Fire proof Sliding Door 9-Jul 237 30-Jun 14-Jul 14 AP R Door drawing/ spec submission pending
Supplier 20 Jul
finalization
Fire proof Leaf Door 9-Jul 237 pending 30-Jun 14-Jul 14 AP R Door drawing/ spec submission pending
NA NA 20 Jul
NA
AP From billing perspective, the material delay
SS 304 Sheets for Floor 30-Jun 14-Jul 14 20 Jul A wont be acceptable
NA
Location of VOC Meter to be updated in
VOC Meter- 03 Qty 30-Jun 246 A
drawings
Existing PCS Skids, Piping & SS 10-Jul 30-Jul Pending Pending A Dismantling WIP-
Floor Dismantling expected completion by 02-Aug