Tank M&I Status

11
M&I Completed
09 07 05 03 01

M&I in progress
12 10 08 06 02
04

M&I yet to be done


Fueling Growth with Innovation & Technology

15 14 13 M&I of 3 Nos tanks – PT- 13, 06 & 10 in


progress

16 17 18 Internal Inspection of old 15 tanks is


scheduled to be completed by 2023 & M&I of
new 5 Nos tanks will be carried out as per 15
19 20
year

PL HO Approved Revised Rolling Plan with M&I


periodicity of 15 years based on Acoustic Emission Test
results
02/06/22 दक्षिण पूर्वी क्षेत्र पाइपलाइन 1
Tank M&I Rolling Plan & Status
M&I Due as per Approved
Tank Year and Month of M&I Planned
Rolling Plan- 15 years Remarks
M&I Status Number M&I completion interval in

PT-15 Sept’ 2016 2031


PT-08 Nov’2017 2032
PT-04 Nov’2018 2033
Completed PT-03 Oct’2019 2034 -
PT-01 Feb’2020 2035
PT-02 Jun’2021 2036
Fueling Growth with Innovation & Technology

PT-14 Nov’2021 2036


Expected Commissioning:
In Progress PT-13 M&I in progress - PT-13 - Jan’2022
PT-06 - Apr’2022
PT-06
Delay due to Covid Ph-2 and monsoon outbreak
PT-10 2021 2021
PT-12 2022 2022 Tender for M&I of PT-10, 12 & 05: LoA awarded for
PT-05 To be done as per 2022 2022 PT-12 on 04.12.2021.
To be done PT-11 rolling plan 2023 2023 Tender cancelled for PT-05 & 10. Re-tendering to be
PT-09 2023 2023 done.
PT-07 2023 2023
PT-16 to PT- 2029-2031
New Tanks 20 M&I Yet to be done

02/06/22 दक्षिण पूर्वी क्षेत्र पाइपलाइन 2


M&I of Tank PT-13
Sr. Point Target Status
no.
1 Work : M&I of PT-13 Scheduled Completion: 13.10.21 Schedule Progress % - 100%
Physical Progress % - 57%
Vendor: M/s Expo Gas Financial Progress % - 35%
Containers Ltd, Mumbai Revised Completion with
Catch up Plan
Covid 2nd Wave: 31.12.21
LoA date: 24.11.20 Hot work completion of Roof : 30.12.2021
W.O. Value: ₹1142 Lakh Commission by 15.02.2022 Hot work completion of Shell : 05.01.2022
Hot work completion of tank bottom : 30.12.2021
Fueling Growth with Innovation & Technology

Painting of tank bottom : 30.01.2022


Specific Notice: Roof painting : 15.01.2022
• 14.12.2020 Shell painting : 05.02.2022
Foam & Sprinkler line installation : 10.02.2022
Water filling for calibration : 10.02.2022
Commissioning with crude: 15.02.2022
Hindrance:
Delay in degasification process/ working with less
manpower due to Covid/ Frequent unseasonal rain
hampering painting progress (From Sept to end Oct)
Material Status:
Roof drain/ duplex fittings/Duplex pipes/GI structure
received at site.

3
M&I of Tank PT-13
 Roof Plate cutting :
Completed
 Roof Plate welding:
30th Dec’21
Fueling Growth with Innovation & Technology

Tank Shell
painting in
progress

02/06/22 4
M&I of Tank PT-06
Sr. Point Target Status
no.
1 Work : M&I of PT-06 Scheduled Completion: Schedule Progress % - 38%
21.04.22 Physical Progress % - 14%
Vendor: M/s Expo Gas Financial Progress % - 10%
Containers Ltd, Mumbai Catch up Plan
LoA date: 24.11.20 Residual crude pumping completion : (completed)
W.O. Value: ₹1142 Lakh Sludge removal : 15.01.22
Hot work completion of Roof : 28.02.22
Fueling Growth with Innovation & Technology

Hot work completion of Shell : 21.02.22


Tank Handover: Hot work completion of tank bottom : 15.02.22
• 22.06.21 Painting of tank bottom : 15.03.22
Roof painting : 31.03.2022
Shell painting : 15.04.2022
Foam & Sprinkler line installation : 20.04.22
Water filling for calibration : 25.03.22
Commissioning with crude: 21.04.22
Hindrance:
Working with less manpower due to Covid/ Frequent unseasonal rain
hampering painting progress (From Sept to end Oct)
Material Status:
Roof drain/ duplex fittings/ GI structure received at site.