Professional Documents
Culture Documents
TCSP10406R0 PDF
TCSP10406R0 PDF
TABLE OF CONTENTS
1.0 SCOPE
LIST OF DRAWINGS
1.0 SCOPE
The purpose of this standard is to describe the techniques and procedure for installation of
XLPE and LPOF cables in the system of Transmission Buisness Unit (TBU) of Saudi
Electricity Company (SEC), Kingdom of Saudi Arabia.
2.2. All equipment required for proper installation shall be certified as operational and
strategically placed to avoid interruption of the installation process.
2.3 Prior to commencing the cable pull, all cable drums shall be set in place and all
necessary equipment, tools and hardware set up to start the cable pull.
Cable pulling shall not be started if it appears that climatic conditions will deteriorate
and cause the cable pulling sequence to be interrupted or delayed.
2.4.1 Barricades, warning signs and warning lights shall be provided to comply
with the requirements of the municipality and traffic police. Warning signs
both in Arabic and English, shall be displayed to caution pedestrians and
traffic. Warning list and signs shall be provided along the trench on both
sides. Steel plates or wooden planks shall be provided across the trench at
entrances to residences.
2.5.1 Cables can be seriously damaged if proper care is not exercised in its storage
in warehouse or contractors’ yards. Following factors shall be considered for
cable storage:
a. Cable drums shall be stored on firm and flat surfaces only so that
flanges of the drum do not sink in the ground.
3.1 The trenches and ducts into which the cable is to be installed must be clean and free
of projections. Stones, sharp edges, etc. that may damage the jacket either during the
installing operation or after the cable is placed in its final position.
3.2.1 All part of the cable shall be maintained under a positive oil pressure because
LPOF cables undergoes changes of hydraulic pressure due to differences in
elevation.
The route profile shall be verified and studied before deciding at which end
of the cable route to place the drum.
3.2.2 A flat profile with differences in elevation not exceeding the maximum oil
pressure of the cable drum oil reservoir will normally present little problem.
3.2.5 Where more than one cable section is involved, the sequence of cable pulling
may require some study. Once a cable has been pulled before the end is
removed from its cable drum, a temporary oil supply is required either from
an oil reservoir or by cross-connection with an adjacent cable section.
4.1 Prior to cable pulling into ducts, the duct must be cleaned with suitable brushes and
swabs followed by a mandrel test. A 300mm long wooden mandrel having a
diameter 20% less than the inside diameter of the duct shall be pulled through each
duct run. The mandrel must pass through freely and upon leaving the duct shall not
show evidence of scoring. To prevent injury to the cable by scraping on the manhole
frame or at the duct opening or in passing over other cables, a suitable flexible
feeding tube shall be used.
4.2 Before pulling cable into open trenches, the trench shall be graded and compacted
with a minimum of 150mm of the specified backfill material. The compacted
backfill materials shall be smooth and free of stones and projections which might
damage the cable. If the cable is to be pulled into a trench inside the substation, the
trench bottom slab shall be made of reinforced concrete.
An adequate number of cable rollers shall be placed in the trench, spaced at intervals
of 1.5 to 2 meters depending on the stiffness of the cable, sufficient to prevent the
cable dragging on the ground between rollers. Where the cable passes around bends,
rollers must be arranged to provide smooth passage and maintain correct installation
bending radii.
4.3 The cable drum is normally set up with the leading end of the cable coming from the
top of the drum. A tendency for turns of cable to become loose and unmanageable
results from pulling the cable from the bottom of the drum. A ramp of two or more
long rollers will assist the cable from the top of the drum into the trench or manhole.
Care must be taken so that minimum installation bending radii are not exceeded
when setting up the rollers leading the cable into the trench or manhole.
a. Hand pulling
b. Direct wind line pulling
c. Carrier wind line or “Bond Pulling”
d. Motorized rollers and puller drives
The selected method will depend on manpower and equipment available and upon
other considerations of pulling tension, sidewall pressure, route configuration and
cable characteristics.
4.4 Where direct wind line pulling is used, the cable end shall be fitted with a properly
designed pulling eye which transfers the winch line tension to the cable conductor.
Cable stockings or Kellems grips must not be used.
A dynamometer fitted to the cable winch is required so that the pulling tension on
the cable may be checked and that safe pulling tensions are not exceeded. To reduce
tension when pulling cable into ducts, a suitable lubricant shall be applied to the
cable. A recommended lubricant is 80% glycerin and 20% water by weight with a
thickening agent added of 1½% to 2½% hydroxyethyl-cellulose. The lubricant
recommended by the cable manufacturer can be used.
For convenience and cleanliness in splicing, the first and last 1.5m of the cable shall
not be lubricated.
Before completing the pulling-in operation and removing the cable end from the drum, a
temporary oil feed must be connected to the leading end of the cable. A source of degassed
cable oil, either a reservoir or an adjacent cable, must be ready and equipped with a suitable
length of treated and filled copper tubing.
The connection is made to the flared fitting on the end of the cable. Ensure that oil is
flowing from both cable and oil source while making the connection to avoid the ingress of
air. Once this connection has been made, the cable drum reservoir may be shutoff and the
cable removed from the drum.
If there is an excess of cable and it has to be cut and capped, this may only be done with the
cable end elevated to form a ‘U’ or oil trap below the point of cutting and with a positive
flow of oil applied to the remote end of the cable.
In all the operations of oil-filled cable installation, cable pulling, connection and
disconnection of oil supplies, cutting and capping, jointing, terminating, etc., the following
points must be observed:
5.1 No parts of the cable system shall be left without a positive oil pressure.
5.2 A source of pressurized degassed cable oil must be available at all times.
5.3 Consideration must be given to static hydraulic pressures when selecting the pressure
of the oil supply to be applied for temporary oil feeds.
5.4 All connectors must be made with a positive oil flow from both ends to be
connected.
5.5 After cutting and capping cable ends and after disconnecting any oil feed line, a
flush of oil shall be made through the fitting to ensure any trapped air is flushed out.
5.6 All oil feed points and accessible connections shall be secured from unauthorized
tampering or vandalism.
After the excavation of cable trench, the following works shall be done:
6.1.1 Pump out the water from the cable trench, if necessary
6.1.2 Remove any obstacles out of the trench
6.1.3 Prepare the laying tools, i.e. drum jacks, shaft tension meter and others stated
in Figure 06-02 and 06-03
6.1.4 Set the cable rollers with spaces of about 1.5m
Cable drum lagging shall be carefully removed. Cable can be unreeled from cable
drum mounted on the transporting trailer or an axle supported by jacks. Unreeling of
cable must be done so that the cable is reeled off from top of the drum. The drum
shall be turned by hand to reduce tension in the cable. The drum shall be rotated in a
direction opposite to the direction of the arrow marked on the drum. (Refer Figure
06-02).
6.3.1 It is very important that the cable not be bent to a radius too small nor be
subjected to abnormal tension. Refer to TES-P-104.05 for minimum bending
radius.
All handling of the cable shall be done smoothly and steadily without any
jerking.
a. Setting of Cable Drum Jacks: The drum shall be raised about 25cm
by adjusting the jacks to gain the same level.
If the trench is sufficiently wide, workers can carry the cable and lay it in the
trench or pull the cable over rollers in the trench by hand.
To carry the cable, the workmen are positioned three (3) to four (4) meters
apart in the trench so the weight shared per person does not exceed 30kg. If
the cable length to be laid is short and the cable coiled, the cable is uncoiled
outside the trench and carefully laid in the trench.
For pulling cable over rollers by hand, the workmen are positioned four (4) to
six (6) meters apart in straight sections of the trench and rollers with skid
plates are used at bends (minimum bending radius of the cable must be
maintained).
After the cable laid in the trench, the cable ends shall be temporarily
supported so that they will not be on ground or in water.
Pulling the cross-linked polyethylene insulated power cable can easily be done by
means of pulling eye previously attached to a cable end of each drum.
The cables shall not be pulled with an excessive tension or excessive sidewall
pressure at curve of the cable route during laying. The tension and the pressure
depend upon the material and cross-sectional area of the conductors. Allowable
pulling tension and sidewall pressure are as follows:
It must be noted that the cable shall be pulled with an appropriate speed to keep the
movements of cable and drum smooth. The drums must never rotate faster than the
cable run. If it is not braked in time, the cable may be drawn in under the drum and
be damaged. The cable must be laid out smoothly and without interruption.
6.5.1 Description
Typical procedures for the cable pulling work are shown on the following
Charter No. 1. Typical positions for cable pulling are shown on Figure 06-02
through 06-05.
Setting Cable pulling winch Inspection of the trench condition Transportation of cable
and drum of wire rope Cleaning the cable duct1 drum and setting it on
for cable pulling cable drum jack
on the pulling eye in line Setting portable telephone Setting guide rollers
with the cable to be along the cable trench with supporting facilities
pulled through duct bank
a. Pulling Direction: One of the ends of the route is selected for setting
the drums and the other is for the winch.
Gravels, sharp edges and any other objects shall be removed on the
bedding sand in the trench.
g. Cleaning the Cable Duct: Prior to the start of cable pulling work, the
cable duct shall be cleaned. Mandrel test shall be conducted.
The properly sized cleaning brush shall be passed through all cable
ducts to remove any obstacles in the duct.
h. Setting Cable Pulling Winch and Drum of Wire Rope for Cable
Pulling: The cable pulling winch is to be fixed firmly so that it can
stand against the pulling force. (Refer to Fig. 06-01).
The wire rope drum for cable pulling shall be settled at the available
position in order to roll up the wire rope easily.
i. Setting the Cable Drum on Cable Drum Jack: The cable drum
transported to the construction site shall be set on the cable drum jack.
The cable drum and the cable drum jack shall be settled at proper
position for cable pulling.
j. Inspecting the Surface of Cable and Oil Leakage: The outer surface
of the cable, oil feeding pipe and cable drum pressure tank shall be
visually inspected and checked to detect oil leakage.
The intervals of the rollers shall be kept about 1.5 to 2m. The rollers
shall be maintained to enhance smooth rotation. If the cable is
planned to be pulled through a curve, curve rollers shall be placed at
proper positions in order to keep the allowable cable bending radius
as per TES-P-104.05.
n. Connecting Cable to Wire Rope for Cable Pulling: The pulling eye
hook that is fixed at the top of the cable shall have the proper size to
be connected to the wire rope for cable pulling through a swivel and
shackles.
o. Pulling Cable: After the facilities and the equipment are properly set,
the portable telephones shall be installed at both ends of the pull with
provision of tapping within the section being pulled.
They are utilized to control the pulling speed and for other
communication.
p. Cable pulling shall start only if all cables required for route’s section
to be pulled are available.
When the leading end of the cable approaches the terminating point at
the winch side or the tail end of the cable is just going off the drum,
the pulling work shall be stopped. The oil feeding copper pipe which
is fastened to the pressure tank on the cable drum and connected to
the cable and tank on drum shall be loosened and extended gradually
by exchanging of pressure tanks.
At this time, the oil shall be flowing over from both outlets
(oil feeding pipe of Tank B and extra connector union on oil
feeding pipe shall be connected to Tank A) in order to avoid
penetration of the air in to the openings.
6. After the Tank B is connected to the cable, the oil feeding pipe
of the Tank A shall be disconnected.
6.6 Cable Routing and Installation Inside Substation Basement/Cable Entry Room
6.6.1 Properly secured trefoil cable clamps from the cable entry ducts in the cellar
wall to the sealing end bay positions shall be provided. The trefoil clamps
shall be installed every 700 mm along the cable route in the cable entry
room. The installed clamps shall have sufficient mechanical strength to
withstand torques in the cables due to faults, surges. SEC shall approve the
clamps prior to installation. All metallic cable support and accessories (i.e.
clamps, sealing) shall be connected (grounded) to the Substation ground
grid.
6.6.2 Necessary fire proofing of the cable inside substations cable entry room/
basement at new substation shall be provided in accordance with
TES-P-104.05.
6.6.3 The power cable circuits shall be tagged immediately on entering the cable
cellar with the name of route, length of the route, size of the conductor,
voltage level and type of insulation. Any crossing between power cables in
basement/cable entry room shall be avoided.
6.6.4 Adequate cable loop not less than five (5) meters in the basement and cable
entry room for any future termination work shall be provided.
6.6.5 The cable clamps and cable supports shall be made of non-magnetic
materials to make the cable clamping arrangements on steel supports do not
produce circulating current/heat in the steel supports.