Part-A : Fill in the Blanks with one word answer: ( Each question carries 1 mark)

1. .........................................is financial advisor to Executive Engineer. *

Divisional Accountant

2. In work 100% check Measurement is to be done by................................... *

A.E.E

3. ...............are the only authorized persons to Record Measurement in MBs. *

Section officer AE/ JE

4. Financial year is starts from ....................... to ........................ *

1 st April to 31 st March

5. Measurements Book contains...................... Pages *

114 or 120

https://docs.google.com/forms/d/e/1FAIpQLScbK3eRK28pFH_mA_gsmQDJseCkJmDAmtM8uNZZRfkhqcsEtw/formResponse 1/4
12/1/2020 FOUNDATION CUM JOB COURSE FOR ENGINEERS (CFC Batch-4) SECOND WEEK TEST

6. Single Tender should be rejected generally with reference to ......................... *

Section 13 of KTPP act

7. KTPP Act means.................................................................................. *

KARNATAKA TRANSPARENCY IN PUBLIC PROC

8. Works costing more than one lakh are to be procured by......................... *

KW1

9. Works costing more than five lakh are to be procured only by......................... *

e- tender

10. In case of discrepancy in quoted rates in words and figures the


......................should be considered. *

least

11. 5% FSD can be returned to the renderer only after.................................. *

completion of DLP Period

https://docs.google.com/forms/d/e/1FAIpQLScbK3eRK28pFH_mA_gsmQDJseCkJmDAmtM8uNZZRfkhqcsEtw/formResponse 2/4
12/1/2020 FOUNDATION CUM JOB COURSE FOR ENGINEERS (CFC Batch-4) SECOND WEEK TEST

12. Additional Security Deposit can be returned after ……………. of the work *

issuing completion certificate

13. Purchase of Furniture’s should be accounted under …………………… *

Minor head of accounts

14. Deposit work should be classified under head of A/c …………………… *

Public account

15. Measurement book is being maintained in form no. ……………………. *

PWG 27

16. Work bills should be in form ……………………….. *

PWG 33b

17. What is the permissible velocity in gravity mains ? ……………………………………….. *

0.9-3 m/sec

18. What is the permissible velocity in pumping mains ? ……………………………………….. *

0.9-1.2 m/sec

https://docs.google.com/forms/d/e/1FAIpQLScbK3eRK28pFH_mA_gsmQDJseCkJmDAmtM8uNZZRfkhqcsEtw/formResponse 3/4
12/1/2020 FOUNDATION CUM JOB COURSE FOR ENGINEERS (CFC Batch-4) SECOND WEEK TEST

19. Self cleansing velocity in sewer line …………………………………………….. *

min 0.6 m/sec

20. What is the significance of closed intervals of contours …………………………. *

Steep slope

Back Next

Never submit passwords through Google Forms.

This content is neither created nor endorsed by Google. Report Abuse - Terms of Service - Privacy Policy

 Forms

https://docs.google.com/forms/d/e/1FAIpQLScbK3eRK28pFH_mA_gsmQDJseCkJmDAmtM8uNZZRfkhqcsEtw/formResponse 4/4

You might also like