Daywork Sheet 1

Date: 04 September 2013


Reference: To construct additional door opening to the kitchen wall
RM
Material - None
Plant - Vibrator ½ man day @ RM150/day 75.00
Labour - 1 skilled worker ½ man day @ RM80/day 40.00
115.00
Profit and attendance @15% 17.25
Total 132.25

Total carried to Variation Order No.4