Activities (CLG)
Manufacturing Engineering Activity - Workshop Cilegon
DATE : June 18th, 2019
• Majority Delivery
6 S - 19068 PT. Profluid 1 unit Glycol Particulate Filter 16-Sep-19 Revision Revision Under Reiew Belum dikerjakan Belum dikerjakan Under Reiew On Progress On Progress 1. Release PR Material on June 17th, 2019
1 unit Glycol Charcoal Filter By Luhur By Rafki PT. Profluid PT. Profluid By Furqon By Furqon
in Jun-Jul 19
7 S - 19070 PT, Hasakona Combustion Chamber 15-Jul-19 Revision N/A N/A On Progress On Progress On Progress N/A N/A 1. Calculation, Drawing and Mat'l by Hasakona
By Luhur By Furqon By Furqon By Furqon
• Schedule
8 S - 19073 PT. Chandra Asri 1 unit Mixer Hopper 30-Jun-19 Revision Revision Approved Finished On Progress Approved o/s Name Plate o/s Name Plate 1. On Progress Fabrication.
By Luhur By Rafki (Closed) (Closed) By Arifudin (Closed) By Absori By Furqon 2. Waiting material Carbon Steel & machining
9 S - 19075 PT. Catur Elang Perkasa 1 unit Degassing Boot 08-Aug-19 Revision Revision Approved On Progress On Progress Under Review o/s Name Plate & o/s Name Plate & 1. Waiting arrival material
Revision
By Rafki
By Customer
(Closed)
Approved
By Furqon
On Progress
By Furqon PT. CEP
Revision Revision
(Closed)
On Progress
By Absori
On Progress On Progress
By Arifudin
On Progress
By Absori
On Progress
By Furqon
On Progress
Overtime
12
1 unit Daily Tank
Revision
By Rafki
Revision
By Absori
On Progress
By Furqon
On Progress
By Furqon
On Progress
By Furqon
On Progress
By Absori
On Progress
By Furqon
13 S - 19090 PT. Asahimas Piping Work Building (1 Line) 31-Aug-19 Revision N/A On Progress On Progress Belum dikerjakan On Progress On Progress On Progress 1. Line 1 Approved & Line 2-3 Prepare
Piping Work Building (3 Lines) 30-Sep-19 By Luhur By Absori By Absori By Arifudin By Absori By Furqon 2. Material Pipe, Fitting & Paint Line 1 on progress
3. Fab. Start in this week
14 S - 19098 PT. Asahimas Rain Cover FU - 5851 30-Jun-19 Revision Closed Approved Finished On Progress Approved o/s Mat'l Packing o/s Mat'l Packing 1. On Progress Fabrication
By Luhur (Closed) (Closed) By Arifudin (Closed) By Absori By Absori
15 S - 19099 PT. CABOT Indonesia Shell Body CL-1 & Platform 28-Jun-19 Under Review N/A By Customer Belum dikerjakan Belum dikerjakan Belum dikerjakan On Progress On Progress 1. Waiting arrival material
Shell Body CL-2 & Platform 07-Jul-19 PT. CABOT By Furqon By Furqon
16 S - 19100 PT. CABOT Indonesia CL-1 Inline Coil 28-Jun-19 Under Review N/A On Progress On Progress On Progress On Progress Closed Closed 1. On Progress Fabrication Inline Coil
PT. CABOT By Syamsudin By Syamsudin By Syamsudin By Arifudin 2. Prepare Skid for transportation
17 S - 19101 PT. CABOT Indonesia Feed Stock CL-1 Inline Coil 28-Jun-19 Under Review N/A (Closed) (Closed) (Closed) (Closed) (Closed) (Closed) 1. On Progress Fabrication
PT. CABOT 2. Waiting material for Flange
18 S - 19065 PT. MFG Konstruksi Tower Rancaekek - Sunyaragi Partial from N/A N/A By Customer On Progress N/A N/A o/s Arm AA6 o/s Arm AA6 1. WO release June 17th, 2019 forStub AA6
(50 Units type AA6, BB6 & DDR6) August up October By Arifudin Tower BB6 Tower BB6 2. Shop Drawing received from MFG Konstruksi
2019 Tower DDR6 Tower DDR6
19 - PT. MFG Konstruksi Tower LLG N/A N/A By Customer Belum dikerjakan N/A N/A Belum dikerjakan Belum dikerjakan 1. Prepare PR Anchor Bolt (June 18th,2019
2. Waiting Shop Drawing from MFG Konstruksi
20 - PT. MFG Konstruksi Gardu Induk Ampel N/A N/A By Customer Belum dikerjakan N/A N/A Belum dikerjakan Belum dikerjakan 1. Waiting Shop Drawing from MFG Konstruksi
21 S - 19079 PT. CABOT Indonesia CL-2 Driyer Lapping & Inlet Cone 1st week July 2019 N/A N/A Approved Approved N/A Approved (Closed) (Closed) 1. Waiting arrival Material
Replacement (Closed) (Closed) (Closed) 2. Errection Site / Installation at site
3. PR Mobile Crane for Installation (Closed)
ENGINEERING
Activities (HO)
*Updated in Red
Fabrication/
Project/ Proposal Project Name/ Description Activities By Status Issue
Construction
meeting with MEGS 210619 Info
Key Notes
• The activities mostly for Tender Support, Supporting MEGS on Rental Compressor tender for
Conoco Philip was the most activities during June 2019
• Construction activities handed over to Construction team by Mid of Jun 2019
• Supporting Cilegon team to prepare mechanical calc
ENGINEERING
Training & Development
Key Notes
• Sharing Session scheduled
• Participant Registered
ENGINEERING
Manhours on Jun 2019 (HO)
Absence Project
14% 19%
Administration
Project
4%
Proposal
Administration
Development
Absence
Proposal
63%
Key Notes
• Supporting Construction Team in Jun 2019
ENGINEERING
Team Productivity
Productive Manhour :
• Engineering Development (Develop Tools, spreadsheet,
calc etc)
• Project Execution
• Proposal
Eng Productivity
90%
88%
86%
84%
82%
80%
78%
76%
74%
April May June
Actual Target