Work out 1

1. Kassa & Sons Construction PLC has signed an agreement with Berhan International Bank
for construction of head office building of G+4 with a total cost of 21,200 Birr (in
thousands). Answer the following questions on the basis of the information given in the table
below. (4 Points)
Activity Predecessor Activity time (Weeks)
A None 5
B A 6
C A 4
D C 3
E B,C 1
F E 4
G D, F 14
H D, G 12
I H 3
Total 52
a. Construct the project network using Activity on Node (AON).
b. Determine the critical path
c. Determine the project's duration, project's Schedule, Earliest Start, Earliest Finish, Latest Start
and Latest Finish times as well as prepare Slack