Professional Documents
Culture Documents
The Grid tie Solar Power Plants without battery may be installed for any office
buildings. As the office buildings have day time energy consumption, Solar System
without battery is suggested, as the battery is the weak link in the system and
requires regular maintenance as well as replacement in every 2-3 years. Also the
efficiency of the battery based system is less due to loss in the battery (around 15%).
The shadow free area required for installation of solar plant is appx 150 sq.feet
(14 Sq.m) per KW. The Solar panels may be installed on the roof of the building.
Sufficient area shall be available for servicing the system. The minimum clearance
required from the parapet wall & in between row of panels is min 2 feet for cleaning
the panels & servicing. In between the row of solar panels sufficient gap need to be
provided to avoid falling of shadow of previous row on the next row.
The Inverter /Power Conditioning Unit (PCU) shall be placed indoor in a safe and
easily accessible place.
The bench mark cost fixed by Ministry of New and Renewable Energy (MNRE) for
Solar Power Plants without battery is as below:
MNRE provides 30% of the benchmark cost (or) 30% of actual cost whichever is less
as capital subsidy for a maximum capacity of 100KWp per system.
The details on how to decide the capacity of the solar system required for a
particular building is enclosed as Annexure -I
The Capacity of the Solar Power Plant (Wp) ie., Wattage of the SPV array,
required for a particular building, may be calculated in following 3 steps. The
minimum of the 3 values may be taken as the capacity of plant.
Step I:
Capacity of Solar Plant (Wp) = 50% of the connected load of the building
For example:
Step II:
Capacity of Solar Plant (Wp) may be such that it generates 25% of the energy
requirement of connected loads in the building in a day.
For example
1 KWp Solar Plant generates approximately 4 -4.5 units a day. Hence 2 KWp
(Value II) plant may be installed.
Step III:
Capacity of Solar Plant (Wp) may be such that, the maximum energy generated
by the plant in an hour is 50% of the energy consumption of the building in an hour.
Energy consumption during 10 am to 3 pm (good sunshine period) may be taken for
this calculation.
1 2 3 4 5
Date Energy meter Energy meter Difference Average consumption
Reading @ 10.00 Hrs Reading @ 15.00 (3-2) in an hour in Units
Hrs (4/(15 Hrs- 10 Hrs))
10.03.13 7456 7466 10 10/5 = 2
Hence 1 KWp (Value III) solar plant which generates maximum 1 Unit in an hour
may be installed.
The minimum among the 3 values is 1 KW. Hence 1 KW SPV array may be selected.
The PCU / Inverter capacity, mentioned in KVA, shall be equal to SPV array
capacity. Eg., 1 KWp PV array shall have PCU of 1 KVA capacity & 5 KWp PV
array shall have PCU of 5 KVA capacity.
ANNEXURE-IIA
DEFINITION
A Grid Tie Solar Photo Voltaic (SPV) power plant consists of SPV array,
Module Mounting Structure, Power Conditioning Unit (PCU) consisting
Maximum Power Point Tracker (MPPT), Inverter, Controls & Protections,
interconnect cables and switches. PV Array is mounted on a suitable
structure. Grid tie SPV system is without battery and should be designed with
necessary features to supplement the grid power during day time.
Components and parts used in the SPV power plants including the PV
modules, metallic structures, cables, junction box, switches, PCUs etc.,
should conform to the BIS or IEC or international specifications, wherever
such specifications are available and applicable.
____V (to be selected based on capacity of the plant). The power output
of the PV module must be reported under standard test conditions
(STC). I_V curve of the sample module should be submitted.
(ii) The mechanical structure shall withstand gusts of wind / cyclonic wind
up to 150km/hr from back side of the panel.
(iii) The offered modules must conform to the latest edition of any of the
(v) PV modules must also qualify Salt Mist Corrosion Testing as per IEC
61701/IS61701.
(viii) Module Junction box (weather proof), where the module terminals shall
be interconnected and output taken, shall be designed for long life out
door operation in harsh environment as per the relevant BIS
specifications and protected against surges. It should have a provision
for “Opening” for replacing the cable, if required.
(ix) PV modules used in solar power plants must be warranted for output
wattage, which should not be less than 90% at the end of 10 years and
80% at the end of 25 years.
(x) Each PV module must use a RF identification tag (RFID), which must
contain the following information:
a. Name of the manufacturer of PV Module
b. Name of the manufacturer of Solar cells
c. Unique Serial Number & Model No. of the module
d. Month and year of the manufacture (separately for Solar cells and
module)
e. Country of origin ( separately for solar cells and module)
f. I-V curve for the module
g. Peak Wattage of the module ,Im, Vm and FF for the module
h. Date and year of obtaining IEC PV module qualification certificate
i. Name of the test lab issuing IEC certificate
j. Other relevant information on traceability of solar cells and
module as per ISO 9000 series
RFID shall be mandatorily placed inside the module laminate.
A distinctive serial number starting with NSM will be engraved on the frame of
the module or screen printed on the tedlar sheet of the module.
Modules shall be North –South oriented at the Tilt Angle of 11o -13o
2. MOUNTING STRUCTURES
The PV modules will be mounted on fixed metallic structures of adequate
strength and appropriate design, which can withstand load of modules and
high wind velocities up to 150 km per hour. The support structure used in the
power plants will be hot dip Galvanized Iron (G.I).
• The minimum clearance of the lowest part of the module structure and
the developed ground level shall not be less than 500 mm.
• The minimum clearance required from the parapet wall of the roof & in
between row of panels is min 2 feet for cleaning the panels & servicing.
• The bidder shall specify installation details of the PV modules and the
support structures with appropriate diagrams and drawings. The work
shall be carried out as per the designs approved by the procuring entity.
4. JUNCTION BOXES
The junction boxes shall be dust proof, vermin and waterproof and made
of FRP / Thermo Plastic. The terminals shall be connected to copper bus
bar arrangement of proper sizes. The junction boxes shall have suitable
cable entry points fitted with cable glands of appropriate sizes for both
incoming and outgoing cables. Suitable markings shall be provided on the
bus bar for easy identification and cable ferrules shall be fitted at the
cable termination points for identification. Each main junction box shall
be fitted with appropriate rating blocking diode. The junction boxes shall
be of reputed make.
(PCU)”. In addition, the PCU shall also house MPPT (Maximum Power
Point Tracker), an interface between Solar PV array & the Inverter, to
maximize Solar PV array energy input into the System. PCU including
DETAILED SPECIFICATION
4)
Switching device MOSFET/IGBT based
Total Harmonic
< 3% with resistive load
7) Distortion
9)
Output Frequency 50 Hz. ± 0.5 Hz.
10) Power Factor > 0.9
Operating
16) temperature 0 – 50 0C
17) Relative Humidity 95% Maximum
20) Protections
4) Under/over output
3) Short circuit
voltage
a. DC SIDE
Lightning: The SPV power plants shall be provided with lightning &over
voltage protection. The main aim in this protection shall be to reduce the
over voltage to a tolerable value before it reaches the PV or other sub
system components. The source of over voltage can be lightning,
atmosphere disturbances etc
existence for at least past one audited ii. Copy of consortium agreement
year. shall be submitted (OR) A letter of
intent to execute a consortium
agreement in the event of a
successful bid shall be signed by
all the partners and submitted
with the bid along with the copy of
proposed Consortium Agreement .
4. PV Modules & PCU of the SPV system Copy of test certificates along with
shall conform to the MNRE standards as reports shall be submitted.
per clause ___
5. Bidder should not be blacklisted by any Necessary Undertaking letter should
of the State or Central Government or be furnished.
organizations of the State or Central
Government as on date of submission of
tender
Turnover in PV Field in the last financial year - Min. Min. Min. Min.
(OR in the current financial year) Rs.25 Rs.1 Rs.5 Rs.10
L Cr. Cr. Cr.
1. PV MODULES:
1.2 In addition, the modules must conform to IEC 61730 Part 1-requirements
for construction & Part 2 - requirements for testing, for safety
qualification or Equivalent IS (Under Dev.)
1.6 WARRANTY
PV modules used in solar power plants/ systems must be warranted for their output
peak watt capacity, which should not be less than 90% at the end of 10 years and 80%
at the end of 25 years.
2.1The BOS items / components of the SPV power plants/ systems deployed under
the Mission must conform to the latest edition of IEC/ E quivalent BIS
Standards/ MNRE specifications / as specified below:
Capacity Test
Self-Discharge
Cables General Test and Measuring IEC 60227 / IS 694
Method PVC insulated cables
for working voltage up to and IEC 60502 / IS 1554 (Pt. I & II)
including 1100 V and UV
resistant for outdoor installation
**In case if the Charge controller is in-built in the inverter, no separate IEC 62093 test is required and
must additionally conform to the relevant national/international Electrical Safety Standards wherever
applicable
Test certificates / reports for the BoS items/ components can be from any of the
NABL/ IEC Accredited Testing Laboratories or MNRE approved test centers.
2.3 WARRANTY
The mechanical structures, electrical works including
power conditioners/inverters/charge controllers/ maximum power point
tracker units/distribution boards/digital meters/ switchgear/ storage batteries,
etc. and overall workmanship of the SPV power plants/ systems must be
warranted against any manufacturing/ design/ installation defects for a minimum
period of 5 years.
Accredited Test centers for MNRE Off-Grid Programme
Lighting Systems Inverter
Charge Controller
>100 W
Lab/
Organizat PV Module as per Battery
MNRE Environment
ion Efficiency Environmental protections Environmental
Specificatio al
ns
Yes Yes Yes
Yes Yes (Including
(IEC61215up MNRE Yes (upto Yes (Including IP) Yes
(Including IP) IP) MNRE
SEC to100WP) Accredited MNRE MNRE 10KVA) MNRE Accredited MNRE Accredited
NABL Accredited MNRE Accredited
Accredited
Accredited Accredited
STC Test Yes Yes Yes Yes
Yes NABL/ Yes NABL/
ERTL Facility NABL/ NABL/ Yes NABL/ NABL/
MNRE MNRE
(east) MNRE MNRE MNRE Up to 1000AH MNRE MNRE
Accredited Accredited
Accredited Accredited Accredited Accredited Accredited
Yes Yes NABL/
Yes
(IEC61215)u MNRE
(up to
nder ICEEE- Accredited Yes Yes
3KVA) Yes NABL/ Yes NABL/
ETDC CB, NABL/ Yes NABL/
MNRE MNRE
(B) IEC 61701 MNRE Up to 100 AH MNRE
NABL/ Accredited Accredited
(upto100WP) Accredited MNRE Accredited
NABL
Accredited
Accredited
Yes Yes
NABL/ (up to
Yes Yes
MNRE 10KVA) Yes NABL/ Yes NABL/
CPRI NABL/ Yes NABL/
No Accredited MNRE MNRE
(B) MNRE Up to 500 AH MNRE
NABL/ Accredited Accredited
Accredited Accredited
MNRE
Accredited
Only Yes Yes
Yes NABL Yes NABL Yes NABL
Electronics (up to (up to
ERTL (N) No Accredited No Accredited Accredited
& luminaire 5KVA) 5KW)
NABL
Accredited NABL NABL
Accredited Accredited
Yes
(IEC61215 Yes Yes
Yes
IEC 61730 (up to (up to
(except Yes NABL Yes NABL Yes NABL
Pt.II and IEC 6KVA) 6KW)
UL (B) battery) Accredited No Accredited Accredited
61701)
NABL
upto400WP Accredited NABL NABL
NABL Accredited Accredited
Accredited
Yes Yes
Yes
(IEC61215 & (up to
Yes NABL Yes NABL (up to Yes NABL
TUV 61730 Pt-II) 10KVA)
NO Accredited No Accredited 10KW) Accredited
Rhineland upto400WP NABL
NABL NABL
Accredited
Accredited Accredited
Yes Yes
Only
(up to (up to
Electronics Yes NABL Yes NABL Yes NABL
5KVA) 5KW)
Inter Tek No & luminaire Accredited No Accredited Accredited
NABL
NABL NABL
Accredited
Accredited Accredited
PDF to Word