You are on page 1of 14

Noell Whessoe, Inc. v. Independent Testing (Stephenson).

However, it averred that it later


Consultants, Inc., G.R. No. 199851, received a letter from Noell Whessoe
November 7, 2018 ( Art. 1729) withdrawing its approval for Independent
Testing Consultants' continued services.
Facts:
Independent Testing Consultants' services
Independent Testing Consultants is engaged in allegedly failed to satisfy the standards set by
the business of conducting non-destructive the OIS and Stephenson. Petrotech further
testing on the gas pipes and vessels of its claimed that due to Independent Testing
industrial customers. Consultants' poor performance, it incurred
additional costs. Thus, it prayed that
Sometime in June 1998, Petrotech, a Independent Testing Consultants be ordered to
subcontractor of Liquigaz, engaged the services pay the additional costs as actual damages.
of Independent Testing Consultants to conduct
non-destructive testing on Liquigaz's piping Issue: WON petitioner is solidarily liable with
systems and liquefied petroleum gas storage Liquigaz and Petrotech.
tanks located in Barangay Alas-Asin, Mariveles,
Ruling:
Bataan. Independent Testing Consultants
conducted the agreed tests. It later billed No. Under Article 1729, respondent Independent
Petrotech, on separate invoices, the amounts of Testing Consultants had a cause of action
P474,617.22 and P588,848.48 for its services. against Liquigaz and petitioner, even if its
However, despite demand, Petrotech refused to contract was only with Petrotech. The Regional
pay. Independent Testing Consultants filed a Trial Court and the Court of Appeals, therefore,
Complaint for collection of sum of money with did not err in concluding that petitioner was
damages against Petrotech, Liquigaz, and Noell solidarily liable with Liquigaz and Petrotech for
Whessoe for P1,063,465.70 plus legal interest. It unpaid fees to respondent Independent Testing
joined Noell Whessoe as a defendant, alleging Consultants. Article 1729 creates a solidary
that it was Liquigaz's contractor that liability between the owner, the contractor, and
subcontracted Petrotech the subcontractor. A solidary obligation is "one
in which each debtor is liable for the entire
In its Answer,Liquigaz argued that Independent
obligation, and each creditor is entitled to
Testing Consultants had no cause of action
demand the whole obligation."[84] Respondent
against it since there were no contractual
Independent Testing Consultants may demand
relations between them and that any contract that
payment for all of its unpaid fees from Liquigaz,
Independent Testing Consultants had was with
petitioner, or Petrotech, even if its contract was
its subcontractors.Noell Whessoe, on the other
only with the latter. However, Article 1729,
hand, denied that it was Liquigaz's contractor
while serving as an exception to the general rule
and that its basic role was merely to supervise
on the privity of contracts, likewise provides for
the construction of its gas plants. It argued that
an exception to this exception. The contractor is
any privity of contract was only with Petrotech.
solidarily liable with the owner and
Thus, it asserted that Petrotech alone should be
subcontractor for any liabilities against a
liable to Independent Testing Consultants... or
supplier despite the absence of contract between
its part, Petrotech alleged that upon Noell
the contractor and the supplier, except when the
Whessoe's approval, Independent Testing
subcontractor has already been fully paid for its
Consultants was chosen to conduct the non-
services. Here, the Court of Appeals found that
destructive testing on Liquigaz's liquefied
there was "uncontroverted evidence that
petroleum gas storage vessel under the
PETROTECH had already been paid for its
supervision of OIS, an inspection firm from the
services
United Kingdom, and of Nick Stephenson
Since Whessoe UK and petitioner should be P45,570,237.90. The Construction Agreement
considered the same entity for the purposes of covered all materials, labor, equipment, and
the Mariveles Terminal Expansion Project, tools, including any other works required. The
Whessoe UK's full payment to Petrotech would project was to be completed within 150 calendar
serve as a valid defense against petitioner's days or by October 10, 1995, to be reckoned
solidary liability. Thus, petitioner still cannot be from Andrada Construction’s posting of a
held solidarily liable with Liquigaz and Performance Bond to answer for liquidated
Petrotech for any remaining receivables from damages, costs to complete the project, and third
respondent Independent Testing Consultants. party claims. The Performance Bond was issued
Any remaining obligations to it should be by Intra Strata Assurance Corporation (Intra
solidarily borne by the owner, Liquigaz, and the Strata).On May 10, 1995, Metro Bottled Water
subcontractor, Petrotech. extended the period of completion to November
30, 1995 upon Andrada Construction’s request,
Q: Sometime in June 1998, Ulysses Corp, a
due to the movement of one (1) bay of the plant
subcontractor engaged the services of Rolly
building, weather conditions, and change
Brothers Co. to conduct non-destructive testing
orders.On November 14, 1995, E.S. De Castro
on Quinta Corp’s piping systems and liquefied
and Associates, Metro Bottled Water’s
petroleum gas storage tanks located in Barangay
consultant for the project, recommended the
Alas-Asin, Mariveles, Bataan. Rolly Corp forfeiture of the Performance Bond to answer for
conducted the agreed tests. It later billed the completion and correction of the project, as
Ulysses Corp, on separate invoices, the amounts well as liquidated damages for delay.On May 2,
of P474,617.22 and P588,848.48 for its services. 1996, Metro Bottled Water filed a claim against
However, despite demand, Ulysses Corp the Performance Bond issued by Intra Strata.
refused to pay. WON Rolly and Ulysses Corp are Andrada Construction opposed the claim for
liable against Quinta Corp. lack of legal and factual basis.On September 6,
1996, Andrada Construction wrote to Metro
ANS: Article 1729 creates a solidary liability Bottled Water contesting E.S. De Castro and
between the owner, the contractor, and the Associates’ Special Report. The works
subcontractor. A solidary obligation is "one in performed by Andrada Construction were
which each debtor is liable for the entire inspected by Metro Bottled Water and E.S. De
obligation, and each creditor is entitled to Castro and Associates. Punch lists were
demand the whole obligation." Rolly Corp may prepared to monitor Andrada Construction’s
demand payment for all of its unpaid fees from rectifications.[ Andrada Construction sent letters
Ulysses, or Rolly Corp, even if its contract was to Metro Bottled Water requesting for payment
only with the latter. of unpaid work accomplishments amounting to
P7,292,721.27. Metro Bottled Water refused to
pay.On August 6, 2001, Andrada Construction
2. Metro Bottled Water Corp. v. Andrada filed a Request for Arbitration before the
Construction & Development Corp., Inc., Construction Industry Arbitration Commission,
G.R. No. 202430, March 6, 2019 (1724) alleging that Metro Bottled Water refused to pay
Facts: its unpaid work accomplishment amounting to
P7,954,961.10, with interest of P494,297.31.
Metro Bottled Water and Andrada Construction Petitioner argues that the Court of Appeals erred
entered into a Construction Agreement for the in applying the principle of unjust enrichment,
construction of a reinforced concrete considering that Article 1724 of the Civil
manufacturing plant in Gateway Business Park, Code provides the requisites for the recovery of
General Trias, Cavite for the contract price of the costs of additional work. It contends that
Article 1724 requires both the written authority nor demand an increase in the price on account
of the owner allowing the changes and a written of the higher cost of labor or materials, save
agreement by the parties as to the increase in when there has been a change in the plans and
costs, neither of which were present in this case. specifications, provided:(1) Such change has
Even the Construction Agreement, it asserts, been authorized by the proprietor in writing; and
requires a written order to the contractor signed (2) The additional price to be paid to the
by the owner, authorizing work changes or contractor has been determined in writing by
adjustments on the contract price or contract both parties. In this case neither of the
period—to which respondent did not comply. exceptions are present therefore, Rolly cannot
demand for a higher price other than that agreed
Issue: Whether or not the Construction Industry
upon in the contract
Arbitration Commission and the Court of
Appeals erred in finding that petitioner Metro 3. CE Construction Corp. v. Araneta
Bottled Water Corporation was liable to Center, Inc., G.R. No. 192725, [August 9,
respondent Andrada Consumption & 2017], 816 PHIL 221-287 (Arts 1715, 1724)
Development Corporation, Inc. for unpaid work
Facts:
accomplishment.
Petitioner CECON was a construction
Ruling:
contractor, which, for more than 25 years, had
No. Petitioner contends that the arbitral tribunal been doing business with respondent ACI, the
should first apply Article 1724 when resolving developer of Araneta Center, Cubao, Quezon
the issue of whether respondent should be City.
compensated for costs incurred in Change Order
Nos. 39 to 109. Petitioner, however, fails to In June 2002, ACI sent invitations to different
recognize that there was no need to apply Article construction companies, including CECON, for
1724, since salient points of the provision had them to bid on a project identified as "Package
already been embodied in the Construction #4 Structure/Mechanical, Electrical, and
Agreement. It is settled that the contract is the Plumbing/Finishes (excluding Part A
law between the parties. Without any ambiguity Substructure)," a part of its redevelopment plan
in Item No. 8 of the Construction Agreement, for Araneta Center Complex. The project would
there was no need to resort to other aids in eventually be the Gateway Mall. As described
interpretation, such as Article 1724 of the Civil by ACI, "[t]he Project involved the design,
Code, to resolve the issue. coordination, construction and completion of all
architectural and structural portions of Part B of
Q: On November 2019, Rolly Corp undertook a
the Works[;] and the construction of the
structure for a stipulated price of Php 14 million
architectural and structural portions of Part A of
in comformity of the plans agreed upon with the
the Works known as Package 4 of the Araneta
land owner Ulysses. On February 2020, Rolly
Center Redevelopment Project. Despite ACI's
Corp  demand an increase in the price on
undertaking, no formal contract documents were
account of the higher cost of labor or materials.
delivered to CECON or otherwise executed
Can Rolly deman a n amount higher than what is
between ACI and CECON. With many changes
stipulated and agreed upon in the contract?
to the project and ACI's delays in delivering
ANS: No. Article 1724. The contractor who drawings and specifications, CECON
undertakes to build a structure or any other work increasingly found itself unable to complete the
for a stipulated price, in conformity with plans project on January 10, 2004. It noted that it had
and specifications agreed upon with the land- to file a total of 15 Requests for Time Extension
owner, can neither withdraw from the contract from June 10, 2003 to December 15, 2003, all of
which ACI failed to timely act on. of the higher cost of labor or materials, save
when there has been a change in the plans and
Exasperated, CECON served notice upon ACI specifications, provided:(1) Such change has
that it would avail of arbitration. On January 29, been authorized by the proprietor in writing; and
2004, it filed with the CIAC its Request for (2) The additional price to be paid to the
Adjudication. It prayed that a total sum of contractor has been determined in writing by
P183,910,176.92 representing adjusted project both parties. In this case neither of the
costs be awarded in its favor. exceptions are present therefore, Rolly cannot
demand for a higher price other than that agreed
Issue: Whether or not the Court of Appeals
upon in the contract
correctly held that the CIAC Arbitral Tribunal
acted beyond its jurisdiction in holding that the
price of P1,540,000,000.00 did not bind the
4. Loadstar Shipping Co., Inc. v. Malayan
parties as an immutable lump-sum.
Insurance Co., Inc., G.R. No. 185565
Ruling: (Resolution), [April 26, 2017], 809 PHIL 736-
750 (Arts 1732-1735)
No. No extraordinary technical or legal
proficiency is required to see that it would be the Facts:
height of absurdity and injustice to insist on the
Loadstar International Shipping, Inc. (Loadstar
payment of an amount the consideration of
Shipping) and Philippine Associated Smelting
which has been reduced to a distant memory.
and Refining Corporation (PASAR) entered into
ACI's invocation of Article 1724 is useless as
a Contract of Affreightment for domestic bulk
the premises for its application are absent. ACI's
transport of the latter’s copper concentrates
position is an invitation for this Court to lend its
which were loaded in Cargo Hold Nos. 1 and 2
imprimatur to unjust enrichment enabled by the
of MV “Bobcat”, a marine vessel owned by
gradual wilting of what should have been a
Loadstar International Shipping Co., Inc.
reliable contractual relation. Basic decency
(Loadstar International) and operated by
impels this Court to not give in to ACI's
Loadstar Shipping under a charter party
advances and instead sustain the CIAC Arbitral
agreement.  The cargo was insured with
Tribunal's conclusion that the amount due to
Malayan Insurance Company, Inc. (Malayan). 
CECON has become susceptible to reasonable
adjustment. The vessel’s chief officer on routine inspection
found a crack on starboard side of the main deck
Q: On November 2019, Rolly Corp undertook a
which caused seawater to enter and wet the
structure for a stipulated price of Php 14 million
cargo. Upon inspection, the Elite Adjusters and
in comformity of the plans agreed upon with the
Surveyor, Inc. (Elite Surveyor) confirmed that
land owner Ulysses. On February 2020, Rolly
samples of copper concentrates from Cargo
Corp  demand an increase in the price on
Hold No. 2 were contaminated by seawater.
account of the higher cost of labor or materials.
Can Rolly deman a n amount higher than what is PASAR sent a formal notice of claim in the
stipulated and agreed upon in the contract? amount of [P]37,477,361.31 to Loadstar
Shipping. On the basis of the Elite Surveyor’s
ANS: No. Article 1724. The contractor who
recommendation, Malayan paid PASAR the
undertakes to build a structure or any other work
amount of [P]32,351,102.32. PASAR signed a
for a stipulated price, in conformity with plans
subrogation receipt in favor of Malayan.  To
and specifications agreed upon with the land-
recover the amount paid and in the exercise of
owner, can neither withdraw from the contract
its right of subrogation, Malayan demanded
nor demand an increase in the price on account
reimbursement from Loadstar Shipping, which
refused to comply.  Consequently, on September passed on to the subrogee.
19, 2001, Malayan instituted with the RTC a
complaint for damages. In its complaint,
Malayan mainly alleged that as a direct and As regards the determination of actual damages,
natural consequence of the unseaworthiness of “[i]t is axiomatic that actual damages must be
the vessel, PASAR suffered loss of the cargo. proved with reasonable degree of certainty and a
Loadstar Shipping and Loadstar International party is entitled only to such compensation for
denied respondent’s allegations and averred that the pecuniary loss that was duly proven. As
respondent’s payment to PASAR, on the basis of Malayan is claiming for actual damages, it bears
the latter’s fraudulent claim, does not entitle the burden of proof to substantiate its claim.
respondent automatic right of recovery by virtue Actual damages are not presumed.  The claimant
of subrogation. must prove the actual amount of loss with a
reasonable degree of certainty premised upon
competent proof and on the best evidence
obtainable.  Specific facts that could afford a
Issue:
basis for measuring whatever compensatory or
WON respondent is entitled to the right of actual damages are borne must be pointed out. 
recovery by virtue of subrogation against Actual damages cannot be anchored on mere
petitioners, on the basis of PASAR’s claim. surmises, speculations or conjectures.

It is not disputed that the copper concentrates


Ruling: carried by M/V Bobcat from Poro Point, La
Malayan’s claim against the petitioners is based Union to Isabel, Leyte were indeed
on subrogation to the rights possessed by contaminated with seawater.  The issue lies on
PASAR as consignee of the allegedly damaged whether such contamination resulted to damage,
goods. The right of subrogation stems from and the costs thereof, if any, incurred by the
Article 2207 of the New Civil Code. The rights insured PASAR. In this case, Malayan, as the
of a subrogee cannot be superior to the rights insurer of PASAR, neither stated nor proved that
possessed by a subrogor. In other words, a the goods are rendered useless or unfit for the
subrogee cannot succeed to a right not possessed purpose intended by PASAR due to
by the subrogor.  A subrogee in effect steps into contamination with seawater.  Hence, there is no
the shoes of the insured and can recover only if basis for the goods’ rejection under Article 365
the insured likewise could have recovered. of the Code of Commerce.  Clearly, it is
Consequently, an insurer indemnifies the insured erroneous for Malayan to reimburse PASAR as
based on the loss or injury the latter actually though the latter suffered from total loss of
suffered from.  If there is no loss or injury, then goods in the absence of proof that PASAR
there is no obligation on the part of the insurer to sustained such kind of loss.
indemnify the insured. Should the insurer pay Q: X has a Tamaraw FX among other cars.
the insured and it turns out that indemnification Every other day during the workweek, he goes
is not due, or if due, the amount paid is to hisoffice in Quezon City using his Tamaraw
excessive, the insurer takes the risk of not being FX and picks up friends as passengers at
able to seek recompense from the alleged designatedpoints along the way. His passengers
wrongdoer.  This is because the supposed pay him a flat fee for the ride, usually P20 per
subrogor did not possess the right to be person, oneway. Although a lawyer, he never
indemnified and therefore, no right to collect is bothered to obtain a license to engage in this
type of income-generating activity. He believes
that he is not a common carrier within the valid and the bus company cannot be heldliable
purview of the law. Doyou agree with him? for the injuries suffered by the employees of
Explain.  Company X on the basis of the contract of
carriage.However, the employees who were
ANS: No. I do not agree with X. A common
injured may proceed against the bus company on
carrier holds himself out to the public as
the basis of a quasi-delict  (culpa aquiliana) but
engaged in the business oftransporting persons
the party charging negligence or wrong doing
or property from place to place, for
has the burden ofproving the same.It has been
compensation, offering his services to thepublic
held that a common carrier is exempt from the
generally. The fact that X has a limited clientele
application of the strict public policygoverning
does not exclude him from the definition of
common carriers where the carrier is not acting
acommon carrier. The law does not make any
as such but as a private carrier. Such strict public
distinction between one whose principal
policy has no force where the public at large is
business activityis the carrying of persons or
not involved, as when the carrier charters its
goods or both, and the one who does such
bustotally for the use of a single party. 
carrying only as an ancillary activity or in the
local idiom, as a “sideline”
5. Heirs of Mendoza v. ES Trucking and
Forwarders, G.R. No. 243237, February 17,
Q: Mabuhay Lines, Inc. a common carrier,
2020 (Art 1732)
entered into a contract with Company X,
whereby it agreed to furnish Company X, for a Facts:
fixed amount, a bus for a company excursion on
On June 13, 2013, at around noontime, Catalina
its anniversary day.It was agreed that Company
P. Mendoza (Catalina) was walking along Sta.
X would have the use of the bus and its driver
Maria Road after visiting a lotto outlet nearby.
from 7:00 am to 7:00pm on the stipulated date,
While she was at the center of the road and
and that the bus driver would be obliged to
attempting to cross its second half, she was
follow the instructions of the company’s general
sideswiped by a 14-wheeler prime mover truck
manager as to the places to be visited. Company
at the junction of Gov. Ramos Street and Sta.
X agreed to bear the cost
Maria Road in Zamboanga City. The prime
of the gasoline consumed.The transportation mover truck bore body no. 5 and green plate no.
contract signed by Company X contained a NAO 152, while the trailer attached to it had
stipulation that Mabuhay Lines,Inc. would be yellow plate no. JZA163. The vehicle is
exempt from liability on account of acts registered under the name of ES Trucking and
or omissions of its employees.On the return trip Forwarders (ES Trucking) with Sumarni Asprer
from the excursion site, the bus had an accident Ruste as its sole proprietor. At the time of the
and several employees ofCompany X were incident, the vehicle was driven by Clin Timtim
injured.State the liability, if any, of Mabuhay (Timtim), a holder of professional driver's
Lines, Inc.  license no. 104-99-069007.
ANS:Although a common carrier, Mabuhay Moments before the incident, Timtim claimed
Lines, Inc. was not acting as such in the instant that he stopped the vehicle at the crossing lane
case but as aprivate carrier. Accordingly, the as the tricycle in front of the prime mover truck
provision applicable to a common carrier in stopped and only began to accelerate once the
respect of extraordinarydiligence cannot be tricycle started moving.
imposed upon the bus company.The stipulation
The two sons of Catalina picked her up from
limiting the liability of Mabuhay Lines, Inc. is
under the fuel tank of the prime mover truck
behind its front left tire and brought her to 6. Federal Express Corporation, v.
Ciudad Medical Zamboanga where she was Luwalhati R. Antonino and Eliza Bettina
pronounced dead.11 Catalina suffered multiple Ricasa Antonino GR. No. 199455, June 27,
abrasions and contusions in the clavicle area, 2018 (1733)
lacerated wound on the cheek, and multiple
Facts: On December 15, 2003, Luwalhati and
abrasions on the abdomen.12 She also suffered
Eliza were in the Philippines. As the monthly
multiple rib fractures.13 The immediate cause of
common charges on the Unit had become due,
death, stated in her Certificate of Death,14 is
they decided to send several Citibank checks to
"Cardio-Pulmonary Arrest Sec. to Vehicular
Veronica Z. Sison, who was based in New York.
Accident."
Citibank checks allegedly amounting to
Issue: Whether ES Trucking is a common US$17,726.18 for the payment of monthly
carrier required by law to observe extraordinary charges and US$11,619.35 for the payment of
diligence in the carriage of passengers and real estate taxes were sent by Luwalhati through
goods. FedEx with Account No. x2546-4948-1 and
Tracking No. 8442 4588 4268. The package was
Ruling:
addressed to Sison who was tasked to deliver the
Yes. Article 1732 of the Civil Code defines checks payable to Maxwell-Kates, Inc. and to
common carriers as persons, corporations, firms the New York County Department of Finance.
or associations engaged in the business of Sison allegedly did not receive the package,
carrying or transporting passengers or goods or resulting in the non-payment of Luwalhati and
both, by land, water, or air, for compensation, Eliza's obligations and the foreclosure of the
offering their services to the public. In this case, Unit.
the Heirs of Catalina established through
Upon learning that the checks were sent on
preponderance of evidence that, at the time of
December 15, 2003, Sison contacted FedEx on
the incident, the vehicle was being used as a
February 9, 2004 to inquire about the non-
truck for hire without securing the necessary
delivery. She was informed that the package was
franchise from the LTFRB. ES Trucking
delivered to her neighbor but there was no
engaged in a truck for hire business, offering
signed receipt.
their vehicles to transport the cargo of its
customers. Noticeably, Edgardo Ruste admitted On March 14, 2004, Luwalhati and Eliza,
that they filed an application to have the vehicle through their counsel, sent a demand letter to
included in their Certificate of Public FedEx for payment of damages due to the non-
Convenience yet their application was never delivery of the package, but FedEx refused to
granted. This is inconsistent with his own claim heed their demand. Hence, on April 5, 2004,
that ES Trucking does not need to register with they filed their Complaint for damages.
the LTFRB because it is not a common carrier
Issue: Whether or not petitioner Federal Express
but a private company. The fact that they
Corporation may be held liable for damages on
considered applying for the inclusion of the
account of its failure to deliver the checks
vehicle in their Certificate of Public
shipped by respondents Luwalhati R. Antonino
Convenience signifies that they are aware of the
and Eliza Bettina Ricasa Antonino to the
franchise requirement of the LTFRB. ES
consignee Veronica Sison
Trucking cannot be excused simply because it is
not registered with the LTFRB and it is a private Ruling:
company. ES Trucking cannot be exonerated
from liability and benefit from its own violation Yes. Petitioner is liable for this loss. It failed to
of the laws and rules governing trucks for hire. ensure that the package was delivered to the
named consignee. The Civil Code mandates
common carriers to observe extraordinary Q: Nelson owned and controlled Sonnel
diligence in caring for the goods they are Construction Company. Acting for the company,
transporting:Article 1733. Common carriers, Nelson contracted the construction of a building.
from the nature of their business and for reasons Without first installing a protective net atop the
of public policy, are bound to observe sidewalks adjoining the construction site, the
extraordinary diligence in the vigilance over the company proceeded with the construction work.
goods and for the safety of the passengers One day a heavy piece of lumber fell from the
transported by them, according to all the building. It smashed a taxicab which at that time
circumstances of each case."Extraordinary had gone offroad and onto the sidewalk in order
diligence is that extreme measure of care and to avoid traffic. The taxicab passenger died as a
caution which persons of unusual prudence and result. Could the heirs hold the taxicab owner
circumspection use for securing and preserving and driver liable? Explain.
their own property or rights." Consistent with
ANS: Yes, the taxicab company can be liable for
the mandate of extraordinary diligence, the Civil
damages because it failed to comply with its
Code stipulates that in case of loss or damage to
obligation as a common carrier to use
goods, common carriers are presumed to be
extraordinary diligence in transporting the
negligent or at fault. Petitioner is unable to
passenger, and because at the time of death of
prove that it exercised extraordinary diligence in
the passenger, the cab driver was violating a
ensuring delivery of the package to its
traffic regulation. Under Art. 2185 of Civil
designated consignee. It claims to have made a
Code, it is presumed that a person driving a
delivery but it even admits that it was not to the
motor vehicle has been negligent if at time of
designated consignee. It asserts instead that it
mishap he was violating a traffic regulation,
was authorized to release the package without
such as when he was driving on the wrong side
the signature of the designated recipient and that
of the road
the neighbor of the consignee, one identified
only as "LGAA 385507," received it This fails
to impress.
Q: B, while drunk, accepted a passenger in his
The assertion that receipt was made by "LGAA taxicab. B then drove the taxi recklessly, and
385507" amounts to little, if any, value in inevitably, it crashed into an electric post,
proving petitioner's successful discharge of its resulting in serious physical injuries to the
duty. "LGAA 385507" is nothing but an passengers. The latter then filed a suit for tort
alphanumeric code that outside of petitioner's against B's operator, A, but A raised the defense
personnel and internal systems signifies nothing. of having exercised extraordinary diligence in
This code does not represent a definite, readily the safety of the passenger. Is his defense
identifiable person, contrary to how commonly tenable?
accepted identifiers, such as numbers attached to
official, public, or professional identifications ANS: No. Article 1733 of the civil code
like social security numbers and professional mandates common carriers, from the nature of
license numbers, function. Reliance on this code their business and for reasons of public policy,
is tantamount to reliance on nothing more than are bound to observe extraordinary diligence in
petitioner's bare, self-serving allegations. the vigilance over the goods and for the safety of
Certainly, this cannot satisfy the requisite of the passengers transported by them, according to
extraordinary diligence consummated through all the circumstances of each case. The state of
delivery to none but "the person who has a right being drunk is a manifestation of recklessness.
to receive" the package. Hence, extraordinary diligence was not
observed.
7. Unitrans International Forwarders, local ship agent respondent TMS Ship Agencies
Inc. v. Insurance Company of North (TSA).
America, G.R. No. 203865, March 13, 2019
Issue: Whether or not Unitrans was able to
(Art 1735 in relation to 1733)
exercise the diligence necessary under the
Facts: foregoing circumstances to exculpate them from
liability
In Melbourne, Australia, South East Asia
Container Line (SEACOL) solicited and Ruling:
received shipment of musical instruments from
No. A common carrier is presumed to have been
shipper Dominant Musical Instrument for
negligent if it fails to prove that it exercised
transportation to and delivery at the port of
extraordinary vigilance over the goods it
Manila. The aforesaid shipment was insured
transported. When the goods shipped are either
with respondent Insurance Company of North
lost or arrived in damaged condition, a
America (ICNA) against all risk in favor of the
presumption arises against the carrier of its
consignee, San Miguel Foundation for the
failure to observe that diligence, and there need
Performing Arts (San Miguel). SEACOL then
not be an express finding of negligence to hold it
loaded the insured shipment on board M/S
liable. To overcome the presumption of
Buxcrown for transportation from Melbourne to
negligence, the common carrier must establish
Singapore. In Singapore, the shipment was
by adequate proof that it exercised extraordinary
transferred from M/S Buxcrown to M/S Doris
diligence over the goods. It must do more than
Wullf for final transportation to the port of
merely show that some other party could be
Manila.
responsible for the damage. In the instant case,
Upon arrival in Manila, the container van was considering that it is undisputed that the subject
discharged from the vessel and was received by goods were severely damaged, the presumption
petitioner Unitrans International Forwarders of negligence on the part of the common carrier,
(Unitrans), and upon stripping, it was found that i.e., Unitrans, arose. Hence, it had to discharge
two of the cartons containing the musical the burden, by way of adequate proof, that it
instruments were in a bad condition. Despite exercised extraordinary diligence over the
such, Unitrans delivered the subject shipment to goods; it is not enough to show that some other
the consignee. After further inspection, it was party might have been responsible for the
found out that two units of musical instruments damage. Unitrans failed to discharge this
were damaged and could no longer be used for burden. Hence, it cannot escape liability
their intended purpose, hence were declared a
Q: B, while drunk, accepted a passenger in his
total loss. Despite repeated demands, Unitrans
taxicab. B then drove the taxi recklessly, and
refused to pay the damages sustained.
inevitably, it crashed into an electric post,
Subsequently, ICNA, as the insurer, paid for and
resulting in serious physical injuries to the
was subrogated the rights to collect from
passengers. The latter then filed a suit for tort
Unitrans. ICNA filed an amended complaint for
against B's operator, A, but A raised the defense
collection of sum of money against South East
of having exercised extraordinary diligence in
Asia Container Line (SEACOL) and the
the safety of the passenger. Is his defense
unknown owner/charterer of the vessel M/S
tenable?
Buxcrown, both doing business in the
Philippines through its local ship agent, ANS: No. Article 1733 of the civil code
petitioner Unitrans International Forwarders mandates common carriers, from the nature of
(Unitrans); and against the unknown charterer of their business and for reasons of public policy,
M/S Doris Wullf, doing business through its are bound to observe extraordinary diligence in
the vigilance over the goods and for the safety of to transport and deliver the same to its
the passengers transported by them, according to warehouse in Biñan, Laguna. Meanwhile,
all the circumstances of each case. The state of Keihin-Everett had an Accreditation Agreement
being drunk is a manifestation of recklessness. with Sunfreight Forwarders whereby the latter
Hence, extraordinary diligence was not undertook to render common carrier services for
observed. the former and to transport inland goods within
the Philippines. Shipment was released from the
Q: Nelson owned and controlled Sonnel
pier by Keihin-Everett and turned over to
Construction Company. Acting for the company,
Sunfreight Forwarders for delivery to Honda
Nelson contracted the construction of a building.
Trading. En route to the latter's warehouse, the
Without first installing a protective net atop the
truck carrying the containers was hijacked and
sidewalks adjoining the construction site, the
the container van with Serial No. TEXU
company proceeded with the construction work.
389360-5 was reportedly taken away. Honda
One day a heavy piece of lumber fell from the
Trading suffered losses in the total amount of
building. It smashed a taxicab which at that time
P2,121,917.04, representing the value of the lost
had gone offroad and onto the sidewalk in order
40 bundles of Aluminum Alloy Ingots. Claiming
to avoid traffic. The taxicab passenger died as a
to have paid Honda Trading's insurance claim
result. Could the heirs hold the taxicab owner
for the loss it suffered, Tokio Marine filed a
and driver liable? Explain.
complaint for damages against Keihin-Everett.
ANS: Yes, the taxicab company can be liable for
Issue: WON Keihin-Everett is liable?
damages because it failed to comply with its
obligation as a common carrier to use Ruling:
extraordinary diligence in transporting the
Yes. Keihin-Everett is liable notwithstanding
passenger, and because at the time of death of
that the cargoes were in the possession of
the passenger, the cab driver was violating a
Sunfreight Forwarders when they were hijacked.
traffic regulation. Under Art. 2185 of Civil
Code, it is presumed that a person driving a As correctly held by the CA, there was no
motor vehicle has been negligent if at time of privity of contract between Honda Trading (to
mishap he was violating a traffic regulation, whose rights Tokio Marine was subrogated) and
such as when he was driving on the wrong side Sunfreight Forwarders. Hence, Keihin-Everett,
of the road as the common carrier, remained responsible to
Honda Trading for the lost cargoes.
In this light, Keihin-Everett, as a common
8. Keihin-Everett Forwarding Co., Inc. v.
carrier, is mandated to observe, under Article
Tokio Marine Malayan Insurance Co., Inc.,
1733 of the Civil Code, extraordinary diligence
G.R. No. 212107, [January 28, 2019]) (1733-
in the vigilance over the goods it transports
1736)
according to all the circumstances of each case.
Facts: In the event that the goods are lost, destroyed or
deteriorated, it is presumed to have been at fault
Honda Trading Phils. Ecozone Corporation
or to have acted negligently, unless it proves that
(Honda Trading) ordered 80 bundles of
it observed extraordinary diligence. To be sure,
Aluminum Alloy Ingots from PT Molten
under Article 1736 of the Civil Code, a common
Aluminum Producer Indonesia. Honda Trading
carrier's extraordinary responsibility over the
insured the entire shipment with Tokio Marine
shipper's goods lasts from the time these goods
& Nichido Fire Insurance Co., Inc. (TMNFIC).
are unconditionally placed in the possession of,
It also engaged the services of Keihin-Everett to
and received by, the carrier for transportation,
clear and withdraw the cargo from the pier and
until they are delivered, actually or to its destination. But while at sea, the vessel
constructively, by the carrier to the consignee, or received a report of a typhoon moving within its
to the person who has a right to receive them. general path. To avoid the typhoon, the vessel
changed its course. However, it was still at the
Hence, at the time Keihin-Everett turned over
fringe of the typhoon when it was repeatedly hit
the custody of the cargoes to Sunfreight
by huge waves, were saved three (3) who
Forwarders for inland transportation, it is still
perished. Is CSC liable to empire? Explain
required to observe extraordinary diligence in
the vigilance of the goods. Failure to ANS: The common carrier incurs no liability for
successfully establish this carries with it the the loss of the cargo during a fortuitous event,
presumption of fault or negligence, thus, because the following circumstances were
rendering Keihin-Everett liable to Honda present: (1) the typhoon was the cause of the
Trading for breach of contract. cargo loss; (2) the carrier did not contribute to
the loss; and (3) the carrier exercised
Q: B, while drunk, accepted a passenger in his
extraordinary diligence in order to minimize the
taxicab. B then drove the taxi recklessly, and
attendant damage before, during and after the
inevitably, it crashed into an electric post,
typhoon
resulting in serious physical injuries to the
passengers. The latter then filed a suit for tort 9. Faj Construction v. Saulog, G.R. No.
against B's operator, A, but A raised the defense 200759, March 25, 2015 (Art. 1715)
of having exercised extraordinary diligence in
Facts:
the safety of the passenger. Is his defense
tenable? On June 15, 1999, petitioner FAJ Construction
and Development Corporation and respondent
ANS: No. Article 1733 of the civil code
Susan M. Saulog entered into an
mandates common carriers, from the nature of
Agreement6 (construction agreement) for the
their business and for reasons of public policy,
construction of a residential building in San
are bound to observe extraordinary diligence in
Lorenzo Village, Makati City for a contract
the vigilance over the goods and for the safety of
price of P12,500,000.00. Payment to petitioner
the passengers transported by them, according to
contractor shall be on a progress billing basis,
all the circumstances of each case. The state of
after inspection of the work by respondent.
being drunk is a manifestation of recklessness.
Hence, extraordinary diligence was not Construction of the building commenced, and
observed. respondent made a corresponding total payment
to petitioner in the amount of P10,592,194.80.
However, for the October 31 and November 6,
Q: On October 30, 2007, M/V Pacific, a 2000 progress billing statements sent by
Philippine registered vessel owned by Cebu petitioner in the total amount of P851,601.58,
Shipping Company (CSC), sank on her voyage respondent refused to pay. After performing
from Hong Kong to Manila. Empire Assurance additional work, petitioner made another request
Company (Emprie) is the insurer of the lost for payment, but respondent again refused to
cargoes loaded on board the vessel which were pay, prompting petitioner to terminate the
consigned to Debenhams Company. After it construction contract pursuant to Article 27(b)
indemnified Debenhams, Empire as subrogee of the Uniform General Conditions of Contract
filed an action for damages against CSC. (A) for Private Construction (or Document 102) of
Assume that the vessel was seaworthy. Before the Construction Industry Authority of the
departing, the vessel was advised by theJapanese Philippines, Department of Trade and Industry.7
Meteorological Center that it was safe to travel
Petitioner then sent demand letters to respondent shows that on January 24, 2000, appellee
on November 24, 2000 and September 28, 2001. approved the extension requested by appellant.
In reply, respondent claimed that petitioner’s This request for extension, by itself, is already
work was defective, and that it should instead be proof of delay. Thus, at the time appellant
made liable thereon. abandoned the project, it already incurred delay.
Verily, it is only proper that appellant be made
Issue: WON Saulog adequately prove her right
to pay the penalty for delay after appellee no
to actual damages for rectification of appellant’s
longer agreed to any further extension.
defective work
Ruling:
Q: XYZ Construction and spouses Dimaano
Yes. Article 1715 of the Civil Code provides
entered into an Agreement construction
that the contractor shall execute the work in such
agreement) for the construction of a residential
a manner that it has the qualities agreed upon
building in San Lorenzo Village, Makati City for
and has no defects which destroy or lessen its
a contract price of P12,500,000.00.  Payment to
value or fitness for its ordinary or stipulated use.
XYZ contractor shall be on a progress billing
Should the work be not of such quality, the
basis, after inspection of the work by spouses
employer may require that the contractor remove
Dimaano. Construction of the building
the defect or execute another work. If the
commenced, and respondent made a
contractor fails or refuses to comply with this
corresponding total payment to XYZ
obligation, the employer may have the defect
Construction in the amount of P10,592,194.80. 
removed or another work executed, at the
However, for the October 31 and November 6,
contractor’s cost.Evidently, Article 1715 gives
2000 progress billing statements sent by XYZ
the employer the options to require the removal
in the total amount of P851,601.58, spuuses
of the work, to rectify the flaws in their work, or
Dimaano refused to pay for defective
to have the work done at the expense of the
workmanship proven by an architect.  After
contractor.
performing additional work, XYZ made another
Here, the defective workmanship was amply request for payment, but spouses Dimaano again
proven by Architect Rhodora Calinawan’s refused to pay, prompting XYZ to terminate the
testimony and documentary evidence i.e., construction contract. XYZ then sent demand
photographs, receipts, and list of the expenses letters to respondent on November 24, 2000 and
needed to rectify appellant’s poorly crafted September 28, 2001.  In reply, spouses Dimaano
work. Hence, We sustain the award of actual claimed that petitioner’s work was defective,
damages based on these testimonial and and that it should instead be made liable thereon.
documentary evidence. Decide

Regarding the penalty for delay in the amount of ANS: Article 1715 gives the Spouses Dimaano
One Million Three Hundred Eighty Seven the options to require the removal of the work,
Thousand Five Hundred Pesos (P1,387,500.00), to rectify the flaws in their work, or to have the
the same should also be sustained. A contract is work done at the expense of the contractor.Here,
the law between the parties, and they are bound the defective workmanship was amply proven
by its stipulations so long as they are not by an architect.  Hence, Spuses Dimaano should
contrary to law, customs, public policy and not be held liable
public morals. The penalty for delay is agreed
10. Shangri-La Properties, Inc. v. BF Corp.,
upon by the parties themselves. The fact that
G.R. Nos. 187552-53 & 187608-09, October
appellant was already delayed in the completion
15, 2019 (Art. 1724)
of the duplex is undisputed. In fact, record
Facts: requisites under Article 1724. Accordingly, the
Court reinstates the Arbitral Tribunal's awards in
The present controversy originated from the
favor of BFC for variation orders included in
agreement of Shangri-la Properties, Inc. (SLPI)
progress billings amounting to
and BF Corporation (BFC) for the execution of
P9,513,987.91 and for change orders not
the builder's work for Phases I and II, and the
included in progress billings amounting to
Car Parking Structure (Carpark) of the EDSA
P6,201,278.50. The Arbitral Tribunal correctly
Plaza Project (Project) in Mandaluyong City,
ruled that BFC had complied with the twin
embodied in the parties' contract documents.
requirements imposed by Article 1724 of the
SLPI was the project owner and BFC was the
Civil Code. Article 1724 governs the recovery of
trade contractor. BFC sued SLPI and the
costs for any additional work because of a
members of the latter's board of directors
subsequent change in the original plans. The
(Alfredo C. Ramos, Rufo B. Colayco, Antonio
underlying purpose of the provision is to prevent
B. Olbes, Gerardo O. Lanuza Jr., Maximo G.
unnecessary litigation for additional costs
Licauco III and Benjamin C. Ramos) for the
incurred by reason of additions or changes in the
collection of P228,630,807.80. The case was
original plan. The provision was undoubtedly
docketed as Civil Case No. 63400 in the
adopted to serve as a safeguard or as a
Regional Trial Court of Pasig City (Branch 157).
substantive condition precedent to recovery.  As
The proceedings before the trial court was
such, added costs can only be allowed upon: (a)
stayed by this court, as affirmed by the Supreme
the written authority from the developer or
Court, until termination of an arbitration
project owner ordering or allowing the changes
proceeding as required in their contract.
in work; and (b) upon written agreement of the
BFC filed a request for arbitration with the parties on the increase in price or cost due to the
Construction Industry Arbitration Commission change in work or design modification.
(CIAC), but the same was eventually dismissed, Compliance with the requisites is a condition
without prejudice, on the ground that the precedent for recovery; the absence of one
arbitration between BFC and SLPI must be requisite bars the claim for additional costs.
undertaken in accordance with Republic Act No. Notably, neither the authority for the changes
876. Subsequently, the trial court revived the made nor the additional price to be paid therefor
case and directed the parties to proceed with the may be proved by any evidence other than the
arbitration proceeding in accordance with written authority and agreement as above-stated.
R.A. No. 876. Engr. Eliseo Evangelista, Ms.
Q: On November 2019, Rolly Corp undertook a
Alicia Tiongson and Atty. Mario Eugenio Lim
structure for a stipulated price of Php 14 million
were tasked to resolve the controversy as
in comformity of the plans agreed upon with the
members of the Arbitral Tribunal.
land owner Ulysses. On February 2020, Rolly
Issue: WON the court of appeals gravely erred Corp  demand an increase in the price on
when it denied the claims of bfc for variation account of the higher cost of labor or materials.
works it was compelled to perform upon the Can Rolly deman a n amount higher than what is
instructions of SLPI. stipulated and agreed upon in the contract?

Ruling: ANS: No. Article 1724. The contractor who


undertakes to build a structure or any other work
Yes. The Court upholds the Arbitral Tribunal. In for a stipulated price, in conformity with plans
our view, the. CA wrongly disregarded the and specifications agreed upon with the land-
specific variation orders that carried the owner, can neither withdraw from the contract
conformity of SLPI, which, when coupled with nor demand an increase in the price on account
the letter dated May 9, 1991, satisfied the of the higher cost of labor or materials, save
when there has been a change in the plans and
specifications, provided:(1) Such change has
been authorized by the proprietor in writing; and
(2) The additional price to be paid to the
contractor has been determined in writing by
both parties. In this case neither of the
exceptions are present therefore, Rolly cannot
demand for a higher price other than that agreed
upon in the contract

You might also like