ENGINEERING

Activities (CLG)
Manufacturing Engineering Activity - Workshop Cilegon
DATE : June 18th, 2019

Cutt . Profile, List


Key Notes
No. Job No. Customer Description Delivery Time Prosedur Mech Kalkulasi Drawing Packing Style NDE Map MRL Mat'l PR Mat'l Keterangan
& Plan
1 S - 18179 PT. Yusonda 8 units Pressure Vessel 2 month after On Progress By Customer By Customer Belum dikerjakan Belum dikerjakan Belum dikerjakan Belum dikerjakan Belum dikerjakan 1. Mat'l by PT. Yusonda
material received By Luhur

2 S - 19025 TPSC Engineering 2 units Tower & 1 unit Beam


32 units Anchor Bolts
31-Jul-19 Under Reiew
TPSC
N/A On Progress
By Syamsudin
On Progress
By Arifudin
Belum dikerjakan
By Furqon
N/A o/s Packing o/s Packing 1. On Progress Erection Drawing & Shop Drawing
2. Waiting Proses Approval Assembly Drawing &
ITP.
• 21 Ongoing
3 S - 19041 JGC Engineering Platform & Additional
Nozzle 6" & 10"
20-Jun-19 Partial Approved
By Luhur
Revision
By Rafki
Under Review
By JGC
On Progress
By Furqon
Belum dikerjakan
By Furqon
On Progress
By Furqon
On Progress
By Furqon
On Progress
By Furqon
1. TQ UNP 380x100x13x20 (Closed)
2. Approval RPE (ASME VIII Div. 2) (parallel) Projects
4 S - 19055 PT. Asahimas 1 unit Tank VE-2212 31-Jul-19 Under Review
PT. ASC
Revision
By Rafki
Approved
(Closed)
On Progress
By Absori
Approved
(Closed)
Approved
(Closed)
o/s Ladder, HR &
Paint
o/s Ladder, HR & 1. On Progress Fabrication bottom, Shell & Roof
Paint • Project Deliveries
in Jun-Sept 19
5 S - 19067 PT. Chandra Asri 1 unit Potable Diesel Tank 30-Jun-19 Revision Revision Approved Finished Approved Approved o/s Name Plate o/s Name Plate 1. On Progress Fabrication.
By Luhur By Rafki (Closed) (Closed) (Closed) (Closed) By Furqon By Furqon 2. Waiting material for Level Glass w/ Acc & Valve

• Majority Delivery
6 S - 19068 PT. Profluid 1 unit Glycol Particulate Filter 16-Sep-19 Revision Revision Under Reiew Belum dikerjakan Belum dikerjakan Under Reiew On Progress On Progress 1. Release PR Material on June 17th, 2019
1 unit Glycol Charcoal Filter By Luhur By Rafki PT. Profluid PT. Profluid By Furqon By Furqon

in Jun-Jul 19
7 S - 19070 PT, Hasakona Combustion Chamber 15-Jul-19 Revision N/A N/A On Progress On Progress On Progress N/A N/A 1. Calculation, Drawing and Mat'l by Hasakona
By Luhur By Furqon By Furqon By Furqon

• Schedule
8 S - 19073 PT. Chandra Asri 1 unit Mixer Hopper 30-Jun-19 Revision Revision Approved Finished On Progress Approved o/s Name Plate o/s Name Plate 1. On Progress Fabrication.
By Luhur By Rafki (Closed) (Closed) By Arifudin (Closed) By Absori By Furqon 2. Waiting material Carbon Steel & machining

9 S - 19075 PT. Catur Elang Perkasa 1 unit Degassing Boot 08-Aug-19 Revision Revision Approved On Progress On Progress Under Review o/s Name Plate & o/s Name Plate & 1. Waiting arrival material

10 S - 19081 Konsorsium RBE &


1 unit Sump Tank

1 unit Metering Package 28-Jun-19


By Luhur

Revision
By Rafki

By Customer
(Closed)

Approved
By Furqon

On Progress
By Furqon PT. CEP

Belum dikerjakan Minor Comment


Packing Mat'l

o/s Bleed Ring


Packing Mat'l

o/s Bleed Ring 1. Waiting Arrival Material


Recovery with
11
PT. Yuan Sejati

S - 19082 Rekayasa Energi Bersama 2 units Filter Housing 28-Jun-19


By Luhur

Revision Revision
(Closed)

On Progress
By Absori

On Progress On Progress
By Arifudin

On Progress
By Absori

On Progress
By Furqon

On Progress
Overtime
12
1 unit Daily Tank

S - 19087 Rekayasa Energi Bersama 1 unit Instrument Air Receiver 27-Jul-19


By Luhur

Revision
By Rafki

Revision
By Absori

On Progress
By Furqon

On Progress
By Furqon

On Progress
By Furqon

On Progress
By Absori

On Progress
By Furqon

On Progress 1. Status Drawing Minor Comment


• Sharing Load with
Engineering HO
By Luhur By Rafki By Absori By Arifudin By Arifudin By Arifudin By Absori By Furqon 2. Material Due Date 29 Mei 2019

13 S - 19090 PT. Asahimas Piping Work Building (1 Line) 31-Aug-19 Revision N/A On Progress On Progress Belum dikerjakan On Progress On Progress On Progress 1. Line 1 Approved & Line 2-3 Prepare
Piping Work Building (3 Lines) 30-Sep-19 By Luhur By Absori By Absori By Arifudin By Absori By Furqon 2. Material Pipe, Fitting & Paint Line 1 on progress
3. Fab. Start in this week
14 S - 19098 PT. Asahimas Rain Cover FU - 5851 30-Jun-19 Revision Closed Approved Finished On Progress Approved o/s Mat'l Packing o/s Mat'l Packing 1. On Progress Fabrication
By Luhur (Closed) (Closed) By Arifudin (Closed) By Absori By Absori

15 S - 19099 PT. CABOT Indonesia Shell Body CL-1 & Platform 28-Jun-19 Under Review N/A By Customer Belum dikerjakan Belum dikerjakan Belum dikerjakan On Progress On Progress 1. Waiting arrival material
Shell Body CL-2 & Platform 07-Jul-19 PT. CABOT By Furqon By Furqon

16 S - 19100 PT. CABOT Indonesia CL-1 Inline Coil 28-Jun-19 Under Review N/A On Progress On Progress On Progress On Progress Closed Closed 1. On Progress Fabrication Inline Coil
PT. CABOT By Syamsudin By Syamsudin By Syamsudin By Arifudin 2. Prepare Skid for transportation

17 S - 19101 PT. CABOT Indonesia Feed Stock CL-1 Inline Coil 28-Jun-19 Under Review N/A (Closed) (Closed) (Closed) (Closed) (Closed) (Closed) 1. On Progress Fabrication
PT. CABOT 2. Waiting material for Flange

18 S - 19065 PT. MFG Konstruksi Tower Rancaekek - Sunyaragi Partial from N/A N/A By Customer On Progress N/A N/A o/s Arm AA6 o/s Arm AA6 1. WO release June 17th, 2019 forStub AA6
(50 Units type AA6, BB6 & DDR6) August up October By Arifudin Tower BB6 Tower BB6 2. Shop Drawing received from MFG Konstruksi
2019 Tower DDR6 Tower DDR6

19 - PT. MFG Konstruksi Tower LLG N/A N/A By Customer Belum dikerjakan N/A N/A Belum dikerjakan Belum dikerjakan 1. Prepare PR Anchor Bolt (June 18th,2019
2. Waiting Shop Drawing from MFG Konstruksi

20 - PT. MFG Konstruksi Gardu Induk Ampel N/A N/A By Customer Belum dikerjakan N/A N/A Belum dikerjakan Belum dikerjakan 1. Waiting Shop Drawing from MFG Konstruksi

21 S - 19079 PT. CABOT Indonesia CL-2 Driyer Lapping & Inlet Cone 1st week July 2019 N/A N/A Approved Approved N/A Approved (Closed) (Closed) 1. Waiting arrival Material
Replacement (Closed) (Closed) (Closed) 2. Errection Site / Installation at site
3. PR Mobile Crane for Installation (Closed)
ENGINEERING
Activities (HO)
*Updated in Red
Fabrication/
Project/ Proposal Project Name/ Description Activities By Status Issue
Construction
meeting with MEGS 210619 Info

There are some document was not submitted


waiting tender document revision from client INfo by CoPi based on doc list prepared by CoPi

site visit by 28-30 Jun 2019, which attended by


1. Idil Fitri
2. Bayu
3. Aryo Info 100%
Clarification & Deviation List Team 100% once we got contract doc revision
Process Calc Olive 100%
Fabrication Proposal RTO Letang tengah rawa operation - Copi
Mechanical Calc for Vessel, Piping, Valve Yere 100%
MTO for Vessel, Piping, Valve Bayu 100%
MTO for Instrument Olive 100%
Foundatio Design and Volume Tosin & Bayu 100%
Access Road Design and Volume Tosin & Bayu 100%
GA & Routing Dedi No need
Project Execution Plan Idil 100%
Compressore data Idil 100% Idil to follow up
HYSYS software sudah dapat dari PEP, Caesar
Software licensed for CAESAR & HYSIS Alfi 100% masih di usahakan
Team CV Idil 100% Idil to collect
Fabrication Proposal NPP fabrication for Taim Weser MTO for built up beam Dedi 100%
Fabrication Project Low Level Gantry- Tj Jati sec 4 shop drawings Dedi 100% for TW2
11 Column (mech calc & MTO) Yere&Bayu 100%
Fabrication Proposal LINE Project - Lotte Chemical 4 Column (Mech Calc & MTO) Yere&Bayu 100%
Package 4 (11 design) (Mech calc & MTO) Yere&Bayu 100%
MTO For ducting Dedi 100%
Fabrication Proposal Q12570-M: Steam coil duct heaters enquiry Gasco
MTO for tube & tube sheet Bayu 0% started by 19 Juli 2019
Mechanical Calculation Yere 100%
Fabrication Proposal MEPI - Rectangular Tank MTO Yere 100%
GA drawing Dedi 100%
Fabrication Proposal Stack for JFE and Technip MTO (budget) Yere 100%

Key Notes
• The activities mostly for Tender Support, Supporting MEGS on Rental Compressor tender for
Conoco Philip was the most activities during June 2019
• Construction activities handed over to Construction team by Mid of Jun 2019
• Supporting Cilegon team to prepare mechanical calc
ENGINEERING
Training & Development

Key Notes
• Sharing Session scheduled
• Participant Registered
ENGINEERING
Manhours on Jun 2019 (HO)

Absence Project
14% 19%
Administration
Project
4%
Proposal
Administration
Development
Absence

Proposal
63%

Eng Manhour June 2019

Key Notes
• Supporting Construction Team in Jun 2019
ENGINEERING
Team Productivity

Productive Manhour :
• Engineering Development (Develop Tools, spreadsheet,
calc etc)
• Project Execution
• Proposal

Non Productive Manhour :


• Team Meeting
• Absence (On Leave, Sick Leave)
• Administration job

Productivity (%): Productive Manhours x 100%


Working Hours
ENGINEERING
Team Productivity

Eng Productivity
90%

88%

86%

84%

82%

80%

78%

76%

74%
April May June

Actual Target