4.The vendor should submit compliance to the Specifications with authorized seal and
signature on the documents.
6. Delivery schedule.
9. Acceptance to BEL's std. LD clause (0.5% per week to a maximum ceiling of 10% of
value of material for delayed supplies) in bid response.
12.Payment term: 100% payment within 30 days of receipt and acceptance of material at
BEL Bangalore.
13. The material will be considered as received only after the receipt of all relevant
documents mentioned in the Purchase order. BEL reserves the right to reject the materials
for non-receipt of the documents mentioned in the PO.
14.PBG : Vendor to be submitted PBG for 10% of the PO value till the completion of
warranty period. ( Format is enclosed along with bid documents)
15.Integrity pact : If the quotation value is more than Rs 300 L, duly signed and stamped
Integrity pact to be submitted along with the quote on your letter head or regular paper. (
Format is enclosed along with bid documents)
16. Indigenous content declaration: Vendors are mandatorily required to submit the
indigenous content is the format provided. Vendors to go through the purchase preference
circular (attached in the bid) for submission of the declaration.