1. The ______________________ shall specify the procedure and format to be


followed in the preparation of the Electrical Diagrams for any Connection Point.
a) Energy Regulatory Commission
b) Universal Charge
c) Transmission Network Provider
d) National Power Corporation
Answer: c) Transmission Network Provider (Reference Page: 68)
2. The User shall prepare and submit to the Transmission Network Provider an
____________ for all the Equipment on the User’s side of the Connection Point,
in accordance with the schedule specified in the Connection Agreement or
Amended Connection Agreement
a) Electrical Diagram
b) Stranded Contract Costs
c) Distribution of Electricity
d) Lifeline Rate
Answer: a) Electrical Diagram (Reference Page: 68)
3. The Electrical Diagrams shall provide an accurate record of the layout and circuit
connections, ratings and identification of Equipment, and related apparatus and
devices at the __________________.
a) Connection Point
b) Disconnection Point
c) Site
d) None of the above
Answer: a) Connection Point (Reference Page: 68)
4. The __________ of the Electrical Diagram shall include the names of authorized
persons together with provisions for the details of revisions, dates, and
signatures.
a) Title page
b) Title block
c) Front page
d) None of the above
Answer: b) Title block (Reference Page: 68)
5. The composite Electrical Diagram prepared by the Transmission Network
Provider or the User, in accordance with the provisions of _________, shall be
the Electrical Diagram to be used for all operation and planning activities
associated with the Connection Point.
a) GCR 4.7.1
JAN MICHAEL B. CASTANEDA
5-EE
b) GCR 4.8.1
c) GCR 4.9.1
d) None of the above
Answer: c) GCR 4.9.1 (Reference Page: 69)
6. What is the title of GCR 4.9?
a) CONNECTION POINT DRAWING REQUIREMENTS
b) ELECTRICAL DIAGRAM REQUIREMENTS
c) GRID DATA REGISTRATION
d) GRID PLANNING RESPONSIBILITIES AND PROCEDURES
Answer b) ELECTRICAL DIAGRAM REQUIREMENTS (Reference Page: 68)
7. What is the title of GCR 4.10?
a) CONNECTION POINT DRAWING REQUIREMENTS
b) ELECTRICAL DIAGRAM REQUIREMENTS
c) GRID DATA REGISTRATION
d) GRID PLANNING RESPONSIBILITIES AND PROCEDURES
Answer a) CONNECTION POINT DRAWING REQUIREMENTS (Reference
Page: 69)
8. GCR 4.10.1.2 states that the User shall prepare and submit to the Transmission
Network Provider the ____________ for the User’s side of the Connection Point,
in accordance with the schedule specified in the Connection Agreement or
Amended Connection Agreement.
a) Costs
b) Universal Charge
c) Electrical Plan
d) Connection Point Drawing
Answer: d) Connection Point Drawing (Reference Page: 69)
9. This states that the Transmission Network Provider shall provide the User with
the Connection Point Drawing for the Transmission Network Provider’s side of
the Connection Point, in accordance with the schedule specified in the
Connection Agreement or Amended Connection Agreement.
a) GCR 4.10.1.2
b) GCR 4.10.1.3
c) GCR 4.10.1.4
d) GCR 4.10.1.5
Answer: b) GCR 4.10.1.3 (Reference Page: 69)
10. The Connection Point Drawing shall be prepared using the Site and Equipment
Identification prescribed in _________. The current status of the Equipment shall
be indicated in the drawing.
JAN MICHAEL B. CASTANEDA
5-EE
a) GO 6.11
b) GO 6.12
c) GO 6.13
d) GO 6.14
Answer: c) GO 6.13 (Reference Page: 70)
11. This states that the title block of the Connection Point Drawing shall include the
names of authorized persons together with provision for the details of revisions,
dates, and signatures.
a) GCR 4.10.2.1
b) GCR 4.10.2.2
c) GCR 4.10.2.3
d) GCR 4.10.2.4
Answer: c) GCR 4.10.2.4 (Reference Page: 70)
12. What is the title of GCR 4.11?
a) CONNECTION POINT DRAWING REQUIREMENTS
b) ELECTRICAL DIAGRAM REQUIREMENTS
c) GRID DATA REGISTRATION
d) GRID PLANNING RESPONSIBILITIES AND PROCEDURES
Answer c) GRID DATA REGISTRATION (Reference Page: 70)
13. The data relating to the Connection Point and the User Development that are
submitted by the User to the Transmission Network Provider shall be registered
according to the following data categories:
(a) Forecast Data;
(b) Estimated Equipment Data; and
(c) Registered Equipment Data.
a) (a) and (b)
b) (a) and (c)
c) (b) and (c)
d) (a), (b), and (c)
Answer: d) (a), (b), and (c) (Reference Page: 70)
14. The Estimated Equipment Data shall contain the User’s best estimate of the
values of parameters and information about the Equipment for the _______
succeeding years.
a) 3
b) 4
c) 5
d) 6
Answer: c) 5 (Reference Page: 71)
JAN MICHAEL B. CASTANEDA
5-EE
15. The data relating to the Connection Point and the User Development that are
submitted by a User applying for a Connection Agreement or an Amended
Connection Agreement shall be registered in _______ stages.
a) 3
b) 4
c) 5
d) 6
Answer: a) 3 (Reference Page: 71)
16. The ___________________ shall contain validated actual values of parameters
and information about the Equipment that are submitted by the User to the
Transmission Network Provider at the connection date. The Registered
Equipment Data shall include the Connected Project Planning Data, which shall
replace any estimated values of parameters and information about the
Equipment previously submitted as Preliminary Project Planning Data and
Committed Project Planning Data.
a) Registered Equipment Data
b) Universal Charge
c) Electrical Plan
d) Connection Point Drawing
Answer: a) Registered Equipment Data (Reference Page: 71)
17. The Estimated Equipment Data shall be updated, confirmed, and replaced with
validated actual values of parameters and information about the Equipment at
the time of connection, which shall become the Connected Project Planning
Data. These data shall be registered in accordance with the categories specified
in ________________ and shall be used in evaluating other applications for Grid
connection or Modification of existing Grid connection and in preparing the
Transmission Development Plan.
a) GCR 4.11.4
b) GCR 4.11.3
c) GCR 4.11.2
d) GCR 4.11.1
Answer: d) GCR 4.11.1 (Reference Page: 71)
18. One purpose of Chapter 5 is to specify the technical studies and planning
procedures that will ensure the safety, Security, Reliability, and Stability of the
__________.
a) Plan
b) Grid
c) Plant
d) User
JAN MICHAEL B. CASTANEDA
5-EE
Answer: b) Grid (Reference Page: 72)
19. What is the title of GP 5.2?
a) CONNECTION POINT DRAWING REQUIREMENTS
b) ELECTRICAL DIAGRAM REQUIREMENTS
c) GRID DATA REGISTRATION
d) GRID PLANNING RESPONSIBILITIES AND PROCEDURES
Answer d) GRID PLANNING RESPONSIBILITIES AND PROCEDURES
(Reference Page: 72)
20. The _______________ shall plan and design transmission control devices to
meet the system performance requirements as defined in Chapter 3 PST. These
devices shall be coordinated with other control devices within a Grid and, where
appropriate, with neighboring Grids.
a) Market Operator
b) System Operator
c) Both a and b
d) None of the above
Answer: b) System Operator (Reference Page: 72)
21. The Forecast Data shall contain the User’s best estimate of the data, including
Energy and Demand, being projected for the __________ succeeding years.
a) 3
b) 4
c) 5
d) 6
Answer: c) 5 (Reference Page: 73)
22. A ___________ shall be performed to evaluate the behavior of the Grid for the
existing and planned Grid facilities under forecasted maximum and minimum
Demand conditions. It shall also be performed to study the impact on the Grid of
the connection of new Generating Plants, Loads, substations or transmission
lines.
a) Steady-State Stability Analysis
b) Transient Stability Study
c) Short Circuit Study
d) Load Flow Study
Answer: c) Load Flow Study (Reference Page: 76)
23. A _________ shall be performed to evaluate the connection of new Generating
Plants, transmission lines, and other facilities that will result in increased fault
duties for Grid Equipment. This study shall identify the Equipment that could be
permanently damaged when the current exceeds the design limit of the
JAN MICHAEL B. CASTANEDA
5-EE
Equipment such as switchyard devices and substation buses. This study shall
also identify the Circuit Breakers, which may fail when interrupting possible short
circuit currents
a) Steady-State Stability Analysis
b) Transient Stability Study
c) Short Circuit Study
d) Load Flow Study
Answer: c) Short Circuit Study (Reference Page: 76)
24. A __________ shall be performed to verify the impacts of the connection of new
Generating Plants, transmission lines, or substations and changes in Grid circuit
configurations on the ability of the Grid to seek a stable operating point following
a transient disturbance.
a) Steady-State Stability Analysis
b) Transient Stability Study
c) Short Circuit Study
d) Load Flow Study
Answer: c) Steady-State Stability Analysis (Reference Page: 76)
25. A three-phase short-circuit study shall be performed for all nodes of the Grid for
different feasible generation, ___________, and system circuit configurations. A
single phase short-circuit study shall also be performed on critical Grid nodes.
These studies shall identify the most severe conditions that the Grid Equipment
may be exposed to.
a) Demand
b) Plan
c) Supply
d) None of the above
Answer: a) Demand (Reference Page: 76)