PROJECT CHARTER
Project Name Balance works of Package CA06
Project Description Part design and construction of (balance works of Package CA06) elevated viaduct and
five elevated stations from ch 4,860.384 mtr to ch 52,729.312 mtr of line 2B of Mumbai
Metro Rail Project in Mumbai.
Start Date 01/04/2018 Planned End date 31/3/2021
Estimated Cost Rs. 10,986 Cr. Date Approved 04/01/2017
Project Sponsor MMRDA Signature KVS/AS/KP
Business Case Stakeholder List
It shall provide connectivity between the Eastern & • MMRDA • Government Agencies
Western Suburban Mumbai. It shall reduce the current • Project Consultant • Citizens
travel time by anything between 50% and 75% • Civil Contractor (s) • Financial Institutions
depending on road conditions. • Systems Contractor (s)
Expected Goals/Deliverables Project Risk(s)
1. Construction of viaduct with various systems. • Delay in handing over unhindered possession of site
2. Construction of 5 stations with systems • Improper documentation/drawing provision
3. Electrical Sub-stations • Delay in materials/machinery availability
4. Rolling Stock • Delay in making payments
5. Signaling System • Inflation due to extending the time period
Payment and Project Management Procurement and Supply Chain Management
through Smart Contracts Using Blockchain
➢ Various deliverables defined at the planning phase can be ➢ Using unique blockchain Id to follow the lifecycle of the
added together with smart contracts which will initiate asset tracking all the necessary specification as well as
the payments according to the worked hours and the ownership changes of the asset.
submitted deliverables, in addition to automatically
updating project’s progress and recording all the
necessary interactions.
There is no exact definition Concurrent delays should Availability of right data ( Right technology to be used
of what concurrent delay be clearly defined and ways Time and progress ). Trust to measure and track data
means. to measure delays should on available data. points
be defined.
Once a concurrent delays is A clause should be put in to Impact of apportionment The terms should be
established, rules are not get delay compensation may be varied for different defined for different
available to calculate the based on labor and contractors. categories of contractors. In
apportionment and this inventory which is specific cases they can be
causes problem. As a result employed. Apportionment defined in consultation with
only time extension is given formula to be used in each the contractor.
and not monetary case should also be defined
compensation.
Policy Changes, RISKS Involved and Mitigation Plan
Delays are considered only if Instead of cumulative delay, There may be A dashboard should be
they involve critical path. part wise delay should be disputes on the maintained, which not only
But due to this those considered. There should be quantum of delay shows project delays and
contractors not in critical liquidated damages for delay and liquidation costs as project progresses,
path may find it difficult to in various activities or damages incurred but also shows contractor
claim compensation milestones which are and this may require wise delay and cost
especially linked with other time to resolve. implications ( Costs to be paid
contractors. and Liquidation damages as
of that day
Definition of delay events is Delays should be defined Contractors or owner The categories should be
not proper categorically and method to may try to make defined in the contract.
resolve each category should changes to favor
be presented themselves