PREPARATION FOR VACUUM OIL FILLING

Since the transformer with a nominal voltage over 200 kV, the oil filling should be applied
as vacuum filling method.

Before vacuum oil filling, the customer should provide separate place (empty tank or oil
bag) to be able to transfer all required oil inside the tank. Then, other steps should be
disclosure to third parties without express authority is
information contained therein. Reproduction, use or

followed for the erection, starting with 1ZBA 4601-212.