You are on page 1of 10

552 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 32, NO.

1, JANUARY 2017

A PMU Placement Scheme Considering Realistic


Costs and Modern Trends in Relaying
Anamitra Pal, Member, IEEE, Anil Kumar S. Vullikanti, Member, IEEE, and S. S. Ravi, Senior Member, IEEE

Abstract—Synchrophasor deployment costs have evolved over Over the past two decades, extensive research has been done
time. The cost of upgrading a substation, which is much larger to solve this problem. The popular techniques that have been
than the cost of an individual device, has emerged as the primary employed for achieving optimal results include simulated an-
constituent of the total expenditure. Given these circumstances, the
optimal phasor measurement unit placement formulation needs to nealing, integer programming, exhaustive search, weighted least
consider not only the number of devices that must be placed at the squares (WLS), Tabu search, (immunity) genetic algorithm, par-
substations, but also the number of substations that must be up- ticle swarm optimization, etc. For the purposes of brevity, the
graded to support those devices. This paper presents an integer lin- following literature survey is limited to some of the archival
ear programming methodology for such a placement scheme while papers that have been published recently. For a more detailed
considering realistic costs and practical constraints. The IEEE 30
bus system is used to illustrate the proposed concept, while the description of PMU placement methodologies, [8] and [9] are
IEEE 118, IEEE 300, and Polish 2383 bus systems are used to show suggested.
the performance of the method under different test environments. In [10], PMU deployment was approached based on a state
Index Terms—Critical-bus concept, dual-use line relay (DULR),
estimation theoretic criterion. The optimization was performed
integer linear programming (ILP), N–t contingency, observability, via convex relaxation and semidefinite programming. In [11],
optimal cost, phasor measurement unit (PMU). constraints such as transmission line outages and measurement
channel limitations were incorporated into the OPP problem for-
I. INTRODUCTION mulation through an integer linear programming (ILP) model.
HASOR measurement unit (PMU) based state estimation ILP was also used in [12] and [13] for solving the OPP problem
P was proposed for the first time in 1985–1986 [1]. Since
then a great deal of research has been carried out to develop
under controlled islanding conditions and detecting bad data
in a hybrid state estimator, respectively. An enumeration-based
efficient state estimation algorithms (hybrid/linear) [2]–[5] and ILP was used in [14] for enhancing the reliability of subsequent
compute optimal locations for placing PMU devices in the grid. PMU additions. A mixed-ILP based multi-objective probabilis-
The latter studies were considered to be mostly “theoretical” tic model for PMU placement was developed in [15]. Fuzzy
or “academic” until, courtesy of Federal funding, many utili- logic was used in [16] for creating a PMU placement frame-
ties began placing these devices in bulk in their networks [6]. work that enhances wide-area situational awareness. In [17],
While doing so, they realized that factors other than the price PMU placement was done using a greedy algorithm for min-
of the device itself were primarily responsible for the high cost imizing state estimation errors. The OPP problem was solved
of synchrophasor deployment. These factors included commu- in [18] by maximizing the determinant of the empirical observ-
nication infrastructure costs, security (cybersecurity) costs, and ability Gramian for performing robust dynamic state estimation.
labor costs [7]. Under such circumstances, it became essential A WLS algorithm with continuous decision variables was used
to reexamine the formulation of the optimal PMU placement to solve the OPP problem in [19], while sequential quadratic
(OPP) problem. programming was used in [20] to attain the dual objectives of
In the traditional formulation, the goal is to find the minimum minimizing the total number of PMU devices and maximizing
number of PMU devices that, when placed in the power net- measurement redundancy of all buses.
work, ensures the attainment of some pre-defined objective(s). Some inferences drawn on the basis of the above literature
survey are summarized as follows:
Manuscript received October 4, 2015; revised February 18, 2016; accepted 1) ILP is the most popular choice for solving OPP problems
April 3, 2016. Date of publication April 7, 2016; date of current version Decem- [11]–[15]: The reason for this is that unlike meta-heuristic
ber 20, 2016. This work was supported in part by the following grants: Defense
Threat Reduction Agency Grant HDTRA1-11-1-0016, DTRA Comprehensive
approaches, ILP always gives an optimal solution. More-
National Incident Management System Contract HDTRA1-11-D-0016-0001, over, with powerful processors and efficient optimizers
and National Science Foundation Network Science and Engineering Grant CNS- (such as Gurobi and CPLEX), even for large systems,
1011769. Paper no. TPWRS-01393-2015.
A. Pal is with the Network Dynamics and Simulation Science Laboratory,
the computational time required for finding the optimal
Biocomplexity Institute, Virginia Tech, Blacksburg, VA 24061 USA (e-mail: locations for PMU placement is not substantial.
anam86@vbi.vt.edu). 2) Transformer tap ratios are not taken into account
A. K. S. Vullikanti is with the Department of Computer Science and the
Biocomplexity Institute, Virginia Tech, Blacksburg, VA 24061 USA (e-mail:
[8]–[20]: The tap settings of the transformers are either
akumar@vbi.vt.edu). assumed to be known or ignored altogether.
S. S. Ravi is with the Department of Computer Science, University of 3) Most of the PMUs considered in the literature are of the
Albany—State University of New York, Albany, NY 12222 USA (e-mail:
sravi@albany.edu).
“bus” type [10]–[20]: That is, when placed at a bus of
Digital Object Identifier 10.1109/TPWRS.2016.2551320 the system, the PMU observes the voltage of that bus and

0885-8950 © 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications standards/publications/rights/index.html for more information.
PAL et al.: PMU PLACEMENT SCHEME CONSIDERING REALISTIC COSTS AND MODERN TRENDS IN RELAYING 553

some or all of the branch currents (depending on whether of placing bus-type PMUs was done substation-wise. However,
measurement channel limitations are considered or not) the intent of that paper was to minimize the total number of
that emerge from that bus. PMU devices. As pointed in [7] and [23], device cost is not
4) Those solutions that satisfy all pre-defined system con- a major portion of the PMU placement cost. Therefore, from a
straints and require the least number of PMUs for doing cost minimization perspective such a formulation is not optimal.
so are considered the best solutions [10]–[20]: This is be- Mishra et al. [25] also came to a similar conclusion. However,
cause the cost of the device is assumed to be the primary Mishra et al. [25] used binary particle swarm optimization for
reason for not placing PMUs at all buses. attaining its objectives which is not guaranteed to always give
In this paper, these inferences will be analyzed using realistic optimal solutions [11], [12], [26].
costs obtained from publicly available reports, as well as by The third factor that influences modern PMU placement is the
considering trends in relaying technologies that are currently in availability of dual-use line relays (DULRs) acting as PMUs.
vogue. Also called branch PMUs in some publications (see [27], [28]),
The rest of the paper is structured as follows. Section II de- they are designed to monitor a single edge by measuring the
scribes through illustrations the need for a new PMU placement voltage and current phasors at one end of the monitored edge.
scheme. The mathematical formulation of the problem and the Unlike traditional PMUs (TPMUs) which are stand-alone and
practical constraints that are handled by the proposed approach whose single function is measuring synchrophasors, DULRs
are described in Section III. The results obtained by applying this are transmission line and transformer protection relays (digi-
approach to standard IEEE systems as well as a 2383 bus Polish tal relays) that while performing their protection functions also
system are summarized in Section IV. Section V concludes the report phasor data. The advantage of using DULRs is that by
paper. enabling synchrophasor functionality inside digital relays, addi-
tional substation panels are not required. This reduces the total
cost and saves precious control house space. DULRs also pro-
II. NEED FOR A NEW PMU PLACEMENT SCHEME vide added benefits such as uniform distribution in the network,
As can be seen from the literature survey in Section I, the adaptability to deployment in multiple stages, higher reliability,
basic objective of any OPP scheme is observability. From a PMU and time-tagged breaker statuses which are practically a ne-
placement perspective, observability is defined as the ability to cessity for linear state estimators [5]. Although Gomez et al.
measure, either directly or indirectly, some or all of the complex [27] highlighted the use of these devices for enhancing reliabil-
voltages (known as states) of a network. Topologically, a power ity of power networks, to the best of our knowledge no PMU
network is a graph whose nodes are buses, one or more of which placement model has exploited their use from a cost-reduction
are placed inside a substation, and whose edges are transmission perspective.
lines or transformers. However, topological observability is not To summarize, a new PMU placement scheme is needed to
the only criterion for a robust PMU placement scheme. Flows achieve the following objectives:
in a power system are governed by Kirchhoff’s laws and a 1) Different buses have different priorities [23]: Since some
variety of transient and dynamic stability constraints must be buses are more important than others from system stabil-
satisfied for the power system to remain resilient to failures. A ity/security perspectives, they must be given higher pref-
big challenge with respect to the resilience requirement is the erence when placing PMUs.
successful integration of large-scale renewable energy sources 2) Substations are different from buses: The new scheme
(especially massive wind farms) with the high-voltage network. must minimize the number of substations where PMUs
PMUs have been found to play important roles in these contexts are placed for observing all the buses of the network,
as they provide real-time knowledge of the operation state [21], while being subject to practical constraints.
[22]. Thus, these criteria must be incorporated while choosing 3) DULRs are to be used for ensuring observability and
locations for placing PMUs in the grid. redundancy: A DULR can measure voltage of both ends
The second factor to be considered regarding PMU placement of an edge. Now, if one node has two incident edges, both
is that although voltages of the buses are meant to be observed, of which have DULRs on either of their ends, then that
PMUs can only be placed in substations. A bus is a single node of node satisfies the N − 1 contingency criterion (which is
the network having a particular voltage value, whereas a substa- the industry norm). It will be shown in the next section
tion is a collection of one or more buses. When a PMU is placed that the methodology developed here can provide N − t
at a substation, that substation has to often undergo disruption redundancy, where t ≥ 1.
of its normal service in order to set up the communication and One way to attain these objectives is to treat substations as
(cyber)-security infrastructures. Although utilities prefer doing super-nodes and grouping buses that are inside a substation into
these upgrades during scheduled outages of a substation or dur- a single node to find the optimal number of such super-nodes
ing the off-peak load period, this may not always be possible in a where PMUs should be placed. However, this approach will not
liberalized electricity market [23]. Similarly, a report published ensure complete bus observability. This is explained through
by the U.S. Department of Energy (DOE) stated that the cost Fig. 1, which shows a multi-level voltage system where circles
of a new installation can be almost 20 times the cost of a PMU indicate substations and colored dots represent buses. Consider-
device [7]. Therefore, the cost of upgrading a substation is an ing the most general case, it is assumed that all buses/substations
important component of the synchrophasor installation cost and have non-zero injections and that the transformer tap settings
must be considered in the OPP formulation. In [24], the task between the different voltage levels inside a substation are not
554 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 32, NO. 1, JANUARY 2017

objectives. The proposed methodology reconciles the two ob-


jectives through a cost-based formulation. It places DULRs on
edges for observing all the buses while minimizing the total
cost, which is the sum of the cost of disrupting substations and
the cost of all DULRs placed.

A. Nomenclature Used
Let the power network be represented by an undirected graph
G (V, E) where V is the set of nodes (buses) and E is the set of
edges (transmission lines or transformers). Further, the node set
V is partitioned into k ≥ 2 blocks B1 , B2 , . . . , Bk , where each
block represents a substation. Let ri denote |Bi | for 1 ≤ i ≤ k.
Since the tap ratios of the transformers are not known, there
is no edge between any pair of nodes inside the same block.
Fig. 1. Example system illustrating the inability of super-node based observ-
Thus, the nodes in each block form an independent set, thereby
ability to ensure complete bus observability. implying that G is a k–partite graph.
Now, each node of V will be denoted by a pair of integers
known. The latter implies that knowing the voltage of a colored (x, y) where x ∈ {1, 2, . . . , k} is the block number and y ∈
dot inside a substation does not translate to knowing the voltage {1, 2, . . . , rx } is an index number within block Bx . Next, a
of a differently colored dot inside the same substation. An ILP lexicographic ordering amongst the nodes is introduced. That
formulation for only minimizing the number of circles (super- is, given two nodes v1 = (x1 , y1 ) and v2 = (x2 , y2 ) from two
nodes or substations) gives the optimal substation locations for different blocks Bx 1 and Bx 2, we define v1 ≺ v2 if x1 < x2 .
PMUs as 1, 2, and 10. However, from the figure it becomes clear Each edge e = {v1 , v2 } ∈ E joins two nodes v1 = (x1 , y1 ) and
that the 500 kV bus in substation 7 is not observed by this solu- v2 = (x2 , y2 ) from two different blocks. When specifying an
tion. Hence, an OPP scheme whose goal is observability of all edge e as {v1 , v2 }, it will be assumed that v1 ≺ v2 ; thus, v1 and
buses and minimization of number of substation installations v2 can be referred to as the low end and the high end of edge e,
cannot be formulated through super-node based observability respectively.
alone. For any node v ∈ V, the neighborhood of v, denoted by Nv ,
Another approach might be to imagine the power network contains the node v itself and all nodes that are adjacent to v. As
as being composed of a number of independent sub-networks a simple extension of this definition, the neighborhood of a set
each of which is comprised of buses that are at a particular of nodes X, denoted by NX , is defined by NX = ∪v∈X Nv . Also,
voltage level. In that case, the example system depicted in Fig. 1 a DULR must be placed at either end of an edge. When a DULR
would consist of not one but three different networks—red, blue, is placed on an edge e = {v1 , v2 }, it can observe both the nodes
and green, respectively. A possible solution obtained from an v1 and v2 . If it is placed on the v1 = (x1 , y1 ) end, which is the
independent ILP formulation for each network is as follows: low end of e, then the block x1 must be disrupted. Likewise, if
PMUs need to be placed on the red bus of substation 2; blue it is placed on the v2 = (x2 , y2 ) end, which is the high end of
buses of substations 5, 7, and 11; and green buses of substations e, then the block x2 must be disrupted. Finally, let ci be the cost
1 and 2 for complete observability of the red, blue, and green of disrupting block Bi for 1 ≤ i ≤ k and let Δ denote the cost
networks, respectively. From this solution it becomes clear that of each DULR. A formulation based on the above terminology
if the sub-networks are treated as completely independent of is described below.
one another, PMUs would need to be placed in five substations.
Considering the objectives outlined in this paper, an optimal
B. Basic DULR Placement Problem (DULRPP)
solution for the system shown in Fig. 1 will be one where PMUs
are placed in four substations, namely, 1, 2, 7 and 10. In terms of The basic version of DULRPP assumes that the given sys-
number and locations of DULRs, a possible solution set could tem does not have any traditional bus PMU or DULR already
be: Three DULRs at substation 1 monitoring edges 1-5, 1-6, and installed. Its goal is to place DULRs on some of the edges so
1-11; three DULRs at substation 2 monitoring edges 2-1, 2-3, that the following conditions are satisfied: (a) all the nodes are
and 2-4; two DULRs at substation 7 monitoring edges 7-1, and observed; and (b) the total cost, which is the sum of the cost of
7-8; and two DULRs at substation 10 monitoring edge 10-5, and disrupting substations and the cost of the DULRs added, is min-
10-9. A formulation which will give such a solution for practical imized. An ILP-based formulation of this problem is developed
power system networks is described in the next section. as follows.
For each substation Bi for 1 ≤ i ≤ k, there is a {0, 1} valued
III. MATHEMATICAL FORMULATION variable yi such that
AND PRACTICAL CONSIDERATIONS

From Fig. 1 it is clear that maximizing bus observ- 1, if substation Bi is disrupted
yi = (1)
ability and minimizing substation disruptions are conflicting 0, otherwise.
PAL et al.: PMU PLACEMENT SCHEME CONSIDERING REALISTIC COSTS AND MODERN TRENDS IN RELAYING 555

For each edge e, there are two {0, 1} valued variables wel and of critical buses and an integer t ≥ 1 that represents the
wehsuch that maximum number of DULRs that may fail. Then, the goal
 is to ensure that each bus v ∈ C is observed by at least one
1, if DULR is placed at the low end of edge e
wel = (2) DULR even when any subset of t or fewer DULRs fail.
0, otherwise Since the failures can be due to the device itself and/or
 outage of the line on which the DULR is placed, this con-
1, if DULR is placed at the high end of edge e
weh = (3) straint ensures observability under N − t contingency. In
0, otherwise. the proposed ILP formulation, this requirement is accom-
Using (1)–(3), the basic objective function can be defined as modated by ensuring that each critical bus is observed
 k  by at least t + 1 DULRs. This is done by replacing the
   constraint specified by (5) with the one given in
h l
Minimize ci yi + Δ we + we . (4)  
i=1 e∈E weh + wel ≥ t + 1 ∀v ∈ C. (8)
Three sets of constraints that must be imposed on the variables e∈E v
used in this basic objective function are defined as follows. For 2) Handling of prohibited substations: In the field, there ex-
any node v, let Lv denote the set of edges incident on v such ist some substations where installations cannot be made in
that for each edge in Lv , v is the low end of that edge. Similarly, the planning horizon established for synchrophasor place-
for any node v, let Hv denote the set of edges incident on v ment. This is a practical constraint and is addressed as fol-
such that for each edge in Hv , v is the high end of that edge. lows: Suppose S ⊆ {B1 , B2 , . . . , Bk } is the set of substa-
Let Ev = Lv ∪ Hv denote the set of all edges incident on node tions that cannot be disrupted. Then, for each substation
v. Then, for each node v ∈ V Bi ∈ S, the constraint yi = 0 must be added to the ILP
 
weh + wel ≥ 1. (5) formulation described in (4)–(7).
e∈E v 3) Handling of existing PMUs: Similar to Item 2 above, there
might be some substations where PMUs may already be
Eq. (5) ensures that each node v is observed by placing a
present. Such existing PMU locations can be integrated
DULR on at least one of the edges incident on v.
into the proposed formulation in the following manner. Let
For each node v = (i, j) and each edge e ∈ Lv
P ⊆ V be the set of nodes at which PMUs have already
yi ≥ wel . (6) been placed. Also, let the PMU placed at the ith node
of P observe the nodes in Mi where Mi ⊆ Ni . Then, the
Eq. (6) ensures that if a DULR is placed on an edge for which
placement of DULRs needs to observe only the nodes in
v = (i, j) is the low end, then Bi must be disrupted.
V − MP , where
Similarly, for each node v = (i, j) and each edge e ∈ Hv 
yi ≥ weh . (7) MP = Mi . (9)
1≤i≤|P|
Eq. (7) ensures that if a DULR is placed on an edge for
In (9), it is assumed that the union operator eliminates du-
which v = (i, j) is the high end, then Bi must be disrupted. This
plicate entries. Therefore, to account for P, the constraint
completes the formulation of the basic DULRPP. Similar to the
specified by (5) needs to only be applied to each node
traditional OPP problem, DULRPP is also NP-complete and this
v ∈ V − MP .
is proved in the Appendix.
4) Handling unknown transformer tap ratios: The tap-
C. Additional Constraints settings of transformers are not known in real-life. If not
considered in the PMU placement formulation, the un-
Practical constraints that can be further imposed on the pro- known tap ratios may reduce the accuracy of the resulting
posed objective function are as follows: state estimates [30], [31]. The proposed formulation ac-
1) Redundancy to critical buses: Measurement redundancy counts for unknown tap ratios in the following manner:
under N − 1 contingency has been a common theme a) At the start of the optimization, any edge that joins
in many papers on PMU placement ([12], [15], [20], two nodes (buses) inside a block (substation) is elim-
[23], etc.). However, a closer inspection of the results inated.
reveals that a large number of substations (>50%) must b) If the elimination of edges causes a node to be dis-
be disrupted in order to provide redundancy to all pha- connected from the rest of the system, then that
sor measurements. A more practical scheme is to provide disconnected node is placed inside a dummy block
redundancy in measurements for only the most important and is connected to the same node(s) of the real
buses of the system. A methodology to identify such crit- block by dummy line(s). If the number of dummy
ical buses has already been proposed in [29]. To provide lines added to the node v of the real block is d,
redundancy in measurement for only the critical buses of where d ≥ 1, then (5) for node v becomes,
the network, the proposed formulation is modified in the  
following way. When a DULR on an edge e fails, it cannot weh + wel ≥ d + 1. (10)
observe any end point of e. Consider a given set C ⊆ V e∈E v
556 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 32, NO. 1, JANUARY 2017

inition of PZI as the iso–voltage zero injection bus(IvZIB)


condition. Thus, all elements of PZI must satisfy the IvZIB
condition. Once PZI is formed, the methodology proposed in
[34] can be extended to the DULRPP for reformulating (5) for
buses belonging to PZI as shown below.
Let |PZI| = k. Depending on the value of k, we explain
below how to construct a set R of objects from which all the
observability constraints can be generated.
For k = 1: Let i be the single element of PZI and Ni be the
neighborhood of i. For each pair of elements p and q in Ni , R
contains the 2-element set {p, q}.
Fig. 2. Handling ZI buses in absence/presence of unknown tap ratios. For k ≥ 2: Let i and j be two elements of PZI. Define Ni and
Nj as the neighborhoods of i and j, respectively. Note that Ni
and Nj may have elements in common. Let Ni,j = Ni ∩ Nj , that
is, Ni,j is the set of elements that occur in both Ni and Nj . Let
c) DULR-based observability of the multi-partite N
i = Ni − Ni,j , that is, N
i is the set of elements that are in Ni
graph is computed next. When a DULR is placed but not in Nj . Similarly, define N
j = Nj − Ni,j . Construct Ri,j
at the end of a line joining a dummy block to a real as follows:
block, the cost of the DULR and the cost of dis- a) For each pair of elements p and q in N
i , add the 2-element
rupting the real block are retained but the cost of set {p, q} to Ri,j .
disrupting the dummy block is ignored. b) For each pair of elements p and q in N
j , add the 2-element
The solution obtained by following this methodology ensures set {p, q} to Ri,j .
that buses located at either end of a transformer are observed by c) For each pair of elements p and q in Ni,j , add the 2-element
different DULRs. Therefore, even if the transformer tap ratios set {p, q} to Ri,j .
are not known, voltages of all the buses of the network can be d) Construct the cross-product set Qi,j = N
i × N
j × Ni,j .
accurately estimated. It is to be noted that Qi,j contains all triples (p, q, r)
5) Presence of zero-injection (ZI) buses: Practical power sys- such thatp ∈ N
i , q ∈ N
j andr ∈ Ni,j . For each triple
tem networks have ZI buses. These are buses through (p, q, r) ∈ Qi,j , add the 3-element set {p, q, r} to Ri,j .
which power neither enters nor leaves the system. Many For the elements i and j of PZI, every 2-element or 3-element
papers on OPP have exploited the presence of ZI buses set in Ri,j leads to an observability constraint. Now, consider
for reducing the total number of PMUs required ([12], each pair of elements i and j in PZI and generate the set Ri,j
[15], [32], etc.). However, with unknown tap ratios, treat- for that pair using steps a–d given above. The collection R
ing all ZI buses in the same way can lead to scenarios from which observability constraints can be generated for all
where topological observability does not guarantee nu- the k ≥ 2 elements of PZI is given by
merical observability [33]. An example of such a scenario 
is shown in Fig. 2. R= Ri,j . (11)
In Fig. 2, solid circles denote buses, dotted circles/ovals de- 1≤i≤j≤k

note substations, numbers refer to bus numbers, letters A to G In (11), it is assumed that the union operator eliminates du-
refer to substations, arrows depict injections, and solid rectan- plicate entries. Finally, for every 2-element set {p, q} and 3-
gles depict DULRs. From the figure it becomes clear that buses element set {p, q, r} in R, the modified observability constraints
2 and 6 are ZI buses while the other buses have non-zero injec- are given in
tions. Buses 6 and 8 inside substation F are at different voltage    h 
levels (indicated by the colors red and blue) and have a trans- weh + wel + we + wel ≥ 1 (12a)
e ∈E p e ∈E q
former between them whose tap ratio is unknown. In Fig. 2(a),
   h   h 
the voltage of bus 4 can be estimated using the DULRs located weh + wel + we + wel + we + wel ≥ 1.
on edge 1-2 and 3-2. In Fig. 2(b), due to the presence of a trans- e ∈E p e ∈E q e ∈E r
former between buses 6 and 8, the DULRs placed at 5-6 and 7-6
(12b)
will not be able to estimate the voltage of bus 8. Since a purely
topological approach does not differentiate between transform- 6) Absence of measurement channel limitation: As each
ers and transmission lines, it cannot account for this failure in DULR only monitors one edge, the problem of measure-
estimation. The proposed approach addresses this concern in ment channel limitation does not arise.
the following manner. Let TZI denote the set of all ZI buses
present in the system. To construct observability constraints, it IV. SIMULATION AND RESULTS
is necessary to consider a subset of TZI, denoted by PZI. A
A. Realistic Costs
formal definition of PZI is as follows. PZI = {x : x ∈ TZI and
for every y ∈ Nx , x and y are at the same voltage level}. For One of the salient points of this paper is that realistic costs
convenience, we refer to the condition specified in the above def- have been considered in specifying the cost objective. Federal
PAL et al.: PMU PLACEMENT SCHEME CONSIDERING REALISTIC COSTS AND MODERN TRENDS IN RELAYING 557

Fig. 3. The substation synchrophasor architecture design that was the basis of
the proposed DULRPP formulation.

agencies such as DOE have collected data on how their invest-


ment has been used by different utilities in purchasing equip-
ment and upgrading infrastructure. Reports published by these
agencies [6], [7] highlight the following facts:
1) The median cost for installing a single PMU at a new
substation was approximately USD43 400. This cost was
comprised of the cost of the device itself as well as de-
sign and engineering costs, labor and material costs for
installation/construction, and overhead [6].
2) There were no economies of scale; that is, projects in-
stalling a greater number of PMUs did not have lower
average costs per device [6]. Fig. 4. DULRs placed in IEEE 30 bus system to satisfy practical constraints.
3) The key drivers of the cost of PMU installations in de-
creasing order of cost, were: communication, security
(mission-critical systems and mission-support systems), ment) failures in the SCADA system, and (b) the PDC inside the
labor (specialized crew or decentralized crews) and cost substation provides a back-up archive of high-resolution PMU
of equipment (that is, PMU hardware cost) [7]. data in case data loss happens in downstream applications.
4) PMU hardware cost was less than 5% of the total cost for
the installed synchrophasor system. The cost of a phasor
data concentrator (PDC) was found to be higher than that B. IEEE 30 Bus System
of a PMU but much less than the cost of the other drivers The IEEE 30 bus system was modified by grouping buses into
mentioned in Item 3 above [7]. substations. This was done using the rule that buses which were
5) Once the other infrastructures were in place, the cost connected by transformers belonged to the same substation. The
of adding more PMUs to a substation was miniscule. remaining buses which were not connected to any transformer
Similarly, the cost of ancillary equipment such as global formed their own independent substations. As such, the IEEE
positioning system (GPS) clocks, network switches and 30 bus system became a 26-substation system as seen in Fig. 4.
routers, etc., were found to be low relative to the cost of In Fig. 4, the black circle/ovals denote substations where buses
upgrading substations [7]. of different voltage levels are present, while the colors red, blue,
Taking these facts into consideration, for the study done here, and green denote the respective voltage networks.
the following costs were associated with the different compo- The PMU placement results for basic observability of this
nents of a synchrophasor installation: system are shown in Table I. For creating this table, ZI buses
1) Cost of disrupting a substation = USD 40 000. were treated as normal buses. When specified numerically, en-
2) Cost of a single DULR device = USD 2000. tries i − j in the third column imply that the PMUs monitor i
3) Cost of a single PDC device = USD 8000 [35], [36]. end of line i − j, where i and j are bus numbers. The results for
Fig. 3 shows the typical design of a substation synchropha- [28] and the proposed approach were obtained using DULRs.
sor architecture that is the basis of the proposed study. TPMUs The number of DULRs required was equal to the number of
(if present) are assumed to already be in place (shown by dot- lines monitored. The results for [12], [37], [40]–[43] were ob-
ted black lines). The proposed formulation is designed to add tained using TPMUs. When a TPMU was placed on a bus and
more DULRs to the substations to provide the desired number the lines monitored by it were not mentioned, then all the lines
of phasor measurements required for complete observability. A that emerged from that bus were assumed to be observed by that
stand-alone PDC is located at every substation where a PMU is TPMU. That is, unless stated explicitly, measurement channel
placed. Some researchers have suggested optimizing the loca- limitation of TPMUs was not considered. The cost of monitoring
tions of PDCs to reduce the cost of communication infrastructure a line using TPMU was set equal to the cost of a DULR device.
[37]–[39]. However, the stand-alone PDC serves two purposes: Also, PDCs were assumed to be placed at those substations
(a) the synchrophasor system becomes independent of (equip- where PMUs were placed.
558 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 32, NO. 1, JANUARY 2017

TABLE I
COST COMPARISON OF PROPOSED TECHNIQUE WITH OTHER APPROACHES FOR THE IEEE 30 BUS SYSTEM


Refs [42] and [43] had two optimal solutions for the IEEE 30 bus system.

TABLE II
COST COMPARISON OF PROPOSED TECHNIQUE WITH OTHER APPROACHES FOR THE THREE LARGE TEST SYSTEMS

Test System Method #TPMU #Lines Monitored #Substations Disrupted System Observable if Tap Ratios are Unknown Total Cost (in USD)

IEEE 118 Bus Ref. [12] 32 132 32 No 1.800 M


Ref. [40] 32 132 31 No 1.752 M
Ref. [41] 32 119 32 No 1.774 M
Ref. [42]∗ 32 126 32 No 1.788 M
32 125 31 No 1.738 M
Ref. [43]∗ 44 74 41 No 2.116 M
38 80 35 No 1.840 M
Proposed – 84 31 Yes 1.656 M
IEEE 300 Bus Ref. [41] 87 337 76 No 4.322 M
Ref. [48] 95 382 80 No 4.604 M
Proposed – 200 75 Yes 4.000 M
Polish 2383 Bus Ref. [41] 746 2503 717 No 39.422 M
Ref. [48] 799 2802 753 No 41.748 M
Proposed – 1572 704 Yes 36.936 M


Refs [42] and [43] had two different optimal solutions for the IEEE 118 bus system.

In the next set of simulations, the following constraints are TABLE III
COST COMPARISON OF PROPOSED TECHNIQUE WITH [29] WHILE CONSIDERING
added to the optimization: (a) Substation 21 is unsuitable for HIGH-VOLTAGE NETWORKS OF THE THREE TEST SYSTEMS AS CRITICAL
synchrophasor deployment; (b) Buses 8 and 13 are critical for
system stability purposes and need N − 1 redundancy; and (c)
Test #Lines #Substations Total Cost
Bus 30 has a TPMU on it which monitors its voltage as well as Syst. Method #TPMU Monitored Disrupted (in USD)
the currents that flow in lines 30–27 and 30–29. Section III-C
IEEE 118 Bus Ref. [29] 39 135 36 1.998 M
explains how the proposed methodology handles these practical Proposed – 88 34 1.808 M
constraints. The results are shown in Fig. 4, where the thick IEEE 300 Bus Ref. [29] 96 356 81 4.600 M
black lines indicate buses observed by the TPMU at bus 30. The Proposed – 206 77 4.108 M
Polish 2383 Bus Ref. [29] 782 2601 737 40.494 M
abbreviations CRIT BUS and PROH SUB denote critical bus Proposed – 1599 712 37.374 M
and prohibited substation, respectively. The colored blue dots
indicate locations where DULRs must be added. From the figure
it becomes clear that all buses are observed by the combination
of the TPMU at bus 30 and the 19 DULRs that were added in 8 The total cost for this DULR placement scheme comes out to be
substations (S2, S4, S6, S8, S10, S16, S20, and S22). Moreover, USD 422 000 = ((40 000 × 8) + (2000 × 19) + (8000 × 8)).
no DULR is placed at the prohibited substation (S21) while the This example highlights the ability of the proposed approach to
critical buses (8 and 13) are observed by independent DULRs. simultaneously handle different practical constraints.
PAL et al.: PMU PLACEMENT SCHEME CONSIDERING REALISTIC COSTS AND MODERN TRENDS IN RELAYING 559

TABLE IV
EFFECT OF ZI BUSES ON RESULTS OBTAINED USING PROPOSED APPROACH∗

Test #Lines #Substations Total Cost CPU


System Scenario #TZI #PZI Monitored Disrupted (in USD) Time (s)

IEEE 118 Bus Basic Observability – – 84 31 1.656 M 0.089763


Basic Observability considering HV buses as Critical – – 88 34 1.808 M 0.066501
Basic Observability considering ZI Buses 10 2 82 30 1.604 M 0.187890
Basic Observability considering ZI Buses and HV buses as Critical 10 2 88 33 1.760 M 0.062640
IEEE 300 Bus Basic Observability – – 200 75 4.000 M 0.038525
Basic Observability considering HV buses as Critical – – 206 77 4.108 M 0.041276
Basic Observability considering ZI Buses 67 20 193 68 3.650 M 0.051294
Basic Observability considering ZI Buses and HV buses as Critical 67 20 199 71 3.806 M 0.041554
Polish 2383 Bus Basic Observability – – 1572 704 36.936 M 1.314919
Basic Observability considering HV buses as Critical – – 1599 712 37.374 M 1.179524
Basic Observability considering ZI Buses 553 376 1350 567 29.916 M 6.892090
Basic Observability considering ZI Buses and HV buses as Critical 553 376 1380 577 30.456 M 6.787720


For the three large test systems, information about the substations which were disrupted and the lines on which the DULRs were placed can be found in [47].

C. Application to Large Systems of the critical portions of the system with only a slight increase
The proposed approach was next applied to IEEE 118 bus, in total investment.
IEEE 300 bus, and Polish 2383 bus systems. The data for the test In the simulations done so far, all buses were assumed to have
systems was obtained from MATPOWER [44] toolbox of MAT- non-zero injections. However, ZI buses do exist in real systems.
LAB [45]. The ILP optimization was performed using GUROBI In order to account for their presence, those ZI buses of the
[46]. The computations were performed on an Intel (R) Core i7 three large test systems which satisfied the IvZIB condition
Processor having a speed of 2.60 GHz and an installed memory described in Section III-C point 5 were treated as ZI buses, and
(RAM) of 16 GB. By combining buses into substations (based the optimizations described in Tables II and III were repeated.
on the locations of the transformers), the three test systems be- The results obtained are shown in Table IV. From the table it is
came a 107-substation, a 184-substation, and a 2215-substation realized that when properly handled, ZI buses can significantly
system, respectively [47]. The results obtained by comparing reduce the cost of synchrophasor deployment without compro-
the proposed approach with other techniques is shown in Ta- mising the accuracy of state observability. Table IV also gives
ble II. The comparison was made while treating ZI buses as the CPU time required for performing the optimizations based
normal buses. Also, unless specified otherwise, all the lines that on the proposed approach.
emerged out of the bus where the TPMU was placed were as-
sumed to be observed by it. Finally, the number of PDCs were V. CONCLUSION
assumed to be equal to the number of disrupted substations. Now that PMUs are being added in bulk in power networks,
From the table it becomes clear that minimizing the number of new formulations of the OPP problem must be considered. Due
buses where PMUs must be placed does not result in a signif- to the emergence of DULRs, the device cost is no longer the
icant decrease in cost of synchrophasor deployment. However, primary impediment to synchrophasor deployment. Moreover,
by reducing the number of substations where installations must it is neither necessary nor practical to place these devices at all
be made, the overall cost can be substantially reduced. Further- available locations. Keeping this in mind, this paper proposes
more, among the compared techniques, the proposed approach an ILP-based DULR placement scheme that minimizes overall
is the only one that ensures system observability when the tap cost while ensuring adequate redundancy under device failures
ratios are not known. Therefore, given that no single technique and/or line outages to the most critical assets. The novelty of this
can be universally superior to all others, the proposed approach paper lies in using a realistic cost objective that considers both
does provide unique techno-economic benefits. the cost of disrupting substations and the cost of DULRs. Thus,
In the next set of simulations, the highest voltage networks communication infrastructure cost, (cyber)-security infrastruc-
of the three test systems were assumed to be critical, requiring ture cost, labor cost, as well as device cost are simultaneously
N − 1 redundancy. This is a valid assumption because utilities optimized. At the same time, practical constraints imposed on
tend to initially place PMUs on their highest voltage level buses the basic objective (of observability) ensure that the results ob-
[49], [50]. The number of high-voltage buses in the three test tained have real-world applications. Therefore, the proposed
systems are 11, 14 and 50, respectively [44], [45]. Table III scheme provides an optimal techno-economic balance to the
compares the results obtained using the proposed method and OPP problem.
the technique developed in [29]. The number of PDCs required
were assumed to be equal to the number of substations disrupted.
From Table III it becomes clear that the proposed method is able APPENDIX
to achieve the desired objective for all the three test systems at Let Γ denote the total cost budget for DULRPP. Thus, the
a lower total cost. A comparison of Tables II and III shows that goal of DULRPP is to place DULRs for complete observability
the proposed approach is able to guarantee real-time protection while ensuring the total cost is ≤ Γ. Before we establish the
560 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 32, NO. 1, JANUARY 2017

complexity of DULRPP, we provide a necessary graph theoretic Laboratory at Virginia Tech have contributed greatly towards
definition. Given an undirected graph H (VH , EH ), a dominating this research.
set of H is a subset V
⊆ VH of nodes such that every node
v ∈ VH − V
is adjacent to some node w ∈ V
; that is, the edge
{v, w} is in EH . In such a case, we say that v is dominated by w. REFERENCES
A dominating set of minimum cardinality is called a minimum [1] A. G. Phadke, J. S. Thorp, and K. J. Karimi, “State estimation with phasor
dominating set (MDS). It is well known that any dominating set measurements,” IEEE Trans. Power Syst., vol. 1, no. 1, pp. 233–238,
Feb. 1986.
V
of a connected undirected graph H can be modified without [2] M. Gol and A. Abur, “A hybrid state estimator for systems with limited
increasing |V
| so that each node w ∈ V
has an edge to at least number of PMUs,” IEEE Trans. Power Syst., vol. 30, no. 3, pp. 1511–1517,
one node v ∈ VH − V
. May 2015.
[3] Y. Chakhchoukh, V. Vittal, and G. T. Heydt, “PMU based state estima-
Theorem 1: DULRPP is NP-complete. tion by integrating correlation,” IEEE Trans. Power Syst., vol. 29, no. 2,
Proof: It is easy to see that DULRPP is in NP, since one pp. 617–626, Mar. 2014.
can guess a placement of DULRs and verify efficiently that it [4] M. Gol and A. Abur, “A robust PMU based three-phase state estima-
tor using modal decoupling,” IEEE Trans. Power Syst., vol. 29, no. 5,
provides full observability and that its cost is at most Γ. pp. 2292–2299, Sep. 2014.
We establish the NP-hardness of DULRPP through a reduc- [5] K. D. Jones, J. S. Thorp, and R. M. Gardner, “Three-phase linear state
tion from the MDS problem defined as follows: given a con- estimation using phasor measurements,” in Proc. IEEE Power Eng. Soc.
General Meeting, Vancouver, BC, Canada, Jul. 21–25, 2013, pp. 1–5.
nected undirected graph H (VH , EH ) and an integer Q ≤ |VH |, [6] U.S. Department of Energy, Electricity Delivery and Reliability, “Syn-
does H have a dominating set of size at most Q? MDS is known chrophasor technologies and their deployment in the recovery act smart
to be NP-complete [51]. grid programs,” Aug. 2013. [Online]. Available: http://energy.gov/sites/
prod/files/2013/08/f2/SynchrophasorRptAug2013.pdf
Given an instance of the MDS problem consisting of the graph [7] U.S. Department of Energy, Office of Electricity Delivery and Energy
H (VH , EH ) and integer Q, we construct an instance of DULRPP Reliability, “Factors affecting PMU installation costs,” Oct. 2014. [On-
as follows. Let |VH | = n and |EH | = m. The graph G (V, E) line]. Available: https://www.smartgrid.gov/files/PMU-cost-study-final-
10162014_1.pdf
of the DULRPP instance is identical to H; that is V = VH and [8] N. M. Manousakis, G. N. Korres, and P. S. Georgilakis, “Taxonomy of
E = EH . Further, each node of V is a block by itself; that is, PMU placement methodologies,” IEEE Trans. Power Syst., vol. 27, no. 2,
there are n = |V| blocks. The cost ci of disrupting any block is pp. 1070–1077, May 2012.
[9] F. Aminifar, M. Fotuhi-Firuzabad, A. Safdarian, A. Davoudi, and
chosen as m + 1 where 1 ≤ i ≤ n. The cost of each DULR is M. Shahidehpour, “Synchrophasor measurement technology in power sys-
chosen as 1. The cost budget Γ is chosen as Q (m + 1) + m. tems: Panorama and state-of-the-art,” IEEE Access, vol. 2, pp. 1607–1628,
This completes the construction. We now prove that there is a Jan. 2015.
[10] V. Kekatos, G. B. Giannakis, and B. Wollenberg, “Optimal placement
solution to DULRPP if and only if there is a solution to the MDS of phasor measurement units via convex relaxation,” IEEE Trans. Power
problem. Syst., vol. 27, no. 3, pp. 1521–1530, Aug. 2012.
Suppose H has a dominating set V
with |V
| ≤ Q. As stated [11] O. Gomez, M. A. Rios, and G. Anders, “Reliability-based phasor mea-
surement unit placement in power systems considering transmission
earlier, we may assume that each node of V
has an edge to at line outages and channel limits,” IET Gener., Transm., Distrib., vol. 8,
least one node of V − V
. We choose the nodes of V
as the no. 1, pp. 121–130, Jan. 2014.
substations to be disrupted. We place a DULR on each edge [12] L. Huang, Y. Sun, J. Xu, W. Gao, J. Zhang, and Z. Wu, “Optimal PMU
placement considering controlled islanding of power system,” IEEE Trans.
{w, v} that joins a node w ∈ V
to a node v ∈ V − V
. This Power Syst., vol. 29, no. 2, pp. 742–755, Mar. 2014.
DULR is placed at the end corresponding to w (since w ∈ V
is [13] B. Gou and R. G. Kavasseri, “Unified PMU placement for observability
a substation that will be disrupted). Using the facts (a) V
is a and bad data detection in state estimation,” IEEE Trans. Power Syst.,
vol. 29, no. 6, pp. 2573–2580, Nov. 2014.
dominating set, (b) each node w ∈ V
has an edge to at least one [14] Y. Wang, C. Wang, W. Li, J. Li, and F. Lin, “Reliability-based incremental
node in V − V
and, (c) number of DULRs placed is at most m PMU placement,” IEEE Trans. Power Syst., vol. 29, no. 6, pp. 2744–2752,
(the number of edges in G); it is easy to verify that this DULR Nov. 2014.
[15] J. Aghaei, A. Baharvandi, A. Rabiee, and M. A. Akbari, “Probabilistic
placement observes all the nodes and the total cost is at most Γ. PMU placement in electric power networks: An MILP-based multiobjec-
In other words, there is a solution to DULRPP. tive model,” IEEE Trans. Ind. Informat., vol. 11, no. 2, pp. 332–341, Apr.
For the converse, suppose there is a solution to DULRPP. In 2015.
[16] R. Sodhi and M. I. Sharieff, “Phasor measurement unit placement frame-
this solution, if Q + 1 or more substations are disrupted, then work for enhanced wide-area situational awareness,” IET Gener., Transm.,
the total cost will be at least (Q + 1) (m + 1), which exceeds Distrib., vol. 9, no. 2, pp. 172–182, Jan. 2015.
the budget Γ = Q (m + 1). Hence, the number of substations [17] P. Yang, Z. Tan, A. Wiesel, and A. Nehorai, “Placement of PMUs con-
sidering measurement phase-angle mismatch,” IEEE Trans. Power Del.,
disrupted is at most Q. Let V
be set of substations that are vol. 30, no. 2, pp. 914–922, Apr. 2015.
disrupted. Using the fact that we have a valid DULR placement, [18] J. Qi, K. Sun, and W. Kang, “Optimal PMU placement for power system
it is easy to verify that V
forms a dominating set for G. Further, dynamic state estimation by using empirical observability Gramian,” IEEE
Trans. Power Syst., vol. 30, no. 4, pp. 2041–2054, Jul. 2015.
since |V
| ≤ Q, we have a solution to MDS, and this completes [19] N. M. Manousakis and G. N. Korres, “A weighted least squares algorithm
the proof. for optimal PMU placement,” IEEE Trans. Power Syst., vol. 28, no. 3, pp.
3499–3500, Aug. 2013.
[20] N. P. Theodorakatos, N. M. Manousakis, and G. N. Korres, “A sequential
quadratic programming method for contingency constrained phasor mea-
ACKNOWLEDGMENT surement unit placement,” Int. Trans. Electr. Energy Syst., vol. 25, no. 12,
The authors would like to thank especially Prof. J. S. Thorp pp. 3185–3211, Dec. 2015.
[21] A. E. Leon and J. A. Solsona, “Power oscillation damping improvement
for his valuable inputs. Many faculty and students of the Power by adding multiple wind farms to wide-area coordinating controls,” IEEE
Laboratory and the Network Dynamics and Simulation Science Trans. Power Syst., vol. 29, no. 3, pp. 1356–1364, May 2014.
PAL et al.: PMU PLACEMENT SCHEME CONSIDERING REALISTIC COSTS AND MODERN TRENDS IN RELAYING 561

[22] H. Morais, P. Vancraeyveld, A. H. B. Pedersen, M. Lind, H. Johannsson, [44] R. D. Zimmerman, C. E. Murillo-Sánchez, and R. J. Thomas, “MAT-
and J. Ostergaard, “SOSPO-SP: Secure operation of sustainable power POWER steady-state operations, planning and analysis tools for power
systems simulation platform for real-time system state evaluation and systems research and education,” IEEE Trans. Power Syst., vol. 26, no. 1,
control,” IEEE Trans. Ind. Informat., vol. 10, no. 4, pp. 2318–2329, Nov. pp. 12–19, Feb. 2011.
2014. [45] MATLAB (Computer Software) Release 2015a, The MathWorks, Inc.,
[23] Z. H. Rather, Z. Chen, P. Thogerson, P. Lund, and B. Kirby, “Realistic Natick, MA, USA, Mar. 2015.
approach for phasor measurement unit placement: consideration of prac- [46] GUROBI Optimization, Inc., “GUROBI Optimizer Reference Manual,”
tical hidden costs,” IEEE Trans. Power Del., vol. 30, no. 1, pp. 3–15, Feb. Version 6.0.2, Houston, TX, USA, Feb. 2015. [Online]. Available:
2015. http://www.gurobi.com
[24] W. Bao, R. Guo, Z. Han, L. Chen, and M. Lu, “A substation oriented [47] Results for the Three Large Test Systems. Results_IEEE118_IEEE300_
approach to optimal phasor measurement units placement,” J. Electr. Eng. Polish2383.pdf. (2016). [Online]. Available: http://staff.vbi.vt.edu/
Technol,, vol. 9, pp. 742–753, Sep. 2014. anam86/Results_IEEE118_IEEE300_Polish2383.pdf
[25] C. Mishra, K. D. Jones, A. Pal, and V. A. Centeno, “A binary PSO-based [48] N. Xie, F. Torelli, E. Bompard, and A. Vaccaro, “A graph theory based
optimal substation coverage algorithm for PMU installations in practical methodology for optimal PMUs placement and multiarea power system
systems,” IET Gener., Transm., Distrib., vol. 10, no. 2, pp. 555–562, Feb. state estimation,” Electr. Power Syst. Res., vol. 119, pp. 25–33, Feb. 2015.
2016. [49] K. D. Jones, A. Pal, and J. S. Thorp, “Methodology for performing syn-
[26] A. Pal, G. A. Sanchez-Ayala, J. S. Thorp, and V. A. Centeno, “A chrophasor data conditioning and validation,” IEEE Trans. Power Syst.,
community-based partitioning approach for PMU placement in large sys- vol. 30, no. 3, pp. 1121–1130, May 2015.
tems,” Electr. Power Compon. Syst., to be published. [50] A. Pal, P. Chatterjee, J. S. Thorp, and V. A. Centeno, “On-line calibration
[27] O. Gomez, C. Portilla, and M. A. Rios, “Reliability analysis of substation of voltage transformers using synchrophasor measurements,” IEEE Trans.
monitoring systems based on branch PMUs,” IEEE Trans. Power Syst., Power Del., vol. 31, no. 1, pp. 370–380, Feb. 2016.
vol. 30, no. 2, pp. 962–969, Mar. 2015. [51] M. R. Garey, and D. S. Johnson, Computers and Intractability: A Guide
[28] R. Emami and A. Abur, “Robust measurement design by placing synchro- to the Theory of NP-Completeness. San Francisco, CA, USA: Freeman,
nized phasor measurements on network branches,” IEEE Trans. Power 1979.
Syst., vol. 25, no. 1, pp. 38–43, Feb. 2010.
[29] A. Pal, G. A. Sanchez, V. A. Centeno, and J. S. Thorp, “A PMU placement
scheme ensuring real-time monitoring of critical buses of the network,”
Anamitra Pal (S’10–M’14) received the B.E. de-
IEEE Trans. Power Del., vol. 29, no. 2, pp. 510–517, Apr. 2014.
gree (summa cum laude) in electrical and electronics
[30] G. N. Korres, P. J. Katsikas, and G. C. Contaxis, “Transformer tap setting
engineering from the Birla Institute of Technology,
observability in state estimation,” IEEE Trans. Power Syst., vol. 19, no. 2,
Mesra, India, in 2008, and the M.S. and Ph.D. degrees
pp. 699–706, May 2004.
in electrical engineering from Virginia Tech, Blacks-
[31] M. Shiroie and S. H. Hosseini, “Observability and estimation of trans-
burg, VA, USA, in 2012 and 2014, respectively. From
former tap setting with minimal PMU placement,” in Proc. IEEE Power
2008 to 2010, he was a Manager with Tata Steel, Ltd.,
Eng. Soc. General Meeting-Conv. Del. Electr. Energy 21st Century, Pitts-
Jamshedpur, India. He was also a summer intern with
burgh, PA, USA, Jul. 20–24, 2008, pp. 1–4.
Electric Power Group, LLC, Pasadena, CA, USA, in
[32] G. N. Korres, N. M. Manousakis, T. C. Xygkis, and J. Löfberg, “Op-
2012 and 2013. He is currently an Applied Electrical
timal phasor measurement unit placement for numerical observability
and Computer Scientist in the Network Dynamics and
in the presence of conventional measurements using semidefinite pro-
Simulation Science Laboratory at the Biocomplexity Institute of Virginia Tech,
gramming,” IET Gener., Transm., Distrib., vol. 9, no. 15, pp. 2427–2436,
Blacksburg. His research interests include power system modeling, transient
Nov. 2015.
and dynamic stability analysis, and wide area measurements-based protection,
[33] N. C. Koutsoukis, N. M. Manousakis, P. S. Georgilakis, and G. N. Korres,
monitoring, and control.
“Numerical observability method for optimal phasor measurement units
placement using recursive Tabu search method,” IET Gener., Transm.,
Distrib., vol. 7, no. 4, pp. 347–356, Apr. 2013.
[34] K. G. Khajeh, E. Bashar, A. M. Rad, and G. B. Gharehpetian, “Integrated
model considering effects of zero injection buses and conventional mea- Anil Kumar S. Vullikanti (M’11) received the Bach-
surements on optimal PMU placement,” IEEE Trans. Smart Grid, to be elor of Technology degree in computer science and
published. engineering from the Indian Institute of Technology,
[35] G. E. Multilin P30 Phasor Data Concentrator. (2016). [Online] Available: Kanpur, India, in 1993, and the Ph.D. degree in com-
https://www.gedigitalenergy.com/multilin/catalog/P30.htm puter science from the Indian Institute of Science,
[36] SEL-3373 Station Phasor Data Concentrator. (2016). [Online] Available: Bangalore, India, in 1999.
https://www.selinc.com/SEL-3373/ He is an Associate Professor at the Department of
[37] M. Shahraeini, M. S. Ghazizadeh, and M. H. Javidi, “Co-optimal place- Computer Science and the Biocomplexity Institute of
ment of measurement devices and their related communication infrastruc- Virginia Tech, Blacksburg, VA, USA. Prior to this, he
ture in wide area measurement systems,” IEEE Trans. Smart Grid, vol. 3, was a Technical Staff Member with the Los Alamos
no. 2, pp. 684–691, Jun. 2012. National Laboratory, Los Alamos, NM, USA. His
[38] D. Georges, “Optimal PMU-based monitoring architecture design for research interests include approximation algorithms, mobile computing, com-
power systems,” Control Eng. Practice, vol. 30, pp. 150–159, Sep. 2014. binatorial optimization, and simulation of large sociotechnical systems.
[39] M. B. Mohammadi, R. A. Hooshmand, and F. H. Fesharaki, “A new ap-
proach for optimal placement of PMUs and their required communication
infrastructure in order to minimize the cost of the WAMS,” IEEE Trans.
Smart Grid, vol. 7, no. 1, pp. 84–93, Jan. 2016. S. S. Ravi (M’85–SM’09) received the B.E. and M.E.
[40] S. Chakrabarti, E. Kyriakides, and D. G. Eliades, “Placement of synchro- degrees from the Indian Institute of Science, Banga-
nized measurements for power system observability,” IEEE Trans. Power lore, India, in 1977 and 1979, respectively, and the
Del., vol. 24, no. 1, pp. 12–19, Jan. 2009. Ph.D. degree in computer science from the Univer-
[41] J. De La Ree, V. Centeno, J. S. Thorp, and A. G. Phadke, “Synchronized sity of Pittsburgh, Pittsburgh, PA, USA, in August
phasor measurement applications in power systems,” IEEE Trans. Smart 1984. Since September 1984, he has been with the
Grid, vol. 1, no. 1, pp. 20–27, Jun. 2010. Computer Science Department at the University at
[42] M. H. F. Wen, J. Xu, and V. O. K. Li, “Optimal multistage PMU place- Albany—State University of New York, Albany, NY,
ment for wide-area monitoring,” IEEE Trans. Power Syst., vol. 28, no. 4, USA, where he is currently a Distinguished Teaching
pp. 4134–4143, Nov. 2013. Professor. His areas of interest include design and
[43] V. Rokkam and R. Bhimasingu, “A novel approach for optimal PMU analysis of algorithms, social network analysis, data
placement considering channel limit,” in Proc. IEEE Int. Conf. Power mining, fault-tolerant computing, wireless networks, and discrete dynamical
Syst. Technol., Chengdu, China, Oct. 20–22, 2014, pp. 1164–1171. systems.

You might also like