150 mm HIGH KERB

TO BE CONSTRUCTED

SHERRIFF STREET
MATCH EXISTING
R2 - 6A(R) FOOTPATH

R1 - 2A
INSTALL NEW
PRAM RAMPS INSTALL NEW
PRAM RAMPS
150 mm HIGH KERB MATCH EXISTING MATCH EXISTING
TO BE CONSTRUCTED FOOTPATH FOOTPATH

TYPICAL GIVEWAY CONSTRUCT NEW


HOLDING LINE FOOTPATH
INSTALL PEDESTRIAN
WALKTHROUGH REFUGE
ASHLEY STREET INCLUDING TACT TILES

150 mm HIGH KERB REMOVE EXISTING 150 mm HIGH KERB


ROUNDABOUT R1 - 2A
TO BE CONSTRUCTED TO BE CONSTRUCTED

MATCH EXISTING MATCH EXISTING


FOOTPATH FOOTPATH
INSTALL NEW
INSTALL NEW PRAM RAMPS
PRAM RAMPS

R2 - 6A(L)
R1 - 2A
PROJECT OUTCOMES
SHERRIFF STREET

REMOVE ALL EXISTING Improve ease of travel and travel time


SPLITTER ISLANDS AT Improve pedestrian access
INTERSECTION
Reduce short cut traffic to sough of Sherriff Street
MATCH EXISTING Attract and restrict traffic to major collector roads
FOOTPATH
DESIGNER: PROJECT
LB

c
DATE:
TORRENSVILLE & THEBARTON LATM NOV 15
CHECKED:

ASHLEY ST & SHERRIFF ST ES


SHEET:
1 OF 1
City of West Torrens UNDERDALE SCALE:
1:200 (A3) DRAWING No.
REV No: 7695-15-XXX