You are on page 1of 4

Multi-Variable Predictive Controller for Bauxite Milling

H.M. Green1*, S.W. Powell2


1 Process Engineering, Rio Tinto Aluminium, Yarwun
2 Process Control, Rio Tinto Aluminium, Yarwun
Corresponding author: Hasting.Green@RioTinto.com

ABSTRACT
Rio Tinto Yarwun refinery has developed a multi-variable predictive controller (MPC) for optimising our
bauxite milling circuit. The controller was initially developed prior to commissioning Yarwun Refinery’s
major expansion in 2012 in response to the greatly increased milling capacity utilisation requirements of
the expanded refinery. Configured using Honeywell’s Profit platform, the application has proved an
effective way to control mill rates and operation so that the plant can be operated up to constraints at all
times.
In addition to delivering higher milling throughput, the MPC has been further developed to deliver
additional layers of optimisation. This has included optimisation between bauxite mills, assisting in
refinery volume management, and optimising the use of different bauxite grades.

1. INTRODUCTION
Yarwun refinery has an extensive advanced
process control application deployment
incorporating 13 multi-variable predictive
controllers (MPCs). This paper outlines a case
study of the development, maintenance, and
benefits of one of these MPCs which is used
for optimising and controlling the bauxite ball
mills. First developed in 2011/12 to address
an expected production bottleneck from a
refinery expansion – the bauxite mill MPC has
proved a robust control solution and a flexible
foundation for further optimising the area.
2. PROJECT IMPLEMENTATION Figure 1. Mill Process Overview
2.1 Background The Yarwun Stage 2 expansion lifted refinery
The first stage of Yarwun Refinery had a nameplate to 3.4 MTPA but only added one
nameplate of 1.4 MTPA and was supported by additional identical bauxite mill. This required
two closed circuit bauxite ball mills. Each mill mill utilisation and throughput per mill to be
is feed with bauxite at a controlled rate from a increased substantially from historic rates (for
bauxite stockpile by conveyor. The bauxite is example, 0.7 MTPA alumina per mill to 1.13
wet ground with digestion liquor and grinding MTPA alumina per mill). Due to concern that
media. The overflow of the mill is pumped this may become a refinery bottleneck, a
across two vibratory wet screens. The screen project was initiated to build an MPC controller
undersize material reports to a tank which is with the objective of maximising mill rates.
pumped to the slurry storage area while the Figure 2 shows relevant equipment during
screen oversize material is recycled to the feed stage 2 construction – the existing and new
chute of the mill. This arrangement for one bauxite mills can be seen in the foreground
mill is shown in Figure 1. with the bauxite stockpiles. The new and old
digestion units are to the left and right of the
photo respectively.
progressed following a typical MPC
development methodology.
Data collection and site survey were
completed in December 2011 with a main
deliverable being a Functional Design
Specification. This phase included reviewing
process flows, objectives and operating
performance; specification of control system
calculations and tuning of required base level
regulatory control strategies.
Detailed design was completed in February
2012. Deliverable being a controller platform
Figure 2. Yarwun Refinery Oct 2010
with initial seed models and step testing plan.
2.2 Project Scope Step testing was completed in 3 shifts in late
Project scope was intentionally limited to one February 2012. Traditionally, model
mill with focus on delivery time and addressing development is done from either first principles
the main optimisation concern – bauxite or open loop step testing. These methods can
throughput. Optimisation of rates between be time consuming and, in the case of open
Mills (e.g. power consumption etc.) was loop step testing, expose the process to large
considered but excluded from scope as it was disturbances and out of control operation.
not a primary concern in the context of the This project was the first time Yarwun Refinery
refinery expansion. The objectives of the MPC has used Honeywell Profit Stepper software
controller are summarised as below: for model identification. This software allows
• Process Objectives: an MPC to operate with seed models under
closed loop control while perturbing the
1. When running Mill-limited, maximise process with numerous small manipulated
the throughput of the mill variable movements. Process response is
captured to allow model identification and
2. When not Mill-limited, must match refinement. The advantages were that it could
process demand (Slurry storage tank be completed quickly, with limited input from
at 90%) operators or disturbance to the process.

• Control Objectives: Final Mill 2 controller build and commissioning


was completed in March 2012. The
1. Avoid Mill trips application was then replicated for use on Mill
1 and 3.
2. Control slurry density to slurry storage
tank within specific range

3. Honour constraints (for example, total 3. FURTHER DEVELOPMENT


recycle flow, tank levels) 3.1 Merging of Individual MPCs

• Excluded: The three individual mill MPCs developed in


2012 were effective at maximising bauxite
1. Grind size: irregular lab throughput. However, they were ineffective at
measurements, no on-line estimation handling common constraints such as slurry
tank level. Typically when mill capacity was
2. Mill power: Site experience had shown not a refinery limit, the slurry storage tanks
this was a concern only if mill density would be filled to their maximum level and
is far off-specification oscillation would be observed in mill rates and
slurry storage level. This was because each
2.3 Project Delivery
MPC took its own independent actions to
Honeywell Advanced Solutions Asia Pacific honour a high slurry storage level constraint.
was engaged to deliver the application as the
Each MPC plans its manipulated variable
available in-house resources were being
moves based on its modelled control variable
utilised to support the expansion.
responses and constraints. With three MPCs
The project was carried out between operating and planning moves independently -
December 2011 and March 2012 and predicting and controlling common constraints
was ineffective as planned manipulated
variable movements were unavailable to the 3.4 Bauxite Grade Utilisation Optimisation
other MPCs. The solution to this problem was
Plant flowsheet changes towards the end of
to change the structure of the MPCs so that all
2017 required differentiation in duty of the
three mills were controlled by a single MPC
three bauxite mills. A high gibbsite grade
rather than three independent MPCs. This
bauxite was processed through one mill and
allowed common controlled variables to be
kept separate from the mono grade bauxite
correctly modelled against predicted
being processed on the other two mills.
manipulated variable moves across all mills.
Excess high gibbsite bauxite slurry is used to
Making this change to merge the MPCs to one top-up the mono slurry to make up volume in
platform was effective at reducing slurry the mono slurry tanks as required.
storage tank level oscillation and allowed
Modification of the MPC to achieve different
optimisation on common constrains to be
process objectives such as maximising one
configured. A learning was that this extra effort
bauxite grade relative to the other has been
could have been avoided if more consideration
greatly simplified due to the use of the existing
was given to the design of common constraints
controller structure compared with
when first building the MPC.
incorporating such a change into a traditional
3.2 Mill Slurry Liquor Optimisation regulatory control strategy.
An opportunity was identified in 2014 to adopt
an alternative operating mode in the Bauxite
4. MAINTENANCE
milling area. Some ullage in the slurry storage
tanks could be utilised for liquor inventory Minimal maintenance has been required for
management during periods of very high the Mill MPC Profit Controller.
refinery liquor inventory. The desired
The issues so far have been minor and only
operating strategy was to limit output density
such that slurry storage tanks were holding exposed through higher production rates over
proportionally higher liquor during these time. These include:
periods. The flexibility of the MPC controller • The impact of the Mill flushing on the slurry
allowed this strategy to be easily implemented tank levels
by simply changing the controller’s objective
optimisation equation depending upon refinery • Minor improvements to the process
volume management requirements. models.

This simple example is mirrored across the • Mill feed rate of increase when the
refinery where it has often been found that manipulated variables have a rate of
operating strategy changes can often be change limit.
achieved by subtle changes in existing MPC
optimisation settings.
5. BENEFITS
3.3 Mill Prioritisation
The MPC has proved over time to be a reliable
A multitude of reasons exist for wanting to and robust method for controlling and
favour rates through one mill relative to optimising Yarwun Refinery’s bauxite ball
another. These could include: mills. When initially commissioned the mill
• Referencing rates away from a mill with an MPC was credited with achieving a capacity
operational issue that doesn’t have online increase of 7.5%. Despite the complex
measurement dynamics of a recycling process, the model
was able to optimise the mill within the
• Trying to preferentially consume from a constraints.
bauxite stock pile.
High utilisation rates approaching 100%
• Favouring a mill that has more reliable (Figure 3) and broad acceptance by plant
instrumentation. operators have been achieved.
The MPC allows this type of biasing to be Some manipulated Variables (MVs) limits ae
easily achieved by simply changing the relative sometimes set incorrectly and can
optimisation values of manipulated variables unnecessarily constrain the operation of the
on each mill. Operator interfaces were equipment and as a result are dropped from
developed to allow flexibility in manipulating the model. The ongoing challenge is the
relative Mill optimisation settings so that rates setting/maintaining of constraint limits that are
through one or another mill can be favoured to real.
take advantage of some unmeasured variable.
Figure 3. Bauxite Mill MPC utilisation (12
months)

6. CONCLUSION
The bauxite milling MPC has been a
successful control change for Yarwun
Refinery. Benefits have included higher
throughput capacity, flexibility and reliability.
Automation of model identification (i.e. use of
Honeywell Profit Stepper software) was
effective for reducing model identification time
and allow closed loop control while performing
identification.
Rework and redesign can be avoided with
greater consideration for future optimisation
objectives and how controller structure will
achieve these.

You might also like