Project Title
Project Leader
Client
Scope
Time
Cost
oject Technical Brief:
Interwood - Expension of
Production House
Sana Mushtaq
Interwood Company
Increase the plant Capacity
3 Months
PKR 50,000,000.00
Sr # WBS > ACTIVITY
Construction of Production House
Complete Material Procurement
1 Land (Excavation)
Surveying Ground and Top levels, Excavtion to the Approved Depth
dressing the loose soil
making up to cut off level
2 Boundry wall
Conceret Mixing, Bricks fixing & leveling
3 Concrete Slab
Digging the ground, Leveling the ground & pouring the mixture of concrete
5 Steel Structure
Marking for footing,excavation, soil bearing capacity test
Footing reinforcment mats, footing casting with RMC
Column shuttering and curing
Refilling of soil,joining plinth
Foundation bolts, leveling,plinth beam fram
Plinth beam shuttering
PEB column fixing, purlins
Roof beams, purlins, bolts
7
Isntallation of Machines
Foundation (for all mechines)
Installation of CNC BIESSE SKIPPER MACHINE
Installation of NANXING MACHINE
Installation of BRANDT MACHINE KDN 340
Installation of SELCO BEAM SAW MACHINE
Installation of Table Saw machine
Installation of CNC WOOD router machine
Installation of CNC WOOD router machine
Installation of Planner wood cutter machin
Balancing
15 Vibration
Substation Work
Switchgear
New Panel Installation
Panel Modification
Cable Tray Installation
Indoor Cable Laying
Indoor Cable termination
Feeder Cabling
Cable Termination
Cable Splice
16 Conduit Installation
Power Wiring
Power Wiring for equipments
Cable Tray Installation
Cable Laying
17 Cable Termination
Lighting Work
Panel Installation and termination
Lighting Fixture installation and termination
Cable tray installation
Cable Laying
Junction Box Installation
18 Conduit Installation
Ground Work
Grounding Electrode installation with well
Grounding Wire Installation and Connection
Automation
Installation of the software
Configuration the whole system
Plan
Duration
1
3
1
1
2
3
3
3
3
11
1
1
1
1
3
1
2
3
2
14
2
1
1
1
1
1
1
1
1
2
2
7
1
1
1
1
1
1
1
1
1
1
4
1
1
1
1
8
1
2
2
2
1
1
2
1
1
2
1
1
Human Resource Material Resource
Digging the ground, Leveling the ground & pouring the mixt
Marking for footing,excavation, soil bearing capacity test
Footing reinforcment mats, footing casting with RMC
Column shuttering and curing
Refilling of soil,joining plinth
Foundation bolts, leveling,plinth beam fram
Plinth beam shuttering
PEB column fixing, purlins
Roof beams, purlins, bolts
Vibration
Switchgear and motor control center installation
New Panel Installation
Panel Modification
Cable Tray Installation
Indoor Cable Laying
Indoor Cable termination
Feeder Cabling
Cable Termination
Cable Splice
Conduit Installation
Power Wiring for equipments
Cable Tray Installation
Cable Laying
Cable Termination
Panel Installation and termination
Lighting Fixture installation and termination
Cable tray installation
Cable Laying
Junction Box Installation
Conduit Installation
Grounding Electrode installation with well
Surveying Ground and Top levels, Excavtion to the Approved Depth 20,000 1
SS 66,800 3
excavation to the approved depth FS 22,600 1
making up to cut off level FS 16,200 1
Conceret Mixing, Bricks fixing & leveling FS 28,000 2
509,796 3
Digging the ground, Leveling the ground & pouring the mix FS 509,796 3
755,142 3
Marking for footing,excavation, soil bearing capacity test FS 755,142 3
2,990,858 11
Footing reinforcment mats, footing casting with RMC FS 25,294 1
Column shuttering and curing FS 450,780 1
Refilling of soil,joining plinth FS 41,400 1
Foundation bolts, leveling,plinth beam fram FS 28,500 1
Plinth beam shuttering FS 277,185 3
PEB column fixing, purlins FS 40,800 1
Roof beams, purlins, bolts FS 815,200 2
Side covering and the roof covering FS 1,311,699 3
Foundation (for all mechines) FS 18,252,264 2
19,098,750 14
Installation of CNC BIESSE SKIPPER MACHINE FS 60,688 2
Installation of NANXING MACHINE FS 3,180,384 1
Installation of BRANDT MACHINE KDN 340 FS 2,673,368 1
Installation of SELCO BEAM SAW MACHINE FS 1,936,118 1
Installation of Table Saw machine FS 2,627,068 1
Installation of CNC WOOD router machine FS 6,658,140 1
Installation of CNC WOOD router machine FS 412,060 1
Installation of Planner wood cutter machin FS 1,217,400 1
Balancing FS 226,548 1
Vibration FS 75,576 2
Switchgear and motor control center installation FS 31,400 2
1,146,788 7
Switchgear and motor control center installation FS 140,054 1
New Panel Installation SS 269,804 1
Panel Modification FS 142,254 1
Cable Tray Installation FS 112,988 1
Indoor Cable Laying FS 344,248 1
Indoor Cable termination FS 42,488 1
Feeder Cabling FS 21,988 1
Cable Termination FS 21,988 1
Cable Splice FS 25,488 1
Conduit Installation FS 25,488 1
159,714 4
Cable Tray Installation FS 49,788 1
Cable Laying FS 72,938 1
Cable Termination FS 14,500 1
Panel Installation and termination FS 22,488 1
204,230 8
Lighting Fixture installation and termination FS 59,388 1
Cable tray installation FS 31,548 2
Cable Laying FS 36,888 2
Junction Box Installation FS 37,368 2
Conduit Installation FS 13,450 1
FS 25,588 1
37,076 2
Grounding Wire Installation and Connection FS 17,788 1
Installation of the software FS 19,288 1
115,000.00 2
Configuration the whole system 46000 1
69000 1
Budgeted
Cost/Day
20,000
52800
22,600
16200
14000
169,932
169,932
251,714
251,714
1,524,002
25,294
450,780
41400
28500
92395
40800
407600
437233
9126132
19014918
30344
3180384
2673368
1936118
2627068
6658140
412060
1217400
226548
37788
15700
1146788
140054
269804
142254
112988
344248
42488
21988
21988
25488
25488
159714
49788
72938
14500
22488
151328
59388
15774
18444
18684
13450
25588
37076
17788
19288
115000
46000
69000