You are on page 1of 1

QUOTATION PLANK SLAB

Quotation: No. 025/2019


Date : 26-Apr-19

To : Keo Morokot Construction Co., Ltd


Att : Mr. Yon Shogun

Site : Toul Tompung, Phnom Penh Tel: 010 503 000 Email:
Project : Shop 017 503 000
Thank you for your interested in our pre-cast concrete slab. We are pleased to quote special price for your project as follow:

CPAC PLANK
Flooring Expert: 1st+2nd+ Roof Floor
Thank you for your interested in our CPAC Pre-cast concrete slab. We are pleased to quote special price for your project as follow:
Description Precast Plank SlabSlab with 240cylinder of
Topping Concrete and RB6@150 or wire mesh # 5mm@150 Quantity Price ( US$ /m2 )
No. Laod per m2 ( REMARK
2
Length P.C wire Thickness(mm) width
kg/m )
2
SDL for soil Live m nømm Precast Topping m Pcs m Product only Amount USD
1 150 250 L≤ 3.50 4ø4 50 60 0.35 152.76 $ 11.50 1,756.74

2 Wiremesh (#4mm@200, 2mx6m) 15 176.76 $ 1.40 247.46 1st Floor


3 Transport wiremesh (#4mm@200, 2mx6m) 15 176.76 $ 30.00 30.00

4 Install , quantity>300m2/time (Case: Install by Crane truck) Total 152.76 $ 2.00 305.52

4 Install , quantity>300m2/time (Case: Install by motor machine) Total 152.76 $ 3.50 534.66 Rate Only
5 Transport with Crane Truck 18.33 ton = 152.76 $ 2.00 305.52

Total Amount 1st Floor (m 2 ) : 152.76

Total Amount 1st Floor Include Transport (Case: Install by Truck) (USD) : 2,645.24

Total Amount 1st Floor Include Transport (Case: Install by Motor machine) (USD) : 2,874.38

6 150 250 L≤ 3.50 4ø4 50 60 0.35 166.07 $ 11.50 1,909.81

7 Wiremesh (#4mm@200, 2mx6m) 16 190.07 $ 1.40 266.10 2nd Floor


8 Transport wiremesh (#4mm@200, 2mx6m) 16 190.07 $ 30.00 30.00

9 Install , quantity>300m2/time (Case: Install by Crane truck) Total 166.07 $ 2.00 332.14

10 Install , quantity>300m2/time (Case: Install by motor machine) 166.07 $ 3.50 581.25 Rate Only
11 Transport with Crane Truck 19.93 ton = 166.07 $ 2.00 332.14

Total Amount 2nd Floor (m 2 ) : 166.07


Total Amount 1st Floor Include Transport (Case: Install by Truck) (USD) : 2,870.18

Total Amount 1st Floor Include Transport (Case: Install by Motor machine) (USD) : 3,119.29

12 150 250 L ≤ 3.50 4ø4 50 70 0.35 169.50 $ 11.50 1,949.25


13 Wiremesh (#4mm@200, 2mx6m) 16 193.50 $ 1.40 270.90 Roof Floor
14 Transport wiremesh (#4mm@200, 2mx6m) 16 193.50 $ 30.00 30.00
15 Install , quantity>300m2/time (Case: Install by Crane truck) Total 169.50 $ 2.00 339.00
16 Install , quantity>300m2/time (Case: Install by motor machine) Total 169.50 $ 3.50 593.25 Rate Only
17 Transport with Crane Truck 20.34 ton = 169.50 $ 2.00 339.00

Total Amount Roof Floor (m 2 ) : 169.50

Total Amount 1st Floor Include Transport (Case: Install by Truck) (USD) : 2,928.15

Total Amount 1st Floor Include Transport (Case: Install by Motor machine) (USD) : 3,182.40

Total Amount All Floor (m2) : 488.33


Total Amount All Floor Include (Products+Transport+Install by Crane
8,443.58
truck+Wiremesh) (USD) :
Total Amount All Floor Include (Products+Transport+Install by motor
9,176.07
machine+Wiremesh) (USD) :
Total Amount Deposit on 30% (USD) : 2,752.82
Remark:

1 The above price is not Included Vat 10%


2 The above price is not Included Concrete Topping
3 Project has to prepare the enough strong road and space area for truck and Crain to install
4 Project has to complete beam and middle support before install Precast slab and has to weld
5 The buyer will pay deposit on 30% on the order date to start Producing
6 The above price is valid to: 30 May 2019
7 For more information please contact us at Mr. Saing Poheng Tel: ,016 948 999, Email : saingpoheng@yahoo.com
8 Please inform the request delivery schedule to us in advance at lease 10 days
9 Remark: All payments should be made to CPAC Cambodia Co., Ltd

Yours Sincerely, We accept the above Quoted Price and all conditions

Mr. SAING Poheng ,Marketing Manager