Service & Training Centre in Niteroi - RJ Thrusters Assembly & Test Plant in DDC - RJ
3
Regional Training Centre – South America
• More than 800 UT vessels delivered or under contruction worldwide. The first
UT vessel built is still in operation – UT 704 Stad Scotsman (1974) and the
UT Design celebrated it’s 40th anniversary in 2014
• An extensive part of the fleet in operation has ORO capabilities
• 54 UT vessels built and in order in Brazil (44 delivered/10 in order)
• 44 UT vessels built at Brazilian yards/19 of them for Brazilian owners. In
order: 10 to be built at Brazilian yards/all of them for Brazilian Owners
• 38 of 54 UT vessels in the Brazilian market have ORO capabilities
BRIEF PRESENTATION OF ROLLS-ROYCE DESIGN UT 535 E
Platform Supply - Oil Spill Response Vessel, Petrobras PSV- OSRV 750 - 10
• Hull lines and internal layout arrangements ensure cost competitive vessels
• RRM equipment system solution included in the design
• Detail engineering delivered to yards
BRIEF PRESENTATION OF ROLLS-ROYCE DESIGN UT 535 E
Main particulars & duties
Platform Supply - Oil Spill Response Vessel, Petrobras PSV- OSRV 750 - 10
Main particulars:
• Main dimensions 61,7 m x 14,00 m x 6,00
• Cargo deck 310m2
• ORO Platform 110 m2
• Deadweight 1500t
• Crew/passengers 21 persons
• ORO equipment according to Petrobras tender requirements
Main duties:
• Carrying of deck cargo,
• Transport of liquid cargo, Fresh water and Fuel oil
• Oil Spill Recovery, cap. 770 m3, tank washing arrangements.
• FW / Steam cap. for min. 7 days ORO operation,
• DFO and FW for min. 25 days standby, plus sailing in addition to 7 days ORO operation
• Oil Spill Dispersing
• Fire Fighting 1 -> 2 monitors midship and two top of wheel house
• DP 1
7
UT 535 E - References in Brazil:
6 vessels delivered
• Hull lines and internal layout arrangements ensure cost competitive vessels
• RRM equipment system solution included in the design
• Detail engineering delivered to yards
Developed version of the UT 535 E with ORO capabilities increased from 770 m3 to 1070 m3
BRIEF PRESENTATION OF ROLLS-ROYCE DESIGN UT 536 E
Main particulars & duties
Main particulars:
• Main dimensions 67,60 m x 14,80 m x 6,20 m
• Cargo deck 400 m2
• ORO platform 110 m2
• Deadweight 2000 t
• ORO equipment according to Petrobras tender requirements.
Main duties:
• Carrying of deck cargo,
• Transport of liquid cargo, Fresh water and Fuel oil
• Oil Spill Recovery, cap. 1070 m3, tank washing arrangements.
• FW / Steam cap. for min. 7 days ORO operation,
• DFO and FW for min 25 days standby, plus sailing in addition to 7 days ORO operation
• Oil Spill Dispersing
• Fire Fighting 1 -> 2 monitors midship and two top of wheel house
• DP 1
Thank you for your attention Rolls-