Integration Overview
This presentation discusses the basic concepts of integrating Oracle Projects (PA)
with five other Oracle Financials modules, namely Oracle General Ledger (GL), Oracle
Purchasing (PO), Oracle Payables (AP), Oracle Receivables (AR) and Oracle Fixed
Assets (FA).
It aims to explain the integration points under the following broad heads:
3
RAJU CHINTHAPATLA
Integration With Oracle General Ledger
PA collects detailed project cost and revenue. These costs are distributed to valid
accounts in the chart of accounts defined in the GL. PA uses AutoAccounting and
Flexbuilder features to derive these accounts. Once distributed, PA transactions are
then summarized and transferred into the journal import table. The journal import
process posts these transactions to the general ledger. The tieback costs and revenue
process in PA verifies that these costs and revenues were posted to valid account code
combinations in the general ledger.
Data Flow
Oracle predefines a journal source and several journal categories for this integration.
The journal source is called ‘Projects’ and the journal categories are as follows:
Labor Cost;
Burden Cost
Total Burdened Cost;
Usage Cost; and,
Revenue.
4
RAJU CHINTHAPATLA
Integration With Oracle General Ledger
Setup parameters – Project Accounting
(N) Setup>System>Implementation Options>Expnd/Costing (Tab Page)
5
RAJU CHINTHAPATLA
Integration With Oracle General Ledger
Setup parameters – Project Accounting
(N) Setup>System>Implementation Options>Billing (Tab Page)
6
RAJU CHINTHAPATLA
Integration With Oracle General Ledger
Setup parameters – General Ledger
(N) Setup>Journal>Sources
7
RAJU CHINTHAPATLA
Integration With Oracle General Ledger
8
RAJU CHINTHAPATLA
Integration With Oracle General Ledger
Concurrent Programs
The following concurrent processes must be executed from Projects, for the data to be
pushed into the journal import tables:
PRC: Interface Labor Costs to GL;
PRC: Interface Usage Costs to GL;
PRC: Interface Total Burdened Costs to GL;
Note: All costs should have been distributed before running these programs
Note: Invoices should have been generated before running this program
9
RAJU CHINTHAPATLA
Integration With Oracle General Ledger
Once data has been interfaced into the journal import tables, the journal import program
must be submitted from the General Ledger module. This process brings the summary
PA transactions into GL and are ready to be posted.
Once the journals are successfully posted, the Tieback processes have to be submitted
from PA. The tieback process identifies and updates Oracle Projects transactions that
have been interfaced to another application.
10
RAJU CHINTHAPATLA
Integration With Oracle Purchasing
Data Flow
Commitments from PO are visible in PA via the Project Status Inquiry (PSI) screen.
There is no intermediary import or interface table between these modules. However, for
project related requisitions and purchase orders, each line item must contain the
following PA information:
project name
task name
expenditure type
expenditure organization
expenditure item date
11
RAJU CHINTHAPATLA
Integration With Oracle Purchasing
Setup Parameters
There are no specific setups to integrate these two modules with the exception of the
Account Generator. Accounting rules need to be set up before charging Purchase
Requisitions and purchase orders against Projects.
In addition, the following profile options need to be reviewed and set as required:
This parameter allows us to enable or disable a user from over-riding the accounting
flexfield generated by the auto accounting. The parameter can be set at a site level as
well as at a responsibility level.
12
RAJU CHINTHAPATLA
Integration With Oracle Purchasing
Concurrent Programs
13
RAJU CHINTHAPATLA
Integration With Oracle Payables
The integration between PA and AP allows for three types of transactions to flow
between them. These are:
supplier invoices;
expense reports; and,
adjustments.
14
RAJU CHINTHAPATLA
Integration With Oracle Payables
Data Flow
Supplier invoices are sent from AP to PA. Each invoice must contain project related
information for this interface, as follows:
project number
task number
expenditure type
expenditure organization
expenditure item date
quantity, if setup option “Cost Rate Required” is set to “Yes”.
Expense reports entered into PA for project related expenditures are sent to AP via the
AP interface tables. AP creates invoices from these expense reports using the Invoice
Import feature, approves and pays the invoices and transfers these accounting
transactions directly to GL.
15
RAJU CHINTHAPATLA
Integration With Oracle Payables
16
RAJU CHINTHAPATLA
Integration With Oracle Payables
Setup Parameters
The following profile options need to be reviewed and set as required :
PA: Summarize Expense Report lines
PA: Default Expenditure Organization in AP/PO
When Importing from Payables, the Invoice Import Source should be = “Oracle
Projects”
Concurrent Programs
The following concurrent manager processes must be invoked to enable the interface
between AP and PA.
PA: Interface Supplier Invoices from Payables
PA: Interface Expense report from Payables
PA: Distribute Expense Report Costs
PA: Interface Expense Reports to Payables
PA: Tieback Expense Reports from Payables
17
RAJU CHINTHAPATLA
Integration With Oracle Payables
18
RAJU CHINTHAPATLA
Integration With Oracle Receivables
PA integrates into AR by generating draft invoices and sending them to AR for printing
and tracking customer payments.
Data Flow
PA loads the invoices into AR via AR’s Auto Invoice feature. Project information is
stored in the invoice via the Line Transaction flexfield.
Setup Parameters
Most of the parameters required for running auto invoice is predefined in Oracle. Viz.
Line Transaction Flexfield
Line Ordering Rules (PA Line Order)
Grouping Rules (PA Grouping Rule)
Invoice Source (PA Invoices)
19
RAJU CHINTHAPATLA
Integration With Oracle Receivables
Setup Parameters
(N) Setup>Financials>Flexfields>Descriptive>Segments – Query for “Line Transaction Flexfield”
20
RAJU CHINTHAPATLA
Integration With Oracle Receivables
Setup Parameters
(N) Setup>Transactions>Auto Invoice>Line Ordering Rules
21
RAJU CHINTHAPATLA
Integration With Oracle Receivables
Setup Parameters
(N) Setup>Transactions>Auto Invoice>Grouping Rules
22
RAJU CHINTHAPATLA
Integration With Oracle Receivables
Concurrent Programs
The following concurrent process must be executed for the data to be pushed into AR:
PRC: Generate Draft Revenue
PRC: Generate Draft Invoices
PRC: Interface Invoices to Receivables
Once data has been interfaced into AR, the Autoinvoice program must be run in AR:
(N) Interfaces > AutoInvoice > AutoInvoice Master Program - with Invoice Source of PA
INVOICES.
Once data has been interfaced to AR, you tieback interfaced invoices into PA by running
the following concurrent manager process:
23
RAJU CHINTHAPATLA
Integration With Fixed Assets
PA collects project related expenditures for capital projects. Using AutoAccounting and
Account generator features, these costs are assigned to a Construction In Process
(CIP) account. When the asset is ready to be placed in service, it is interfaced to FA.
Data Flow
When expenditures for capital projects are collected PA, they are classified as
capitilazable or non - capitalizable. These costs are then interfaced from PA to FA via
the FA Mass Additions Table from where they are posted to the FA Assets Table. They
are then posted to the GL via the GL interface table, at which point the CIP account is
relieved and costs transferred to the asset account.
24
RAJU CHINTHAPATLA
Integration With Fixed Assets
Setup Parameters
PA needs the following FA implementation features in place before data from PA can be
interfaced to FA.
Corporate book
Category flexfield
Location flexfield
Asset key flexfield
Concurrent Programs
25
RAJU CHINTHAPATLA
Integration With Fixed Assets
From FA, we have to review the mass additions and update the status of the lines from
New, Merged or Cost Adjustment to Post.
The Post Mass Additions Program has to be run after reviewing the lines.
After successful posting of the Asset lines, the following program has to be run from PA: