You are on page 1of 2

Item - 1 Providing and laying one layer WBM 7.5cm consolidated thickness using1.

00 cum of stone agregare conforming to IRC grade per 10 sqm of road surface and 0.23
cum of binder materials of approved quality per 10 sqm of road surface I/c coinsdolidation of the same rolling of the surface to camber superelevation and grade by
using template straight edges and spirit level in layer not exceeding 100mm to 130mm thick (spread) thickness dry and wet rolling with 8 to 10 tonne roller i/c earth
edging 30 cm width on both side and applying binding materials as specified with carriage charge of all materials complete.
a) I.R.C. Grade-III

= Rs. 2,397.80 /cum


Transportation P/239
Above 40mm stone aggregate 0.45 x Rs 1,013.23 = Rs 455.95 /cum
Below 40 mm stone aggregate 0.45 x Rs 934.47 = Rs 420.51 /cum
Binding material/Moorum 0.23 x Rs 345.94 = Rs 79.57 /cum
= Rs. 3,353.83 /cum
Item - 2 Providing and laying bituminous macadam of 50mm as per clause 504.1 of "MOST" specification for base course with binder content @ 4% by weight of
total mix including preparation of bases excluding filling of pot holes, cleaning the surface with wire brushes etc. and providing suitable edge supports
heating of binder and aggregate handling of materials, screening, mixing, in hot mix plant conforming and transporting, laying and finishing with paver
finisher to the required level, grade and camber, rolling by power roller etc, complete including running.14.28.1 Using Bitumen (80/100)
p/149 = Rs.496.60 / sqm
i/c Preparing surface by brushing with wire brushes for remaining caked mud etc. Sweeping with brooms and
finally fanning the cleared surface with gunny bags to removed all loose dirt etc.b).Black topped surface.