Professional Documents
Culture Documents
Preliminaries Part
Preliminarie 91 17-May-18 15-Aug-18 15-Aug-18, Preliminaries Part
A2025 Commencement Date as per Engineer Instruction 0 17-May-18 Commencement Date as per Engineer Instruction
A2026 Mobilization / Fencing Permit Application by Shurooq 1 21-May-18 21-May-18 Mobilization / Fencing Permit Application by Shurooq
A2027 Mobilization / Fencing Permit Approval 9 22-May-18 30-May-18 Mobilization / Fencing Permit Approval
A2046 Installation of Hoarding & Signboard 16 31-May-18 15-Jun-18 Installation of Hoarding & Signboard
A2095 Mobilization & Site Offices Setup 16 31-May-18 15-Jun-18 Mobilization & Site Offices Setup
A2105 The Client Approval on issuing of Engineer IFC drawings / 0 19-May-18 The Client Approval on issuing of Engineer IFC drawings / documents
documents
A2115 1 28-May-18 28-May-18 Piling Design Submission to Sharjah Municipality by Shurooq
Piling Design Submission to Sharjah Municipality by Shurooq
A2130 Building Permit Approval 79 29-May-18 15-Aug-18 Building Permit Approval
Submittals b
by ZETAS 7 17-May-18 23-May-18 23-May-18, Submittals by ZETAS
A2065 Design and Design Drawings 4 17-May-18 20-May-18 Design and Design Drawings
A2155 Material & Subcontractor Prequalification 7 17-May-18 23-May-18 Material & Subcontractor Prequalification
A2175 Design and Design Drawings 7 21-May-18 27-May-18 Design and Design Drawings
A2225 Material & Subcontractor Prequalification 7 24-May-18 30-May-18 Material & Subcontractor Prequalification
A1958 Preliminary Test Pile Construction - 6 nos (750 mm - 1000 mm) 9 11-Jul-18 19-Jul-18 Preliminary Test Pile Construction - 6 nos (750 mm - 1000 mm)
Foundation Pile Construction 120 16-Aug-18 13-Dec-18 13-Dec-18, Foundation Pile Con
A2310 * Pile Testing (Static Load, Dynamic Load, Tensile Load, Caliper 100 05-Sep-18 13-Dec-18 * Pile Testing (Static Load, Dyna
Logging & Durability Test) See note below
Note: *Cross Hole Sonic and Integrity Tests will be done by ZETAS after pile head breaking works to be performed by others
** Based on Sharjah Municipality Design Meeting Appointment
Actual Work Milestone TASK filter: All Activities
Remaining Work Summary Based on the available site working hours being 24 hours per working day © Primavera Systems, Inc.
Critical Remaining Work and 6 working days per week excluding Friday and Public Holidays.