Professional Documents
Culture Documents
Jewalikarsir Paper On Bus Bar Prot PDF
Jewalikarsir Paper On Bus Bar Prot PDF
FAULT
Fig 2: Present practice of Z3 usage
The gravity of this situation can be reduced to a large extent
if bus coupler / bus sectionalizer breaker can be opened before
any Zone 2 operation takes place. This can be achieved by use
Zone 2 Trip Zone 2 Trip of reverse zone available with numerical distance protection
relays. The necessary configuration & settings are discussed
here. The suggested scheme is applicable to following bus
Fig 1: Non operation of busbar protection. configurations.
1. 2 Main + 1 Aux. bus with bus coupler breaker.
Practices for enhancing reliability of Busbar protection: 2. 1 Main + 1 Aux. bus with Main bus divided in two sections
For enhancing the reliability of busbar protection; following with sectionalizer breaker.
practices are adopted. 3. 1 Main bus with sectionalizer breaker.
1. Main and check zones in busbar protection. By way of opening the bus coupler before any Zone
2 operation; the bus fault will be limited the faulty bus section.
Author is working as Deputy Executive Engineer (Testing) at 400 kV This fault will be eventually cleared by the remote Zone 2
Girwali substation of MSETCL .
403
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
protections of the lines; transformer / generator backup & 5) This output contact will be used to trip bus coupler /
protections connected to that bus section only. (Ref. Fig 3) sectionalizer breaker.
Stage 2: The stage 2 will be from the operation of the reverse
zone element set to a time delay of more than zone2 time.
Zone 2 Trip
With currently adopted timings for 400 kV lines as discussed
Reverse zone of
above; it can be set to 400 mS. This will be used to trip the
line own breaker of the protected line.
Reverse Zone Stage 1 ---------- Trip Bus coupler.
T = 200 mS
Reverse Zone Stage 2 ---------- Trip line breaker of protected
line.
The stage 1 will trip the bus coupler breaker and isolate the
faulty section. The fault will now be cleared by the remote end
Zone 2 Trip distance protections in Zone 2 or the T/F and generators
connected to the faulty section only. If any of the remote lines
fails to trip till the stage 2 operation; stage 2 will trip the line
Figure 3: Reverse zone suggested usage breakers at local end.
Requirements of the scheme: If the fault remains till the time of stage 2 operation a
1. Time: thought can be given to initiate tripping of faulty bus section
1. Bus coupler breaker should open before any remote Zone 2 totally(i.e. along with transformers and generators) instead of
operation. waiting for their backup protection operation.
2. Bus coupler trip should not be initiated before Zone 1 fault A logical representation of the scheme is shown in
clearance time. following diagram.
3. The bus coupler trip should not initiate the LBB (50Z) of
line protected by the distance protection from which the
Reverse Zone Start Timer
bus coupler trip is obtained. (200 mS)
2. Impedance:
1. The reverse zone always must cover the local bus
completely.
2. The reverse zone should never encroach into Zone 2 of any AND Reverse Zone
of the lines connected to the bus. LOGIC Stage 1 trip
3. The reverse zone can be set to cover 10% of protected line
impedance.
4. A setting of 20% of shortest line impedance can be used for
all lines where a short and a long line are connected to the Reverse Zone Trip (T=400mS) Reverse Zone Stage 2 trip
same bus.
Considering these requirements a two stage configuration of Figure 4: Reverse zone 2 stage operation logic.
reverse zone is suggested.
Two stage reverse zone
1. Numerical distance relays are having separately settable
The reverse zone stage1 operation logic is like creating a
impedance zones for reach as well as direction.
new zone of operation inside the relay.
2. The reverse zone impedance to be set to cover the bus fault.
The impedance setting to be adopted as per the Trip protected line
Any forward zone trip OR
requirements discussed above. A fixed impedance so as to LOGIC
breaker
cover the bus can also be thought over in this case for all Reverse Zone Stage 2 trip
Start LBB of
the lines connected to the bus. protected line
3. A two stage trip is to be obtained from this reverse zone
element.
Reverse Zone Stage 1 trip Trip bus coupler
4. Stage 1: The reverse zone stage 1 will be obtained as breaker
below.
The reverse zone start signal will be used to start an internal Start LBB of Bus
timer. The timer will be set to less than Zone2 time setting of Coupler
404
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
included applying faults through the kit and replaying of ii. Zone 2= 400 mS
actual fault records. The relay was set to real line settings of iii. Zone 3 = 700 mS to 1 S
one of the lines in the MSETCL 400 kV network. b. Reverse Zone timings suggested
i. Stage 1 = 250/300 mS
Rev Zone Start Timer T=200mS ii. Stage 2 = 500/600 mS
Z4
200 Check: For a Zone 1 fault in 30% of line section the fault
DDB #195 Pick-Up
0 clearance time with only back up protection in service should
0
Z4 & Pick-Up Relay Label 08
DDB #007
be less than the stage1 trip time of reverse zone used to trip
DDB #195 0
the bus coupler.
Rev Zone Start Trip Bus Coupler Configuration possibilities and LBB:
The numerical relays are providing lot of flexibility for
Figure 6: Reverse Zone stage 1 logic as implemented their configuration. Different logical formations can be
in Micom P442 possibly configured in the relay to achieve the same functional
behavior. The functional behavior of the numerical relays is
always a combination of its logic configuration and settings
The possibility of having similar configuration with REL adopted.
521 relay is also verified. Some possibilities while configuring & setting the relay for
Implementation: The possibilities of configuration and adoption of this busbar backup scheme are discussed below.
checks required are discussed in view of present protection In this the logical formation shown in the logic diagram (Fig.4
practice of 400 kV & 220 kV lines. & 5) above to initiate the stage 1 is referred as ‘new zone’ and
Case 1: 400 kV Substation where two distance protections reverse zone of the relay is referred as ‘reverse zone’.
(Main1 & Main2) are provided on all lines. 1. New Zone = Stage 1 & Reverse Zone = Stage 2
Following situations are considered for this case. a. This is as shown in the logic diagram (Fig.4 & 5) and
1. Both numerical protections on line: Following possibilities described already. This is the recommended
exists in this case. configuration.
a. The reverse zone stage 1 and stage 2 tripping can be 2. New Zone = Stage 2 & Reverse Zone = Stage 1
separately obtained from each of the relays. It is essential In this case following precautions are essential.
in this case that the reverse zone stage 1 trip should not a. The stage 1 trip needs to be disconnected from all
initiate the LBB protection. general trip conditions inside the relay.
b. Only one of the protections can be used for a two stage b. The stage 1 trip should not initiate the internal or
reverse zone. external LBB of the feeder. The external LBB initiation
c. A series combination of stage1 reverse zone from both can be avoided in wiring. In cases where internal LBB is
is also possible. used; a configuration change becomes essential. A check
2. One numerical and one static distance protection: should be made with the relay logic for possibility of
a. Only numerical protection will be used for two stage separation of such initiation condition.
reverse zone. c. The stage 2 here needs to be connected to the general
3. Suggested timings for 400 kV trip conditions initiated from the relay. The stage2 will
a. Present Zone timings initiate the LBB of the feeder.
i. Zone1 = 0 mS 3. Reverse Zone = Stage 1 and No stage 2
ii. Zone 2= 300 mS a. If any of the relay is not providing facility for creation
iii. Zone 3 = 500 mS to 1 S of new zones this configuration can be used.
b. Reverse Zone timings suggested b. The stage 1 trip needs to be disconnected from all
i. Stage 1 = 200 mS general trip conditions inside the relay.
ii. Stage 2 = 400 mS c. Here also the stage 1 trip should not initiate the
Case2: 220 kV substations where the main protection is internal or external LBB of the feeder. The necessary care
distance and back up is IDMT O/C & E/F as discussed in 2 above is applicable here.
In such condition the scheme can be applied safely as far as 4. Rev Zone of Main1 = Stage 1 and Rev Zone of Main2 =
all of the distance protection relays connected to the Stage 2
concerned bus is in service and functioning correctly. a. When both main1 and main2 both numerical distance
The scheme can also be safely applied when the Zone1 fault relays are provided; it is possible to configure the reverse
clearance time on the overlapping area of reverse zones and zones of one for stage1 and the other for stage2.
Zone1 with only back up protection operation can be b. The stage1 trip needs to be disconnected from all
coordinated with the reverse zone stage1 operating time. As general trip conditions.
the Zone 2 operating time for 220 kV lines is 400 mS, the c. Here also the stage 1 trip should not initiate the
stage 1 reverse Zone time can be taken to 300 mS for tripping internal or external LBB of the feeder. The necessary care
of bus couplers in this case. as discussed in 2 above is applicable here.
1. Suggested timings for 220 kV d. The stage 2 here needs to be connected to the general
a. Present Zone timings trip conditions initiated from the relay. The stage2 will
i. Zone1 = 0 mS initiate the LBB of the feeder.
405
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
References:
1. Micom P442 technical manual.
2. REL 521 technical manual.
3. Protection relay application guide- AREVA
406