ANNEX B - TENTATIVE IMPLEMENTATION AND MANNING SCHEDULE

PROPOSED PROJECT IMPLEMENTATION SCHEDULE ( as of April 15, 2018)


Awarding of GENCON
Awarding of
Excavation Works Watertightness

2017 2018 2019 2020


Activity D J F M A M J J A S O N D J F M A M J J A S O N D J F
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
ACTIVITY
PRECONSTRUCTION 5 Months 9 Months `

CONSTRUCTION
4
Excavation Works M
5 Months
12
GENCON / Concreting Works M
12 Months
11
Aluminum and Glass Works / Watertightness 11 Months
M

Basic Architectural Works 14 Months

MEPF Works 18 Months

POST-CONSTRUCTION 2 Months

MILESTONE DATES
EXCAVATION WORKS INCLUSIVE DATES

a. Issuance of BID PLANS (Excavation Works) January 15, 2018


b. BIDDING Stage January 15, 2018 to April 15, 2018
Awarding of Excavation Works April 15, 2018
Acquisition of Excavation Permit April 15 to May 15, 2018
c. Start of Excavation WORKS April 15, 2018
END of Excavation WORKS September 15, 2018

GENERAL CONSTRUCTION WORKS

a. Issuance of BID PLANS May 15, 2018


b. BIDDING Stage May 15, 2018 to August 15,2018
Awarding of GENCON Works August 15, 2018
Acquisition of Building Permit August 15 to September 15, 2018
c. START of GENCON WORKS August 15, 2018
END of GENCON Works January 30, 2020

FAÇADE WORKS

a. Awarding of Aluminum , Glass and Glazing Works December 15, 2018


b. Water Tightness November 15, 2019