1. General
1.1. All of documents and drawings shall be written in English and prepared in computer form by
a word processing package and a computer-aided-drafting (CAD) package.
If proposed equipment or components are substantially new or recently modified design, the
Purchaser may require the Supplier to provide detailed information including manufacturing
documents and drawings to enable the Owner to consider whether to accept such
equipment or components.
1.2. Document and drawing shall be submitted in both paper form and computer form as the
following number of sets;
Remark*1:
Following manual shall be provided 3 Originals and 2 sets of USBs or External Hard Drives.
- Operation and Maintenance Manual
- Commissioning Procedure Manual
- Shop Test Procedure Manual
For Information
Drawings and documents returned with marks "FOR INFORMATION" means the drawings
and documents have been regarded by the Purchaser as requiring no review,
The drawings and documents which are not subject to review shall be stamped "FOR
INFORMATION". However, the Purchaser shall reserve the right to comment on these
drawings and documents and inform Supplier to treat these drawings and documents as "FOR
REVIEW" subjects.
For Review
The Supplier shall furnish the drawings and documents submitted to the Purchaser for review
with a stamp "FOR REVIEW", the date of submission, and the Vendor's signature.
Issued Dec 16, 2020 Page 179
Requisition for
A copy of each drawing or document reviewed will be returned to the Supplier as stipulated
herein. Copies of drawings and documents returned to the Supplier will be accompanied by
stamps and/or markings by the Purchaser.
Purchaser will respond by returning the drawings and documents to the Supplier with marks
"FOR INFORMATION", "NO EXCEPTIONS NOTED", "EXCEPTIONS NOTED", or
"RETURNED FOR CORRECTION".
Final
When drawings and documents are returned with marks ''NO EXCEPTIONS NOTED" the
Supplier shall submit the drawing and documents for final distribution as entitled "Final
Drawings".
Exceptions Noted
When drawings and documents are returned marked "EXCEPTIONS NOTED", the changes
shall be made as noted thereon and the modifications shall be submitted to the Purchaser.
When drawings and documents are returned marked "RETURNED FOR CORRECTION", the
corrections shall be made as instructed by the Purchaser, and the corrections shall be
resubmitted.
When a drawing or a document is revised and resubmitted, the Supplier shall include and
issue number and revision description in the drawing revision block. All revisions pertaining to
that particular drawing or document issue shall be marked with a black circle, or otherwise
clearly noted on the drawing or document.
The review of drawings and documents by the Purchaser will not relieve the Supplier any part
of the Supplier's responsibility for the correctness of his drawings and documents. The
Purchaser will have the right to require Supplier to make any changes in design to make the
equipment conformed to the requirements and intent of the technical requirements without
additional cost to the Purchaser.
Issued Dec 16, 2020 Page 180
Requisition for
As-Built
After completion of erection and commissioning, the Supplier shall update all the drawings and
documents to incorporate changes in the field and submit them to the Purchaser with stamps
"AS-BUILT".
All of documents and drawings shall be arrived at the Purchaser’s office within the
schedule specified below. All schedule as below shall be counted from after the receipt
of order. All documents and drawings, which are not limited to below list, will be
provided by Supplier to Purchaser for EPC work.
First Submission
List of Require Document Schedule
(After Purchase order)
First Submission
List of Require Document Schedule
(After Purchase order)
Submission Schedule
List of Require Document
(After Purchase order)
Submission Schedule
List of Require Document
(After Purchase order)
Note
1. Every month within TBCth of the month (Cut of date, TBCth of the month)
2. Submission date is after inspection and test 1 week
3. Submission date is before on board 2 weeks
4. The manuals shall include a full and comprehensive set of operations and
maintenance instructions and drawings. The documents shall include
recommended maintenance schedules.
5. The system description and the specific equipment requirement for each major
item stating the function, required equipment, design basis, process data, method
of operation and control, and interface requirements with other systems of the
Plant.
3. Standards of Documents
3.1 Drawing
All drawings, diagrams, etc., shall comply with the following minimum requirements. Size
shall be in accordance with ISO A-series, as follows:
a. A0 841 x 1189 mm
b. A1 594 x 841 mm
c. A2 420 x 594 mm
d. A3 297 x 420 mm
e. A4 210 x 297 mm
Issued Dec 16, 2020 Page 183
Requisition for
In addition electronic copies of all drawings/manuals and other documents issued to the
Purchaser shall be provided in a format to be agreed between the Supplier and the
Purchaser.
Prints shall be on white paper of 110-gram quality. Blue prints will not be accepted. The title
block shall be in the lower right-hand corner of the drawing, and the drawing when submitted
shall be folded to A4 size with the complete title visible. The title block shall contain the
following minimum information:
1. Owner's name
2. Project title
3. Owner's contract number
4. Manufacturer's name
5. Manufacturer's drawing number
6. Brief title (clearly defining content of drawing)
7. Revision number and revision date
8. Scale and scale bar (when applicable)
9. Plant and equipment identification number
A space approximately 7 x 6 cm above the title block shall be left blank for approval stamp.
A revision column adjacent to the title block shall define briefly the revisions made for each