Professional Documents
Culture Documents
file://dallplmp10/plm/Adlib/Input/f1b3fb0f-4b48-48d0-9499-da17c407126d/Ap... 1/14/2020
E0660-P10361121-H03-2001 (Rev 05)
MS002-076-PPL001-H03-2001 (Rev 05)
Uncontrolled Document - Destroy after Review
Inspection & Test Plan
THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Revision History & Amendment Register
Rev.
Date Detailed Description of Change Ref. Section
No.
23 Aug 2019 1 Added “CS” on the document title Page 1 to 25
23 Aug 2019 1 Added “Sumitomo Corp” for customer. Page 1 of 25
Uncontrolled Document - Destroy after Review
23 Aug 2019 1 Added row for PP/PIM and document approval. Section 1
23 Aug 2019 1 Added intervention points for SC, McDermott and BP. Page 4 to 24
23 Aug 2019 1 Added Chloride content test of rinse water 5.9
23 Aug 2019 1 Added “as per manufacturer’s data sheet”. 6.1
23 Aug 2019 1 Deleted “only during PQT”. 6.8
23 Aug 2019 1 Added “partly coated pipe” under Production. 7.5
23 Aug 2019 1 Updated requirement for colour band. “Colour band to be applied after OMS inspection”. 8.2
23 Aug 2019 1 Added bar code requirement. 8.3
Added “Pipes for OMS inspection (16” OD), the end caps may be installed after OMS
23 Aug 2019 1 9.1
inspection”.
Added “(For 6.625” OD and 30” OD) after Normal Temp FBE and “(For 16.75” OD) after
23 Aug 2019 1 11.2 a
High Temp FBE.
18 Oct 2019 2 Reference document MS002-MT-SPE-076-00005 updated to Rev. B03. Page 2 of 26
18 Oct 2019 2 Updated HOLD References Page 2 of 26
18 Oct 2019 2 PQT requirement updated as per MS002-MT-SPE-076-00005 Rev. B03. 3.1
Reference to Table A.1, A.2, A.3 and A.4 changed to Table A.2, A.3, A.4 and A.5 as per
18 Oct 2019 2 All relevant sections
MS002-MT-SPE-076-00005 Rev. B03.
18 Oct 2019 2 Amended McDermott and BP intervention pts as per comments dated 10th of Sep 2019. 3.1, 3.2
Amended McDermott intervention points to align with Sumitomo as discussed during the
18 Oct 2019 2 Page 8 to 16
PIM.
2.4, 2.6, 2.9, 11.2,
18 Oct 2019 2 Revised laboratory test report form number.
11.3
18 Oct 2019 2 Added UT gauge for wall thickness measurement. 4.2
Revised pre heat temperature after pre-wash as discussed during PIM and as per DVR No.
18 Oct 2019 2 4.6
E0660-P10361121-N09-2001.
Updated steel defect and irregularities removal requirement and added UT gauge for wall
18 Oct 2019 2 4.12
thickness measurement.
18 Oct 2019 2 Revised coating line speed tolerance to +/- 5 % as discussed during PIM. 6.8
Changed frequency from continuous to every pipe as per Table A.3 of MS002-MT-SPE-076-
18 Oct 2019 2 6.1
00005 Rev. B03.
Revised the coating roughness to minimum 80 microns as discussed during the PIM and as
18 Oct 2019 2 7.4
per revised Line Pipe Coating Specification MS002-MT-SPE-076-00005 Rev. B03
18 Oct 2019 2 Added details on repair qualification testing. 13.2
Amend reference document for MS002-MT-SPE-076-00021 Rev.B04 and MS002-PL-DAT- Reference
25 Nov 2019 3
076-00003 Rev. C03. Documents
Insert E0660-P10361121-N09-2003, DV 013 and E0660-P10361121-N09-2001, DV 011 in Reference
25 Nov 2019 3
Reference Documents. Documents
Hold References,
25 Nov 2019 3 Removed HOLD 1, 2, 4 and 5.
2.3, 2.5, 3.1, 4.6
Amend pipe size for PQT 16.75 inch OD x 32mm WT and Heat profile with 34mm WT. Heat
25 Nov 2019 3 3.1, 12.2
profile for 30.0 inch OD x 21 mm WT and 30.2 mm WT.
25 Nov 2019 3 Amend salt check before hot water wash and test using Elcometer 130. 4.3, 4.16
25 Nov 2019 3 Amend for adhesive thickness to be measured with the combination of FBE with adhesive. 7.2
25 Nov 2019 3 Amend Cutback requirement to 200 -10/+5 mm only for 30.0inch OD. 7.7, Figure 1
25 Nov 2019 3 Amend hookable end cap / bevel protector. 9.1
25 Nov 2019 3 Added Degree of Cure and Adhesion test for heat profile test. 12.1, 12.2
25 Nov 2019 3 Added surface preparation requirement for repair. 14.3, 14.4
23 Dec 2019 4 Added Holiday requirements as agreed during discussion with SC and McDermott 7.5
MS002-MT-SPE-076-00005 Rev. B03, dated 11th September 2019, Line Pipe Coating Specification – Anti Corrosion Coating
MS002-PL-DAT-076-00001 Rev. C01, dated 09th April 2019, Anti Corrosion Line Pipe Coating Data Sheet.
MS002-MT-SPE-076-00021 Rev. B04, dated 05th September 2019, Specification for Concrete Weight Coating.
Uncontrolled Document - Destroy after Review
MS002-PL-DAT-076-00003 Rev. C03, dated 19th September 2019, Line Pipe Concrete Coating Data Sheet.
ISO 21809-1:2011, Petroleum and Natural Gas Industries – External Coatings for Buried or Submerged Pipelines Used in
Pipeline Transportation Systems – Part 1: Polyolefin Coatings (3-layer PE and 3-layer PP)
E0660-P10361121-N09-2003, DV 013 – Technical Query for PP Adhesive and PP Top Coat – Raw Material testing
requirement (Batch Certificate)
E0660-P10361121-N09-2001, DV 011 – Technical Query for Pre heat pipe temperature prior abrasive.
Hold References
Table of Content
1. PPM/PIM AND DOCUMENTATION REQUIREMENT ................................................................................................... 5
Uncontrolled Document - Destroy after Review
2. RAW MATERIAL RECEIPT & VERIFICATION ................................................................................................................ 5
3. PQT REQUIREMENT ................................................................................................................................................. 10
4. INCOMING RACK AND SURFACE PREPARATION ...................................................................................................... 11
5. CHEMICAL PRETREATMENT ..................................................................................................................................... 14
6. 3LPP COATING – PREHEAT AND APPLICATION ........................................................................................................ 16
7. 3LPP COATING INSPECTION AND TESTING .............................................................................................................. 17
8. MARKING IDENTIFICATION ...................................................................................................................................... 19
9. PIPE PRESERVATION ................................................................................................................................................ 20
10. FIELD TESTING .......................................................................................................................................................... 20
11. LABORATORY/ OUT OF LINE INSPECTION ................................................................................................................ 21
12. RETEST ..................................................................................................................................................................... 24
13. COATING REPAIRS .................................................................................................................................................... 25
14. STRIPPING OF COATED PIPE .................................................................................................................................... 26
15. EQUIPMENT CALIBRATION OR VERIFICATION ......................................................................................................... 27
FIGURE 1. CUTBACK DETAILS ................................................................................................................................... 28
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
1.1 PPM/PIM Customer --- --- --- PPM/PIM to be conducted prior to project execution. H H H H MOM
comments
---
dated 15- ITP and
1.2 Approval of documentations Aug-2019 --- --- --- Approved ITP and MPS. H H H H
MPS
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
MS002-MT-
SPE-076- Each
i. Shelf life 5.3 --- Each bath As per manufacturer specified.
00005 batch
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Note:
Salt test paper must be fully wetted prior to insertion PQT PQT
MS002-MT- Elcometer W W
All PQT Start of shift into the Elcometer 130
Salt level check before hot water SPE-076- 8.1, 130 pipes and 1 pipe
4.3 00005 Table HNC M/R QF07-2-1
wash SSPC Guide (at each in 20 at In case the salt content is not met, pipe shall be Prod Prod
A.2
15 end) each end pressure washed in conformance with NACE WJ-4 or WFO WFO
Minutes of better, with potable water not exceeding 250 ppm M M
KOM 04 Nov soluble chloride ion concentration, until compliant
2019 with less than 2 µg/cm2.This may be performed
offline.
Table WFO WFO
4.4 Pipe Prewash using hot water Visual All pipes Every pipe Full coverage V M --
A.2 M M
MS002-MT- Table
SPE-076- A.2
00005 Start of
Table Start of
Whirling shift, Air temperature shall be greater than 10 °C.
shift, then WFO WFO
4.5 Environmental condition ISO 21809-1 8 Hygrometer & then RH less than 85%. HC M/R QF07-2-1
max. 4 M M
RH Calculator max. 4 Record dew pint
hours
hours
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
MS002-MT- 8.2,
SPE-076- Table
PQT PQT
00005 A.2
W W
Start of Pipe preheating shall be 45 – 65 °C
Pipe temperature after prewash prior Contact All PQT
4.6 ISO 21809-1 10.1.1, shift, then 1 Pipe surface temperature is at least 5 °C above dew HNC M/R QF07-2-1
to blasting Pyrometer pipes Prod Prod
Table8 per hour point.
WFO WFO
E0660-
/M /M
P10361121-
N09-2001
Start of
Start of
MS002-MT- shift,
Table Sieve shift, then
4.7 Abrasive check – Sieve analysis SPE-076- then Less than 5% fines and pass sieve size requirement HNC W W M/R QF07-2-2
A.2 (ISO 11125-2) max. 4
00005 max. 4
hours
hours
MS002-MT- 8.2 Flotation on
4.8 Abrasive check (for oil) SPE-076- At start of No oil contamination HNC W W M/R QF07-2-2
water At start shift or any
00005
Absorbent of PQT changes of
4.9 Abrasive check (for water) abrasive No water contamination HNC W W M/R QF07-2-2
ISO 21809-1 10.1.2 paper
MS002-MT- 5.1,
SPE-076- 8.2,
Start of
00005 Table
shift,
A.2 Once per
4.10 Abrasive – Salt / Chloride Content ASTM D4940 then Less than or equal to 60 µS/cm HNC W W M/R QF07-2-2
shift
max. 4
ISO 21809-1 10.1.2,
hours
Table
8
Start of
Start of
shift, then
MS002-MT- shift,
Table max. 1 per
4.11 Compressed air SPE-076- ASTM D4285 then No oil or water contamination. HNC W W M/R QF07-2-1
A.2 hour plus
00005 max. 1
after any
per hour
stoppage
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
MS002-MT- 8.3
PQT PQT
SPE-076-
Elcometer130 All PQT Start of shift W W
00005
Salt level check (after blast) – if pipes and 1 pipe
4.16 10.1.4, SSPC Guide Less than 2 µg/cm². HNC M/R QF07-2-1
surface pre-treatment is not used. (at each in 20 at Prod Prod
ISO 21809-1 Table 15 end) each end WFO WFO
8
/M /M
PQT PQT
W W
MS002-MT- Record blasting line speed during PQT.
At start Twice per
4.17 Blasting parameters SPE-076- 8 Visual Blasting speed during production shall be within ± HNC M/R QF07-2-1
of PQT shift Prod Prod
00005 10% of result during PQT.
WFO WFO
/M /M
Not more than 4 hours.
No oxidation, tarnishing or contamination on blasted
pipe.
MS002-MT-
All PQT
4.18 Time interval after blasting to coating SPE-076- 8, 8.2 Monitor All pipes M M M M ---
pipes Note: If the time interval exceeds 4 hours or
00005
oxidation, tarnishing or contamination are detected,
the pipe shall be reprocessed.
MS002-MT-
All PQT Secured coupling insertion and no damage on the
4.19 Pipe coupling insertion SPE-076- 8 Visual All pipes VM M M M ---
pipes bevel.
00005
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
5.3 Acid coverage Visual 100% acid coverage HMC V M M/R QF07-2-1
pH paper/ pH Every
5.5 pH of pipe surface before rinse 1 to 2 HMC M/R QF07-2-1
meter pipe PQT PQT
W W
MS002-MT- 8.3, Start of shift
SPE-076- Table and 1 pipe 6 to 7 Prod Prod
00005 A.2 pH paper/ pH Every in 20
5.6 pH of pipe surface after rinse HMC WFO WFO M/R QF07-2-1
ISO 21809-1 10.1.4 meter pipe Note:
/M /M
The pH shall not be lower than the pH RO water
TC C1
MS002-MT- 8.3
pH paper/ pH Once per
5.7 pH of rinse water SPE-076- At start Record. HMC W W M/R QF07-2-1
meter shift
00005
MS002-MT- 8.3
SPE-076- Start of shift
Pressure Every WFO WFO
5.8 Rinse water pressure 00005 and 1 pipe Minimum 1200 psi HMC M/R QF07-2-1
gauge pipe M M
10.1.4 in 20
ISO 21809-1
Customer
comment CSN Kit or At start Once per
5.9 Chloride content of rinse water --- Max 50 ppm HNC W W M/R QF07-2-1
dated 15- TDS Meter of PQT day
Aug-2019
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
representa
tive
locations)
Testex tape
MS002-MT- All PQT Once per Full coverage.
7.4 Sintercoat roughness SPE-076- 8.7 HDC W W M/R QF07-2-5
Visual pipes shift Minimum 80 µm.
00005
standard
MS002-MT- Table The number of holidays shall not exceed the
SPE-076- A.3 following:
00005
Start of shift 1 holiday per metre length of FBE coated
ISO 21809-2 and after pipe/partly coated. Example: 12 holidays for 12.2 m
ISO 21809-2 1 FBE
7.5 Holiday detection (FBE) stoppage coated pipe. HNC W W M/R QF07-2-5
pipe
5V/µm (partly
coated pipe) If holidays are more than the specified above, pipe
and process will be investigated. Another pipe will
be coated until the criteria is achieved.
MS002-MT- Table
SPE-076- A.3 PQT PQT
00005 All PQT W W
ISO 21809-1 pipes Final accepted coating shall be free from holiday
7.6 Holiday detection on 3LPP coating All pipes HNC M/R QF07-2-5
ISO 21809-1 Table Annex B (Full Refer to repair section on repair criteria. Prod Prod
7, system) WFO WFO
Table /M /M
9
MS002-MT- 8.8
SPE-076-
00005
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
MS002-MT- 8.10,
All PQT WFO
7.8 Residual magnetism SPE-076- Table Gauss meter All pipes Maximum 20 Gauss HNC M/R M/R QF07-2-5
00005 A.5 pipes /M
Customer
comments All PQT 2 Bar code stickers attached at both pipe ends W/M/
8.3 Bar code sticker --- Visual All pipes HVM M/R M/R ---
dated 15- pipes 180° apart. [HOLD 1] R
Aug-2019
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
MS002-MT- Table
SPE-076- A.5 ISO 21809-1 At 23 ± 3 °C
00005 Annex F All Max. 0.1 mm.
One pipe HT
a. Penetration (indentation) Table PQT W W M/R LQF07-2-9
per shift C
ISO 21809-1 7 at 23 ± 3˚C pipe At 90 ± 2 °C
Table and 90 ± 2˚C Max. 0.3 mm.
9
MS002-MT- ISO 21809-1 All One per ≥ 10 J/mm.
Table HT
b. Impact resistance SPE-076- Annex E PQT 500 30 locations without penetration or loss of adhesion W W M/R LQF07-2-9
A.5 C
00005 at 23 ± 3˚C pipe pipes of coating.
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Samples of
coating
removed from No more than 10% of sectioned area taken up by
MS002-MT- Table pipe and All One per
air entrapment. HT
c. Air entrapment SPE-076- A.4 sectioned. PQT 500 W W M/R LQF07-2-9
No more than 10% of thickness occupied by air. C
00005 Sections pipe pipes
examined No link up of air voids.
under X40
magnification
MS002-MT- Table
SPE-076- A.5
00005 All One per
Table ISO 21809-1 HT
d. Flexibility PQT 500 No cracking at 2.0º per pipe diameter length W W M/R LQF07-2-9
ISO 21809-1 7 Annex I C
pipe pipes
Table
9
In 3% NaCl,
-1.5V for 28 All
days, Less than 15 mm disbondment average radius HT
PQT --- W W M/R LQF07-2-9
at 90 ± 2°C, disbondment. C
pipe
ISO 21809-1
Annex H
In 3% NaCl,
-1.5V for 28 All
MS002-MT-
Table days, Less than 6 mm disbondment average radius HT
e. Cathodic disbondment SPE-076- PQT --- W W M/R LQF07-2-9
A.5 at 23 ± 2°C, disbondment. C
00005 pipe
ISO 21809-1
Annex H
In 3% NaCl,
-3.5V for 24 All One per
hours, Less than 6 mm disbondment average radius HT
PQT 500 W W M/R LQF07-2-9
at 65 ± 2°C, disbondment. C
pipe pipes
ISO 21809-1
Annex H
MS002-MT- Table 28 days test
SPE-076- A.5 80 °C ± 3 °C, One HT
--- Average ≤ 2 and maximum ≤ 3. W W M/R LQF07-2-9
00005 ISO 21809-1 pipe C
Annex M
f. Hot water immersion test
ISO 21809-1 11, 48 hours test One per
Table 80 °C ± 3 °C, One HT
500 Average ≤ 2 and maximum ≤ 3. W W M/R LQF07-2-9
7 ISO 21809-1 pipe C
pipes
Annex M
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Section 12 FIELD AND LAB TESTING FOR PIPES UNDER HEAT PROFILE QUALIFICATION
MS002-MT- Table
SPE-076- A.3
00005
ISO 21809-2 1 FBE
12.1 Adhesion (FBE) TC C5 -- Rating 1 to 2. HTC W W M/R QF07-2-8
Annex A.4 pipe
Minutes KOM
date 04 Nov
2019
Normal Temp FBE (For 30” OD x 21 mm and 30.2
mm WT)
Tg4 - Tg3 = -2°C to +3°C
Minutes KOM DSC Machine Tg2 greater than 95°C
1 FBE
12.2 Degree of cure (FBE) date 04 Nov -- ISO 21809-1 -- HTC W W M/R QF07-2-9
pipe
2019 Annex D 1 High Temp FBE (For 16.75” OD x 34 mm WT)
Tg2, Tg3 and Tg4 greater or equal to Tg as per
manufacturer specification
Tg4-Tg3 less than or equal to 3°C.
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Section 13 RETEST
If a production-coated pipe fails to conform to
acceptance criteria for a specified test, pipe length
shall be rejected, clearly marked and quarantined
unless approved otherwise by Client.
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
ISO 21809-1 12, Each All coating damage, whether a result of application
14.1 Repair criteria Table Visual Once or testing within the following criteria shall be HVC H H W QF07-2-10
repair
9 repaired.
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
C Record & Raise Documents H Hold Point N Non-Destructive Testing V Visual Inspection S Surveillance
Legend D Dimensional Inspection I Random Inspection R Review W Witness
WF
E Examine / Endorse Documents M Monitor T Destructive Testing Witness First Of
O
Inspection & Test Plan – THREE LAYER POLYPROPYLENE COATING FOR CS LINEPIPE
Customer: Project: BS Project No:
Sumitomo Corporation BP Tortue 17‐0102
Table 1