Professional Documents
Culture Documents
Manhours
Manhours
30" Round
Fabricate & Erect .054 .008 .001 .063
Strip .008 .008 .001 .017
Total .062 .016 .002 .080
30" Round
Fabricate & Erect .056 .008 .001 .065
Strip .008 .008 .001 .017
Total .064 .016 .002 .082
Manhours
Manhours
Manhours
Manhours
Manhours
36" Round
Fabricate & erect .050 .006 .001 .057
Strip .006 .006 .001 .013
Total .056 .012 .002 .070
Manhours
Manhours
Column Caps
Hoist & buggies 2.40 .15 – 2.55
Tilt-Up Concrete Panels Crane, bucket & buggies 1.95 .12 .12 2.19
MANHOURS PER SQUARE FOOT
Manhours include the placement and
vibration of concrete and the finishing,
curing and erection of panels. Manhours
Manhours are based on the placing of
concrete in pre-erected forms on a flat Item Laborer Cement Iron Total
level location easily accessible for both Finisher Worker
placing and erection operations.
Placing concrete manhours are based Pre-Cast Panels 6" Thick
on placing concrete direct from ready Place Concrete .147 – – .147
mix truck into forms. Finish & Cure .002 .015 – .017
Manhours do not include the fabrica- Erect Panels – – .120 .120
tion, erection or stripping of forms.
Manhours
Manhours
Manhours
Manhours
Manhours
Manhours
Item Per Ton Per cwt
Item Manhours
per 100 sq ft
Integral Topping
1
Topping Finish ⁄2" by hand .029
1
MANHOURS PER SQUARE FOOT ⁄2" by machine .018
Manhours are for topping finish and in- 1" by hand .068
clude mixing and stand-by time where 1" by machine .022
required.
Manhours do not include the placing
and vibrating of main floors. Separate Topping
1
⁄2" by hand .036
1
⁄2" by machine .018
1" by hand .068
Manhours
Surface Finish
Cement
Finisher Laborer Total
Concrete Finish
MANHOURS PER SQUARE FOOT Carborundum Rub .045 – .045
Manhours are for the types of finish not- Remove Fins or Ties – Point & Patch .030 – .030
ed and include all necessary operations. Machine Trowel & Hand Burnish .015 – .015
In most areas, craft jurisdiction pre-
Hand Steel Trowel .030 – .030
vents laborers from helping cement fin-
ishers. Should this be the case, use total Woodfloat .001 – .001
hours as listed for cement finisher Broom .003 – .003
hours.
Screeding Off .003 .003 .006
Cure & Protect .002 – .002
Grout Column Bases (1") .250 .025 .500
PUBLICATION #C620129
Copyright © 1962, The Aberdeen Group
All rights reserved