Nama : NOFRY HENCE TARUMASELY

NIM : 7100190112
Kelas : 04
Tugas : 3 Perpetaan

PEMBACAAN RAMBU
JARAK TTITIK
TITIK + A3A3:G29 Belakan KET.
Detail Muka (M) TINGGI
g
(BM-1) 3,093 46 523,427
1 2,855 38 523,665
2 0,989 30 525,531
3 1,983 22 524,537
4 1,312 18 525,208
5 T1 = 1,52 525
6 1,128 28 525,392
7 2,166 36 524,354
8 1,568 44 524,924
9 3,416 48 523,104
10 2,897 50 523,623
(BM-2) 1,498 54 525,022
(BM-2) 1,236 44 524,798
11 2,562 38 523,696
12 0,379 32 525,879
13 3,251 25 523,007
14 3,373 20 522,885
15 T2 = 1,46 524,798
16 1,342 15 524,916
(BM-3) 2,604 26 523,684
(BM-3) 0,778 25 524,406
17 0,366 15 525,540
18 T3 = 1,50 524,406
19 1,189 16 524,016
20 3,403 25 522,503
 Perhitungan :

Elevasi T5 = 525 m
Ti = 1,52 m

a. BM1 = 3,093
ΔT5 – BM1 = 1,52 – 3,093 = -1,573
Elevasi BM1 = 525 + (-1,573)
= 523,427 m

- T1 = 2,855
ΔT5 – T1 = 1,52 – 2,855 = -1,335
Elevasi T1 = 525 + (-1,335)
= 523,665 m

- T2 = 0,989
ΔT5 – T2 = 1,52 – 0,989 = 0,531
Elevasi T2 = 525 + 0,531
= 525,531 m

- T3 = 1,983
ΔT5 – T3 = 1,52 – 1,983 = -0,463
Elevasi T3 = 525 + (-0,463)
= 524,537 m

- T4 = 1,312
ΔT5 – T4 = 1,52 – 1,312 = 0,208
Elevasi T4 = 525 + 0,208
= 525,208 m

- T5 = 525 m

- T6 = 1,128
ΔT5 – T5 = 1,52 – 1,128 = 0,392
Elevasi T5 = 525 + 0,392
= 525,392 m

- T7 = 2,166
ΔT5 – T7 = 1,52 – 2,166 = -0,646
Elevasi T7 = 525 + (-0,646)
= 524,354 m

- T8 = 1,568
ΔT5 – T8 = 1,52 – 1,568 = -0,048
Elevasi T8 = 525 + (-0,048)
= 524,952 m
- T9 = 3,416
ΔT5 – T9 = 1,52 – 3,416 = -1,896
Elevasi T1 = 525 + (-1,896)
= 523,104 m

- T10 = 2,897
ΔT5 – T10 = 1,52 – 2,897 = -1,377
Elevasi T1 = 525 + (-1,377)
= 523,623 m

- T1 = 2,855
ΔT5 – T1 = 1,52 – 2,855 = -1,335
Elevasi T1 = 525 + (-1,335)
= 523,665 m

b. BM2 = 1,498 (dari T5)


ΔT5 – BM2 = 1,52 – 1,498 = 0,022
Elevasi BM2 = 525 + 0,022
= 525,022 m

- BM2 = 1,236 (dari T5i)


ΔTi5 – BM2 = 1,236 – 1,46 = -0,224
Elevasi BM2 = 525,022 + (-0,224)
= 524,798 m

- T11 = 2,562
ΔTi5 – T11 = 1,46 – 2,562 = -1,102
Elevasi T11 = 524,798 + (-1,102)
= 523,696 m

- T12 = 0,379
ΔTi5 – T12 = 1,46 – 0,379 = 1,081
Elevasi T12 = 524,798 + 1,081
= 525,87 m

- T13 = 3,251
ΔTi5 – T13 = 1,46 – 3,251 = -1,791
Elevasi T13 = 524,798 + (-1,791)
= 523,007 m

- T14 = 3,373
ΔTi5 – T14 = 1,46 – 3,373 = -1,913
Elevasi T14 = 524,798 + (-1,913)
= 522,885 m
- T15 = BM2 (dari Ti5) = 524,798 m

- T16 = 1,342
ΔTi5 – T16 = 1,46 – 1,342 = 0,118
Elevasi T16 = 524,798 + 0,118
= 524,916 m

- BM3 (dari Ti5) = 2,604


ΔTi5 – BM3 = 1,46 – 2,604 = -1,114
Elevasi BM3 = 524,798 + (-1,114)
= 523,684 m

- BM3 (dari Ti8) = 0,778


ΔTi8 – BM3 = 1,50 – 0,778 = 0,722
Elevasi BM3 = 523,684 + 0,722
= 524,406 m

- T17 = 0,366
ΔTi8 – T17 = 1,50 – 0,366 = 1,134
Elevasi T17 = 524,406 + 1,134
= 525,54 m

- T18 = BM3 (dari T18) = 524,406 m

- T19 = 1,189
ΔTi8 – T19 = 1,50 – 1,189 = -0,39
Elevasi T19 = 524,406 + (-0,39)
= 525,016 m

- T20 = 3,403
ΔTi8 – T20 = 1,50 – 3,403 = -1,903
Elevasi T20 = 524,406 + (-1,903)
= 522,503 m