WORK SUMMARY
Lot 1-
Parapet wall block work and plastering completed
Screeding is 60% done.
Groves (Moulding) and setting on going.
Lot 2-
Roofing parapet wall block and plastering completed
Screeding is 80% done.
Nogging (Open house) 80%
Lot 3-
Parapet block wall 90%
Screeding 80% done
Lot 4-
parapet block wall 90% done
Screeding 5% done
Lot 9-
Parapet wall 100% done.
Screeding 95% done.
Electrical review ongoing.
Nogging ongoing.
Roofing 90% and copping ongoing.
Lot 10-
Screeding 95% done.
Nogging 40% done.
FD 8-
Parapet wall in progress.
FD 9-
Parapet wall in progress.
Screeding (external) 70%.
RETAINING WALLS-
Retaining wall by the theme pack – carpeting work completed.
Wall (along lot 10-13) casted.
The Bridge-
All bridge reinforcement wall completed.
Retaining wall around it ongoing.
Bridge casted.
General note:
APPENDIX
LOT 10-Screeding 95% (external) and Nogging 40%