You are on page 1of 2

BULK MATERIAL CONSUMPTION PER UNIT

Concrete Works
Cement Sand Aggregate
S.No Description Unit
Bags Cum 40mm 20mm
1 P.C.C 1:5:10 Cum 2.70 0.60 0.95
2 P.C.C 1:4:8 Cum 3.24 0.60 0.95
3 P.C.C 1:3:6 Cum 4.46 0.60 0.90
4 P.C.C 1:2:4 Cum 6.36 0.60 0.90
5 P.C.C 1:1.5:3 Cum 8.00 0.60 0.90
6 PCC 7.5 Cum 3.00 0.60 0.90
7 PCC M-10 Cum 4.40 0.60 0.90
8 RCC M-15 Cum 5.60 0.60 0.90
9 RCC M-20 Cum 6.20 0.60 0.85
10 RCC M-25 Cum 7.20 0.60 0.85
11 RCC M-30 Cum 8.00 0.60 0.85
12 RCC M-35 Cum 8.80 0.60 0.85
13 RCC M-40 Cum 9.00 0.55 0.85
14 RCC M-45 Cum 10.40 0.55 0.85
Note:
a) If the Minimum Cement Content specified by the client is more Than the above norms
norms. Then Client's Norms shall be adopted.
b) Sand Consumption Norms are Inclusive of Bulkage
c) For Pre-stressed Concrete works. The max cement Content is Limited to 10.60 bags
per Cum
d) For Bored Cast-Insitu Pile Concrete, the following Cement Content Shall be used
RCC M-20 400 Kgs
RCC M-25 445 Kgs
RCC M-30 495 Kgs
RCC M-35 545 Kgs
MASONRY WORKS
Cement Sand Bricks C.Blocks
S.no Description Unit
Bags Cum Nos Hol/Sol
1 BW in cm 1:3 -Table Moulded Bricks Cum 2.34 0.30 450
2 BW in cm 1:4 -Table Moulded Bricks Cum 1.74 0.30 450
3 BW in cm 1:5 -Table Moulded Bricks Cum 1.42 0.30 450
4 BW in cm 1:6 -Table Moulded Bricks Cum 1.25 0.28 450
5 Half BW in cm 1:4 -Table Moulded Bricks Sqm 0.27 0.035 52
6 Half BW in cm 1:4 -Table Moulded Bricks Sqm 0.21 0.035 52
7 200 mm tk Block masonry cm 1:3 Sqm 0.25 0.03 12.5
8 200 mm tk Block masonry cm 1:4 Sqm 0.20 0.03 12.5
9 200 mm tk Block masonry cm 1:5 Sqm 0.15 0.03 12.5
10 150 mm tk Block masonry cm 1:3 Sqm 0.20 0.022 12.5
11 150 mm tk Block masonry cm 1:4 Sqm 0.14 0.022 12.5
12 150 mm tk Block masonry cm 1:5 Sqm 0.12 0.022 12.5
13 100 mm tk Block masonry cm 1:3 Sqm 0.13 0.015 12.5
14 100 mm tk Block masonry cm 1:4 Sqm 0.10 0.015 12.5

S.No R.R.Masonry in CM 1:6 Qty Unit


1 Boulder 1.3 Cum
Bond Stone 9 Nos
Cement 1.65 Bags
Sand 0.35 Cum
2 SS Masonry in CM 1:6
Size stone 90 Cum
Bond Stone 15 Nos
Cement 1.5 Bags
Sand 0.32 Cum
3 SS Masonry in CM 1:5
Size stone 90 Cum
Bond Stone 15 Nos
Cement 1.98 Bags
Sand 0.35 Cum

PLASTERING WORKS
S.no Description Unit Cement Sand
1 12mm Tk in CM 1:3 Sqm 0.15 0.015 0.0153
2 12mm Tk in CM 1:4 Sqm 0.11 0.015
3 12mm Tk in CM 1:5 Sqm 0.09 0.015
4 12mm Tk in CM 1:6 Sqm 0.07 0.015
5 15mm Tk in CM 1:3 Sqm 0.18 0.018
6 15mm Tk in CM 1:4 Sqm 0.13 0.018
7 15mm Tk in CM 1:5 Sqm 0.11 0.018
8 15mm Tk in CM 1:6 Sqm 0.09 0.018
9 20mm Tk in CM 1:3 Sqm 0.23 0.03
10 20mm Tk in CM 1:4 Sqm 0.17 0.03
11 20mm Tk in CM 1:5 Sqm 0.14 0.03
12 20mm Tk in CM 1:6 Sqm 0.11 0.03
13 18mm Tk Plaster in two coats (12mm tk cm 1:5 & 6mm tk in cm 1:6) Sqm 0.13 0.03
14 18mm Tk Plaster in two coats (12mm tk cm 1:5 & 6mm tk in cm 1:3) Sqm 0.18 0.03
15 6mm Tk Ceiling Plaster in CM 1:3 Sqm 0.07 0.01
16 6mm Tk Ceiling Plaster in CM 1:4 Sqm 0.05 0.01
Note:
Where Plaster is to be finished with a floating coat of neat cement, take 2.2 kg per Sqm. Extra Cement

S.No Description of Items Unit Cement


Masonry Works In Bag
1 RR Masonry in CM 1:4 Cum 2.51
2 RR Masonry in CM 1:5 Cum 2.05
3 RR Masonry in CM 1:6 Cum 1.65
4 CR Masonry in CM 1:6 Cum 1.5
5 Projected Brick Bands drip Course in cm 1:6 Finished with 12mm tk Cement Plaster 1:6 Cum 2.51