You are on page 1of 1

DETAIL OF MEASUREMENT

L B H/D
Sr. Sub-Head and Items of work Nos Measurement Unit Quintity
No.
1 Plain/Reinforced cement concrete Grade M-20
(1:2:4nominal mix using concrete mixture) in
pier foundations
1st step 1 3.000 3.00 0.45 cum 4.05
2nd step 1 (3.00+1.2)/2 (3.00+1.2)/2 1.00 cum 4.41
3rd step 1 1.200 1.20 1.05 cum 1.51
9.97 Cum
2 Reinforced cement concrete Grade M-25 CC
1:1.5:3
Pier 1 3.14 0.3*0.3 3.00 cum 0.85
0.85 Cum
3 Reinforced cement concrete Grade M-25 in
superstructure
Beam 1 10.00 0.45 0.60 cum 2.70
Slab slopy portion 2 10.00 0.675 (0.25+0.15)/2 cum 2.70

5.40 Cum