You are on page 1of 12

ID Outline

TaskTask Name Duration Start Finish Predecessors


Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20 Dec '20
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07
0 0 Cable Trenches 69 Tue Fri 04/12/20
Upgrading at days 01/09/20
Minerva Substation
1 1 Contract award 1 day Tue 01/09/20 Tue 01/09/20

2 2 Preparation, 5 days Wed 02/09/20 Tue 08/09/20 1


submission, review
and approval of OHS
File, and program

3 3 Site handover 1 day Wed 09/09/20 Wed 09/09/20 2

4 4 Site establishment 3 days Thu 10/09/20 Mon 14/09/20 3

5 5 Underground utility 1 day Tue 15/09/20 Tue 15/09/20 4


scan
6 6 Prep work 6 days Wed 16/09/20 Wed 23/09/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Outline
TaskTask Name Duration Start Finish Predecessors
Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20 Dec '20
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07
7 6.1 Remove stone 2 days Wed 16/09/20 Thu 17/09/20 5
yard
8 6.2 Remove trench 2 days Wed 16/09/20 Thu 17/09/20 5
covers
9 6.3 Remove unused 2 days Fri 18/09/20 Mon 21/09/20 8
cables
10 6.4 Remove existing 1 day Tue 22/09/20 Tue 22/09/20 9
top angles
11 6.5 Clean cable trench 1 day Wed 23/09/20 Wed 23/09/20 10

12 7 Brickwork 17 daysThu 24/09/20 Fri 16/10/20 6

13 7.1 Setting out 1 day Thu 24/09/20 Thu 24/09/20 6

14 7.2 Excavation 2 days Fri 25/09/20 Mon 28/09/20 13

15 7.3 Compact bottom 3 days Tue 29/09/20 Thu 01/10/20 14


of excavation

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Outline
TaskTask Name Duration Start Finish Predecessors
Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20 Dec '20
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07
16 7.4 Test compaction 1 day Fri 02/10/20 Fri 02/10/20 15

17 7.5 Soil poisioning 1 day Mon 05/10/20 Mon 05/10/20 16

18 7.6 Cast concrete 1 day Tue 06/10/20 Tue 06/10/20 17


blinding
19 7.7 Cure concrete 7 days Wed 07/10/20 Thu 15/10/20 18
blinding
20 7.8 Brickwork setting 1 day Fri 16/10/20 Fri 16/10/20 19
out
21 7.9 Lay bricks 5 days Fri 25/09/20 Thu 01/10/20 13

22 7.10 Cement wash 2 days Fri 02/10/20 Mon 05/10/20 21


brickwork
23 7.11 Inspect brickwork 1 day Tue 06/10/20 Tue 06/10/20 22

24 8 Concrete work 29 daysMon 19/10/20 Thu 26/11/20 12

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Outline
TaskTask Name Duration Start Finish Predecessors
Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20 Dec '20
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07
25 8.1 Breakout existing 1 day Mon 19/10/20 Mon 19/10/20 12
top angle anchors
26 8.2 Mechanically 1 day Mon 19/10/20 Mon 19/10/20 12
clean existing
concrete ramp
27 8.3 Apply bonding 1 day Tue 20/10/20 Tue 20/10/20 26
primer
28 8.4 Backfill with G5 5 days Mon 19/10/20 Fri 23/10/20 12
and compact
29 8.5 Soil poisioning 1 day Mon 26/10/20 Mon 26/10/20 28

30 8.6 Stabilise 2 days Tue 27/10/20 Wed 28/10/20 29

31 8.7 Test compaction 1 day Mon 02/11/20 Mon 02/11/20 30FS+2 days

32 8.8 Formwork 1 day Tue 03/11/20 Tue 03/11/20 31

33 8.9 Lay mesh 2 days Wed 04/11/20 Thu 05/11/20 32


reinforcing

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Outline
TaskTask Name Duration Start Finish Predecessors
Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20 Dec '20
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07
34 8.10 Inspect G5 and 1 day Fri 06/11/20 Fri 06/11/20 33
mesh reinforcing
35 8.11 Cast concrete 2 days Mon 09/11/20 Tue 10/11/20 34

36 8.12 Finish concrete 1 day Wed 11/11/20 Wed 11/11/20 35

37 8.13 Cure concrete 7 days Wed 11/11/20 Thu 19/11/20 35


ramp
38 8.14 Drill in angle irons 3 days Fri 20/11/20 Tue 24/11/20 37

39 8.15 Reinstate trench 2 days Wed 25/11/20 Thu 26/11/20 38


covers
40 9 Reinstate stone yard 1 day Fri 27/11/20 Fri 27/11/20 39

41 10 Remove rubble 1 day Mon 30/11/20 Mon 30/11/20 40

42 11 Final inspections 1 day Tue 01/12/20 Tue 01/12/20 41

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Outline
TaskTask Name Duration Start Finish Predecessors
Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20 Dec '20
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07
43 12 Project completion 1 day Wed 02/12/20 Wed 02/12/20 42

44 13 Project handover 1 day Wed 02/12/20 Wed 02/12/20 42

45 14 Site 2 days Thu 03/12/20 Fri 04/12/20 44


ede-establishment

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21
07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21
07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21
07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21
07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21
07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21
07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Cable Trenches Upgrad
Summary Manual Summary Rollup Progress
Date: Wed 22/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12