Professional Documents
Culture Documents
1
Neil Beeraspat USI # 1012008
Acknowledgement
Acknowledgments are given to the following persons for their valued input which resulted in the
successful completion of this final year project report:
Mr. Ronald Roberts, Senior Engineer, Transport and Planning Unit, Ministry of Public
Infrastructure for his technical support and guidance throughout the completion of this
project.
My parents and other family members for their support both financially and physically in
the completion of this project.
2
Neil Beeraspat USI # 1012008
Abstract
This project deals with the Re- Design of the East Bank Berbice Road (Islington to Glasgow).
Both a flexible and a rigid pavement are designed and recommendations are made to decide
which option is better for the area. Before the pavements are designed, the various field tests
(DCP, traffic counts etc.) are done to deduce all the necessary design input parameters that are
needed for both designs which are done according to the AASHTO Design of Pavement
Structures 1993. From the designs, information such as layer thicknesses are deduced after which
a cost analysis is done so as to provide the variations in costs for both options which will lead to
recommendations made as to the better choice for the Islington Glasgow section of the East Bank
of Berbice.
3
Neil Beeraspat USI # 1012008
Table of Contents
Acknowledgement.......................................................................................................................................2
Abstract.......................................................................................................................................................3
List of Abbreviations....................................................................................................................................6
List of Symbols.............................................................................................................................................7
List of Figures...............................................................................................................................................8
List of Tables................................................................................................................................................9
1.0 Introduction.........................................................................................................................................10
1.1 Background......................................................................................................................................10
1.2 Statement of Problem.....................................................................................................................12
1.3 Research Question...........................................................................................................................13
1.4 Aim..................................................................................................................................................13
1.5 Objective..........................................................................................................................................13
1.6 Scope...............................................................................................................................................14
2.0 Literature Review................................................................................................................................15
2.0.1 Paving of Roads............................................................................................................................15
2.0.2 Drainage methods used for Pavements........................................................................................16
2.0.3 DCP...............................................................................................................................................16
2.0.4 Pavement Design..........................................................................................................................17
2.0.5 Design Input..................................................................................................................................17
2.0.5.1 Flexible Pavement Design Input.............................................................................................17
2.0.5.2 Rigid Pavement Design Input.................................................................................................20
3.0 Methodology.......................................................................................................................................24
3.1 Theoretical Work.............................................................................................................................24
3.2 Practical Work..................................................................................................................................25
3.3 Gantt Chart......................................................................................................................................28
3.4 Critical Path Analysis........................................................................................................................29
4.0 Data Analysis.......................................................................................................................................33
4.1 Design Results..................................................................................................................................33
4.2 Cost Analysis....................................................................................................................................36
4.4 Actual Budget..................................................................................................................................50
5.0 Discussion............................................................................................................................................51
4
Neil Beeraspat USI # 1012008
6.0 Conclusion...........................................................................................................................................53
7.0 Reference............................................................................................................................................54
8.0 Appendix A......................................................................................................................................57
Appendix B: Traffic Count Data Sheets..................................................................................................61
ADT Calculations................................................................................................................................63
ESAL Spreadsheet..............................................................................................................................64
Appendix C: Condition Survey Data Sheets...........................................................................................65
Appendix D: Benkelman Beam Deflection Test Results.........................................................................77
Appendix E: Axle Load Survey Results...................................................................................................78
Appendix F: Design Charts and Cross Sections......................................................................................79
Appendix G: DCP Results.......................................................................................................................86
5
Neil Beeraspat USI # 1012008
List of Abbreviations
6
Neil Beeraspat USI # 1012008
List of Symbols
Reliability -R
Terminal Serviceability - Pt
Drainage Coefficient - Cd
7
Neil Beeraspat USI # 1012008
List of Figures
Figure 6: Chart for estimating structural layer coefficient of dense graded Asphalt Concrete (80)
Figure 11: Cross- sectional view of proposed layer design for flexible pavement.................. (86)
Figure 12: Cross- sectional view of proposed layer design for rigid pavement……………… (86)
8
Neil Beeraspat USI # 1012008
List of Tables
Table 2: Recommended Load Transfer Coefficients for various pavement Types……….. (22)
9
Neil Beeraspat USI # 1012008
1.0 Introduction
1.1 Background
The Islington to Glasgow road is the access road to communities along the East Bank of Berbice.
It was first constructed in the early 1970’s by the Ministry of Works, Hydraulics and Supply
which serves as the only access to Mara. Rice cultivation was the main source of income in that
community. This route served as the only access which farmers used to transport their produce to
the town of New Amsterdam.
The average population of Mara at the time of construction was approximately 380 persons. This
access road was first constructed with the use of gravel; it was readily available and was more
economical to use at the time of construction. Overtime various industries started to expand their
operations on the East Bank of Berbice (i.e. Bermine in the Everton community and Guyana
Sugar Corporation (Guysuco) at Providence), which provided employment for persons. This
expansion resulted in the need for more housing in nearby areas hence more housing schemes
were established which led to deterioration of the road because of population increase. In the
early 80’s the road was redesigned and instead of using gravel, the Ministry of Public Works
used asphaltic concrete as the surface course.
It was first recapped in 1993, using Double Bituminous Surface Treatment (DBST) as the
surface course. At this time the area had become more populated and the average population of
the Islington Glasgow area was now in excess of 1250 persons approximately. (Obtained from
‘History of EBB road’, MPI 2016)
The 42 km right of way varies significantly in width between New Amsterdam and Mara, which
the road width decreases from approximately 11.40 m to 2.45 metres. There are no lane
markings, but road users treat the road as a two lane carriageway for the entire length of the road.
There is no speed limit signage along the entire road, however the actual speed limit of the road
is 50 kmph according to the traffic laws of New Amsterdam.
Presently, the area has developed rapidly; more schools, churches, housing schemes and other
industries namely: Sol Terminal Plant, Guysuco Wharf, BLT fertilizer bagging & blending
10
Neil Beeraspat USI # 1012008
facility etc. now established. This development resulted in a tremendous increase in populace as
well as vehicular population in the area which caused the road to deteriorate faster. This
happened because in the initial design and recapping, this major increase in population was not
designed for. The road shoulders at most parts have also deteriorated due to excess rainwater
being lodged at the corners of the road. On inspection it was noted that at the corners of the road
the vegetation currently there acts as a hindrance to the rainwater to run off into nearby drains.
According to residents in the area rehabilitation works have been done on the deteriorated road
over the years (i.e. filling of all potholes on the road and patching parts of it) but this doesn’t
serve as a permanent solution to the problem and will only solve it temporarily due to the work
not being done to standard.
This research sets out to establish a new design for this road which will cater for future
developments which include increase of population and also vehicular population with a lifespan
of 20 years. Both a flexible and rigid pavement will be designed for and recommendations will
be made as to which option is better for the area.
11
Neil Beeraspat USI # 1012008
With the increasing volume of vehicles traversing the EBB, the condition of the road from
Islington to Glasgow has worsened over the years. This coupled with the fact that the road has
served far beyond its expected lifespan has left it in a deteriorated state which results in
commuters having difficulties traversing from communities along the EBB to the town of New
Amsterdam. Sub-standard rehabilitation works have been done periodically (i.e. filling up of
potholes and patching parts of the road) but it hasn’t improved the condition of the present road.
There is also an issue of water being lodged at the shoulders of the road which creates distresses
at the edges of the road. A re- design of the road that caters for increase in man as well as
vehicular population will provide comfort to all users and also measures will be put in place to
solve the issue of water lodged at the shoulders of the road.
12
Neil Beeraspat USI # 1012008
What is the best design for the Islington to Glasgow section of the East Bank of Berbice Road?
1.4 Aim
The aim of this research is to provide a better paved access road for commuters in the Islington
Glasgow area on the East Bank of Berbice.
1.5 Objective
13
Neil Beeraspat USI # 1012008
1.6 Scope
In order to provide a better paved access road for commuters in the Islington Glasgow area on
the EBB, this research will focus on redesigning the Islington to Glasgow road. Data collected
from the traffic counts will be used in the research. Information such as thickness of existing
asphaltic concrete, strength of sub base layer, deflection of the road and average loading will be
collected. The road is approximately 1140 metres long starting from the start Islington and
ending at the start of Glasgow.
14
Neil Beeraspat USI # 1012008
Construction of asphalt roads are done in three steps; production of asphalt mixture, placing and
compaction. Studies done by (Vaitkus et al., 2009) show that Hot Mix Asphalt (HMA) which is
more commonly used is very hazardous to the environment; its emission of Carbon Dioxide and
other dangerous gases to the environment is very high. When placing and producing the HMA,
the fumes are very dangerous for road works and asphalt plant workers to inhale. The
introduction of the use of Warm Mix Asphalt (WMA) reduces the temperature at which it is laid
to be paved on the road and it also lowers the emission of CO 2 and other harmful gases to the
environment.
Roads are commonly paved the same way; an asphalt mixer lays the material on the road, the
road workers evenly distribute the mix across the span of road and the paver compact the mix
and does the final grade to the pavement. The paving methods generally remain the same
according to studies done but new technologies are being used to lessen the harm to the
environment while maintaining the quality of roads built, the use of WMA on roads is becoming
more frequent and has shown much improvement in terms of production cost and paving
temperature and also more eco- friendly.
15
Neil Beeraspat USI # 1012008
In Guyana, the method of draining existing rainwater off the roadways that has been adopted by
all pavement engineers is to make the slope of the embankment two times that of the road slope.
(Obtained from MPI 2016)
2.0.3 DCP
In the initial phase of any road construction, Dynamic Cone Penetration (DCP) tests are
conducted to evaluate the present state of the road. Studies on Coring in Guyana shows it is
conducted by a corer that drills down into the sub layer to determine the thickness of the existing
asphalt. However, this method is a more traditional method that is used around the world.
Ground Penetrating Radar (GPR) is the more commonly used method; this method is done by
emitting radar signals into the layer which is transmitted to a monitor that records all the data.
Studies done by (Saarenketo and Scullion, 2000) in USA show that the GPR provides the layer
thickness, detects subsurface defects and also evaluates base course quality
Dynamic Cone Penetration (DCP) tests are done to assess the strength of the sub base layer.
Studies on DCP Testing in Guyana shows that it is conducted after the coring and is done by
dropping a hammer-like weight onto a penetration cone which is placed in drilled hole and the
blows per penetration is measured. Research done by (Chen et al., 2001) concludes that DCP is
one of the lowest- cost alternatives for characterization of pavement qualities. It is also fairly
easy to collect and analyze the data for the sub base layer. By conducting the DCP in a drilled
hole (in Guyana drilled hole is the coring sample’s hole), the error of estimate is reduced by 20
percent.
16
Neil Beeraspat USI # 1012008
2.0.5.1.1 Reliability
Reliability is defined as the probability that serviceability will be maintained at an adequate level
from the user’s point of view throughout the design life of the pavement. (Yoder and Witczak,
1975).
The reliability factor accounts for any change in traffic and performance predictions and
provides a level of assurance (R) that the pavement will survive the period in which it was
designed for. The reliability factor is dependent on the volume of traffic, difficulty of diverting
traffic and the risk of not performing to expectation all needs to be taken into account before
choosing a suitable reliability factor. (Highway and Officials, 1993)
17
Neil Beeraspat USI # 1012008
2.0.5.1.2 Serviceability
The term “present serviceability” is used to represent the momentary ability of pavement to serve
traffic, and the performance of the pavement was represented by its serviceability history in
conjunction with its load application history. (Terzi, 2007)
The serviceability is measured in Present Serviceability Index (PSI) and ranges from 0
(impossible road) to 5 (perfect road). Selection of the lowest allowable PSI (terminal
serviceability, Pt) is based on the lowest index that will be tolerated before rehabilitation and
ranges from 2.0 – 2.5. The original serviceability, P 0 also needs to be considered and it ranges
from 4.2 – 4.5. (Highway and Officials, 1993)
The overall standard deviation is a factor that is used to compensate for any deviation on a
construction site or any variance in traffic projections that are considered over the course of the
pavement’s useful life. This factor usually ranges from 0.30-0.40 for rigid pavements and from
0.40-0.50 for flexible pavements. (Timm et al., 2000)
18
Neil Beeraspat USI # 1012008
Equivalent Single Axle Load (ESAL) is a concept developed from data collected at the American
Association of State Highway Officials (AASHO) Road Test to establish a damage relationship
for comparing the effects of axles carrying different loads. The reference axle load is an 18,000-
lb or 18 kips. (Huang, 1993)
The CBR can be determined from conducting a Dynamic Cone Penetration Test (DCP) to the
depth of the subgrade. The MR value can then be correlated with the CBR value obtained by the
following equation:
19
Neil Beeraspat USI # 1012008
Before designing a rigid pavement, there are some variables that have to be determined via
different field tests which are conducted by the engineers. Before the design starts however, the
design engineer must decide which type of rigid pavement he will design. There are two types of
rigid pavement namely:
Jointed Pavements- There are two twos of jointed pavements; Plain Jointed Pavement
(JCP) and jointed reinforcement concrete pavement (JRCP). The JCP pavements are rigid
pavements that are designed without steel reinforcements. These pavements use dowel
bars to join together two separate concrete slabs. The maximum slab lengths for JCP are
6m. Jointed reinforcement concrete pavements, (JRCP) are pavements that are designed
with steel reinforcements. The reinforcements are used if there is a high probability of
transverse cracking occurring during the pavement life due to different conditions.
The modulus of subgrade reaction (k) is developed for rigid pavement designs just as the
effective roadbed soil resilient modulus is developed for flexible pavements. It estimates the
support of the layers below a rigid pavement surface course (the PCC slab). The modulus of
subgrade reaction came about because work done by Westergaard during the 1920s developed
the k-value as a spring constant to model the support beneath the slab.
20
Neil Beeraspat USI # 1012008
The modulus of rupture (flexural strength) is only necessary for rigid pavement designs. The
modulus of rupture required by the design procedure is the mean value determined after 28 days
using the three point loading (ASTM C78).
The modulus of rupture can also be correlated to the compressive strength of the concrete used.
Work done by Kirtikumar K. Shah, 1969 shows that the modulus of rupture can be determined
by correlating it to the compressive strength of the concrete at 28 days. His research concluded
the following equation used to determine the flexural strength of concrete:
f r=modulus of rupture
21
Neil Beeraspat USI # 1012008
0.5
Ec =57000∗(f ¿ ¿ c ' ) ¿
The load transfer coefficient, J is a factor used in rigid pavement design to account for the ability
of the concrete pavement to transfer load across discontinuities such as cracks and joints. The J
value generally increases as traffic loads increase since aggregate load transfer decreases with
load repetitions. The table below displays recommended load transfer coefficients for various
pavement types and design conditions. (Highway and Officials, 1993)
Table 2: Recommended Load Transfer Coefficients for various pavement Types (Sourced from
Part II Chapter 2 of the AASHTO design of pavement structures, 1993)
22
Neil Beeraspat USI # 1012008
For rigid pavements, the level of expected drainage is obtained through the use of a drainage
coefficient, Cd. As a basis for comparison, the value of C d for conditions of the AASHO test is
1.0. It is determined by identifying how long the water takes to be removed from the pavement
and the percentage of time the pavement is exposed to moisture level above saturation. (Yoder
and Witczak, 1975)
The table below shows the recommended values for the drainage coefficient for rigid pavements:
Table 3: Recommended Values of Drainage Coefficients for rigid Pavements (Sourced from Part
II Chapter 2 of the AASHTO design of pavement structures, 1993)
23
Neil Beeraspat USI # 1012008
3.0 Methodology
The researcher’s methodology was done in two phases; the Theoretical Work and the Practical
Work. Data collected from the practical work were used in the Data Analysis. Data was collected
via the different tests proposed by the researcher. All tests were completed within the given
timeline. A quantitative study was executed, this was done to facilitate all readers to have a clear
understanding of the data collected and are represented on various charts and graphs.
The theoretical work of this research was obtained from various sources; articles from accredited
scholars that have been published on designs of roads and from various textbooks that are related
to the use of asphalt and concrete on roads as surface courses. Information was also gathered
from MPI which included all historical data and previous works done on the East Bank Berbice
Road.
24
Neil Beeraspat USI # 1012008
The practical work for this project encompasses a Condition Survey, Traffic Counts and the
various field tests proposed.
Condition Survey- A condition Survey is comprised of the following parts; Pavement distresses,
Pavement Width, Drainage and Shoulder Width. This survey will be done by the researcher and
the data collected will be used in the analysis.
Successful redesigning of the road can only be achieved when knowledge of the various types of
distresses occurring in the pavement is known. The pavement distresses will be assessed on the
basis of the following:
Alligator Cracks- These are a series of interconnected cracks caused by fatigue failure in
the pavement under repeated traffic loading.
Longitudinal Cracks- These are cracks that run longitudinal to the center line.
Depressions- This refers to areas of the pavement that has a lower elevation than the
surrounding pavement.
Raveling- Refers to the progressive disintegration of HMA layer from the surface
downward which is caused by dislodgement of aggregate particles.
Pot holes- These are bowl shaped depressions that penetrate through the existing asphalt
all the way to the base course. (AASHTO Design of Pavement Structures 1993)
Traffic Counts- Vehicular counts were done for two days from 6am-6pm daily and was used in
the Data Analysis. This count was conducted after the condition survey has been completed.
25
Neil Beeraspat USI # 1012008
Fields Tests
Benkelman Beam Deflection Test- This test is done in the initial stage of all road construction.
It is a test that measures the deflection of the existing pavement. It is done by having a single
axle truck with dual tires inflated to 70 to 80 psi and the truck itself weighing typically 80 KN.
The deflection is recorded as the truck moves along the road. The researcher will use the
deflection data collected from this test in the analysis.
Dynamic Cone Penetration Test (DCP) - DCP is done to determine the resistance to
penetration of the existing sub base layer. It is usually done after coring, the coring sample is
removed and the DCP instrument is placed in the surface of the sub base. The penetrating cone is
placed in the ground and a hammer is dropped from a height and penetration per blow is
recorded. The researcher will record the data collected after completing this test.
Axle Load Survey- This is a survey done to provide the average pavement loading. It is
conducted by the manual capture of vehicle weights using a portable weigh scale under low
speed conditions.
Establish Pavement Design- After all the data is collected, a suitable design was produced for
the road. The road was designed using the AASHTO Design of Pavement Structures 1993, both
a rigid and flexible pavement were designed for and recommendations were made as to the better
option.
26
Neil Beeraspat USI # 1012008
Cost Analysis- After completing both designs, a bill of quantities was produced for both options
to help support recommendations that are made as to the better option for the area. The rates
were produced with the help of local contractors in Berbice.
27
Neil Beeraspat USI # 1012008
28
Neil Beeraspat USI # 1012008
DU- Duration
Float = Late Finish (LF) – Duration (DU) – Early Start (ES) …. (3)
29
Neil Beeraspat USI # 1012008
Condition Survey E D 7
DCP F E 7
Data Analysis I H 6
30
Neil Beeraspat USI # 1012008
31
Neil Beeraspat USI # 1012008
Activity A: 46 – 46 - 0 = 0
Activity B: 47 - 1 - 46 = 0
Activity C: 48 – 1 - 47 = 0
Activity D: 50 – 2 - 48 = 0
Activity E: 57 - 7 - 50 = 0
Activity F: 64 – 7 - 57 = 0
Activity G: 66 – 2 - 64 = 0
Activity H: 68 – 2 - 66 = 0
Activity I: 74 – 6 - 68 = 0
Activity J: 75 - 1 - 74 = 0
Activity K: 95 - 20 - 75 = 0
Activity L: 113 – 18 – 95 = 0
Since all activities have a Float of 0, therefore all the activities are critical. The activities with
two red crossed through the arrows indicated that the task is critical.
32
Neil Beeraspat USI # 1012008
A formative analysis was done for this project. As the project progressed, more information on
the AASHTO Design of pavement structures 1993 was obtained, the designs were completed
according to specifications from the guide. All data that were collected are displayed on various
charts and graphs to allow understanding of work to all readers.
SN=a 1 D 1 +a2 D 2 m2 +a 3 D 3 m 3
33
Neil Beeraspat USI # 1012008
SN obtained ¿ graph=4
Where;
a1, a2, a3 are layer coefficients representative of surface, base and subbase courses
respectively.
D1, D2, D3 are actual layer thicknesses for the surface, base and subbase course
respectively.
m2, m3 are drainage coefficients for the base and subbase course respectively.
Layer
Layer Drainage Structural
Layer Material Thickness
Coefficient Coefficient Number (SN)
(inches)
Asphaltic Concrete 0.44 1 4 (100mm)
Cement Stabilized white 4
0.26 1 5 (125mm)
sand/ sand clay
White Sand 0.07 1 12 (600mm)
34
Neil Beeraspat USI # 1012008
Dowel Diameter: 7/8 inches (22 mm) @ 12 inch spacing and 18 inch lengths (Part II Chapter
2.4.2 AASHTO Design of Pavement Structures, 1993)
The mix design ratio that will be used is a 1:2:3 @ 0.45 water cement ratio.
35
Neil Beeraspat USI # 1012008
36
Neil Beeraspat USI # 1012008
37
Neil Beeraspat USI # 1012008
2.5 Removal of Traffic Signs, Traffic Signals, Street 1 SUM $550 $550
lights etc.
Section 02030: Earthworks
2.6 Roadway Excavation 15,000 m3 $350 $5,250,000
Excavation and the placement in embankments of
all materials necessary for the construction of the
earthworks
m3
2.7 Ditch Excavation 5,000 $100 $500,000
m3
2.8 Clay Backfill 10,000 $600 $6,000,000
Placing and compacting of selected clay for road
shoulders and backfill to structure
2.9 Cleaning and Shaping of existing drains 2000 m $1,000 $2,000,000
Includes the requirements and procedures for
cleaning and shaping existing open drains,
ditches, side drains and irrigation canals in
excess of the general maintenance
requirements of the Contract
Section 02040: Roadside Improvement Material
2.1 Roadside Improvement Material (Grass Seeding) 4000 m $550 $2,200,000
38
Neil Beeraspat USI # 1012008
Bill 4: Pavement
39
Neil Beeraspat USI # 1012008
40
Neil Beeraspat USI # 1012008
41
Neil Beeraspat USI # 1012008
42
Neil Beeraspat USI # 1012008
43
Neil Beeraspat USI # 1012008
prov.
1.6 Permanent Relocation of Electrical Utilities NA NA NA
Sum
prov.
1.7 Permanent Relocation of Water Utilities NA NA NA
Sum
Permanent Relocation of Telephone prov.
1.8 Na NA NA
Utilities Sum
1.9 Contractor’s Programme 1 Sum $40,000 $40,000
2.5 Removal of Traffic Signs, Traffic Signals, Street 1 SUM $550 $550
lights etc.
Section 02030: Earthworks
44
Neil Beeraspat USI # 1012008
Bill 4: Pavement
47
Neil Beeraspat USI # 1012008
48
Neil Beeraspat USI # 1012008
1 Labour $10000
3 Stationary $10000
49
Neil Beeraspat USI # 1012008
4 Transportation $10000
5 Miscellaneous $10000
Total $40000
5.0 Discussion
For this project ‘A Re- Design of the East Bank Berbice Road (Islington to Glasgow)’, two
designs were done; a flexible pavement and a rigid pavement. All necessary field tests were done
so as to obtain the necessary variables for each respective design.
Traffic counts were done to estimate the Average Daily Traffic (ADT) which was later used to
determine the Equivalent Single Axle Load (ESAL) for both designs. The Dynamic Cone
Penetration Test (DCP) was also done to estimate the California Bearing Ratio (CBR) value for
the subgrade. All variables for the rigid pavement design were obtained for the design process as
highlighted earlier in the document. Both designs were done according to the AASHTO Design
of Pavement Structures 1993.
50
Neil Beeraspat USI # 1012008
The results for both design options were highlighted earlier in the document. A Bill of Quantities
(BOQ) was produced for both options giving estimated costs for both designs.
Advantages of constructing the flexible pavement over the rigid pavement for the Islington
Glasgow area are as follows:
It is the more cost effective options as shown in the BOQs. It will need more maintenance
works during its design life but this option has the smaller initial cost.
Most local contractors have more knowledge about flexible pavements in terms of
construction methods compared to rigid pavements. In Guyana, most of the roads (both
main and miscellaneous) are flexible pavements and most construction companies have
greater knowledge and experience in constructing flexible pavements compared to rigid
pavements.
For the flexible pavements, traffic can be allowed to traverse after the base course is laid
and compacted, so there won’t be much traffic congestion during the construction
process. The construction can be done per lane so as to facilitate traffic to still traverse
along the East Bank Berbice road. For the rigid pavement however, the Jointed Concrete
Pavement (JCP) slab needs to be casted and cured before traffic is allowed to traverse the
area. The average curing time for concrete to reach its maximum compressive strength is
28 days. In addition, each slab can be constructed to a maximum length of six meters
(6m), so to avoid traffic congestion a detour path would have to be constructed to help
facilitate traffic flow during the construction process. The Eastern side of the road has the
Berbice River nearby so the Western side of the road would be used for the detour, the
lands behind the housing area would be used so as to not disrupt the residential area. The
cost for the detour would be a lump sum in the BOQs because the exact cost would be
known until construction which will result in the rigid pavement costing a lot more than
the flexible pavement.
For both pavements the major environmental impacts that are foreseen if either options are
constructed are as follows:
Dust- Dust will affect nearby residents for both pavement options. For both options the
subbase layer is white sand and if not properly soaked after placing and compacting can
51
Neil Beeraspat USI # 1012008
lead to dust being prevalent in the area. To combat this impact, the sand would be soaked
after placing.
Noise- Noise from the construction equipment will cause disturbance to residents during
their day to day activities. To combat this, all machinery that would be used would be
serviced and properly maintained so as to limit the amount of noise the machineries
make. Also sound barriers in the form of fences can be used to fence off the construction
area to limit the amount of noise reaching the residents.
So in my view the better option for the area is the flexible pavement due to the reasons stated
previously. The actual thicknesses for each layer are provided in the results section of the
document and a cross section of the proposed layer design is provided in the appendix.
6.0 Conclusion
It can be concluded that after all the data required was collected for both designs and both the
rigid and flexible pavements were designed it is recommended that the flexible pavement be
constructed for the Islington Glasgow area for the East Bank Berbice road.
52
Neil Beeraspat USI # 1012008
7.0 Reference
Arora, M. G., et al. (1994). "Long-term pavement performance history of sulfur-extended asphalt
test roads in eastern province of Saudi Arabia." Transportation Research Record (1435).
53
Neil Beeraspat USI # 1012008
Cahill, T. H., et al. (2004). "Asphalt-The Right Choice for Porous Pavements." Better Roads
74(11).
Chen, D.-H., et al. (2001). "Application of dynamic cone penetrometer in evaluation of base and
subgrade layers." Transportation Research Record: Journal of the Transportation Research Board
(1764): 1-10.
De Beer, M., et al. (1997). Determination of pneumatic tyre/pavement interface contact stresses
under moving loads and some effects on pavements with thin asphalt surfacing layers. Proc., 8th
International Conference on Asphalt Pavements.
Fauchard, C., et al. (2003). "GPR performances for thickness calibration on road test sites." Ndt
& E International 36(2): 67-75.
Grant, M. and R. Walker (1972). The development of overlay design procedures based on the
application of elastic theory. Presented at the Third International Conference on the Structural
Design of Asphalt Pavements, Grosvenor House, Park Lane, London, England, Sept. 11-15,
1972.
Hafez, I. H. F. (1997). Development of a simplified asphalt mix stability procedure for use in
Superpave volumetric mix design.
Hall, K. T., et al. (2001). Rehabilitation strategies for highway pavements, Transportation
Research Board.
Isenring, T., et al. (1990). "Experiences with porous asphalt in Switzerland." Transportation
Research Record(1265).
Li, J., et al. (2009). "Calibration of flexible pavement in mechanistic-empirical pavement design
guide for Washington state." Transportation Research Record: Journal of the Transportation
Research Board(2095): 73-83.
54
Neil Beeraspat USI # 1012008
McPherson, E. G. and J. Muchnick (2005). "Effect of street tree shade on asphalt concrete
pavement performance." Journal of Arboriculture 31(6): 303.
Mehrkar-Asl, S. (1996). Concrete Stress Relief Coring: Theory and Practice. Proceedings of the
FIP First Symposium on Post Tensioned Concrete Structures, London.
Mohammad, L., et al. (2006). "Permanent deformation analysis of hot-mix asphalt mixtures with
simple performance tests and 2002 mechanistic-empirical pavement design software."
Transportation Research Record: Journal of the Transportation Research Board(1970): 133-142.
Nicholson, J. P. (1977). Mixture for pavement bases and the like, Google Patents.
Noyce, D. A., et al. (2005). "Incorporating road safety into pavement management: maximizing
asphalt pavement surface friction for road safety improvements." Draft Literature Review and
State Surveys, Midwest Regional University Transportation Center (UMTRI), Madison,
Wisconsin.
Reese, R. (1997). "Properties of aged asphalt binder related to asphalt concrete fatigue life."
Journal of the Association of Asphalt Paving Technologists 66.
Roberts, F. L., et al. (2002). "History of hot mix asphalt mixture design in the United States."
Journal of Materials in Civil Engineering 14(4): 279-293.
Saarenketo, T. and T. Scullion (2000). "Road evaluation with ground penetrating radar." Journal
of applied geophysics 43(2): 119-138.
Taha, R., et al. (2002). "Cement stabilization of reclaimed asphalt pavement aggregate for road
bases and subbases." Journal of Materials in Civil Engineering 14(3): 239-245.
55
Neil Beeraspat USI # 1012008
Vaitkus, A., et al. (2009). "Analysis and evaluation of possibilities for the use of warm mix
asphalt in Lithuania." The Baltic Journal of Road and Bridge Engineering 4(2): 80-86.
Wiley, T. W. (2002). Method of and apparatus for heating a road surface for repaving, Google
Patents.
Shah, K. K. (1969). The Relationship of the Modulus of Rupture and the Compressive Strength
of Ultracal-30 Micro- Concrete, Brigham
Witzcak, M. W. (2002). Simple performance test for superpave mix design, Transportation
Research Board.
TERZI, S. 2007. Modeling the pavement serviceability ratio of flexible highway pavements by
artificial neural networks. Construction and Building Materials, 21, 590-593.
YODER, E. J. & WITCZAK, M. W. 1975. Principles of pavement design, John Wiley & Sons.
8.0 Appendix A
57
Neil Beeraspat USI # 1012008
58
Neil Beeraspat USI # 1012008
Picture showing the DCP test being done (taken by N. Beeraspat 03/06/2017)
59
Neil Beeraspat USI # 1012008
60
Neil Beeraspat USI # 1012008
ADT Calculations
16 hrs 16 hrs
3522 3533
Using a 95% confidence limit for 24 hour traffic with 5% tolerance = 7055/0.95
= 7427 vehicles
ADT = 7427/2
63
Neil Beeraspat USI # 1012008
ESAL Spreadsheet
Tf
Truck Factor 1.2
Y Years 20
r Growth Factor 6 %
G G= (1+r)^0.58Y 1.97
D Directional Distribution 50 %
64
Neil Beeraspat USI # 1012008
(Condition Survey Data Sheets obtained from ASTM D 6433 and also deduct values were
estimated from graphs in the ASTM D 6433)
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 32 22 15 10 8.2 5.5 5 0.06 97.76 7 48
2 32 22 15 10 8.2 5.5 2 0.06 94.76 6 47
3 32 22 15 10 8.2 2 2 0.06 91.26 5 52
4 32 22 15 10 2 2 2 0.06 85.06 4 54
5 32 22 15 2 2 2 2 0.06 77.06 3 48
6 32 22 2 2 2 2 2 0.06 64.06 2 32
7 32 2 2 2 2 2 2 0.06 44.06 1 46
8 32 2 2 2 2 2 2 0.06 44.06
9
Rating- Poor
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
66
Neil Beeraspat USI # 1012008
q
# Deduct Value Total CDV
1 28 18 12 10 9.5 5.5 5 0.061 88.061 7 41
2 28 18 12 10 9.5 5.5 2 0.061 85.061 6 43
3 28 18 12 10 9.5 2 2 0.061 81.561 5 47
4 28 18 12 10 2 2 2 0.061 74.061 4 48
5 28 18 12 2 2 2 2 0.061 66.061 3 42
6 28 18 2 2 2 2 2 0.061 56.061 2 42
7 28 2 2 2 2 2 2 0.061 40.061 1 41
8
Rating- Poor
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
67
Neil Beeraspat USI # 1012008
Rating- Poor
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
68
Neil Beeraspat USI # 1012008
1 28 21 14 6 0.061 69.061 4 38
2 28 21 14 2 0.061 65.061 3 42
3 28 21 2 2 0.061 53.061 2 45
4 28 2 2 2 0.061 34.061 1 38
5 28 2 2 2 0.061 34.061
Rating- Poor
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
69
Neil Beeraspat USI # 1012008
q
# Deduct Value Total CDV
1 20 14 13 12.5 5.5 1.7 66.7 5 36
2 20 14 13 12.5 2 1.7 63.2 4 45
3 20 14 13 2 2 1.7 52.7 3 34
4 20 14 2 2 2 1.7 41.7 2 40
5 20 2 2 2 2 1.7 29.7 1 30
6
Rating- Poor
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 21.5 20 19.9 11 2.1 74.5 5 42
2 21.5 20 19.9 11 2 74.4 4 44
3 21.5 20 19.9 2 2 65.4 3 42
4 21.5 20 2 2 2 47.5 2 40
5 21.5 2 2 2 2 29.5 1 30
Rating- Fair
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 38 19.9 9.5 8 0.35 75.75 4 44
2 38 19.9 9.5 2 0.35 69.75 3 48
3 38 19.9 2 2 0.35 62.25 2 46
4 38 2 2 2 0.35 44.35 1 46
5
Rating- Poor
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 48 37 12 11.5 9 8 7.5 0.39 133.39 7 66
2 48 37 12 11.5 9 8 2 0.39 127.89 6 66
3 48 37 12 11.5 9 2 2 0.39 121.89 5 70
4 48 37 12 11.5 2 2 2 0.39 114.89 4 72
5 48 37 12 2 2 2 2 0.39 105.39 3 66
6 48 37 2 2 2 2 2 0.39 95.39 2 68
7 48 2 2 2 2 2 2 0.39 60.39 1 60
8
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 66 20 14 10 9.9 5 0.06 124.96 6 62
2 66 20 14 10 9.9 2 0.06 121.96 5 70
3 66 20 14 10 2 2 0.06 114.06 4 72
4 66 20 14 2 2 2 0.06 106.06 3 66
5 66 20 2 2 2 2 0.06 94.06 2 66
6 66 2 2 2 2 2 0.06 76.06 1 74
7
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 51.5 42 14 12 11 9.5 0.225 140.225 6 73
2 51.5 42 14 12 11 2 0.225 132.725 5 74
3 51.5 42 14 12 2 2 0.225 123.725 4 70
4 51.5 42 14 2 2 2 0.225 113.725 3 68
5 51.5 42 2 2 2 2 0.225 101.725 2 72
6 51.5 2 2 2 2 2 0.225 61.725 1 62
7
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 36 18 17 8 4.4 83.4 5 48
2 36 18 17 8 2 81 4 46
3 36 18 17 2 2 75 3 49
4 36 18 2 2 2 60 2 44
5 36 2 2 2 2 44 1 44
Rating- Poor
Sketch:
Asphalt Surfaced Road Condition Survey Sheet
q
# Deduct Value Total CDV
1 41.5 15 14 11 1.85 83.35 4 52
2 41.5 15 14 2 1.85 74.35 3 49
3 41.5 15 2 2 1.85 62.35 2 46
4 41.5 2 2 2 1.85 49.35 1 51
5
Rating- Poor
(Results for this field test as well as Axle Load Survey were obtained from MPI on 13/03/2017)
Rut Depth
Normalized Rut Normalized d0
d0 (mm) Depth (mm)
Station
0+000 2 0.322 1 0.383
0+050 2 0.374 0 0.33
0+100 7 0.991 1 0.722
0+150 1 0.678 11 1.243
0+200 13 1.913 3 2.348
0+250 3 1.748 8 2.174
0+300 9 1.93 13 2.243
77
Neil Beeraspat USI # 1012008
78
Neil Beeraspat USI # 1012008
Appendix E: Axle Load Survey Results AXLE LOAD (KG) Equivalent Load Factor Breakdown
Survey Vehicle Axle Description of E‐ Empty P‐
Time Reg No Origin Destination Wheel Axle Axle Axle Axle Type Wtg ESAL Axle Type Wtg ESAL Axle Type Wtg ESAL
No. Category Configuration Load/Cargo PartFull F‐ Full Total
1 2 3 1 2 3
New Congo
8:16:00 AM BSS 9400 Big Bus 1:02 Nil E L 940 1,060 S 1,800 0.118 S 2,060 0.118 ‐ 0 0.236
1 Amsterdam Creek
R 860 1,000
East Bank
8:22:00 AM GMM 7229 Tanker 1:02:02 Fuel P Corentyne L 1,810 2,460 2,610 S 3,760 0.118 S 4,970 0.399 S 4,700 0.399 0.916
2 Berbice
R 1,950 2,510 2,090
New East Bank
8:35:00 AM _ Pick up 1:02 Passenger P L 560 400 S 1,080 0.118 S 750 0.0003 ‐ 0 0.1183
3 Amsterdam Berbice
R 520 350
8:38:00 AM GRR 2231 Truck 1:01 Goods P Corentyne De Kinderen L 1,450 1,610 S 2,780 0.118 S 3,130 0.118 ‐ 0 0.236
4
R 1,330 1,520
New East Bank
8:41:00 AM GGG 1067 Truck 1:02 Passenger P L 1,680 2,680 S 3,190 0.118 S 4,890 0.399 ‐ 0 0.517
5 Amsterdam Berbice
R 1,510 2,210
Tractor &
8:56:00 AM 24560 1:01:01 Nil E Vryheid Rotter Dam L 260 770 720 S 540 0.0003 S 1,560 0.118 S 1,460 0.118 0.2363
6 trailer
R 280 790 740
8:58:00 AM GJJ 7143 Canter 1:02 Nil E Plegt Anker Glasgow L 600 410 S 1,310 0.118 S 1,010 0.118 ‐ 0 0.236
7
R 710 600
West Coast
9:00:00 AM GJJ 9437 Canter 1:02 Goods P Sisters L 1,170 1,920 S 2,180 0.118 S 3,570 0.118 ‐ 0 0.236
8 Berbice
R 1,010 1,650
New East Bank
9:02:00 AM 24524 Tractor 1:01:02 Earth F L 1,410 2,350 2,120 S 2,910 0.118 S 4,950 0.399 S 4,420 0.118 0.635
9 Amsterdam Berbice
R 1,500 2,600 2,300
New
9:05:00 AM GRR 7387 Truck 1:02 Passenger P Everton L 1,700 1,560 S 3,430 0.118 S 3,360 0.118 ‐ 0 0.236
10 Amsterdam
R 1,730 1,800
New East Bank
9:24:00 AM GHH 1062 Canter 1:02 Passenger P L 660 420 S 1,400 0.118 S 1,030 0.118 ‐ 0 0.236
11 Amsterdam Berbice
R 740 610
New
9:30:00 AM GSS 3583 Canter 1:02 Passenger P Brothers L 640 500 S 1,290 0.118 S 950 0.118 ‐ 0 0.236
12 Amsterdam
R 650 450
New
9:40:00 AM GNN 6513 Tanker 1:02 Passenger P Belle Vue L 2,020 1,950 S 4,160 0.118 S 3,750 0.118 ‐ 0 0.236
13 Amsterdam
R 2,140 1,800
New East Bank
9:50:00 AM GNN 321 Canter 1:02 Equipment F L 620 1,510 S 1,210 0.118 S 3,140 0.118 ‐ 0 0.236
14 Amsterdam Berbice
R 590 1,630
East Bank
10:15:00 AM GRR 7929 Canter 1:02 Passenger P Corentyne L 850 550 S 1,670 0.118 S 1,130 0.118 ‐ 0 0.236
15 Berbice
R 820 580
New
10:17:00 AM GPP 235 Canter 1:02 Goods P Lons Dale L 870 480 S 1,670 0.118 S 890 0.0003 ‐ 0 0.1183
16 Amsterdam
R 800 410
New East Bank
10:25:00 AM GSS 3277 Truck 1:02 Nil E L 1,390 880 S 2,870 0.118 S 1,660 0.118 ‐ 0 0.236
17 Amsterdam Berbice
R 1,480 780
New
10:27:00 AM GMM 4383 Tanker 1:02:02 Nil E Sisters L 2,440 1,900 1,850 S 4,970 0.399 S 3,250 0.118 S 3,140 0.118 0.635
18 Amsterdam
R 2,530 1,350 1,290
Figure 6: Chart for estimating structural layer coefficient of dense graded Asphalt concrete
(Sourced from Part II Chapter 2 of the AASHTO design of Pavement structures, 1993)
80
Neil Beeraspat USI # 1012008
Figure 7: Variation in a2 for cement- treated bases (Sourced from Part II Chapter 2 of the
AASHTO design of pavement structures, 1993)
81
Neil Beeraspat USI # 1012008
Figure 8: Variations in Granular Subbase layer coefficient (Sourced from Part II Chapter 2 of the
AASHTO design of pavement structures, 1993)
82
Neil Beeraspat USI # 1012008
Figure 9: Design Chart for Flexible Pavement (Sourced from Part II Chapter 3 of the AASHTO
design of pavement structures, 1993)
83
Neil Beeraspat USI # 1012008
84
Neil Beeraspat USI # 1012008
Figure 10: Design Chart for Rigid Pavements (Sourced from Part II Chapter 3 of the AASHTO
design of pavement structures, 1993)
85
Neil Beeraspat USI # 1012008
Figure 11: Cross- sectional view of proposed layer design for flexible pavement option.
Figure 12: Cross- sectional view of proposed layer design for rigid pavement option.
86
Neil Beeraspat USI # 1012008