MARYAM BEACH RESIDENCE ON PLOT NO.

844 TENTATIVE WORK PROGRAMME

FOUNDATION PILING WORKS


Activity ID Activity Name Original Start Finish
Duration 2018 2019
May Jun Jul Aug Sep Oct Nov Dec Jan
MARYAM BEACH
BEA RESIDENCE 211 17-May-18 13-Dec-18 13-Dec-18, MARYAM BEACH R

Preliminaries Part
Preliminarie 91 17-May-18 15-Aug-18 15-Aug-18, Preliminaries Part

A2025 Commencement Date as per Engineer Instruction 0 17-May-18 Commencement Date as per Engineer Instruction

A2026 Mobilization / Fencing Permit Application by Shurooq 1 21-May-18 21-May-18 Mobilization / Fencing Permit Application by Shurooq

A2027 Mobilization / Fencing Permit Approval 9 22-May-18 30-May-18 Mobilization / Fencing Permit Approval

A2036 Mobilization / Fencing Permit 0 31-May-18 Mobilization / Fencing Permit

A2037 Demarcation Certificate by Shurooq 0 31-May-18 Demarcation Certificate by Shurooq

A2046 Installation of Hoarding & Signboard 16 31-May-18 15-Jun-18 Installation of Hoarding & Signboard

A2095 Mobilization & Site Offices Setup 16 31-May-18 15-Jun-18 Mobilization & Site Offices Setup

A2100 Mobilization of Piling Equipment 16 31-May-18 15-Jun-18 Mobilization of Piling Equipment

A2105 The Client Approval on issuing of Engineer IFC drawings / 0 19-May-18 The Client Approval on issuing of Engineer IFC drawings / documents
documents
A2115 1 28-May-18 28-May-18 Piling Design Submission to Sharjah Municipality by Shurooq
Piling Design Submission to Sharjah Municipality by Shurooq
A2130 Building Permit Approval 79 29-May-18 15-Aug-18 Building Permit Approval

A2235 Building Permit** 0 15-Aug-18 Building Permit

A2245 Utilities NOC's by Shurooq 0 15-Jun-18 Utilities NOC's by Shurooq

A2255 Construction NOC's by Shurooq 0 15-Jun-18 Construction NOC's by Shurooq

Submittals b
by ZETAS 7 17-May-18 23-May-18 23-May-18, Submittals by ZETAS

A2035 Tentative Work Schedule 1 17-May-18 17-May-18 Tentative Work Schedule

A2055 Method Statement 7 17-May-18 23-May-18 Method Statement

A2065 Design and Design Drawings 4 17-May-18 20-May-18 Design and Design Drawings

A2080 Site Logistic Plan 4 17-May-18 20-May-18 Site Logistic Plan

A2085 HSE Plan 7 17-May-18 23-May-18 HSE Plan

A2135 QA/QC Plan 7 17-May-18 23-May-18 QA/QC Plan

A2145 Site Organizational Chart 1 17-May-18 17-May-18 Site Organizational Chart

A2155 Material & Subcontractor Prequalification 7 17-May-18 23-May-18 Material & Subcontractor Prequalification

Approvals by Engineer 13 18-May-18 30-May-18 30-May-18, Approvals by Engineer

A2045 Tentative Work Schedule 7 18-May-18 24-May-18 Tentative Work Schedule

A2165 Method Statement 7 24-May-18 30-May-18 Method Statement

A2175 Design and Design Drawings 7 21-May-18 27-May-18 Design and Design Drawings

A2190 Site Logistic Plan 7 21-May-18 27-May-18 Site Logistic Plan

A2195 HSE Plan 7 24-May-18 30-May-18 HSE Plan

A2205 QA/QC Plan 7 24-May-18 30-May-18 QA/QC Plan

A2215 Site Organizational Chart 7 18-May-18 24-May-18 Site Organizational Chart

A2225 Material & Subcontractor Prequalification 7 24-May-18 30-May-18 Material & Subcontractor Prequalification

Preliminary Test Pile 46 11-Jul-18 25-Aug-18 25-Aug-18, Preliminary Test Pile

A1958 Preliminary Test Pile Construction - 6 nos (750 mm - 1000 mm) 9 11-Jul-18 19-Jul-18 Preliminary Test Pile Construction - 6 nos (750 mm - 1000 mm)

A1968 Testing 20 30-Jul-18 18-Aug-18 Testing

A1978 Reporting 17 09-Aug-18 25-Aug-18 Reporting

Foundation Pile Construction 120 16-Aug-18 13-Dec-18 13-Dec-18, Foundation Pile Con

A2310 * Pile Testing (Static Load, Dynamic Load, Tensile Load, Caliper 100 05-Sep-18 13-Dec-18 * Pile Testing (Static Load, Dyna
Logging & Durability Test) See note below

Zone 1 33 16-Aug-18 17-Sep-18 17-Sep-18, Zone 1

A2240 Foundation Pile Construction 33 16-Aug-18 17-Sep-18 Foundation Pile Construction

Zone 2 33 14-Sep-18 16-Oct-18 16-Oct-18, Zone 2

A2260 Foundation Pile Construction 33 14-Sep-18 16-Oct-18 Foundation Pile Construction

Zone 3 33 13-Oct-18 14-Nov-18 14-Nov-18, Zone 3

A2280 Foundation Pile Construction 33 13-Oct-18 14-Nov-18 Foundation Pile Construction

Zone 4 33 11-Nov-18 13-Dec-18 13-Dec-18, Zone 4

A2300 Foundation Pile Construction 33 11-Nov-18 13-Dec-18 Foundation Pile Construction

Completion of Work 0 13-Dec-18 13-Dec-18 13-Dec-18, Completion of Work

A1830 Completion of Work 0 13-Dec-18 Completion of Work

Note: *Cross Hole Sonic and Integrity Tests will be done by ZETAS after pile head breaking works to be performed by others
** Based on Sharjah Municipality Design Meeting Appointment
Actual Work Milestone TASK filter: All Activities

Remaining Work Summary Based on the available site working hours being 24 hours per working day © Primavera Systems, Inc.
Critical Remaining Work and 6 working days per week excluding Friday and Public Holidays.