Cementing Design
Cementing Design
ITEM
1. Description
2. Preparation
3. The main factor contacting with
the displacing ratio
4. Rule and method
5. Procedure
1、 Description
Basic rule
⚫ Keep the annular pressure balance while
pumping and WOC
⚫ Displace all the mud away the cementing
section
⚫ The lost circulation or oil/gas/water
channeling into the annular will not
happen
1、 Description
Main contents
① Well conditions : analyzing the
temperature/ pressure / open hole
condition/mud properties
② Selecting the cementing type and method
③ Slurry design: weight/ volume /properties
④ Ahead water and behind water design
1、 Description
Main contents
⑤ Selecting the cementing equipment
and tools/casing accessories
⑥ Displacing technology design:
Displacing speed/operation program
⑦ Preparation before cementing:
cleaning the open hole/adjusting the
mud properties
⑧ Cementing result evaluation
1、 Description
Design procedure :
① Selecting and analyzing the basic data used
for the design
② Deciding the cementing method
③ Calculating the volume of slurry/ahead
water/behind water/displacing mud
④ Planning the position of the casing accessories
⑤ Making the operation procedures and the plan
1、 Description
Design procedure :
⑥ Simulating and evaluation the cementing
operation, comparing the design results
⑦ Adjusting the design data on the base of the
simulating and evaluation
⑧ Carry out the design cementing procedures
⑨ Analyzing and evaluating the operation
results
2、 Preparation
Return speed
Re
(m/s)
冲洗液
normal:
mud + ahead water(pre-flush/spacer/pre-flush) 隔离液
Tow stage:
mud + ahead water(pre-flush/spacer)+ slurry(tail)
4、 The rule and the method of cementing design
⚫ Volume calculation
– Volume of slurry
– Volume of cement
– Volume of mixing water
– Volume of additives
– Volume of ahead water(pre-flush/spacer)
– Volume of displacing fluid
4、 The rule and the method of cementing design
q=10·Qc·60/1000
q----volume of pre-flush m3
Qc----displacing capacity L/s
4、 The rule and the method of cementing design
⚫ Following resistance
⚫ Static pressure in the annular and casing
⚫ Pressure at well head
⚫ Pressure at casing shoe
⚫ Turbulent follow contacting time
5、Cementing design procedure
(1) Selecting and analysis the basic data for the design
(2) Making the first cementing plan
① selecting cementing method
② design the displacing form
③ calculating the volume of ahead water
④ design the slurry column in the annular
⑤ design the type of slurry and the properties for
the well condition
5、Cementing design procedure