Professional Documents
Culture Documents
Contaminated Soil
and Groundwater
EP 95-0387
HSE
MANUAL
1.3 The Current Approach and Need for a Soil 6.2.6 Soil contamination 31
Framework Plan 1 6.2.7 Type of soil 31
4 Risk Evaluation 13
4.1 The Risk Evaluation Process 13
4.2 The Hazards 14
4.2.1 Health 14
4.2.2 Damage to underground systems 14
4.2.3 Environmental spread 15
4.3 Determination of Exposure Category 17
4.4 Determination of Spread Category 20
4.5 Determination of Urgency Category 23
4.6 Determination of Priorities Within Urgency
Categories 24
SUMMARY
This document is adapted from the English translation of the NAM documents 'Raamplan Bodem
NAM: Algemene bescrijving en Handleiding voor bodembeheer op NAM-lokaties'. (NAM Soil
Framework Plan: General Description and Manual for Soil Management at NAM Locations). The
original translation was issued as EP 93-0341. The work described in this document was done by
NAM to provide a framework for dealing with contaminated sites, focusing on setting priorities for
site remediation. It has been adopted as section EP 95-0387 of the HSE Manual to provide Opcos with
an example of a pragmatic approach to setting priorities for contaminated sites. The practical value of
this work has been demonstrated by the NAM, enabling the company to pursue a scientifically sound
and cost effective approach to site remediation, which is fully endorsed by relevant competent
authorities in the Netherlands. The approach described in this report was developed against a
background of evolving legislation within the Netherlands, both at the national and local level, and
therefore reflects the regulatory regime of that country. However, the underlying principles of the
approach are applicable to all EP Opcos, with a clear focus on risk-based site assessment, coupled
with unequivocal criteria for setting priorities. Indeed, this approach is advocated throughout the
Group for dealing with contaminated soil and groundwater. The report should be interpreted in this
context, building on the principles of risk-based site assessment and the use of clear criteria to set
priorities for site remediation, but with Opcos assessing the relevance of more specific aspects to their
own circumstances. In this context, Opcos should always ensure that any plans they formulate to
address potential soil and groundwater contamination issues are thoroughly discussed and agreed with
local competent authorities. Finally, this report complements EP 95-0385 Environmental Quality
Standards - Soil and Groundwater and EP 95-0386 Monitoring Soil and Groundwater.
1 INTRODUCTION
1.1 Background
The work group in NAM responsible for strategic clean-up and operational criteria were given the
task of drawing up a framework plan for cleaning up contaminated soil at NAM sites, in which
operational decision-making criteria for tackling soil contamination are specified. As part of the
framework of environmental protection, it became evident at the start of the project that a systematic
approach to soil contamination was needed (ie a soil management approach instead of ad hoc clean-
ups).
1.3 The Current Approach and Need for a Soil Framework Plan
The current approach to soil contamination in the Netherlands can be characterised by the fact that
every contaminated site is treated as a separate project. This is also the case for NAM, except that the
various sites are compared systematically with each other. The sequence of steps involved in
assessing contamination is described in Figure 1.1.
In terms of the current approach, the following points should be noted in conjunction with this
sequence:
1. Cross-section surveys have been carried out in all areas and on the basis of these surveys, the
initial situation and the potential contamination sources estimated.
2. Procedures have been drawn up to obtain an individual picture of soil quality at each site. The
exploratory and detailed surveys, clean-up survey/plan and actual clean-up are established phases
of this procedure. The first two phases (the surveys) are carried out fairly uniformly within NAM,
but the remainder are tailored to each site.
3. Each survey phase is followed by a decision step to determine whether or not to proceed with the
next phase and, if so, with what priority.
4. Criteria for the first decision step and prioritisation for detailed surveys were developed in NAM
in 1987. The methodology is based on the source-path-object model. A score is obtained by use
of weighting factors.
5. No instrument is currently available for the second decision step (determining the priority for
clean-up surveys). In practice it has been carried out using qualitative risk assessment and
priorities set on the basis of this evaluation, internal logistics and third-party interests.
6. There is no instrument available for the third decision step and this has been assessed by
individual business units.
The magnitude of the soil contamination problem reveals the following concerns:
1. NAM's implementation is not uniform and consequently decision-making is dependent on local
government.
2. There is no instrument by which to weigh up where and when to carry out a clean-up.
3. There is no instrument to enable soil clean-up operations to be clearly planned and budgeted.
4. The costs of soil clean-up are so high that it is being questioned with increasing urgency whether
these measures are cost effective.
The practical objectives of these principles can be summarised for the different stages as follows:
1. When acquiring a site, establish soil quality by means of a soil survey.
2. For an operating a site, establish the soil quality by means of a soil survey (if not already done in
1 above) and monitor soil quality.
3. For an operating site, avoid soil contamination (eg by impermeable floors to contain leaks,
prompt clean-up in the event of spillages etc).
4. When leaving a site, restore soil quality to an acceptable level.
Soil management is an integral part of site management and should take place with the same degree of
efficiency and effectiveness, including the final process of site restoration.
SUBJECT INFORMATION
Contamination situation zone map and assessment of soil and groundwater contamination
measurements of contaminated soil
contamination concentrations
organic substance
lutum content
concentrations of heavy metals (influence choice of clean-up
method)
measurements of contaminated groundwater
contamination concentrations
pH
EC
chloride
iron and manganese
measurements around the zone (for assessing reliability of extent)
soil air measurements
Hydrological data soil structure
piezometric head measurements and estimate of groundwater flow
interpretation of soil profile
soil permeability (estimate)
seepage/infiltration
regional extractions
Data for risk evaluation use of surroundings
site
surface water
groundwater
Depending on the type of oil, the oil is usually found in the soil, or also in the groundwater
around the soil contamination. The latter is especially the case if aromatics are present in the oil.
chloride contamination in the groundwater (salt)
used chemicals occasionally found as individual contaminants, (eg corrosion inhibitors).
Two types of contamination occur at oil sites:
a heavier oil in the soil, with no oil contaminants in the groundwater
oil and aromatics (whether added or not) with a small quantity of contaminated groundwater
near the soil contamination.
Chloride contamination in the groundwater:
can give rise to problems for plants and can affect freshwater stocks
is difficult to clean up
extraction of groundwater can cause more damage than that caused by the contamination
health risks of chloride contamination are zero.
The aim is to establish the soil quality in the interests of legal liability.
at operating sites (exploratory and detailed surveys and in the event of incidents)
The aim is to determine the risk and collect information relating to future control measures or in
the case of incidents to collect data to aid the immediate removal of the soil contamination.
at abandonment
The aim is to collect data for the removal of the contamination.
For guidance on soil and groundwater surveys see EP 95-0386.
The minimum requirements for the parts of soil surveys to be undertaken at the stages of acquisition,
during operation and at abandonment are summarised in Table 3.2.
Historical survey x x x x
Determination of nature x x x x x x
of contamination
Determination of extent of x x x
contamination
Demonstrate x x x
uncontaminated parts
Investigation into x x x
processing of
contaminated soil
Health risk
Underground infrastructure
Environmental spread
Notes:
1. Oil, condensate and mercury contamination are considered to determine the risk of soil
contamination. On the basis of the present data, glycol, chloride and corrosion inhibitors
produce no or negligible additional risk over and above the first three contaminants.
2. It is assumed that the measurements of mineral oil and VAH (especially BTEX) are a measure
of an oil contamination. Since aliphatic hydrocarbons are not a health risk at the maximum
conceivable exposure arising from the soil contamination, BTEX can be considered as a
yardstick for the risk arising from an oil contamination. The benzene measurement is considered
a yardstick for condensate contamination: it is the most mobile component, the most toxic and is
always present in condensate.
3. Soil-air measurements can aid health risk assessment, since exposure via the air is the
determinative exposure route for condensate. In the supporting report, the soil-air concentrations
are calculated at various soil concentrations.
A remaining problem is the reliability of the monitoring system. There is still insufficient insight into
the relationship between sample representativeness, the observation network density, the sampling
frequency and the reliability of the monitoring system as a whole.
4 RISK EVALUATION
4.2.1 Health
Calculation of exposure
The determining factor for health is the probability of persons being exposed to contaminants in the
soil (the top three metres of soil are the most important) to such an extent that this amounts to a
hazard. Various standards are available for assessing the exposure, although only for a limited number
of substances. By calculating the exposure to a contaminant for a defined behaviour and for a certain
degree of soil contamination, exposure figures can be linked to concentrations in the soil. This
concept has been developed for oil, condensate and mercury with the aid of the HESP exposure model
developed by SIPM (HSE/3).
Assessment of exposure
This framework plan divides the degree of exposure into a number of categories:
daily exposure above the standard applying to the general population
The probability of employees receiving an exposure above the standard is then unacceptably
high.
daily exposure only above the standard in extreme activity scenarios
The probability of employees receiving an exposure above the standard only exists under special
circumstances, such as excavating work.
daily exposure for each scenario below the standard
The probability of employees receiving an exposure above the standard as a result of the soil
contamination is then zero.
no question of exposure
This is made on the basis that there is no contamination in the top three metres of soil.
Exposure levels for establishing health risk are given in Table 4.1.
Exposure level Soil, GW, Soil, GW, Soil, GW, Soil, GW, Soil, GW,
mg/ g/l mg/ g/l mg/ g/l mg/ g/l mg/ g/l
kgdm kgdm kgdm kgdm kgdm
Detection limit 0.2 0.01 0.2 0.01 0.2 0.01 0.2 0.01 0.2 0.2
Attack 125 30,000 115 9000 100 3000 120 3000 6.0 25
Spread implies that the extent of the soil contamination increases. The longer the delay until
action is taken, the higher the ultimate clean-up costs. Measures should be taken to combat
further spread at the earliest stage that is cost effective. Sites can be ranked on the basis of this
principle, with the age of the contamination and the hydrological system playing a major role (a
recent contamination in a regional system will be given higher priority than an old
contamination in a local system).
final restoration of soil quality must not be allowed to become impossible as a result of
spreading
As a general rule of thumb, although spread will be less in a soil of lower permeability, the
clean-up will be more difficult. Cleaning up condensate in a clay or peat layer will be
considerably more complex and therefore more expensive than in a sand layer. It is worth
tackling a contaminated site before the contamination reaches a low-permeability layer.
Sites with soil contamination can be divided into three categories:
present groundwater contamination is unacceptable
This is because the contamination is beyond the fence and immediate action is required.
present groundwater contamination is still within the site
Immediate action is not necessary, but the contamination is spreading to such an extent that the
contaminants will soon pass beyond the fence, or the costs will rise disproportionately due to the
spread. Based on detailed surveys, the groundwater flow speeds and the overall contamination
picture, the decision as to whether these criteria are being met will have to be taken on a site-by-
site basis.
all other cases.
6. Is the concentration in the contamination source higher than the level at which the probability is
great that pure solvents are or have been present in the ground (the Attack level)?
This question should be answered 'yes' if the maximum measured soil concentration or the
average of the groundwater concentrations in the contamination source exceed the
concentrations (O) given in Table 4.1.
7. Do any plastic drinking water pipes (HDPE or PVC) run through the contamination zone?
If the water pipe is metal, this question should be answered 'no'.
8. Is the concentration of the contamination source higher than the level at which volatile aromatic
hydrocarbons could permeate through the drinking water pipe (the ABN-D level)?
This question should be answered in the affirmative if the maximum measured soil
concentration or the average of the groundwater concentrations in the contamination source
exceed the concentrations (D) shown in Table 4.1.
Explanatory note: The ABN-D level is the concentration in the soil at which the standard in
the drinking water could be exceeded by permeation of substances through the drinking water
pipe.
Table 4.1 does not give the ABN-D, the Attack or the ABN-MAC for all substances. This is because
of the chemical properties of the substances. The relevant questions on exceeding these values should
then be answered in the negative.
– Type 1c
Transition system with a non-homogeneous, relatively impermeable cover layer underlain
by a water-bearing layer in a regional infiltration situation.
or local system, with thin, permeable cover layer underlain by a thin, relatively
impermeable layer and thereunder a permeable, water-bearing layer:
– Type 2
Sub regional system with permeable layer up to an average of 20 metres, underlain by a
relatively impermeable layer.
– Type 3
Regional system with a thick permeable layer (20 to 80 m-gs) underlain by a relatively
impermeable layer.
In the case of local systems, 1a and 1b, it is not possible in principle for contaminants to spread
outside the site via the groundwater.
For a more detailed description of the hydrological systems, see Appendix I.
3. Does the groundwater contamination zone extend beyond the fence or is the surface water
outside the fence contaminated?
Even if a contamination has been identified directly beside the fence, this question should be
answered in the affirmative.
4. Will the groundwater contamination zone extend beyond the fence in the future?
The 'future' is here understood to mean within the expected operational life of the site. The
calculation of the time for a zone to reach the perimeter fence is based on the safe assumption
that the contaminants move with the groundwater. For example, if a zone is located at a distance
of 100 metres from the fence and the horizontal flow speed is 20 m/year, it is assumed that the
contaminants will pass the fence in five years. If the contaminants move so fast that the costs
threaten to increase exceptionally, the site may be put in spread category 2, even though there is
no threat of the contaminants getting outside the fence within the site's operational life.
5. Has surface water contamination been observed outside the fence which can be related to site
activities?
This question can be answered in the affirmative if VAH, oil or mercury is encountered in the
ditch water or ditch sludge. NB: it is often not known where this contamination comes from.
Investigating this is the first step in the series of measures to be taken.
6. Is surface water contamination expected in the future as a result of groundwater contamination
at the site?
Depending on the hydrological system, it is possible to estimate which part of the precipitation
excess will finally end up in the surface water. It is also possible to estimate a timescale for this
on the basis of a site sketch. This question is only answered in the negative if there is no surface
water nearby or if control measures are taken on the site to prevent groundwater contamination
ending up in the surface water.
Urgency category 1
priority 1: sites with exposure category 1
All these sites should be dealt with immediately, since here we have an actual risk needing to be
eliminated.
priority 2: sites with spread category 1
– hydrological systems 1c, 2 and 3
1. use of groundwater
2. extent of groundwater contamination
3. surface water load.
– hydrological systems 1a and 1b
1. use of surface water
2. surface water load.
Urgency category 2
Priority setting on basis of expected cost increase per year within the boundary condition of the time
of passing the perimeter.
Urgency category 1a
immediate elimination of the risk
This can be done by protecting the employees concerned or by cutting off the exposure routes,
or alternatively by removing the soil contamination. In the first case, the site will be assigned to
a different urgency category, while in the second case the site will either fall into urgency
category 5 or, not being contaminated, will fall outside the urgency categories.
contaminated groundwater and/or surface water outside the fence
If present, should be immediately removed (see also urgency category 1b). Take such measures
to combat spread of contaminated groundwater and/or surface water within the fence such that it
will not be able to move to or outside the fence in the future (see also urgency category 2).
Urgency category 1b
Groundwater contamination outside the fence should be tackled immediately. In general, this should
be done with the aid of a groundwater extraction system. In most cases, the contamination source will
also have to be removed for reasons of efficiency.
If the surface water outside the fence is contaminated, the following measures will have to be taken:
eliminate the cause of the surface water contamination (either a soil contamination or water
from the site)
removal of any contaminated water or sludge.
Urgency category 2
draw up procedures to prevent a potential hazard resulting from exposure becoming an actual
hazard
For example safety procedures during excavation work (only for urgency category 2a).
prevent groundwater contamination from spreading beyond the fence
The timescale in which a groundwater management system actually has to be set up depends on
local circumstances. The relevant information is derived from the detailed survey and the
subsequent risk evaluation.
Urgency category 3
Draw up procedures to prevent a potential hazard resulting from exposure becoming an actual hazard,
eg safety procedures during excavation work.
column shows the extent of the total zone. The sum of the extent of the various zones is the total
contaminated volume.
6.2.9 Measures
This indicates roughly what measures are necessary and the timescale. This information will be a
summary of a clean-up survey/plan or a management plan.
APPENDIX I
HYDROLOGICAL SYSTEMS
I.1 Introduction
The spread of contaminants in the soil can lead to risks for public health and the environment, damage
to third-party property and an increase in clean-up costs. The spread of contaminants is dependent on
the chemical properties of the contamination, the soil structure and the groundwater flow. An
extensive investigation is needed to gain an insight into the spread of contaminants and the related
risks and costs. Numerous 'location-specific' factors are relevant in such an investigation.
In order to enable a rapid estimate of the order of magnitude of the spread, a classification into
hydrological systems has been made. This classification is discussed in I.3. In I.3 the hydrological
characteristics of nine gas sites are screened on the basis of this classification. According to the results
of this screening, advice is given for the use of the hydrological system classification.
I.2.1 General
The following classification has been developed by NAM and serves as an example. The hydrological
system classification is based on the theory and terminology of hydrological system analysis. Central
to this system analysis is the relationship between the infiltration area where the groundwater enters
the soil and the seepage zone where the groundwater leaves the soil. In the classification of
hydrological systems a similar relationship (but here specifically for the spread of contaminants) is
searched for between the places where the contaminated groundwater enters the soil and where it
subsequently leaves it. Three hydrological systems can be distinguished for the spread of the
contaminants, namely:
local systems
sub regional systems
regional systems.
Depending on the permeability of the cover layer and the regional groundwater flow, three different
local systems can be distinguished:
1a, local system with low-permeability cover layer and regional seepage
1b, local system with high-permeability cover layer and regional seepage
1c, local system with low-permeability cover layer and regional infiltration
(transition to sub regional or regional system possible).
Local systems with a low-permeability layer are generally found in western Holland and the north of
Friesland and Groningen, where the top soil consists of Holocene clay/peat deposits. A local system
may also be present with a high-permeability cover layer (phreatic water-bearing layer) in
combination with a regional seepage situation. The seepage flow 'forces' the groundwater that had
infiltrated on the site to flow away to the surrounding ditches.
A characteristic of all local systems is the radial run-off of the groundwater to the site ditches and/or
perimeter ditches. The radial flow is the result of a convex groundwater table between the ditches
such that the groundwater flows radially away from the centre of the site to the nearest ditch.
In local systems with a regional seepage situation (la and 1b), some or all of the contaminated
groundwater can be 'trapped' between the local infiltration flow and the regional seepage flow. This
gives rise to stagnant groundwater, that hardly spreads any further.
In local systems with regional infiltration, in addition to the radial flow to the ditches some of the
contaminated groundwater can flow from the low-permeability cover layer to the deep water-bearing
layer. Thus the local spreading can change over to a sub regional or regional spreading (hydrological
system 2 or 3, see I.2.3 or I.2.4 respectively).
The spreading of contaminants in a low-permeability clay and peat layer proceeds relatively slowly
due to the specific soil characteristics of these layers. However, these same soil characteristics make
decontamination a costlier, lengthier and more complex process than a clean-up in a sand layer.
Despite a low spreading speed and possibly lower risks, a timely clean-up of the contaminants may be
desirable.
Once the contaminated groundwater is removed via the ditches, the quantity of contaminated
groundwater will not increase any further. Spreading risks associated with local systems are therefore
mainly limited to public health and environmental risks that can arise by contamination of the surface
water (eg watering of cattle).
The contaminated groundwater will finally end up in the surface water of a sub regional seepage area.
The contaminated groundwater might also be extracted by a well. There is not much chance of this,
however, since the permeability of the water-bearing layer is often too low for the extraction of large
quantities of groundwater. Small-scale groundwater extractions for irrigation are, however, possible.
As well as the spread of contaminants via the sub regional groundwater flow, contamination of the
local surface water (site and ring ditches) can also occur. Because the sites are often filled and are thus
higher than the immediate vicinity, radial run-off to the ditches may also occur. This is particularly
likely if the low-permeability layer is situated not far below the surface. In the case of a very shallow
low-permeability layer (eg 3 m below the surface), the contaminated groundwater might run off
mainly radially to the ditches, so that it would seem as if it were a local system (compare with
hydrological system 1b, see I.2.2).
The spreading of contaminants in a sub regional system can lead to damage and/or risk from:
spreading beyond the site boundaries
contamination of surface water (local and sub regional)
extra clean-up costs due to increased quantity of contaminated groundwater.
I.3.1 General
To assess the usefulness of the hydrological system classification, the spread of contaminants at nine
NAM gas sites was examined in detail. The groundwater contamination situation at gas sites is
generally a function of the presence of volatile aromatic hydrocarbons (condensates). For benzene,
which is very mobile, it can be assumed that it moves at the same speed as the groundwater. As well
as the usefulness of the hydrological systems, the relationship between the volume of contaminated
groundwater and the age of the site was also examined.
The main hydrological characteristics of the gas sites are briefly discussed in the following
paragraphs. The findings of the detailed study of the hydrological system and the contamination
pictures of the gas sites are summarised in Table I.1.
The situation at the Dalen 2 gas site is a transition from a local system (1c) to a regional system. The
contamination has penetrated through the clay-loam layer and ended up in the deep water-bearing
layer. The average increase in the volume of contaminated groundwater is about 2000 m 3/year. It may
be expected that the volume of contaminated groundwater will increase considerably quicker in the
future because spreading will take place in three dimensions.
Key:
= urgency classification according to framework plan
= hydrological system according to framework plan classification
= use of groundwater around the site (water catch. = water catchment area; curr. use
= current use of groundwater; pot. use = potential use of groundwater; nature =
groundwater of importance for nature reserve).
= amount of contaminated groundwater in m3 as reported in detailed survey
= amount of contaminated soil in m3 as reported in detailed survey
= use of the surface water around the site (w. cat. = surface water used for watering
cattle; irrig. = surface water used for irrigation of agricultural area; curr. use =
surface water is used for other purposes; nature = groundwater of importance for
nature reserve).
= annual quantity of contaminated groundwater that could reach the surface water.
= costs calculated according to the formula from the framework plan (costs of
contaminated mercury soil at Tietjerk 200, Vries 3, Spitsbergen 2 and Eemskanaal
are not included).
= clean up costs can vary between ƒ 122,000 and ƒ 1,650,000.
APPENDIX II
SAMPLE PROFORMA FOR SOIL INFORMATION SYSTEM
Table II.1 Sample proforma for soil information system
Data Project data Units Information source
total
8 Urgency category
Base monitoring
Specific monitoring
Soil survey
Control measures
ABBREVIATIONS
ABN Actual exposure level (measured or calculated) at a given soil concentration
of a specific substance.
ABN-TDInorm Soil concentration at which the exposure level exceeds the total daily intake
(TDI) for a normal scenario at an industrial site.
ABN-TDIspec Soil concentration at which the actual exposure level exceeds the total daily
intake (TDI) for a special scenario at an industrial site.
attack Calculated soil concentration at which cables and piping may be attacked.
ABN-D Soil concentration at which drinking water contamination due to permeation
through HDPE piping is possible.
ABN-MAC Soil concentration at which the MAC value (maximum acceptable
concentration in the air in a work situation) is possible.
BSB Soil clean-up at (existing) industrial sites.
Oele Com. (BSB com.) committee consisting of representatives from government and
industry which has studied ways of tackling soil contamination on existing
industrial sites in the Netherlands.
BTEX Benzene, toluene, ethylbenzene and xylenes. These are the determinative
substances for volatile aromatic hydrocarbons.
m-gs Metres below ground surface.
mg/kg dm mg/kg dry mix.
g/l Microgram per litre: the usual unit for concentrations of contaminating
substances in ground water.
NEN Netherlands Standard, as issued by the Netherlands Standards Institute.
TDI Total Daily Intake: intake of substances in an acceptable amount.
Comparable with the official ADI (Acceptable Daily Intake).
RIVM Dutch Governmental Institute for Environmental Hygiene.
GLOSSARY
A glossary of commonly used terms in HSE is given in both EP 95-0100 HSE Management Systems
and EP 95-0300 Overview Hazards and Effects Management Process.