Professional Documents
Culture Documents
Concrete Canvas comes in rolls 1.0m or 1.1m wide. absorbs energy from impacts.
Available lengths are 4.5m (weighing 60kg) or 200m
(weighing over 1.5t). Rolls come in three thicknesses:
5mm, 8mm and 13mm.
Materials quantity
Concrete Canvas can replace up to 100mm of
reinforced in-situ concrete in ditch lining
applications.
An 8mm thick roll is sufficient for many erosion
and ditch lining applications.
Materials wastage
Off-cuts do not generally occur. Unused lengths
can be left on the roll for the next project.
No perishable formwork or additional
reinforcement is needed.
M4 interceptor drain lining: M4, Wiltshire, UK
Embodied carbon
Using an 8mm roll of Concrete Canvas can reduce Concrete slabs with sand and cement was
embodied carbon by up to 95% compared with considered. The material cost of concrete slabs
conventional concrete solutions. was lower; however, Concrete Canvas was overall
more cost effective due to the reduction in
Water use construction time and labour costs.
Less water is needed to hydrate Concrete Canvas Three workers laid 20 metres (100m2) each day.
than is contained within in-situ concrete. Cascades were created by laying the fabric over
Loses only 3% by mass under water (specialist concrete bagwork.
underwater concretes typically lose 10-15%). The interceptor drains were completed in
November 2010 and there has been no need for
Life span (e.g. durability)
maintenance since. (Pipes would likely have
Life expectancy of over 50 years.
required periodic maintenance to clear blockages.)
More easily deconstructed than insitu or precast
concrete.
Sections of fabric can be cut, un-pegged, and
Bedwas coal mine ditch lining
lifted out of the channel.
Project type: Ditch lining at a disused spoil tip
Location: Wales
M4 interceptor drain lining Client: Caerphilly Council
Construction: Concrete Canvas laid longitudinally
Project type: Interceptor drain lining
with cascades Caerphilly Council needed a solution to create 2000
Location: Wiltshire linear metres of temporary ditches to prevent erosion
Client: Highways Agency of the coal mine spoil tip. The solution had to be:
Contractor: Enterprisemouchel
easy to transport to the top of the mountain;
Engineer: R&W Civil Engineering
Construction: Concrete Canvas laid transversely watertight;
resistant to vandalism;
Enterprisemouchel needed to clear and repair an quick and easy to install; and
interceptor drain adjacent to the M4. A key project
very cost effective.
requirement was to introduce a series of cascades to
reduce the water flow rate. Originally a series of pipes
The cost of using Concrete Canvas was compared to
and headwalls was considered, but concerns over pipe
the cost of conventional concrete methods.
blockages prompted the team to consider alternatives.
Conventional methods (e.g. insitu concrete) were
estimated to cost £200 /m2 including labour. Concrete
Canvas cost £50 /m2 including labour.
The Environment Agency needed to divert the course
of a stream that flowed through a quarry, to prevent
heavy metal contaminants reaching a river. Concrete
Canvas was used to create 200m of ditch to carry the
contaminated water to a clay bed filtering site. The
fabric was laid in longitudinal strips with overlaps.
While we have tried to make sure this case study is accurate, we cannot accept responsibility or be held legally responsible for any loss or damage
arising out of or in connection with this information being inaccurate, incomplete or misleading. This material is copyrighted. You can copy it free
of charge as long as the material is accurate and not used in a misleading context. You must identify the source of the material and acknowledge
our copyright. You must not use material to endorse or suggest we have endorsed a commercial product or service. For more details please see
our terms and conditions on our website at www.wrap.org.uk
www.wrap.org.uk/construction