LABOR COST

Date: December 6, 2020'


Project Name: INSTALLATION OF ELECTRICAL WIRING SYSTEM ON THE NEW HOUSE EXTENSION
Project Owner: MR.& MRS. VILLARAZA
Location: PCH 1 DAMILAG, MANOLO FORTICH BUKIDNON

SCOPE OF WORKS
Item No. Description Qty Unit Labor Cost Amount

A. INSTALLATION OF WIRING, CONDUITS AND FITTINGS FOR THE LIGHTINGS


1 Track Light (3 Lights) 1 set 330.00 330.00
2 Pendant Light 3 pcs 330.00 990.00
3 Led Strip Lights, 14.4W/m, 4000k, WW 10 m 80.00 800.00
4 Flourescent 1 pcs 330.00 330.00

B. INSTALLATION OF WIRING , CONDUITS AND FITTINGS FOR OUTLETS & SWITCHES


1 Duplex Universal Outlet, w/ ground 16 A, WWG-402 5 pcs 330.00 1,650.00
2 Switch, 3 Gang Wide Series, WWS-213, Wide Series 2 pcs 330.00 660.00

C. DESIGN AND LOAD COMPUTATION 1 lot 1,000.00 1,000.00


Evaluation of Existing Load Schedule, Wire Sizes, Fuses
and Re-Compute the Total Load, Wire Sizes and Breaker Protection
Total 5,760.00
Work Contingency, 5%
Total Labor Cost 5,760.00

Prepared by:

ENGR. JULIUS A. DEMATA, REE


Electrical Contractor