A9390 66 Rammed Earth Jali 09-May-16 03-Aug-16 15-Mar-16 31-May-16 Rammed Earth Jali
A9380 66 Curtain Wall / Aluminium Works 09-May-16 03-Aug-16 15-Mar-16 31-May-16 Curtain Wall /
BLOCK-D (359.58M) 71 03-Aug-16 25-Oct-16 31-May-16 31-Aug-16 25
A9400 71 Rammed Earth Wall Cladding 03-Aug-16 25-Oct-16 31-May-16 31-Aug-16 Ra
A9420 71 Rammed Earth Jali 03-Aug-16 25-Oct-16 31-May-16 31-Aug-16 Ra
A9410 71 Curtain Wall / Aluminium Works 03-Aug-16 25-Oct-16 31-May-16 31-Aug-16 Cu
EXTERNAL WORKS 763 30-Oct-14 A 04-Nov-16 08-Nov-14 12-Sep-16
BOUNDARY WALL 609 12-Feb-15 02-Sep-16 26-Nov-14 11-Jun-16 02-Sep-1
Civil Works 425 12-Feb-15 22-Jul-16 26-Nov-14 03-May-16 22-Jul-16, Civil Works
EARTH WORKS 154 12-Feb-15 19-Aug-15 26-Nov-14 03-Jun-15 19-Aug-15, EARTH WORKS
A01573 149 Lean Concrete 18-Feb-15 19-Aug-15 02-Dec-14 03-Jun-15 Lean Concrete
A01572 150 Excavation 12-Feb-15 14-Aug-15 26-Nov-14 29-May-15 Excavation
FOOTING 151 24-Feb-15 28-Aug-15 09-Dec-14 12-Jun-15 28-Aug-15, FOOTING
A01575 150 Reinforcement 24-Feb-15 27-Aug-15 09-Dec-14 10-Jun-15 Reinforcement
A01576 150 Formwork 26-Feb-15 28-Aug-15 11-Dec-14 12-Jun-15 Formwork
A01577 149 Concrete Pouring 27-Feb-15 28-Aug-15 12-Dec-14 12-Jun-15 Concrete Pouring
PLINTH BEAM/FOUNDATION 148 05-Mar-15 03-Sep-15 18-Dec-14 18-Jun-15 03-Sep-15, PLINTH BEAM/FOUNDATION
A01579 142 Reinforcement 05-Mar-15 27-Aug-15 18-Dec-14 11-Jun-15 Reinforcement
A01580 141 Formwork 11-Mar-15 01-Sep-15 24-Dec-14 16-Jun-15 Formwork
A01581 142 Concrete Pouring 12-Mar-15 03-Sep-15 25-Dec-14 18-Jun-15 Concrete Pouring
RAMMED EARTH REINFORCED WALL 394 19-Mar-15 22-Jul-16 01-Jan-15 03-May-16 22-Jul-16, RAM
Boundary Wall - Type - B (Rammed Earth Wall) - 216
West & East Site 19-Mar-15 16-Dec-15 01-Jan-15 17-Sep-15 16-Dec-15, Boundary Wall - Type - B (Ramme
A9430 142 Reinforcement 19-Mar-15 10-Sep-15 01-Jan-15 25-Jun-15 Reinforcement
A9440 141 Formwork 25-Mar-15 15-Sep-15 07-Jan-15 30-Jun-15 Formwork
A9450 141 Concrete 26-Mar-15 15-Sep-15 08-Jan-15 30-Jun-15 Concrete
Delivery / Service Court 35 16-Sep-15 05-Nov-15 01-Jul-15 07-Aug-15 05-Nov-15, Delivery / Service Court
A9460 23 Reinforcement 16-Sep-15 20-Oct-15 01-Jul-15 04-Aug-15 Reinforcement
A9470 28 Formwork 01-Oct-15 04-Nov-15 06-Jul-15 07-Aug-15 Formwork
A9480 28 Concrete 01-Oct-15 05-Nov-15 06-Jul-15 07-Aug-15 Concrete
Entry Court - 1 (Employees, Vehicular) 35 05-Nov-15 16-Dec-15 10-Aug-15 17-Sep-15 16-Dec-15, Entry Court - 1 (Employees, Vehicular)
A9490 30 Reinforcement 05-Nov-15 10-Dec-15 10-Aug-15 11-Sep-15 Reinforcement
A9500 30 Formwork 10-Nov-15 15-Dec-15 13-Aug-15 16-Sep-15 Formwork
A9510 30 Concrete 11-Nov-15 16-Dec-15 13-Aug-15 17-Sep-15 Concrete
Boundary Wall - Type - A (Steel Fence with Rammed
178 Earth Wall) - North & South Side 16-Dec-15 22-Jul-16 17-Sep-15 03-May-16 22-Jul-16, Boun
A01583 148 Reinforcement 16-Dec-15 08-Jun-16 17-Sep-15 10-Mar-16 Reinforcement
A01584 147 Formwork 22-Dec-15 13-Jun-16 01-Oct-15 22-Mar-16 Formwork
A01585 147 Concrete 23-Dec-15 13-Jun-16 01-Oct-15 23-Mar-16 Concrete
Entry Court - 2 (Visitors, Pedestrians) 26 14-Jun-16 22-Jul-16 23-Mar-16 03-May-16 22-Jul-16, Entry
A9520 22 Reinforcement 14-Jun-16 18-Jul-16 23-Mar-16 27-Apr-16 Reinforcement
A9530 21 Formwork 20-Jun-16 22-Jul-16 28-Mar-16 02-May-16 Formwork
A9540 21 Concrete 20-Jun-16 22-Jul-16 29-Mar-16 03-May-16 Concrete
Electical Works 600 20-Feb-15 02-Sep-16 05-Dec-14 11-Jun-16 02-Sep-1
Conduiting Works 490 20-Feb-15 23-May-16 05-Dec-14 23-Feb-16 23-May-16, Conduiting Works

Primary Baseline Remaining Work Milestone Page 25 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
Beam/Foundation 170 05-Mar-15 11-Aug-15 18-Dec-14 26-May-15 11-Aug-15, Beam/Foundation
A6530 170 Conduiting for Manhole 05-Mar-15 11-Aug-15 18-Dec-14 26-May-15 Conduiting for Manhole
A6540 170 Conduiting for Lighting and ELV System05-Mar-15 11-Aug-15 18-Dec-14 26-May-15 Conduiting for Lighting and ELV System
Wall 170 16-Dec-15 23-May-16 17-Sep-15 23-Feb-16 23-May-16, Wall
A6550 170 Conduiting for Manhole 16-Dec-15 23-May-16 17-Sep-15 23-Feb-16 Conduiting for Manhole
A6560 170 Conduiting for Lighting and ELV System16-Dec-15 23-May-16 17-Sep-15 23-Feb-16 Conduiting for Lighting a
Footing 180 20-Feb-15 07-Aug-15 05-Dec-14 22-May-15 07-Aug-15, Footing
A6500 180 Conduiting for Manhole 20-Feb-15 07-Aug-15 05-Dec-14 22-May-15 Conduiting for Manhole
A6520 180 Conduiting for Lighting and ELV System20-Feb-15 07-Aug-15 05-Dec-14 22-May-15 Conduiting for Lighting and ELV System
Electrical Works 240 22-Jan-16 02-Sep-16 31-Oct-15 11-Jun-16 02-Sep-1
A6580 150 Light Pole installation 19-Feb-16 08-Jul-16 28-Nov-15 16-Apr-16 Light Pole installation
A6590 180 fixing of Lights 18-Mar-16 02-Sep-16 26-Dec-15 11-Jun-16 fixing of Lights
A6570 150 Cable Laying 22-Jan-16 10-Jun-16 31-Oct-15 19-Mar-16 Cable Laying
TANKS 157 30-Oct-14 A 28-May-15 08-Nov-14 22-May-15 28-May-15, TANKS
U.G. Water Tanks 157 30-Oct-14 A 28-May-15 08-Nov-14 22-May-15 28-May-15, U.G. Water Tanks
A01557 42 Termite Treatment 24-Nov-14 A 17-Mar-15 22-Nov-14 13-Jan-15 Termite Treatment
A01558 44 Lean Concrete 23-Nov-14 A 17-Mar-15 21-Nov-14 13-Jan-15 Lean Concrete
A01556 42 Excavation 30-Oct-14 A 03-Mar-15 08-Nov-14 27-Dec-14 Excavation
U.G. Domestic Water Tank 49 17-Mar-15 13-May-15 13-Jan-15 09-Mar-15 13-May-15, U.G. Domestic Water Tank
Bottom Slab 12 17-Mar-15 31-Mar-15 13-Jan-15 04-Feb-15 31-Mar-15, Bottom Slab
A9550 0 Reinforcement 17-Mar-15 17-Mar-15 13-Jan-15 21-Jan-15 Reinforcement
A9560 0 Pouring 31-Mar-15 31-Mar-15 27-Jan-15 04-Feb-15 Pouring
Walls 13 09-Apr-15 24-Apr-15 05-Feb-15 20-Feb-15 24-Apr-15, Walls
A9570 7 Reinforcement 09-Apr-15 17-Apr-15 05-Feb-15 13-Feb-15 Reinforcement
A9580 7 Formwork 16-Apr-15 24-Apr-15 12-Feb-15 19-Feb-15 Formwork
A9590 5 Concrete Pouring 20-Apr-15 24-Apr-15 13-Feb-15 20-Feb-15 Concrete Pouring
Top Slab 14 27-Apr-15 13-May-15 20-Feb-15 09-Mar-15 13-May-15, Top Slab
A9610 7 Reinforcement 04-May-15 11-May-15 27-Feb-15 06-Mar-15 Reinforcement
A9600 7 Formwork 27-Apr-15 04-May-15 20-Feb-15 02-Mar-15 Formwork
A9620 7 Concrete Pouring 05-May-15 13-May-15 27-Feb-15 09-Mar-15 Concrete Pouring
U.G. Treated Water Tank 50 30-Mar-15 28-May-15 26-Jan-15 25-Mar-15 28-May-15, U.G. Treated Water Tank
Bottom Slab 20 30-Mar-15 22-Apr-15 26-Jan-15 18-Feb-15 22-Apr-15, Bottom Slab
A9630 8 Reinforcement 30-Mar-15 08-Apr-15 26-Jan-15 04-Feb-15 Reinforcement
A9640 8 Pouring 13-Apr-15 22-Apr-15 09-Feb-15 18-Feb-15 Pouring
Walls 14 22-Apr-15 08-May-15 18-Feb-15 06-Mar-15 08-May-15, Walls
A9650 8 Reinforcement 22-Apr-15 01-May-15 18-Feb-15 27-Feb-15 Reinforcement
A9660 8 Formwork 29-Apr-15 08-May-15 25-Feb-15 05-Mar-15 Formwork
A9670 7 Concrete Pouring 30-Apr-15 08-May-15 26-Feb-15 06-Mar-15 Concrete Pouring
Top Slab 18 07-May-15 28-May-15 05-Mar-15 25-Mar-15 28-May-15, Top Slab
A9690 8 Reinforcement 13-May-15 22-May-15 11-Mar-15 20-Mar-15 Reinforcement
A9680 18 Formwork 07-May-15 28-May-15 05-Mar-15 25-Mar-15 Formwork
A9700 8 Concrete Pouring 15-May-15 25-May-15 13-Mar-15 23-Mar-15 Concrete Pouring
U.G Storm Water Tank 72 25-Nov-14 A 02-Apr-15 12-Feb-15 22-May-15 02-Apr-15, U.G Storm Water Tank
Bottom Slab 54 25-Nov-14 A 06-Dec-14 A 12-Feb-15 16-Apr-15 06-Dec-14 A, Bottom Slab
A9710 42 Reinforcement 25-Nov-14 A 05-Dec-14 A 12-Feb-15 02-Apr-15 Reinforcement
A9720 32 Pouring 06-Dec-14 A 06-Dec-14 A 10-Mar-15 16-Apr-15 Pouring
Walls 56 07-Dec-14 A 23-Feb-15 19-Mar-15 15-May-15 23-Feb-15, Walls
A9730 42 Reinforcement 07-Dec-14 A 12-Jan-15 A 19-Mar-15 07-May-15 Reinforcement
A9740 44 Formwork 18-Dec-14 A 20-Feb-15 26-Mar-15 14-May-15 Formwork
A9750 43 Concrete Pouring 06-Jan-15 A 23-Feb-15 26-Mar-15 15-May-15 Concrete Pouring
Top Slab 43 12-Feb-15 02-Apr-15 02-Apr-15 22-May-15 02-Apr-15, Top Slab
A9770 34 Reinforcement 18-Feb-15 30-Mar-15 09-Apr-15 18-May-15 Reinforcement
A9760 43 Formwork 12-Feb-15 02-Apr-15 02-Apr-15 22-May-15 Formwork

Primary Baseline Remaining Work Milestone Page 26 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
A9780 32 Concrete Pouring 23-Feb-15 01-Apr-15 13-Apr-15 20-May-15 Concrete Pouring
Diesel Tank 48 12-Feb-15 08-Apr-15 02-Mar-15 27-Apr-15 08-Apr-15, Diesel Tank
Bottom Slab 18 12-Feb-15 04-Mar-15 02-Mar-15 23-Mar-15 04-Mar-15, Bottom Slab
A9790 6 Reinforcement 12-Feb-15 18-Feb-15 02-Mar-15 09-Mar-15 Reinforcement
A9800 6 Pouring 25-Feb-15 04-Mar-15 16-Mar-15 23-Mar-15 Pouring
Walls 11 09-Mar-15 20-Mar-15 25-Mar-15 08-Apr-15 20-Mar-15, Walls
A9810 5 Reinforcement 09-Mar-15 13-Mar-15 25-Mar-15 01-Apr-15 Reinforcement
A9820 5 Formwork 16-Mar-15 20-Mar-15 01-Apr-15 07-Apr-15 Formwork
A9830 5 Concrete Pouring 16-Mar-15 20-Mar-15 01-Apr-15 08-Apr-15 Concrete Pouring
Top Slab 15 23-Mar-15 08-Apr-15 08-Apr-15 27-Apr-15 08-Apr-15, Top Slab
A9850 5 Reinforcement 30-Mar-15 03-Apr-15 15-Apr-15 21-Apr-15 Reinforcement
A9840 15 Formwork 23-Mar-15 08-Apr-15 08-Apr-15 27-Apr-15 Formwork
A9860 6 Concrete Pouring 30-Mar-15 06-Apr-15 16-Apr-15 23-Apr-15 Concrete Pouring
Septic Tank 44 02-Mar-15 22-Apr-15 19-Mar-15 11-May-15 22-Apr-15, Septic Tank
Bottom Slab 17 02-Mar-15 20-Mar-15 19-Mar-15 09-Apr-15 20-Mar-15, Bottom Slab
A01560 5 Reinforcement 02-Mar-15 06-Mar-15 19-Mar-15 26-Mar-15 Reinforcement
A01561 6 Pouring 13-Mar-15 20-Mar-15 02-Apr-15 09-Apr-15 Pouring
Walls 12 24-Mar-15 07-Apr-15 13-Apr-15 24-Apr-15 07-Apr-15, Walls
A01563 6 Reinforcement 24-Mar-15 30-Mar-15 13-Apr-15 17-Apr-15 Reinforcement
A01564 6 Formwork 30-Mar-15 06-Apr-15 20-Apr-15 24-Apr-15 Formwork
A01565 6 Concrete Pouring 31-Mar-15 07-Apr-15 20-Apr-15 24-Apr-15 Concrete Pouring
Top Slab 13 07-Apr-15 22-Apr-15 27-Apr-15 11-May-15 22-Apr-15, Top Slab
A01568 6 Reinforcement 13-Apr-15 20-Apr-15 04-May-15 08-May-15 Reinforcement
A01567 6 Formwork 07-Apr-15 13-Apr-15 27-Apr-15 01-May-15 Formwork
A01569 6 Concrete Pouring 15-Apr-15 22-Apr-15 04-May-15 11-May-15 Concrete Pouring
MS TOWER 145 08-Apr-15 12-Oct-15 01-Jan-15 09-Jul-15 12-Oct-15, MS TOWER
A01588 50 Prefabrication of Steel Structure 14-Apr-15 11-Jun-15 12-Jan-15 10-Mar-15 Prefabrication of Steel Structure
A01587 17 Making of Foundations With Templates 08-Apr-15 28-Apr-15 01-Jan-15 21-Jan-15 Making of Foundations With Templates
A01589 49 Eraction and Installation of Steel Structure
13-May-15 09-Jul-15 09-Feb-15 07-Apr-15 Eraction and Installation of Steel Structure
A01590 66 Cladding and Finishing Works 09-Jul-15 12-Oct-15 07-Apr-15 09-Jul-15 Cladding and Finishing Works
ELECTRIFICATION WORKS 96 13-Jun-16 12-Oct-16 23-Mar-16 22-Jul-16 12-O
A01605 96 External Lighting Arrangements 13-Jun-16 12-Oct-16 23-Mar-16 22-Jul-16 Exte
MECHANICAL WORKS 158 03-Mar-15 28-Jul-15 15-Dec-14 26-May-15 28-Jul-15, MECHANICAL WORKS
TANKS 110 16-Apr-15 28-Jul-15 12-Feb-15 26-May-15 28-Jul-15, TANKS
A1730 20 TANK MANHOLE COVERS 09-Jul-15 28-Jul-15 07-May-15 26-May-15 TANK MANHOLE COVERS
A1720 90 PIIPE SLEEVES FOR TANKS 16-Apr-15 09-Jul-15 12-Feb-15 07-May-15 PIIPE SLEEVES FOR TANKS
BOUNDARY WALL 110 03-Mar-15 13-Jun-15 15-Dec-14 27-Mar-15 13-Jun-15, BOUNDARY WALL
A1740 110 EXTERNAL SEWERAGE, FIRE HYDRANT
03-Mar-15
AND DRIP13-Jun-15
IRRIGATION PIPING
15-Dec-14 27-Mar-15 EXTERNAL SEWERAGE, FIRE HYDRANT AND DRIP IRRIGATION PIPING
LAND SCAPING 137 18-Feb-16 05-Aug-16 31-Dec-15 17-Jun-16 05-Aug-16, L
Civil Works 82 18-Feb-16 24-May-16 31-Dec-15 05-Apr-16 24-May-16, Civil Works
A01595 59 Water Proofing 17-Mar-16 24-May-16 27-Jan-16 05-Apr-16 Water Proofing
A01594 58 Making of Water Bodies 03-Mar-16 10-May-16 14-Jan-16 22-Mar-16 Making of Water Bodies
A01593 57 Making of Planter & Water Chanels 18-Feb-16 25-Apr-16 31-Dec-15 04-Mar-16 Making of Planter & Water Chanels
Plantation 70 06-May-16 05-Aug-16 21-Mar-16 17-Jun-16 05-Aug-16, Plantation
A01598 54 Spreading of Cow Maneure 16-May-16 27-Jul-16 30-Mar-16 09-Jun-16 Spreading of C
A01597 55 Spreading and Levelling of Sweet Earth06-May-16 19-Jul-16 21-Mar-16 01-Jun-16 Spreading and L
A01599 53 Plantation 26-May-16 05-Aug-16 07-Apr-16 17-Jun-16 Plantation
CLEANOUT AND HANDOVER 23 08-Oct-16 04-Nov-16 16-Aug-16 12-Sep-16
A01608 21 Removing of all Equipments 11-Oct-16 04-Nov-16 18-Aug-16 12-Sep-16
A01609 23 Handover 08-Oct-16 04-Nov-16 16-Aug-16 12-Sep-16
A01610 8 Demobilization 26-Oct-16 04-Nov-16* 02-Sep-16 12-Sep-16
A01607 21 Cleaning/House Keeping 11-Oct-16 04-Nov-16 18-Aug-16 12-Sep-16

Primary Baseline Remaining Work Milestone Page 27 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
Construction of Margalla Building, Islamabad Classic Schedule Layout
Activity ID Original Duration Activity Name Start Finish BL1 Start BL1 Finish 2014 2015 2016
M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N
TESTING AND COMMISIONING OF MEP WORKS 115 16-Apr-16 02-Aug-16 24-Mar-16 15-Jun-16 02-Aug-16, TE
HVAC WORKS 90 10-May-16 02-Aug-16 24-Mar-16 15-Jun-16 02-Aug-16, H
A7530 90 TESTING AND COMMISSIONING OF HVAC
10-May-16
SYSTEMS
02-Aug-16 24-Mar-16 15-Jun-16 TESTING AND
PLUMBING WORKS 90 16-Apr-16 09-Jul-16 24-Mar-16 15-Jun-16 09-Jul-16, PLUM
A7520 90 TESTING AND COMMISSIONING OF PUMPS
16-Apr-16
AND ALLIED
09-Jul-16
EQUIPMENTS
24-Mar-16 15-Jun-16 TESTING AND C
FIRE FIGHTING WORKS 90 10-May-16 02-Aug-16 24-Mar-16 15-Jun-16 02-Aug-16, FI
A7540 90 TESTING AND COMMISSIONING OF FIRE
10-May-16
FIGHTING02-Aug-16
SYSTEMS 24-Mar-16 15-Jun-16 TESTING AND
BMS WORKS 90 10-May-16 02-Aug-16 24-Mar-16 15-Jun-16 02-Aug-16, BM
A7550 90 TESTING AND COMMISSIONING OF BMS
10-May-16 02-Aug-16 24-Mar-16 15-Jun-16 TESTING AND
ELECTRICAL WORKS 90 10-May-16 02-Aug-16 24-Mar-16 15-Jun-16 02-Aug-16, EL
A7560 90 TESTING AND COMMISSIONING OF ELECTRICAL
10-May-16 WORKS
02-Aug-16 24-Mar-16 15-Jun-16 TESTING AND

Primary Baseline Remaining Work Milestone Page 28 of 28 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

ANNEXURE II

Submittals and Shop Drawings Status

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
STATUS TOTAL CIVIL MECHANICAL ELECTRICAL
SUBMITTED 75 29 33 13
MARGALLA BUILDING PENDING 29 11 15 3
APPROVED 33 18 13 2
SUBMITTALS STATUS FOR CIVIL & MEP APPROVED WITH
7 - 1 6
COMMENTS
REJECTED 6 - 4 2
APPRIVAL TIME (MAJOR ITEMS) 15 DAYS
UPDATED 3-Feb-15
APPROVAL TIME (MINOR ITEMS) 07 DAYS

CONSULTANT'S RESPONSE
VARIANCE VARIANCE MATERIAL
S.NO. DISCIPLINE REF NO. DESCRIPTION SUBMISSION SUBMITTAL STATUS REMARKS
ACTUAL (DAYS) STATUS SOURCE ORIGIN
RESPONSE DUE
RESPONSE

1st 7-Jul-14 22-Jul-14 12-Aug-14 (21) Delayed Approved with Comments Re-submission required
1 Electrical Elec 01 CONDUITS & PIPES (WITH ACCESSORIES) LOCAL
Formal approval is
2nd 27-Aug-14 11-Sep-14 18-Sep-14 (7) Delayed Approved with Comments
awaited from Arcop
1st 7-Jul-14 22-Jul-14 13-Aug-14 (22) Delayed Rejected Re-submission required
EARTHING AND LIGHTNING PROTECTION
2 Electrical Elec 02 LOCAL
SYSTEM Formal Approval is
2nd 27-Aug-14 11-Sep-14 16-Sep-14 (5) Delayed Approved with Comments
awaited from Arcop
POWER, LOW VOLTAGE, WIRING & EARTHING
3 Electrical Elec 03 1st 27-Aug-14 11-Sep-14 2-Oct-14 (21) Delayed Approved with Comments - LOCAL
CABLES
1st 5-Sep-14 20-Sep-14 3-Oct-14 (13) Delayed Rejected Re-submission required
4 Electrical Elec 04 ELEVATORS IMPORTED
Re-submission required
2nd 10-Nov-14 25-Nov-14 8-Dec-14 (3) Delayed Rejected
by GC
5 Electrical Elec 05 CABLE TRAY, LADDER AND TRUNKING 1st 5-Sep-14 20-Sep-14 2-Oct-14 (12) On Time Approved with Comments - LOCAL

1st 9-Oct-14 24-Oct-14 24-Oct-14 - On Time Approved with Comments Re-submission required IMPORTED
6 Electrical Elec 06 SWITCHES & SOCKETS
2nd 20-Jan-15 4-Feb-15 1 Pending

7 Electrical Elec 07 BUS BAR RISERS & TAP OFF BOX 1st 13-Oct-14 28-Oct-14 29-Oct-14 (1) On Time Approved with Comments - IMPORTED

1st 9-Oct-14 24-Oct-14 24-Oct-14 - On Time Approved with Comments Re-submission required IMPORTED
8 Electrical Elec 08 JUNCTION & SERVICE OUTLET BOXES
2nd 31-Dec-14 15-Jan-15 27-Jan-15 (12) Delayed Rejected
9 Electrical Elec 01.a PVC/UPVC CONDUIT AND ITS ACCESSORIES 1st 31-Oct-14 15-Nov-14 11-Nov-14 4 On Time Approved
Formal approval is
10 Electrical Elec 06.a BACK BOXES FOR SWITCHES AND SOCKETS 1st 31-Oct-14 15-Nov-14 5-Nov-14 10 On Time Approved with Comments
awaited from Arcop
1st 10-Nov-14 25-Nov-14 13-Nov-14 12 On Time Rejected
11 Electrical Elec.09 INTERIOR LIGHT FIXTURE
2nd 19-Dec-14 3-Jan-15 23-Dec-14 11 On Time Approved

LIGHT FIXTURES, (EXTERNAL) UNDER WATER


12 Electrical Elec.10 1st 9-Jan-15 24-Jan-15 (10) Delayed Pending
WALL LIGHT & UNDER WATER FLOOR LIGHT
STATUS TOTAL CIVIL MECHANICAL ELECTRICAL
SUBMITTED 75 29 33 13
MARGALLA BUILDING PENDING 29 11 15 3
APPROVED 33 18 13 2
SUBMITTALS STATUS FOR CIVIL & MEP APPROVED WITH
7 - 1 6
COMMENTS
REJECTED 6 - 4 2
APPRIVAL TIME (MAJOR ITEMS) 15 DAYS
UPDATED 3-Feb-15
APPROVAL TIME (MINOR ITEMS) 07 DAYS

CONSULTANT'S RESPONSE
VARIANCE VARIANCE MATERIAL
S.NO. DISCIPLINE REF NO. DESCRIPTION SUBMISSION SUBMITTAL STATUS REMARKS
ACTUAL (DAYS) STATUS SOURCE ORIGIN
RESPONSE DUE
RESPONSE

LIGHT FIXTURES, (EXTERNAL) UNDER WATER


13
1 Electrical
Electrical Elec.10-b
Elec 01 CONDUITS 1st 27-Jan-15 11-Feb-15 Pending
WALL LIGHT&&PIPES (WITH
UNDER ACCESSORIES)
WATER FLOOR LIGHT LOCAL

1 Civil Struct 01 CRYSTALLINE WATERPROOFING AQUAFIN IC 1st 7-Aug-14 22-Aug-14 15-Aug-14 7 On Time Approved - LOCAL
SIKA SEAL 105 - WATERPROOFING TO CONCRETE
2 Civil Struct 02 1st 24-Jul-14 8-Aug-14 7-Aug-14 1 On Time Approved - LOCAL
JOINTS
3 Civil Struct 03 SWELLING BAR AT CONCRETE JOINTS 1st 24-Jul-14 8-Aug-14 7-Aug-14 1 On Time Approved - LOCAL
REAR GUARD 9" WIDE (CONCRETE JOINT WITH 1st 24-Jul-14 8-Aug-14 7-Aug-14 1 On Time Rejected -
4 Civil Struct 04 LOCAL
LEAN) 2nd 29-Aug-14 13-Sep-14 1-Oct-14 (18) Delayed Approved -
5 Civil Struct 05 TERMITE PROOFING BIFLEX PRO FROM FMC 1st 24-Jul-14 8-Aug-14 7-Aug-14 1 On Time Approved - LOCAL
CONCRETE TILE FOR CEMENT COLOUR TONE
6 Civil Struct 06 1st 7-Aug-14 22-Aug-14 30-Sep-14 (39) Delayed Approved - LOCAL
APPROVAL
7 Civil Struct 07 Neoprene Pad 1st 17-Nov-14 2-Dec-14 19-Nov-14 13 On Time Approved
1st 26-Jul-14 10-Aug-14 29-Aug-14 (19) Delayed Rejected -
8 Civil Arch 01 OCEAN BROWN STONE (STONE CLADDING) 2nd 6-Sep-14 21-Sep-14 16-Sep-14 5 On Time Rejected Re-submission required IMPORTED **
3rd 3-Oct-14 18-Oct-14 6-Nov-14 (19) Delayed Approved -
1st 6-Aug-14 21-Aug-14 29-Aug-14 (8) Delayed Rejected -
9 Civil Arch 02 VITRIFIED TILES (NATIONAL TILES) LOCAL
2nd 8-Sep-14 23-Sep-14 16-Sep-14 7 On Time Approved -

1st 19-Aug-14 3-Sep-14 17-Sep-14 (153) Delayed Rejected Re-submission required


10 Civil Arch 03 METAL PAN CEILING IMPORTED **
2nd 16-Oct-14 31-Oct-14 24-Oct-14 7 On Time Approved -

1st 25-Aug-14 9-Sep-14 29-Aug-14 11 On Time Rejected Re-submission required


11 Civil Arch 04 GYPSUM FALSE CEILING IMPORTED
2nd 3-Oct-14 18-Oct-14 31-Oct-14 (25) Delayed Approved -
STATUS TOTAL CIVIL MECHANICAL ELECTRICAL
SUBMITTED 75 29 33 13
MARGALLA BUILDING PENDING 29 11 15 3
APPROVED 33 18 13 2
SUBMITTALS STATUS FOR CIVIL & MEP APPROVED WITH
7 - 1 6
COMMENTS
REJECTED 6 - 4 2
APPRIVAL TIME (MAJOR ITEMS) 15 DAYS
UPDATED 3-Feb-15
APPROVAL TIME (MINOR ITEMS) 07 DAYS

CONSULTANT'S RESPONSE
VARIANCE VARIANCE MATERIAL
S.NO. DISCIPLINE REF NO. DESCRIPTION SUBMISSION SUBMITTAL STATUS REMARKS
ACTUAL (DAYS) STATUS SOURCE ORIGIN
RESPONSE DUE
RESPONSE

1st 28-Aug-14 12-Sep-14 30-Sep-14 (18) Delayed Rejected Re-submission required IMPORTED
12 Civil Arch 05 GLAZED PORCELAIN TILES ACCESSORIES)
1 Electrical Elec 01 CONDUITS & PIPES (WITH LOCAL
2nd 7-Nov-14 22-Nov-14 7-Nov-14 15 On Time Approved -
1st 28-Aug-14 12-Sep-14 30-Sep-14 (18) Delayed Rejected Re-submission required IMPORTED
13 Civil Arch 06 MATT PORCELAIN TILES
2nd 7-Nov-14 22-Nov-14 7-Nov-14 15 On Time Approved -
INTERNAL AND EXTERNAL PAINT (SHADE CARDS
14 Civil Arch 07 1st 10-Sep-14 25-Sep-14 17-Sep-14 8 On Time Approved - LOCAL
BY JOTUN)
1st 29-Sep-14 14-Oct-14 2-Oct-14 12 On Time Rejected Re-submission required IMPORTED
15 Civil Arch 08 CARPET TILES
2nd 31-Oct-14 15-Nov-14 (80) Delayed Pending
1st 30-Sep-14 15-Oct-14 2-Oct-14 13 On Time Rejected Re-submission required
16 Civil Arch 09 CORIAN / VANITY / COUNTER TOPS IMPORTED
2nd 13-Oct-14 28-Oct-14 16-Oct-14 12 On Time Approved -
17 Civil Arch 10 AUTOMATIC REVOLVING DOOR 1st 3-Oct-14 18-Oct-14 (108) Delayed Pending - IMPORTED
GYPSUM BOARD 12MM WITH HANGING
18 Civil Arch 11 1st 17-Nov-14 2-Dec-14 19-Nov-14 13 On Time Approved
SYSTEM
19 Civil Arch 12 METAL PAN CEILING (300*1200) 1st 9-Dec-14 24-Dec-14 18-Dec-14 6 On Time Approved
1st 11-Dec-14 26-Dec-14 Rejected
20 Civil Arch 13 VINYLE FLOOR
2nd 9-Dec-14 24-Dec-14 23-Jan-15 (30) Delayed Approved
21 Civil Arch 14 RAISED FLOOR 1st 15-Dec-14 30-Dec-14 (35) Delayed Pending
22 Civil Arch 15 RUBBER FLOOR 1st 17-Dec-14 1-Jan-15 (33) Delayed Pending
23 Civil Arch 16 ALUMINIUM DOOR FRAME SECTION 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
24 Civil Arch 17 JODHPUR STONE 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
25 Civil Arch 18 WOOD FLOOR 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
26 Civil Arch 19 WOODEN SCREEN 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
27 Civil Arch 20 WOODEN GLAZED PARTITION 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
28 Civil Arch 21 WOOD AND GLASS RAILING 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
29 Civil Arch 22 WOODEN DOOR 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
STATUS TOTAL CIVIL MECHANICAL ELECTRICAL
SUBMITTED 75 29 33 13
MARGALLA BUILDING PENDING 29 11 15 3
APPROVED 33 18 13 2
SUBMITTALS STATUS FOR CIVIL & MEP APPROVED WITH
7 - 1 6
COMMENTS
REJECTED 6 - 4 2
APPRIVAL TIME (MAJOR ITEMS) 15 DAYS
UPDATED 3-Feb-15
APPROVAL TIME (MINOR ITEMS) 07 DAYS

CONSULTANT'S RESPONSE
VARIANCE VARIANCE MATERIAL
S.NO. DISCIPLINE REF NO. DESCRIPTION SUBMISSION SUBMITTAL STATUS REMARKS
ACTUAL (DAYS) STATUS SOURCE ORIGIN
RESPONSE DUE
RESPONSE
1 Mechanical Mech 01 PPR PIPE 1st 21-Jul-14 5-Aug-14 18-Aug-14 (13) Delayed Approved with Comments - LOCAL
1 Electrical Elec 01 CONDUITS & PIPES (WITH ACCESSORIES) LOCAL
2 Mechanical Mech 02 CHILLED BEAM 1st 28-Jul-14 12-Aug-14 29-Aug-14 (17) Delayed Rejected Re-submission required IMPORTED *

1st 8-Aug-14 23-Aug-14 29-Aug-14 (6) Delayed Rejected Re-submission required


uPVC PIPE & FITTINGS (Above Ground & Under LOCAL
3 Mechanical Mech 03
Ground) 2nd 20-Sep-14 5-Oct-14 24-Oct-14 (19) Delayed Rejected Re-submission required
3rd 12-Nov-14 27-Nov-14 25-Nov-14 2 On Time Approved

4 Mechanical Mech 04 FCU 1st 26-Aug-14 10-Sep-14 12-Sep-14 (2) Delayed Rejected Re-submission required IMPORTED *

5 Mechanical Mech 05 FAHU & AHU 1st 26-Aug-14 10-Sep-14 25-Sep-14 (15) Delayed Rejected Re-submission required IMPORTED *
6 Mechanical Mech 06 VAV BOXES 1st 1-Sep-14 16-Sep-14 24-Oct-14 (38) Delayed Approved - IMPORTED *
1st 24-Sep-14 9-Oct-14 24-Oct-14 (15) Delayed Rejected Re-submission required IMPORTED *
7 Mechanical Mech 07 WATER COOLED SCREW CHILLER
2nd 4-Dec-14 19-Dec-14 (46) Delayed pending
1st 24-Sep-14 9-Oct-14 24-Oct-14 (15) Delayed Rejected Re-submission required IMPORTED *
8 Mechanical Mech 08 AIR COOLED SCREW CHILLER
2nd 4-Dec-14 19-Dec-14 (46) Delayed Pending
FIRE, PLUMBING & HVAC WORKS - PIPE HANGER
Mechanical Mech 09 1st 27-Sep-14 12-Oct-14 30-Oct-14 (18) Delayed Rejected Re-submission required LOCAL
9 & SUPPORTS (HILTI BRAND)
2nd 27-Jan-15 11-Feb-15 8 Pending

1st 27-Sep-14 12-Oct-14 30-Oct-14 (18) Delayed Rejected Re-submission required LOCAL
FIRE, PLUMBING & HVAC WORKS - PIPE HANGER
10 Mechanical Mech 010
& SUPPORTS (FISCRH BRAND)
2nd 12-Nov-14 27-Nov-14 25-Nov-14 2 On Time Approved
STATUS TOTAL CIVIL MECHANICAL ELECTRICAL
SUBMITTED 75 29 33 13
MARGALLA BUILDING PENDING 29 11 15 3
APPROVED 33 18 13 2
SUBMITTALS STATUS FOR CIVIL & MEP APPROVED WITH
7 - 1 6
COMMENTS
REJECTED 6 - 4 2
APPRIVAL TIME (MAJOR ITEMS) 15 DAYS
UPDATED 3-Feb-15
APPROVAL TIME (MINOR ITEMS) 07 DAYS

CONSULTANT'S RESPONSE
VARIANCE VARIANCE MATERIAL
S.NO. DISCIPLINE REF NO. DESCRIPTION SUBMISSION SUBMITTAL STATUS REMARKS
ACTUAL (DAYS) STATUS SOURCE ORIGIN
RESPONSE DUE
RESPONSE
SEAMLESS SCHEDULE 40 PIPE (FIRE AND
Mechanical 1st 30-Sep-14 15-Oct-14 24-Oct-14 (9) Delayed Approved -
1 Electrical Elec 01 NATURAL
CONDUITSGAS)
& PIPES (WITH ACCESSORIES) LOCAL
11 Mech 011
Mechanical 1st 30-Sep-14 15-Oct-14 24-Oct-14 (9) Delayed Rejected Re-submission required
SEAMLESS SCHEDULE 40 PIPE FOR FIRE
SUPRESSION
12 Mech 018 2nd 5-Nov-14 20-Nov-14 11-Nov-14 9 On Time Approved -

1st 30-Sep-14 15-Oct-14 24-Oct-14 (9) Delayed Rejected Re-submission required


ELASTOMETRIC RUBBER INSULATION
13 Mechanical Mech 012
(FORTELFLEX)
2nd 31-Dec-14 15-Jan-15 (19) Delayed Pending

14 Mechanical Mech 012(A) ELASTOMETRIC RUBBER INSULATION(AEROFLEX) 1st 31-Dec-14 15-Jan-15 (19) Delayed Pending

GROOVED FITTING FR MS SCHEDULE 40 FIRE


15 1st 30-Sep-14 15-Oct-14 24-Oct-14 (9) Delayed Approved -
SUPRESSION PIPE 2.5" DIA. AND ABOVE)

1st 30-Sep-14 15-Oct-14 24-Oct-14 (9) Delayed Rejected Re-submission required


THREADED FITTINGS FOR MS SCHEDULE 40 PIPE
16 Mechanical Mech 013
(2" DIA. AND BELOW)
2nd 12-Nov-14 27-Nov-14 26-Nov-14 1 On Time Approved

THREAD FITTING (FIRE FIGHTING) (HIELD PIPES &


17 1ST 31-Dec-14 15-Jan-15 16-Jan-15 1 On Time Approved
FITTINGS)

1st 10-Oct-14 25-Oct-14 24-Oct-14 1 On Time Rejected Re-submission required


18 Mechanical Mech 014 PIPES FOR CHILLED WATER
2nd 13-Nov-14 28-Nov-14 3-Dec-14 (5) Delayed APPROVED

1st 10-Oct-14 25-Oct-14 27-Oct-14 (2) Delayed Rejected Re-submission required


FITTING FOR CHILLED WATER PIPE AND FITTINGS
19 Mechanical Mech 015
FOR NATURAL GAS
2nd 13-Nov-14 28-Nov-14 26-Nov-14 2 On Time Approved
STATUS TOTAL CIVIL MECHANICAL ELECTRICAL
SUBMITTED 75 29 33 13
MARGALLA BUILDING PENDING 29 11 15 3
APPROVED 33 18 13 2
SUBMITTALS STATUS FOR CIVIL & MEP APPROVED WITH
7 - 1 6
COMMENTS
REJECTED 6 - 4 2
APPRIVAL TIME (MAJOR ITEMS) 15 DAYS
UPDATED 3-Feb-15
APPROVAL TIME (MINOR ITEMS) 07 DAYS

CONSULTANT'S RESPONSE
VARIANCE VARIANCE MATERIAL
S.NO. DISCIPLINE REF NO. DESCRIPTION SUBMISSION SUBMITTAL STATUS REMARKS
ACTUAL (DAYS) STATUS SOURCE ORIGIN
RESPONSE DUE
RESPONSE
uPVC PRESSURE PIPE AND FITTINGS
20 Mechanical Mech 019 1st 5-Nov-14 20-Nov-14 11-Nov-14 9 On Time Approved -
1 Electrical Elec 01 (HEPWORTH)
CONDUITS & PIPES (WITH ACCESSORIES) LOCAL
21 Mechanical Mech 020 PRE-INSULATED DUCTS 1st 5-Nov-14 20-Nov-14 11-Nov-14 9 On Time Approved -
Resubmission
1st 17-Nov-14 2-Dec-14 5-Dec-14 (3) Delayed
Required
22 Mechanical Mech 021 VENTILATION & EXHAUST FANS
2nd 16-Jan-15 31-Jan-15 (3) Delayed Pending

23 Mechanical Mech 022 CONDUITS FOR BMS 1st 1-Dec-14 16-Dec-14 11-Dec-14 5 On Time Approved

24 Mechanical Mech 023 WATER MANAGEMENT SYSTEM 1st 10-Dec-14 25-Dec-14 (10) Delayed Pending

25 Mechanical Mech 024 PLUMBING PUMPS 1st 8-Dec-14 23-Dec-14 (42) Delayed Pending

26 Mechanical Mech 025 FIRE PUMPS 1st 8-Dec-14 23-Dec-14 (42) Delayed Pending

27 Mechanical Mech 026 HVAC PUMPS 1st 8-Dec-14 23-Dec-14 (42) Delayed Pending

28 Mechanical Mech 027 BUILDING MANAGEMENT SYSTEM 1ST 31-Dec-14 15-Jan-15 (19) Delayed Pending

29 Mechanical Mech 028 NOVEC 1230 (FIRE FIGHTING WORK) 1ST 16-Jan-15 31-Jan-15 (3) Delayed Pending

30 Mechanical Mech 029 VALVES (PLUMBING & HVAC WORKS) 1st 26-Jan-15 10-Feb-15 Pending

31 Mechanical Mech 030 JOHNSONS & TOTO (PLUMBING WORKS) 1st 2-Feb-15 17-Feb-15 Pending

32 Mechanical Mech 031 AIR DEVICES (HVAC WORKS) 1st 2-Feb-15 17-Feb-15 Pending

33 Mechanical Mech 032 G.I SHEET (HVAC WORKS) 1st 2-Feb-15 17-Feb-15 Pending

Item on Critical Path. Requires immediate approval.

IMPORTED * Planned on 150 day lead time.


IMPORTED ** Planned on 180 day lead time.
STATUS CIVIL MECHANICAL ELECTRICAL TOTAL
MARGALLA BUILDING SUBMITTED 97 69 39 205

SHOP DRAWING STATUS FOR CIVIL & MEP APPROVED


APPROVED WITH
64 32 0 96
3 1 17 21
COMMENTS
APPROVAL TIME 15 DAYS PENDING 14 25 19 58
UPDATED February 3, 2015 REJECTED 3 11 3 17

CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE
Approved by Engineer
1 Civil PCL/MBI/14-001a Parking Proposed Excavation Layout Plan 1st 10-Jun-14 25-Jun-14 13-Jun-14 12 On-Time Approved
on Site
Approved by Engineer
2 Civil PCL/MBI/14-001b Parking Proposed Excavation Layout Plan(Sections) 1st 10-Jun-14 25-Jun-14 13-Jun-14 12 On-Time Approved
on Site
Approved by Engineer
3 Civil PCL/MBI/14-001c Parking Proposed Excavation Layout Plan(Sections) 1st 10-Jun-14 25-Jun-14 13-Jun-14 12 On-Time Approved
on Site
Approved by Engineer
4 Civil PCL/MBI/14-002 Misc. Foundation Sections & Details 1st 9-Jun-14 24-Jun-14 9-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
5 Civil PCL/MBI/14-003 Foundation Layout Plan Proposed Expansion Joint 1st 9-Jun-14 24-Jun-14 9-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
6 Civil PCL/MBI/14-004a Grid Reference W.R.T Plot Boundary (As Per Drawing) 1st 13-Jun-14 28-Jun-14 13-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
7 Civil PCL/MBI/14-004b Grid Reference W.R.T Plot Boundary (As Per Site/Deep Well Working) 1st 13-Jun-14 28-Jun-14 13-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
8 Civil PCL/MBI/14-005 Parking Excavation Level Plan 1st 13-Jun-14 28-Jun-14 25-Jun-14 3 On-Time Approved
on Site
9 Civil PCL/MBI/14-007 Block C Excavation Layout Plan 1st 7-Jul-14 22-Jul-14 27-Aug-14 (36) Delayed Approved -
10 Civil PCL/MBI/14-008a Parking Footing Section (Bottom Lvl. 206175) Revised Dwg Level 206500 1st 3-Jul-14 18-Jul-14 5-Aug-14 (18) Delayed Approved -
11 Civil PCL/MBI/14-008b Parking Footing Section (Bottom Lvl. 204950) Revised Dwg Level 205275 1st 3-Jul-14 18-Jul-14 5-Aug-14 (18) Delayed Approved -
12 Civil PCL/MBI/14-008c Parking Footing Section (Bottom Lvl. 205775) Revised Dwg Level 206100 1st 3-Jul-14 18-Jul-14 5-Aug-14 (18) Delayed Approved -
13 Civil PCL/MBI/14-009 Main Building Lower Ground Floor Excavation Level Plan & Section 1st 17-Jul-14 1-Aug-14 7-Aug-14 (6) Delayed Approved -
14 Civil PCL/MBI/14-010 Parking Retaining Wall Proposed Vertical Steel Bars 1st 22-Jul-14 6-Aug-14 25-Aug-14 (19) Delayed Approved -
15 Civil PCL/MBI/14-011 Parking Footing Plan & Details 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
16 Civil PCL/MBI/14-011A Parking Footing Plan & Details A 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
17 Civil PCL/MBI/14-012 Parking Footing Section Footing F-5 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
18 Civil PCL/MBI/14-013 Parking Footing Section (Bottom Lvl. 206175) 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
SUBMITTED FOR
19 Civil PCL/MBI/14-014 Parking Columns Layout Plan 1st 21-Aug-14 - - - - -
INFORMATION ONLY
20 Civil PCL/MBI/14-014A Typical Columns Detail 1st 21-Aug-14 5-Sep-14 7-Nov-14 (63) Delayed Approved

SUBMITTED FOR
21 Civil PCL/MBI/14-014B Typical Columns Section 1st 21-Aug-14 - - - - -
INFORMATION ONLY
22 Civil PCL/MBI/14-015 U.G Storm Water sedimentation Tank Proposed Size & Location Coordinate 1st 28-Aug-14 12-Sep-14 9-Oct-14 (27) Delayed Approved

SUBMITTED FOR
23 Civil PCL/MBI/14-016 Pile as Built Location and Detail 1st 4-Sep-14 - - - - -
INFORMATION ONLY
Proposal Rejected(
Parking Basement wall Section & Detail 150mm Thick Gravel With Water Drain Out
24 Civil PCL/MBI/14-017 1st 6-Sep-14 - - - - - Work on the basis of
Arrangement
original Drawings)
SUBMITTED FOR
25 Civil PCL/MBI/14-018 NGL Plan Margalla Building Lower Ground Floor Block C & Part Block D (Joint Survey) 1st 11-Sep-14 - - - - -
INFORMATION ONLY
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE

SUBMITTED FOR
26 Civil PCL/MBI/14-019 NGL Plan Margalla Building Ground Floor Block D ( Joint Survey) 1st 11-Sep-14 - - - - -
INFORMATION ONLY

SUBMITTED FOR
27 Civil PCL/MBI/14-020 NGL Plan Margalla Building Ground Floor Block A ( Joint Survey) 2nd 12-Sep-14 - - - - -
INFORMATION ONLY
28 Civil PCL/MBI/14-021 Propsed Pile Cap Reinforcement 1st 13-Sep-14 28-Sep-14 22-Sep-14 6 On-Time Approved -
Welding will be done
29 Civil PCL/MBI/14-022 Propsed Steel Anchoring in Pile 1st 15-Sep-14 30-Sep-14 25-Sep-14 5 On-Time Approved
instead of anchoring
Sent To Client Office on
30 Civil PCL/MBI/14-023 Propsed SOG Dowels in Columns Plan 1st 20-Sep-14 5-Oct-14 22-Sep-14 13 On-Time Approved
Site
Sent To Client Office on
31 Civil PCL/MBI/14-023A Propsed SOG Dowels in Columns Sections 1st 20-Sep-14 5-Oct-14 22-Sep-14 13 On-Time Approved
Site
To be re- Sent To Client Office on
32 Civil PCL/MBI/14-024 Detail of Air Proofing 1st 23-Sep-14 8-Oct-14
submitted Site
SUBMITTED FOR
33 Civil PCL/MBI/14-025 Pile as Built Location and Detail (upto Date) 1st 27-Sep-14 - - -
INFORMATION ONLY

SUBMITTED FOR
34 Civil PCL/MBI/14-026 NGL Plan Margalla Building Ground Floor Block B ( Joint Survey) 1st 30-Sep-14 - - -
INFORMATION ONLY

SUBMITTED FOR
35 Civil PCL/MBI/14-027 NGL Plan Margalla Building Ground Floor Block E (Joint Survey) 1st 21-Oct-14 5-Nov-14 -
INFORMATION ONLY
Approved Re-
Re submitted on 8-11-
1st 8-Nov-14 23-Nov-14 7-Nov-14 16 On-Time Submission
14
Required.
36 Civil PCL/MBI/14-028 LOWER GROUND FLOOR PILE CAP LAYOUT PLAN
SUBMITTED FOR
2nd 8-Nov-14
INFORMATION ONLY
37 Civil PCL/MBI/14-029 Block A PILE CAP LAYOUT PLAN 1st 30-Oct-14 14-Nov-14 7-Nov-14 7 On-Time Approved
Approved Re-
Re submitted on 11-11-
1st 30-Oct-14 14-Nov-14 7-Nov-14 7 On-Time Submission
14
Required.
38 Civil PCL/MBI/14-030 Block E PILE CAP LAYOUT PLAN
SUBMITTED FOR
2nd 11-Nov-14
INFORMATION ONLY
39 Civil PCL/MBI/14-031 Block B PILE CAP LAYOUT PLAN 1st 31-Oct-14 15-Nov-14 7-Nov-14 8 On-Time Approved
40 Civil PCL/MBI/14-032 PILE CAP LAYOUT PLAN Water Body-3 1st 1-Nov-14 16-Nov-14 22-Nov-14 (6) Delayed Approved
41 Civil PCL/MBI/14-033 Block B Excavation Level Plan & Section 1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Approved
1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Rejected
42 Civil PCL/MBI/14-034 Lower Ground Floor SOG Beams 2nd 6-Dec-14 21-Dec-14 11-Dec-14 10 On-Time To be revised
3rd 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time Approved
1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Rejected
43 Civil PCL/MBI/14-035 Water Body Part-1 Beams
2nd 1-Jan-15 16-Jan-15 6-Jan-15 10 On-Time Approved
1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Rejected
44 Civil PCL/MBI/14-036 Lower GF Column-Wall Plan and Detail
2nd 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved

SUBMITTED FOR
45 Civil PCL/MBI/14-037 Parking Building Proposed Stone Ballast Under SOG 1st 8-Nov-14 23-Nov-14 -
INFORMATION ONLY

SUBMITTED FOR
46 Civil PCL/MBI/14-038 Pile As Built LOCATION/COORDINATES (Up To Date) 1st 7-Nov-14 22-Nov-14 -
INFORMATION ONLY
SUBMITTED FOR
47 Civil 2nd 11-Nov-14 26-Nov-14 Approved
PCL/MBI/14-030 GROUND FLOOR BLOCK E PILE CAP LAYOUT- REV01 INFORMATION ONLY
SUBMITTED FOR
48 Civil 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY
PCL/MBI/14-039 PARKING RETAINING WALL POUR PLANS AND SECTIONS
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE

SUBMITTED FOR
49 Civil 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY
PCL/MBI/14-040 GROUND FLOOR BLOCK A PILE CAP LAYOUT (REVISED)
SUBMITTED FOR
50 Civil GROUND FLOOR BLOCK B PILE CAP LAYOUT (REVISED) 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY
PCL/MBI/14-041
SUBMITTED FOR
51 Civil PCL/MBI/14-042 Block F PILE CAP LAYOUT PLAN 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY

SUBMITTED FOR
52 Civil PCL/MBI/14-043 Pile As Built LOCATION/COORDINATES (Up To Date) 1st 11-Nov-14 26-Nov-14 -
INFORMATION ONLY
Approved As
53 Civil PCL/MBI/14-044 Parking Ramp Level Plan & Sections 1st 12-Nov-14 27-Nov-14 26-Nov-14 1 On-Time
corrected
54 Civil PCL/MBI/14-045 Block E Excavation Level Plan & Section 1st 17-Nov-14 2-Dec-14 17-Nov-14 15 On-Time Approved
55 Civil PCL/MBI/14-046 Block A Excavation Level Plan & Section 1st 17-Nov-14 2-Dec-14 17-Nov-14 15 On-Time Approved
56 Civil PCL/MBI/14-047 U.G. STORM WATER SEDIMENTATION TANK Raft & Framing Plan 1st 17-Nov-14 2-Dec-14 21-Nov-14 11 On-Time Approved
57 Civil PCL/MBI/14-048 Parking SOG Pour Plan and Sections 1st 17-Nov-14 2-Dec-14 19-Nov-14 13 On-Time Approved
SUBMITTED FOR
58 Civil PCL/MBI/14-049 Pile As Built LOCATION/COORDINATES (Up To Date) 1st 18-Nov-14 3-Dec-14 -
INFORMATION ONLY
59 Civil PCL/MBI/14-050 Block D Ground Floor PILE CAP LAYOUT PLAN 1st 19-Nov-14 4-Dec-14 21-Nov-14 13 On-Time Approved
SUBMITTED FOR
60 Civil PCL/MBI/14-051 WB-1 PILE CAP LAYOUT PLAN 1st 20-Nov-14 5-Dec-14 -
INFORMATION ONLY
61 Civil PCL/MBI/14-052 Water Body Part-1 Excavation Level Plan & Section 1st 20-Nov-14 5-Dec-14 4-Dec-14 On-Time Approved
62 Civil PCL/MBI/14-053 LOWER GROUND FLOOR RETAINING WALL FORMWORK & SOG DOWEL DETAIL 1st 22-Nov-14 7-Dec-14 22-Nov-14 15 On-Time Approved
63 Civil PCL/MBI/14-054 U.G Storm Water sedimentation Tank wall beam & Slab Reinforcement 1st 25-Nov-14 10-Dec-14 26-Nov-14 14 On-Time Approved
64 Civil PCL/MBI/14-055 Excavation Plan & Section Water Body-2 1st 28-Nov-14 13-Dec-14 4-Dec-14 9 On-Time Approved
65 Civil PCL/MBI/14-056 Excavation Plan & Section Water Body-3 1st 28-Nov-14 13-Dec-14 4-Dec-14 9 On-Time Approved
1st 28-Nov-14 13-Dec-14 4-Dec-14 9 On-Time Resubmit
66 Civil PCL/MBI/14-057 Excavation Plan & Section Block D Ground Floor
2nd 6-Dec-14 21-Dec-14 11-Dec-14 10 On-Time Approved

SUBMITTED FOR
67 Civil PCL/MBI/14-058 Pile As Built LOCATION/COORDINATES (Final) 1st 28-Nov-14 13-Dec-14 -
INFORMATION ONLY
68 Civil PCL/MBI/14-059 Block F PILE CAP LAYOUT PLAN (Revised) 1st 2-Dec-14 17-Dec-14 4-Dec-14 On-Time Approved
69 Civil PCL/MBI/14-060 Water Body Part-2 PILE CAP LAYOUT PLAN 1st 2-Dec-14 17-Dec-14 4-Dec-14 On-Time Approved
70 Civil PCL/MBI/14-061 MS Tower FRAMING PLAN & BASE PLATE DETAIL 1st 2-Dec-14 17-Dec-14 (48) Delayed Pending
71 Civil PCL/MBI/14-061A MS Tower ELEVATION 1st 2-Dec-14 17-Dec-14 (48) Delayed Pending
72 Civil PCL/MBI/14-061B MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 (48) Delayed Pending
73 Civil PCL/MBI/14-061C MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 (48) Delayed Pending
74 Civil PCL/MBI/14-061D MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 (48) Delayed Pending
75 Civil PCL/MBI/14-061E MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 (48) Delayed Pending
76 Civil PCL/MBI/14-061F MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 (48) Delayed Pending
77 Civil PCL/MBI/14-062 Parking Slab & Column Pour Plan 1st 6-Dec-14 21-Dec-14 24-Dec-14 Delayed Approved
78 Civil PCL/MBI/14-063 Block F Excavation Level Plan & Section 1st 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved
79 Civil PCL/MBI/14-064 Collection & STP Water Tanks Size and Location Coordinates 1st 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved Architect to confirm
80 Civil PCL/MBI/14-065 Fuel Storage & Domestic Water Tanks Size and Location Coordinates 1st 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved Architect to confirm
81 Civil PCL/MBI/14-066 Block F Ground Beams & SOG 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time To be revised
82 Civil PCL/MBI/14-067 Domestic Water Tank Wall & Slab (Top & Bottom) 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time Approved Follow Arch Levels
83 Civil PCL/MBI/14-068 STP Water Tank Wall & Slab (Top & Bottom) 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time Approved Follow Arch Levels
84 Civil PCL/MBI/14-069 Block F R.Wall Plan & Section 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time To be revised
85 Civil PCL/MBI/14-070 Bloc E Ground Beam & SOG 1st 12-Dec-14 27-Dec-14 17-Dec-14 10 On-Time Approved
86 Civil PCL/MBI/14-071 Block A Column & Wall Setting out Plan 1st 12-Dec-14 27-Dec-14 17-Dec-14 10 On-Time Approved
87 Civil PCL/MBI/14-072 Block A SOG & Beams 1st 15-Dec-14 30-Dec-14 17-Dec-14 13 On-Time Approved
88 Civil PCL/MBI/14-073 Block B Ground Floor Column & Wall Setting out Plan 1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Approved
89 Civil PCL/MBI/14-074 Block E Ground Floor Column & Wall Setting out Plan 1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Approved
90 Civil PCL/MBI/14-075 Block B Ground Beams & SOG 1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Approved
1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Rejected
91 Civil PCL/MBI/14-076 Block D Ground Beams & SOG
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE
91 Civil PCL/MBI/14-076 Block D Ground Beams & SOG
2nd 21-Jan-15 5-Feb-15 Pending
Approved As
92 Civil PCL/MBI/14-077 Fuel Storage Tank Wall & Slab 1st 1-Jan-15 16-Jan-15 6-Jan-15
corrected
1st 26-Dec-14 10-Jan-15 6-Jan-15 On-Time Rejected
93 Civil PCL/MBI/14-078 Collection Tank Wall & Slab
2nd 21-Jan-15 5-Feb-15 Pending
94 Civil PCL/MBI/14-079 GROUND FLOOR BLOCK C & D COLUMN & WALL SETTING OUT PLAN 1st 21-Jan-15 5-Feb-15 Pending
95 Civil PCL/MBI/14-080 Block F Ground Floor Column & Wall Setting Out Plan 1st 30-Jan-15 14-Feb-15 Pending
96 Civil PCL/MBI/14-081 U.G Storm Water Tank Excavation Plan & Sections 1st 30-Jan-15 14-Feb-15 Pending
97 Civil PCL/MBI/14-082 Water Body Part-2 SOG Bams & Wall 1st 30-Jan-15 14-Feb-15 Pending
1 Mechanical SEL-193-SD-D-DETAIL-1 DRAINAGE STANDARD DETAIL-1 1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) On-Time Rejected
2 Mechanical SEL-193-SD-D-DETAIL-2 DRAINAGE STANDARD DETAIL-2 1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
3 Mechanical SEL-193-SD-D-BAS.2 DRAINAGE LAYOUT FOR BASEMENT 2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
4 Mechanical SEL-193-SD-D-BAS.2.1 DRAINAGE LAYOUT FOR BASEMENT 2 (Part-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
5 Mechanical SEL-193-SD-D-BAS.2.2 DRAINAGE LAYOUT FOR BASEMENT 2 (Part-2) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
6 Mechanical SEL-193-SD-P-DETAIL-1 WATER SUPPLY STANDARD DETAIL 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected To be re-submitted
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
7 Mechanical SEL-193-SD-P-BAS.2 WATER SUPPLY LAYOUT FOR BASEMENT 2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
8 Mechanical SEL-193-SD-P-BAS.2.1 WATER SUPPLY LAYOUT FOR BASEMENT 2 (Part-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
9 Mechanical SEL-193-SD-P-BAS.2.2 WATER SUPPLY LAYOUT FOR BASEMENT 2 (Part-2) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
10 Mechanical SEL-193-SD-M-DETAIL-1 HVAC STANDARD DETAIL-1 1st 28-Jul-14 12-Aug-14 5-Sep-14 (24) Delayed Rejected To be re-submitted
11 Mechanical SEL-193-SD-M-DETAIL-2 HVAC STANDARD DETAIL-2 1st 28-Jul-14 12-Aug-14 5-Sep-14 (24) Delayed Rejected To be re-submitted
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
12 Mechanical SEL-193-SD-M-BAS.1 HVAC LAYOUT FOR BASEMENT 2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
13 Mechanical SEL-193-SD-M-BAS.1.1 HVAC LAYOUT FOR BASEMENT 2 (Part-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed Rejected
14 Mechanical SEL-193-SD-M-BAS.1.2 HVAC LAYOUT FOR BASEMENT 2 (Part-12) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved

15 Mechanical PCL-SEL-193-SD-P-PARK WATER SUPPLY LAYOUT FOR SURFACE PARKING 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time Rejected To be re-submitted

16 Mechanical PCL-SEL-193-SD-P-PARK-1.1 WATER SUPPLY LAYOUT FOR SURFACE PARKING (PART-1) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time Rejected To be re-submitted

17 Mechanical PCL-SEL-193-SD-P-PARK-1.2 WATER SUPPLY LAYOUT FOR SURFACE PARKING (PART-2) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time Rejected To be re-submitted

18 Mechanical PCL-SEL-193-SD-D-S.PARKING DRAINAGE LAYOUT FOR SURFACE PARKING 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time Rejected To be re-submitted

19 Mechanical PCL-SEL-193-SD-D-S.PARK.1 DRAINAGE LAYOUT FOR SURFACE PARKING (PART-1) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time Rejected To be re-submitted

20 Mechanical PCL-SEL-193-SD-D-S.PARK.2 DRAINAGE LAYOUT FOR SURFACE PARKING (PART-2) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time Rejected To be re-submitted
1st 25-Aug-14 9-Sep-14 5-Sep-14 4 Delayed Rejected
21 Mechanical PCL-SEL-193-SD-F-BAS.2 FIRE FIGHTING LAYOUT FOR BASEMENT-2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 25-Aug-14 9-Sep-14 5-Sep-14 4 Delayed Rejected
22 Mechanical PCL-SEL-193-SD-F-BAS.2.1 FIRE FIGHTING LAYOUT FOR BASEMENT-2 (PART-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE
1st 25-Aug-14 9-Sep-14 5-Sep-14 4 Delayed Rejected
23 Mechanical PCL-SEL-193-SD-F-BAS.2.2 FIRE FIGHTING LAYOUT FOR BASEMENT-2 (PART-2) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
24 Mechanical PCL-SEL-193-SD-D-LGF DRAINAGE LAYOUT FOR LOWER GROUND FLOOR 1st 10-Nov-14 25-Nov-14 (70) Delayed Pending
25 Mechanical PCL-SEL-193-SD-D-LGF-1.1 DRAINAGE LAYOUT FOR LOWER GROUND FLOOR (PART-1) 1st 10-Nov-14 25-Nov-14 (70) Delayed Pending
Approved with
26 Mechanical PCL-SEL-193-SD-P-LGF WATER SUPPLY LAYOUT FOR LOWER GROUND FLOOR 1st 10-Nov-14 25-Nov-14 21-Jan-15 (57) Delayed
Comments

27 Mechanical PCL-SEL-193-SD-P-LGF-1.1 WATER SUPPLY LAYOUT FOR LOWER GROUND FLOOR (PART-1) 1st 10-Nov-14 25-Nov-14 8-Jan-15 (44) Delayed Approved

28 Mechanical SEL-193-SD-M-BAS.1 HVAC LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

29 Mechanical SEL-193-SD-M-BAS.1.1 HVAC LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

30 Mechanical SEL-193-SD-M-BAS.1.2 HVAC LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

31 Mechanical SEL-193-SD-F-BASE.1 FIRE PROTECTION LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

32 Mechanical SEL-193-SD-F-BASE.1.1 FIRE PROTECTION LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

33 Mechanical SEL-193-SD-F-BASE.1.2 FIRE PROTECTION LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

34 Mechanical SEL-193-SD-D-BAS.1 DRAINAGE LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
35 Mechanical SEL-193-SD-D-BAS.1.1 DRAINAGE LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
36 Mechanical SEL-193-SD-D-BAS.1.2 DRAINAGE LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
37 Mechanical SEL-193-SD-P-BAS.1 WATER SUPPLY LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
38 Mechanical SEL-193-SD-P-BAS.1.1 WATER SUPPLY LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
39 Mechanical SEL-193-SD-P-BAS.1.2 WATER SUPPLY LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
40 Mechanical SEL-193-SD-M-GF HVAC LAYOUT FOR GROUND FLOOR 1st 8-Jan-15 23-Jan-15 (11) Delayed Pending
41 Mechanical SEL-193-SD-M-GF.1 HVAC LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
42 Mechanical SEL-193-SD-M-GF.1.3 HVAC LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 8-Jan-15 23-Jan-15 (11) Delayed Pending
43 Mechanical SEL-193-SD-M-GF.1.4 HVAC LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
44 Mechanical SEL-193-SD-M-GF.1.5 HVAC LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
45 Mechanical SEL-193-SD-D-GF DRAINAGE LAYOUT FOR GROUND FLOOR 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
46 Mechanical SEL-193-SD-D-GF-1.1 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
47 Mechanical SEL-193-SD-D-GF-1.2 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-B & C) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
48 Mechanical SEL-193-SD-D-GF-1.3 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
49 Mechanical SEL-193-SD-D-GF-1.4 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
50 Mechanical SEL-193-SD-P-GF WATER SUPPLY LAYOUT FOR GROUND FLOOR 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
51 Mechanical SEL-193-SD-P-GF-1.1 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
52 Mechanical SEL-193-SD-P-GF-1.2 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-B & C) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
53 Mechanical SEL-193-SD-P-GF-1.3 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
54 Mechanical SEL-193-SD-P-GF-1.4 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
55 Mechanical SEL-193-SD-P-SWT UNDER GROUND STORM WATER TANK 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
56 Mechanical SEL-193-SD-F-GF FIRE FIGHTING LAYOUT FOR GROUND FLOOR 1st 8-Jan-15 23-Jan-15 (11) Delayed Pending
57 Mechanical SEL-193-SD-F-GF-1 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
58 Mechanical SEL-193-SD-F-GF-1.3 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 8-Jan-15 23-Jan-15 (11) Delayed Pending
59 Mechanical SEL-193-SD-F-GF-1.4 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
60 Mechanical SEL-193-SD-F-GF-1.5 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
61 Mechanical SEL-193-SD-M-GF-1.2 HVAC Layout for Ground Floor (Block-B & C) 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
62 Mechanical SEL-193-SD-F-GF-1.2 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-B & C) 1st 24-Dec-14 8-Jan-15 (26) Delayed Pending
63 Mechanical SEL-193-SD- P & F -LGF-1 DOMESTIC WATER & FIRE RESERVE UG TANK 1 & 2 1st 31-Dec-14 15-Jan-15 (19) Delayed Pending
64 Mechanical SEL-193-SD- Slee-LGF LOWER GROUND FLOOR SLEEVE 1st 31-Dec-14 15-Jan-15 8-Jan-15 7 On-Time approved
65 Mechanical SEL-193-SD-P-WB-GF WATER BODY LAYOUT FOR GROUND FLOOR 1st 15-Jan-15 30-Jan-15 (4) Delayed Pending
66 Mechanical SEL-193-SD-P-WB-GF-1.1 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-1) 1st 15-Jan-15 30-Jan-15 (4) Delayed Pending
67 Mechanical SEL-193-SD-P-WB-GF-1.2 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-2) 1st 15-Jan-15 30-Jan-15 (4) Delayed Pending
68 Mechanical SEL-193-SD-P-WB-GF-1.3 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-3) 1st 15-Jan-15 30-Jan-15 (4) Delayed Pending
69 Mechanical SEL-193-SD-P-WB-GF-1.4 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-4) 1st 15-Jan-15 30-Jan-15 (4) Delayed Pending
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE
Returned due to minor
changes "Re-
1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
1 Electrical MEP-E-04-05-01 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-A)
Mechanical Shop
Drawing is required"
2nd 5-Dec-14 20-Dec-14 (45) Delayed Pending
Returned due to minor
changes "Re-
1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
2 Electrical MEP-E-05-05-01 ELECTRICAL SYSTEM 1 LAYOUT FOR GROUND FLOOR (BLOCK- A)
Mechanical Shop
Drawing is required"
2nd 5-Dec-14 20-Dec-14 (45) Delayed Pending
Returned due to minor
changes "Re-
1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
3 Electrical MEP-E-07-05-01 IT & SECURITY LAYOUT FOR GROUND FLOOR (BLOCK- A)
Mechanical Shop
Drawing is required"
2nd 5-Dec-14 20-Dec-14 (45) Delayed Pending
Returned due to minor
changes "Re-
4 Electrical MEP-E-04-05-03 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR GROUND FLOOR (BLOCK- E) 1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
Mechanical Shop
Drawing is required"
Returned due to minor
changes "Re-
5 Electrical MEP-E-05-05-03 ELECTRICAL SYSTEM 1 LAYOUT FOR GROUND FLOOR (BLOCK- E) 1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
Mechanical Shop
Drawing is required"
Returned due to minor
changes "Re-
6 Electrical MEP-E-07-05-03 IT & SECURITY LAYOUT FOR GROUND FLOOR (BLOCK- E) 1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
Mechanical Shop
Drawing is required"
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
required
7 Electrical PCL-MEP-E04-01.01 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
8
required
Electrical PCL-MEP-E04-01.02 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 29-Oct-14 (15) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
9
required
Electrical PCL-MEP-E05-01.01 ELECTRICAL SYSTEM 1 LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
10
required
Electrical PCL-MEP-E05-01.02 ELECTRICAL SYSTEM 1 LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
required
11 Electrical PCL-MEP-E06-01.01 ELECTRICAL SYSTEM 2 LAYOUT FOR BASEMENT-2 (PART-1)
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE
11 Electrical PCL-MEP-E06-01.01 ELECTRICAL SYSTEM 2 LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
12
required
Electrical PCL-MEP-E06-01.02 ELECTRICAL SYSTEM 2 LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
13
required
Electrical PCL-MEP-E07-01.01 IT & SECURITY LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
14
required
Electrical PCL-MEP-E07-01.02 IT & SECURITY LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
Approved with
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed
Comments
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
required
Returned due to minor
15
Electrical PCL-MEP-E06-05.01 ELECTRICAL SYSTEM 2 LAYOUT FOR GROUND FLOOR BLOCK A changes "Re-
2nd 1-Sep-14 16-Sep-14 17-Sep-14 (1) Delayed Returned submission along
Mechanical Shop
Drawing is required"
3rd 5-Dec-14 20-Dec-14 (45) Delayed Pending
Approved with
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed re-submission
required
16 Electrical PCL-MEP-E06-05.03 ELECTRICAL SYSTEM 2 LAYOUT FOR GROUND FLOOR BLOCK E
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE
Returned due to minor
16 Electrical PCL-MEP-E06-05.03 ELECTRICAL SYSTEM 2 LAYOUT FOR GROUND FLOOR BLOCK E
changes "Re-
2nd 1-Sep-14 16-Sep-14 17-Sep-14 (1) Delayed Returned submission along
Mechanical Shop
Drawing is required"
Approved with
1st 9-Jul-14 24-Jul-14 13-Aug-14 (20) Delayed re-submission
17 Electrical PCL-MEP-E10.01 LIGHTNING PROTECTION LAYOUT FOR ROOF required
Approved with
2nd 1-Sep-14 16-Sep-14 18-Sep-14 (2) Delayed
comments
Approved with
1st 9-Jul-14 24-Jul-14 13-Aug-14 (20) Delayed re-submission
18 Electrical PCL-MEP-E10.02 EARTHING SYSTEM LAYOUT required
Approved with
2nd 1-Sep-14 16-Sep-14 18-Sep-14 (2) Delayed
comments
LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR LOWER GROUND FLOOR ( PART
19 Electrical MEP-E-04-04-01 1st 22-Oct-14 6-Nov-14 (89) Delayed Pending
PLAN)
20 Electrical MEP-E-05-04-01 ELECTRICAL SYSTEM 1 LAYOUT FOR LOWER GROUND FLOOR ( PART PLAN ) 1st 22-Oct-14 6-Nov-14 (89) Delayed Pending
21 Electrical MEP-E-06-04-01 ELECTRICAL SYSTEM II LAYOUT FOR LOWER GROUND FLOOR ( PART PLAN ) 1st 22-Oct-14 6-Nov-14 (89) Delayed Pending
22 Electrical MEP-E-07-04-01 IT & SECURITY LAYOUT FOR LOWER GROUND FLOOR ( PART PLAN ) 1st 22-Oct-14 6-Nov-14 (89) Delayed Pending
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
23 Electrical MEP-E-04-02-01 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT - 1 ( PART-I) Approved with
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
24 Electrical MEP-E-04-02-02 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT - 1 ( PART-II ) Approved with
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
25 Electrical MEP-E-05-02-01 ELECTRICAL SYSTEM I LAYOUT FOR BASEMENT 1 ( PART I) Approved with
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
26 Electrical MEP-E-05-02-02 ELECTRICAL SYSTEM I LAYOUT FOR BASEMENT 1 ( PART II) Approved with
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
27 Electrical MEP-E-06-02.01 ELECTRICAL SYSTEM II LAYOUT FOR BASEMENT 1 ( PART I ) Approved with
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
28 Electrical MEP-E-06-02.02 ELECTRICAL SYSTEM II LAYOUT FOR BASEMENT 1 ( PART II ) Approved with
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Comments
CONSULTANT'S
RESPONSE VARIANCE VARIANCE SUBMITTAL
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION REMARKS
RESPONSE ACTUAL (DAYS) STATUS STATUS
DUE RESPONSE
Re-Submission
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
Required
29 Electrical MEP-E-07-02-01 IT & SECURITY LAYOUT FOR BASEMENT 1 ( PART - I ) Re-Submission
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Rejected
Required
3rd 9-Dec-14 24-Dec-14 (41) Delayed Pending
Re-Submission
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
Required
30 Electrical MEP-E-07-02-02 IT & SECURITY LAYOUT FOR BASEMENT 1 ( PART - II) Re-Submission
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Rejected
Required
3rd 9-Dec-14 24-Dec-14 (41) Delayed Pending
31 Electrical MEP-E04-05.04 Lighting & Emergency Lighting Layout for Ground Floor D & F 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
32 Electrical MEP-E05-05.04 Electrical System 1 Layout for Ground Floor D & F 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
33 Electrical MEP-E06-05.04 Electrical System 2 Layout for Ground Floor D & F 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
34 Electrical MEP-E07-05.04 I.T & Security Layout for Ground Floor D & F 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
35 Electrical MEP-E06-09 Electrical System 2 Layout for Kitchen Equipment Ground Floor D & F 1st 5-Dec-14 20-Dec-14 (45) Delayed Pending
36 Electrical MEP-E-04-05-02 Lighting and Emergency Lighting Layout for Ground Floor ( Block - B & C) 1st 31-Dec-14 15-Jan-15 (19) Delayed Pending
37 Electrical MEP-E-05-05-02 Electrical System 1 Layout For Ground Floor ( Block- B and C ) 1st 31-Dec-14 15-Jan-15 (19) Delayed Pending
38 Electrical MEP-E-06-05-02 Electrical System II Layout for Ground Floor ( Block B and C) 1st 31-Dec-14 15-Jan-15 (19) Delayed Pending
39 Electrical MEP-E-07-05-02 IT & Security Layout for Ground Floor ( Block-B and C) 1st 31-Dec-14 15-Jan-15 (19) Delayed Pending
Critical Items
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

ANNEXURE III

Request for Information (RFI) Log

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
MARGALLA BUILDING
RFI SUBMITTAL STATUS FOR CIVIL & MEP
UPDATED January 31, 2015

SUBMISSION RESPONSE RESPONSE


S.NO. S.NO. REF NO. DESCRIPTION DRAWING REFERENCE
DATE RECIEVED DURATION

In Block C (LG) two Columns at grid (EW26/NS61-NS63) falling out from pile
1 Civil 1 18-Oct-14 YES - S-110
cap. Please Advice
Pile Cut Off Level is high in Block E Pile Cap level is higher than S.O.G level At
2 Civil 2 18-Oct-14 YES - S-100, S-101, S-102
grid (EW40/NS16) Pile Cap Ref (PC61)
In Block A pile cap no PC-9 & PC-10 level difference is 1.1m at Grid NS23.
3 Civil 3 18-Oct-14 YES - S-100, S-101, S-103
Please Clarify, As in Beam concrete is not possible in this scenario

Undeground Sedimentaion Tank drawings are not correlating between


4 Civil 4 30-Oct-14 YES - S-400, A1-001
Architectural and Structural Drawings. Please Clarify

Parking Block Lower Basement Ramp Structural Logitudinal Section is


required at Grid (B26-B29/AC09-AC10). In Parking Area Lower Ground Floor
5 Civil 5 in Structural Drawing RCC Wall is not shown on Grid (B26-B29/AC09) while in 8-Nov-14 YES - S-060, A4-501, A3-203
Architectural drawing RCC wall is shown. Please Advice. Require Detail for
water Channels if required in Basement 2, Ramp Starting Point.

In Parking area Ramp when level are calculated from given slope they
6 Civil 6 doesnot match with the level given on architectural drawing. Drawings 12-Nov-14 YES - A4-501
Attached. Please Advice

In Water Body, Pile Resting on a Grid EW17/NS53 found to be dislocated


7 Civil 7 19-Nov-14 YES - S-100
from the planned location by 2.29m, Please advice further course of action.

The Reinforcement Detail for pool Wall along the Grid EW26 at ground floor
is not indicated in section 16/S-162. Reinforcement for the pool wall is not
shown on the section 16/S-161. Please advise if the pool wall section along
S-120, S-161, S-162, S-
8 Civil 8 the Grid EW26 has Similar reinforcement as the wall section in NS44 or 17-Dec-14
163
Otherwise please provide section. Also in 16/S-162 Plese clarify the detail of
space between basement wall and pool wall whether it is woid or fill
material. Please provide level for Corbel beam shown in 16/S-162.

Please Clarify and Confirm,


1)Parking Stair ST-12 Structural Drawing (S-180) & Architural Drawing (A4-
9 Civil 9 301) Levels do not 19-Jan-15 S-180, A3-301
match with each other.
2) Stair Case Landing & Lower Basement foot path finishing detail is required.
Please Clarify and Confirm,
1) Block F Grid NS69 & EW45 Detail of U Shape Concrete Section/Column at
Ground & First
Floor Level is not avialable.
10 Civil 10 19-Jan-15 S-120, S-130
2) Block D Grid NS30-32 & EW37 Column detail of C33 and C9 with U section
at Ground to
Roof Level is not avialable.
Please Clarify and Confirm,
11 Civil 11 1) Please provide Upper Basement Beam, Landing Detail and Layout at Grid 19-Jan-15
B26 Between AC9-AC10
12 Electrical - Proposal for sleeve location through retaining wall in Plant Room at LG. 21-Jan-15
13 Electrical - Proposal for sleeve location in Block F at Ground floor. 8-Jan-15
14 Electrical 12 Requst for clarification of Access control provisions. 21-Jan-15
15 Civil 13 Request for clarification of storm water channel detail 21-Jan-15
16 Civil 14 Request for clarification for basement floor and ramp levels. 21-Jan-15
17 Civil 15 Request for clarification for continuous beam in Block F, Ground Floor 26-Jan-15
Trench Detail from Lower Ground Block - C to Block - F (High lighted in
18 Mechanical 16 27-Jan-15 MEP-M04.04
attached drawing)
The scope of flue piping for Generators dia 18" MS schedule 40. It's shown in
19 Mechanical 17 27-Jan-15 MEP-M04.09.02
drawing however absent from Bill of Quantities (BOQ).
SUBMISSION RESPONSE RESPONSE
S.NO. S.NO. REF NO. DESCRIPTION DRAWING REFERENCE
DATE RECIEVED DURATION

75mm dia pipeline is dropping in sedimentation tank which is not shown in


20 Mechanical 18 27-Jan-15 MEP-P04.11
any plan, please clarify.
The route of 450mm dia pipe line shown in drawing A6-020, Crossing the
21 Mechanical 19 27-Jan-15 A6-020
storm water tank from SMH-15 to trench. Also provide schedule of all SMH
22 Mechanical 20 Drawing TW.01 At the Earliest 27-Jan-15 MEP-P04.10.01
23 Mechanical 21 Chlorine Dioxide Dosing, Water Resource, Piping Location & Pipe Size. 27-Jan-15 MEP-P04.11
The Size of Over flow pipes for Over Head Water Tanks & Under Ground
24 Mechanical 22 27-Jan-15 MEP.P05.01
Water Tanks.
PPR Pipe dia 125mm shown on drawing which is not available in PPR
25 Mechanical 23 material. What pipe material should be used for above 110mm pipe dia. 27-Jan-15
Please Confim
26 Electrical 24 Request for clarification of IT racks, installation details and dimensions. 30-Jan-15 MEP.E06.06.02
CRITICAL ITEM
GENERAL CONTRACTOR’S MONTHLY PROGRESS REPORT | JANUARY 2015

ANNEXURE IV

Resource Deployment Status

Client / Owner | Telenor Pakistan (Pvt.) Ltd. Contractor | Paragon Constructors (Pvt.) Ltd. Annexure I
PLANT & EQUIPMENT DEPLOYMENT STATUS JANUARY 2015
SR.NO. EQUIPMENT/PLANT QTY.
1 Generator(250 KVA) 1
2 Generator(100 KVA) 1
3 Generator(275 KVA) 1
4 Generator(60 KVA) 1
5 Generator(6.5 KVA) 1
6 Tower Crane 2
7 Mobile Crane 1
8 Batching Plant 1
9 Transit Mixer 4
10 Concrete Mobile Pump 1
11 Concrete Stationary Pump 1
12 Vibratory Roller (12 tonne) 1
13 Vibratory Roller (1.5 tonne) 4
14 Loader 2
15 Dumper 4
16 Mini Dumper 1
17 Tractor Trolley 2
18 Bowzer 2
19 Truck 1
20 Vans 2
21 Cars 2
22 Motorcycle 1
23 Plate Compactor 4
24 Air Compressor 1
25 Vibrator Shaft 6
26 Welding Plant 13
27 Power Press 2
28 Power Cutter 1
29 Lathe Machine 1
30 Steel Bending Machine 4
31 Steel Cutting Machine 4
32 Grinder 9" 5
33 Straight Edge 4
34 Dewatering Pump [25,3,3,4 HP] 6
35 Termite Spray Gun 2
36 Hilti Electric Hammer 2
37 Toko Pneumatic Hammer 2
38 Compression Machine (Cylinder Testing) 1
39 Fuel Dispenser 1
40 Auto Level 3
41 Total Station 4
42 Concrete Mixer 1
43 Pneumatic Rammer 2
44 Hand Rammer 3
TOTAL EQUIPMENT 109
HUMAN RESOURCE DEPLOYMENT STATUS - JANUARY 2015
DISCIPLINE PCL CIVIL SUB- PPE SEL TOTAL
CONTRACTOR
CONSTRUCTION MANAGEMENT & TECHNICAL
Project Director 1 1
Deputy General Manager / Project
Manager 1 1 2
Construction Manager / Deputy
Construction Manager (Civil) 4 4
Manager Project Planning & Controls 1 1
Project Coordinator (Mechanical) 1 1
Mechanical Engineer 1 1
Electrical Engineer 2 2
QA/QC Manager 1 1
Laboratory Technician 1 1
Laboratory Helper 3 3
Assistant Planning Engineer 2 2
Manager Contracts 1 1
Quantity Surveyor 2 2
Assistant Quantity Surveyor 1 1
Site Engineer (Civil) 4 4
Site Engineer (Mechanical) 2 2
Site Engineer (Electrical) 1 1
Trainee Engineer (Electrical) 1 1
Supervisor (Electrical) 1 1
Senior Supervisor (Civil) 1 1
Supervisor (Civil) 4 4
Junior Supervisor / Trainee (Civil) 3 3
Senior Surveyor 1 1
Surveyor 3 3
Assistant Surveyor 2 2
Survey Helper 9 9
Senior CAD Draughtsman 1 1
CAD Draughtsman 1 3 1 5
Document Controller 1 1
HSE Incharge 1 1
HSE Officer 1 1
Male Nurse 1 1
Mechanical Manager (Plant &
Equipment) 1 1
Steel Fixing Supervisor 1 1
Total 56 0 7 4 67
ADMINISTRATION
Senior Administration Manager 1 1
Administration Officer 1 1 2
Admin. Assistant 1 1
Procurement Manager 1 1
HUMAN RESOURCE DEPLOYMENT STATUS - JANUARY 2015
DISCIPLINE PCL CIVIL SUB- PPE SEL TOTAL
CONTRACTOR
Procurement Officer 1 1
Store Incharge 1 1
Store Keeper 1 1 1 3
Store Helpers 2 2
Material Checker / Weight Bridge
Operator 2 2
Accounts Manager 1 1
Accounts Officer 1 1 1 3
Internal Auditor 1 1
Assistant IT Engineer 1 1
Data Entry Operator 1 1
Drivers 3 3
Camp Boss 1 1
Cook and Laundry 5 5
Security Guards 8 8
Office support staff 5 5
Site Mess & Canteen Staff 16
Total 38 16 2 3 43
MECHANICAL OPERATORS
Tower Crane Operators 3 3
Rigger & Tower Crane Helpers 6 6
Batching Plant Operator / Assistant 3 3
Transit Mixer Drivers & Helper 8 8
Mobile Crane Operator & Helper 3 3
Mobile Concrete Pump Operator &
Helper 3 3
Loader Operator & Helper 4 4
Vibratory Roller Operator 5 5
Excavator and Dumper Operator 9 9
Tractor Driver 3 3
Mechanical Operators and Helpers 12 12
Generator Operator 2 2
Mechanics 3 3
Electricians 5 5
Lathe Machine Operator 1 1
Welder 6 6 12
Fabricator & Helper 3 7 10
Total 65 27 0 0 92
SITE PRODUCTION
Scaffolding Foreman 2 2
Scaffolders 25 25
Carpentry and General Foreman 3 4 7
Carpenters 9 43 52
Carpentry Helper 4 27 31
Masons 11 2 13
HUMAN RESOURCE DEPLOYMENT STATUS - JANUARY 2015
DISCIPLINE PCL CIVIL SUB- PPE SEL TOTAL
CONTRACTOR
Mason Helpers 3 2 5
Half Mason 2 2
Steel Fixing Foreman 1 3 4
Steel Fixers 4 46 50
Steel Fixing Helper 1 17 18
Stone Cutter 7 7
Water Carrier 6 6
Labour Foreman 3 1 4
General Labour 31 10 41
Concreting Labour 33 33
Housekeeping Foreman 1 1
Housekeeping Labour 10 10
Plumber and Assistants 2 4 6
Plumbing Welder 1 1
Electrician & Helpers 5 5
Total 125 188 5 5 323
TOTAL 284 231 14 12 525