Professional Documents
Culture Documents
Once printed this specification becomes an uncontrolled copy of the online version.
03.79.42.1110
NS-1™ Number: NS 03.79.42.1110
Revision Date: June 2007
Equipment Name: STUFFING BOX EQUIPMENT
Manufacturer: GENERAL
Model/Type: VARIOUS
Material Group: LOW ALLOY STEEL
Service: NON-SOUR
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 1
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
SCOPE
This COMBINED NS-1™ specification specifies the minimum quality and inspection requirements applied to
wrought Low Alloy Steel Stuffing Box Equipment.
It applies to:
The matrix of this COMBINED NS-1™ provides a quality template that can be applied to any make and type of
Stuffing Box Assembly. This COMBINED NS-1™ specification in combination with the manufacturer’s parts list
(s) and drawing(s) completes the product quality specification.
When ordering spare parts or sub-assemblies, the applicable quality requirements shall be those specified for
the components supplemented by the relevant requirements called out for the complete assembly.
Design verification, approval and other design related parameters are specifically excluded from this COMBINED
NS-1™ specification.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 2
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
SUPPLEMENTARY REQUIREMENTS
The following requirements are supplementary to, and shall be applied in conjunction with, the Quality Sub-
Specifications of this NS-1™:
1. WELDING
No fabrication or repair welding shall be performed.
2. MATERIAL TESTING
(Ref. Sub-Spec. 10.1 & Sub-Spec. 10.4)
3. IMPACT TESTING
(Ref. Sub-Spec. 150.1)
3.1 The Charpy-V notch energy level shall be 41 joules (30 ft lbs) minimum average of three test
specimens at a test temperature of -18°C (0°F). No individual value shall be less than 34 joules (25 ft
lbs).
3.2 Impact testing shall be carried out on a heat basis as described in API Spec. 16A, latest revision.
4. HYDROSTATIC TESTING
(Ref. Sub-Spec. 100.2)
4.1 Each stuffing box assembly shall be hydrostatically tested to the manufacturer’s procedures and
specifications with the following minimum requirements:
a. The test pressure shall be 2 times rated working pressure for equipment ratings below 69 MPa
(10,000 psi).
b. The pressure holding period shall be not less than 15 minutes. Equipment with hydraulic packing
systems (when applicable): The hydraulic system shall be hydrostatically tested at 1.5 times
R.W.P. of the system, with a holding period of no less than five minutes.
d. The timing of the tests shall not start until the test pressure has stabilized, the stuffing box
assembly and its pressure measuring devices have been isolated from the pressure source and all
external body surfaces have been thoroughly dried.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 3
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
MATRIX
Equipment Name: Stuffing Box Equipment
Specification: 03.79.42.1110
Manufacturer: General
Model/Type: Various
Material Group: Low Alloy
Service: Non-Sour
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 4
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 5
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 6
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Complete Assembly
Number Title
10.1 Material Certificates – General
10.2.2 Material Certificates – Assembly Certificate
20.3 Traceability – Serialization Traceability
90.1 Dimensional Inspection – General
100.2 Hydrostatic Testing – General
160.1 Non-Conformity Procedure – General
170.1 Boxing/Packing/Marking – General
180.1.3 Quality Documentation for Non-Welded Products
Notes
1. When applicable; Threaded parts shall be magnetic particle examined in accordance with Sub-Spec 40.6.1.3,
Sub-Spec 40.6.2.3 and Sub-Spec 40.6.3.2 as indicated.
2. Parts designed to take combined loads (e.g. tension & compression): The most stringent quality requirements
based on the "Worst Case" loading condition shall apply. In such cases class code B1,D shall be the default.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 7