ID WBS Task Name Duration Start Finish Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr

uration Start Finish Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 1 PROJECT BHP 425 d Mon 29-07-19 Tue 29-12-20

2 1.1 GENERAL PROJECT OUTLINE 15 d Mon 29-07-19 Thu 15-08-19

3 1.1.1 LoA Received 9d Mon 29-07-19 Wed 07-08-19

4 1.1.2 Contract Signing 2d Wed 07-08-19 Thu 08-08-19

5 1.1.3 Commencement Date 4d Fri 09-08-19 Thu 15-08-19

6 1.2 ENGINEERING - DESIGN 275 d Thu 15-08-19 Thu 16-07-20

7 1.2.1 SCADA System 120 d Wed 21-08-19 Wed 15-01-20

8 1.2.1.1 Topology 5d Wed 21-08-19 Tue 27-08-19 SACHA

9 1.2.1.2 Design Memorandum 5d Wed 28-08-19 Tue 03-09-19 SACHA

10 1.2.1.3 Signa List 10 d Wed 28-08-19 Mon 09-09-19 DEWAN,PELDON

11 1.2.1.4 Bought out items sepecification 20 d Wed 21-08-19 Mon 16-09-19

12 1.2.1.4.1 Specification of UPS 10 d Tue 03-09-19 Mon 16-09-19 DEWAN

13 1.2.1.4.2 Specification of Computers 10 d Wed 21-08-19 Tue 03-09-19 PELDON

14 1.2.1.4.3 Specification of Network System 10 d Wed 21-08-19 Tue 03-09-19 PELDON

15 1.2.1.4.4 Quality Assurance Plan 10 d Tue 03-09-19 Mon 16-09-19 PELDON

16 1.2.1.5 Software Application of SCADA 100 d Mon 16-09-19 Wed 15-01-20

17 1.2.1.5.1 Software Tool box Application of SCADA 100 d Mon 16-09-19 Wed 15-01-20 DEWAN,PELDON

18 1.2.1.5.2 Screen Designing 100 d Mon 16-09-19 Wed 15-01-20 PELDON,DEWAN

19 1.2.2 Protection system 275 d Thu 15-08-19 Thu 16-07-20

20 1.2.2.1 Retrofitting of Unit PRT Eplan Drawings (US) 10 d Thu 15-08-19 Tue 27-08-19 KINLEY

21 1.2.2.2 Retrofitting of Unit PRT Eplan Drawings (LS) 15 d Thu 15-08-19 Tue 03-09-19 SHERUB

22 1.2.2.3 Retrofitting of Bus Bar PRT 11kV Eplan Drawing (LS) 20 d Tue 03-09-19 Thu 26-09-19 SHERUB

23 1.2.2.4 Retrofitting of PRT 66kV line (US to Switchyard) 10 d Wed 28-08-19 Mon 09-09-19 KINLEY

24 1.2.2.5 Unit SLD ( US) 10 d Mon 09-09-19 Fri 20-09-19 KINLEY

25 1.2.2.6 Unit SLD (LS) 10 d Thu 26-09-19 Wed 09-10-19 SHERUB

26 1.2.2.7 220kV Bus Bar Control & PRT Drawing 30 d Wed 22-01-20 Thu 27-02-20 SHERUB

27 1.2.2.8 220kV Semtokha Line Control PRT Drawing 20 d Wed 09-10-19 Mon 04-11-19 SHERUB

28 1.2.2.9 220kV Tsirang Line Control PRT Drawing 20 d Mon 04-11-19 Wed 27-11-19 SHERUB

29 1.2.2.10 11/220kV GT1 Control PRT Drawing 20 d Wed 27-11-19 Mon 23-12-19 SHERUB

30 1.2.2.11 11/220kV GT2 Control PRT Drawing 5d Mon 23-12-19 Fri 27-12-19 SHERUB

31 1.2.2.12 220/66kV ICT Control PRT Drawing 20 d Fri 27-12-19 Tue 21-01-20 SHERUB

32 1.2.2.13 66/11kV DT Control PRT Drawing 20 d Mon 09-09-19 Thu 03-10-19 KINLEY

33 1.2.2.14 66kV Incomer Control PRT Drawing 20 d Thu 03-10-19 Mon 28-10-19 KINLEY

34 1.2.2.15 66kV Line 11 Control PRT Drawing 20 d Mon 28-10-19 Thu 21-11-19 KINLEY

35 1.2.2.16 66kV Line 12 Control PRT Drawing 20 d Thu 21-11-19 Mon 16-12-19 KINLEY

36 1.2.2.17 66kV Bus Section Control PRT Drawing 20 d Mon 16-12-19 Thu 09-01-20 KINLEY

37 1.2.2.18 SLD 220kV 5d Thu 27-02-20 Wed 04-03-20 SHERUB

38 1.2.2.19 SLD 66kV 5d Thu 09-01-20 Wed 15-01-20 KINLEY

39 1.2.2.20 Documents 45 d Wed 04-03-20 Tue 28-04-20

40 1.2.2.20.1 Design Memorandum 15 d Wed 04-03-20 Mon 23-03-20 KINLEY,SHERUB

41 1.2.2.20.2 Quality Assurance Plan 15 d Mon 23-03-20 Thu 09-04-20 SACHA

42 1.2.2.20.3 Spare Part List 15 d Thu 09-04-20 Tue 28-04-20 KINLEY,SHERUB

43 1.2.2.21 Setting Calcuation for PRT 65 d Wed 29-04-20 Thu 16-07-20

44 1.2.2.21.1 Setting Calculations 30 d Wed 29-04-20 Thu 04-06-20 SHERUB,KINLEY

45 1.2.2.21.2 Engineering of Bay Controller 30 d Wed 10-06-20 Thu 16-07-20 KINLEY,SHERUB

46 1.3 SUBMISSION OF DRAWING & DOCUMENTS FOR 130 d Wed 28-08-19 Mon 03-02-20
APPROVAL
47 1.3.1 SCADA Drawings & Documents 2d Mon 09-09-19 Wed 11-09-19

48 1.3.2 Computer System BoM 2d Mon 09-09-19 Wed 11-09-19

49 1.3.3 Retrofitting of Unit PRT Eplan Drawings (US) 2d Wed 28-08-19 Thu 29-08-19

50 1.3.4 Retrofitting of Unit PRT Eplan Drawings (LS) 2d Tue 03-09-19 Thu 05-09-19

51 1.3.5 Retrofitting of Bus Bar PRT 11kV Eplan Drawing (LS) 2d Thu 26-09-19 Mon 30-09-19

52 1.3.6 Retrofitting of PRT 66kV line (US to Switchyard) 2d Mon 09-09-19 Wed 11-09-19

Task Summary External Milestone Inactive Milestone Duration-only Start-only Deadline


Project: PSP_STR
Split Project Summary Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Date: Thu 03-10-1
Milestone External Tasks Inactive Task Manual Task Manual Summary Progress

Page 1
ID WBS Task Name Duration Start Finish Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
53 1.3.7 220kV & 66kV PRT Drawings & Documents 10 d Wed 22-01-20 Mon 03-02-20

54 1.3.8 PRT BoM 10 d Wed 22-01-20 Mon 03-02-20

55 1.4 APPROVAL FROM CUSTOMER 148 d Thu 29-08-19 Thu 27-02-20

56 1.4.1 SCADA Drawings & Documents 20 d Wed 11-09-19 Fri 04-10-19

57 1.4.2 Computer System BoM 20 d Wed 11-09-19 Fri 04-10-19

58 1.4.3 Retrofitting of Unit PRT Eplan Drawings (US) 20 d Thu 29-08-19 Tue 24-09-19

59 1.4.4 Retrofitting of Unit PRT Eplan Drawings (LS) 20 d Thu 05-09-19 Mon 30-09-19

60 1.4.5 Retrofitting of Bus Bar PRT 11kV Eplan Drawing (LS) 20 d Mon 30-09-19 Thu 24-10-19

61 1.4.6 Retrofitting of PRT 66kV line (US to LS) 20 d Wed 11-09-19 Fri 04-10-19

62 1.4.7 220kV & 66kV PRT Drawings & Documents 20 d Mon 03-02-20 Thu 27-02-20

63 1.4.8 PRT BoM 20 d Mon 03-02-20 Thu 27-02-20

64 1.5 PROCUREMENT 205 d Tue 03-09-19 Mon 11-05-20

65 1.5.1 SCADA 120 d Tue 03-09-19 Tue 28-01-20

66 1.5.1.1 Computer system 120 d Tue 03-09-19 Tue 28-01-20

67 1.5.1.1.1 Receipt of Material 120 d Tue 03-09-19 Tue 28-01-20 DEWAN,PELDON

68 1.5.1.2 Network Componenets 120 d Tue 03-09-19 Tue 28-01-20

69 1.5.1.2.1 Receipt of Material 120 d Tue 03-09-19 Tue 28-01-20 DEWAN,PELDON

70 1.5.1.3 UPS System 120 d Tue 03-09-19 Tue 28-01-20

71 1.5.1.3.1 Receipt of Material 120 d Tue 03-09-19 Tue 28-01-20 DEWAN,PELDON

72 1.5.2 Protection System 205 d Tue 03-09-19 Mon 11-05-20

73 1.5.2.1 Unit Protection Relays 70 d Tue 03-09-19 Wed 27-11-19

74 1.5.2.1.1 Receipt of Material 60 d Tue 03-09-19 Thu 14-11-19 KINLEY,SHERUB

75 1.5.2.2 Schneider Protection Relays 120 d Tue 03-09-19 Tue 28-01-20

76 1.5.2.2.1 Receipt of Material 120 d Tue 03-09-19 Tue 28-01-20 KINLEY,SHERUB

77 1.5.2.3 Procurement of Cable 60 d Thu 27-02-20 Mon 11-05-20

78 1.5.2.3.1 Receipt of Material 60 d Thu 27-02-20 Mon 11-05-20 KINLEY,SHERUB

79 1.5.2.4 Rittal Panels 120 d Tue 03-09-19 Tue 28-01-20

80 1.5.2.4.1 Receipt of Panels 120 d Tue 03-09-19 Tue 28-01-20 ARVIND

81 1.6 MANUFACTURING OF PRT CUBICLES 135 d Fri 14-02-20 Wed 29-07-20

82 1.6.1 First Lot 32 d Fri 14-02-20 Wed 25-03-20

83 1.6.1.1 66kV Basochhu line 20 d Fri 14-02-20 Tue 10-03-20

84 1.6.1.2 66kV bus section 20 d Fri 14-02-20 Tue 10-03-20 SURESH

85 1.6.1.3 66/11kV Distribution Trf 20 d Fri 14-02-20 Tue 10-03-20

86 1.6.1.4 Workshop Test 5d Wed 11-03-20 Tue 17-03-20 KINLEY,SHERUB

87 1.6.1.5 Notice for FAT 2d Tue 17-03-20 Thu 19-03-20 SACHA

88 1.6.1.6 FAT 5d Thu 19-03-20 Wed 25-03-20 SACHA

89 1.6.2 Second Lot 115 d Wed 11-03-20 Wed 29-07-20

90 1.6.2.1 66kV Lobasa line 30 d Wed 11-03-20 Thu 16-04-20

91 1.6.2.2 220kV semthoka line 30 d Wed 11-03-20 Thu 16-04-20

92 1.6.2.3 220kV Tsirang Line 30 d Wed 11-03-20 Thu 16-04-20

93 1.6.2.4 GT-1 30 d Thu 16-04-20 Fri 22-05-20

94 1.6.2.5 GT-2 30 d Thu 16-04-20 Fri 22-05-20

95 1.6.2.6 220kV ICT 30 d Thu 16-04-20 Fri 22-05-20

96 1.6.2.7 66kV ICT 20 d Fri 22-05-20 Tue 16-06-20

97 1.6.2.8 220kV Bus Bar 20 d Fri 22-05-20 Tue 16-06-20

98 1.6.2.9 11kV control 20 d Fri 22-05-20 Tue 16-06-20

99 1.6.2.10 Workshop Test 20 d Wed 17-06-20 Fri 10-07-20

100 1.6.2.11 Notice For FAT 5d Fri 10-07-20 Thu 16-07-20

101 1.6.2.12 FAT 10 d Thu 16-07-20 Wed 29-07-20

102 1.7 TRANSPORT & LOGISTICS 133 d Thu 12-03-20 Mon 24-08-20

103 1.7.1 First Lot 15 d Thu 12-03-20 Tue 31-03-20

104 1.7.1.1 Packing Preperation 5d Thu 12-03-20 Thu 19-03-20

Task Summary External Milestone Inactive Milestone Duration-only Start-only Deadline


Project: PSP_STR
Split Project Summary Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Date: Thu 03-10-1
Milestone External Tasks Inactive Task Manual Task Manual Summary Progress

Page 2
ID WBS Task Name Duration Start Finish Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
105 1.7.1.2 Panels 5d Wed 25-03-20 Tue 31-03-20 SURESH

106 1.7.2 Second Lot 25 d Thu 23-07-20 Mon 24-08-20

107 1.7.2.1 Packing Preperation 10 d Thu 23-07-20 Tue 04-08-20

108 1.7.2.2 Panels 10 d Wed 05-08-20 Mon 17-08-20

109 1.7.2.3 Computer System 5d Mon 17-08-20 Mon 24-08-20 SURESH

110 1.7.2.4 Optical Cable and Accessories 5d Mon 17-08-20 Mon 24-08-20 SURESH

111 1.7.2.5 Cables 5d Mon 17-08-20 Mon 24-08-20 SURESH

112 1.8 INSTALLATION AT SITE 270 d Tue 28-01-20 Wed 23-12-20

113 1.8.1 SCADA 41 d Tue 25-08-20 Tue 13-10-20

114 1.8.1.1 Arrival at Site ( second Lot) 5d Tue 25-08-20 Mon 31-08-20

115 1.8.1.2 Placing of Computer System 5d Wed 30-09-20 Tue 06-10-20

116 1.8.1.3 Installation of UPS 6d Tue 06-10-20 Tue 13-10-20

117 1.8.2 PRT System 270 d Tue 28-01-20 Wed 23-12-20

118 1.8.2.1 Retrofitting of Unit PRT (LS) &11kV Bus Bar 15 d Thu 12-03-20 Tue 31-03-20

119 1.8.2.2 Retrofitting of Unit PRT (US) 11 d Tue 28-01-20 Mon 10-02-20

120 1.8.2.3 Installation of PRT 217.71 d Wed 01-04-20 Wed 23-12-20

121 1.8.2.3.1 Retrofitting of PRT 66kV line (US to LS) 5d Wed 01-04-20 Tue 07-04-20

122 1.8.2.3.2 66kV Basaochhu Line 5d Mon 13-04-20 Mon 20-04-20

123 1.8.2.3.3 66kV bus Section 5d Fri 24-04-20 Thu 30-04-20

124 1.8.2.3.4 66/11kV Distribution Trf 5d Thu 07-05-20 Wed 13-05-20

125 1.8.2.3.5 66kV lobesa line 4d Thu 01-10-20 Tue 06-10-20

126 1.8.2.3.6 220kV semthoka line 4d Mon 12-10-20 Thu 15-10-20

127 1.8.2.3.7 220kV Tsirang line 4d Wed 21-10-20 Mon 26-10-20

128 1.8.2.3.8 GT-1 4d Fri 30-10-20 Wed 04-11-20

129 1.8.2.3.9 GT-2 4d Tue 10-11-20 Fri 13-11-20

130 1.8.2.3.10 220kV ICT 4d Thu 19-11-20 Tue 24-11-20

131 1.8.2.3.11 66kV ICT 4d Mon 30-11-20 Thu 03-12-20

132 1.8.2.3.12 220kV bus bar 4d Wed 09-12-20 Mon 14-12-20

133 1.8.2.3.13 11kV control 4d Fri 18-12-20 Wed 23-12-20

134 1.9 COMMISSIONING 228.43 d Wed 25-03-20 Tue 29-12-20

135 1.9.1 Commissionig of SCADA 23.71 d Fri 25-09-20 Fri 23-10-20

136 1.9.1.1 Notice for Commissioning 5d Fri 25-09-20 Thu 01-10-20

137 1.9.1.2 Commissiong Test 5d Tue 06-10-20 Tue 13-10-20

138 1.9.1.3 Commissiong of Computer System 10 d Tue 13-10-20 Fri 23-10-20

139 1.9.2 Commission of PRT 228.43 d Wed 25-03-20 Tue 29-12-20

140 1.9.2.1 Notice for Commissioning 5d Wed 25-03-20 Tue 31-03-20

141 1.9.2.2 Retrofitting of PRT 66kV line (US to LS) 5d Tue 07-04-20 Mon 13-04-20

142 1.9.2.3 66kV Basaochhu Line 5d Mon 20-04-20 Fri 24-04-20

143 1.9.2.4 66kV bus Section 5d Fri 01-05-20 Thu 07-05-20

144 1.9.2.5 66/11kV Distribution Trf 5d Wed 13-05-20 Wed 20-05-20

145 1.9.2.6 66kV lobesa line 5d Tue 06-10-20 Mon 12-10-20

146 1.9.2.7 220kV semthoka line 5d Thu 15-10-20 Wed 21-10-20

147 1.9.2.8 220kV Tsirang line 5d Mon 26-10-20 Fri 30-10-20

148 1.9.2.9 GT-1 5d Wed 04-11-20 Tue 10-11-20

149 1.9.2.10 GT-2 5d Fri 13-11-20 Thu 19-11-20

150 1.9.2.11 220kV ICT 5d Tue 24-11-20 Mon 30-11-20

151 1.9.2.12 66kV ICT 5d Thu 03-12-20 Wed 09-12-20

152 1.9.2.13 220kV bus bar 5d Mon 14-12-20 Fri 18-12-20

153 1.9.2.14 11kV control 5d Wed 23-12-20 Tue 29-12-20

Task Summary External Milestone Inactive Milestone Duration-only Start-only Deadline


Project: PSP_STR
Split Project Summary Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Date: Thu 03-10-1
Milestone External Tasks Inactive Task Manual Task Manual Summary Progress