Professional Documents
Culture Documents
As the professional courses not only require the theoretical knowledge but practical
knowledge too, that is why college started conducting training program for the students, so
that they can get ample view of practical problems. I find it a matter of honour in showing the
feeling of indebtedness and thankfulness to the Principal, GURU NANAK DEV
ENGINEERING COLLEGE , LUDHIANA for providing this opportunity to carry out the
six months industrial training
This is certify that I Banty Kumar Sangra student of Civil 7th Semester Roll No-150377
,University Roll no :- 1606595 has undergone industrial training in “Gammon India
limited Engineers& Contractors” as required of six month project semester for the award
of Degree of Civil Engineering, GURU NANAK DEV ENGINEERING COLLEGE and
prepared the report entitled “FOUR LANNING OF UDHAMPUR-RAMBAN SEC. OF
NH-1A” which is an authentic record of my work carried out at Udhampur, Jammu.
If any discrepancy is found regarding the originality of this project I may be held
responsible. I have not copied from any report submitted earlier this or any other university
this is purely original and authentic work.
LIST OF ABBREVIATIONS
LIST OF FIGURES
LIST OF TABLES
CHAPTER 1 Introduction 10
2.2 History 15
2.5 Awards/Achievements 18
3.1.1 Surveying 19
3.1.2 Earthwork 22
6.3 Test‟s 61
7.1 Cement 90
7.2 Aggregates 90
7.3 Admixers 91
CHAPTER 8 Safety 98
Conclusion 108
o MAJOR INTERSECTIONS: 2
o MINOR INTERSECTIONS: 5
Prime Minister Shri Narendra Modi, has given its approval for development of
the four laning of the Udhampur – Ramban section of NH-1A (now NH-44) in
J&K. This work will be under the NHDP Phase-II. The approval is in
Engineering, Procurement and Construction (EPC) mode.
The cost is estimated to be Rs. 1709.99 crores including cost of land acquisition,
resettlement and rehabilitation and other pre-construction activities. The total
length of the road will be approximately 40.07 kms.
Gammon India has secured a 1709.99 crore project from NHAI for four laning of
Udhampur to Ramban section of NH-1A from 67 to 89 and 130 to 151 kms.
The project was started on 28th September 2015 and has a period of 1095 days to
complete the project. After the completion of the project the company has to
maintain it for 4 more years after completion.
• MD :- Abhijit Rajan
Bankers : DBS Bank, ICICI Bank, IDBI Bank, Indian Bank, Karnataka Bank,
Oriental Bank of Commerce, Punjab National Bank, Syndicate Bank, Union
Bank of India, UCO Bank, United Bank of India, Central Bank of India,
Canara Bank, Bank of Baroda, Allahabad Bank, Bank of Maharashtra
Auditors : Natvarlal Vepari
Gammon India is not only the largest civil engineering construction company
in India, but can lay claim for the largest number of bridges built in the whole
of Commonwealth. With over seventy years of tradition in the field of
construction. Gammon is a name that is inextricably woven into the fabric of
India.
This insatiable quest has led Gammon to pioneer Reinforced and Prestressed
Concrete, Long span bridges, Under water concreting using the Colcrete
process, Thin shell structures, Non–Shrinking concrete, Aluminium trusses
for launching precast, prestressed beams and many more
Bramhaputra Bridge
Gorakhpur By Pass
Kosi Bridge
March 2010 – Gammon India won Rs 631.81 crore order from Delhi Tourism
and Transportation Development Corporation (DTTDC). The order is for
construction of bridge which approaches over river Yamuna at Wazirabad,
Delhi.
February 2010 – Gammon India has bagged a contract form the International
Society for Krishna Consciousness (ISKCON) worth Rs 137.28 crore. The
order comprises construction of Sri Chaitanya Chandrodaya Mandir and
Indian Educational & Cultural Centre at Sri Mayapur, Dist: Nadia, West
Bengal.
IIBE–7th Annual Award Nite for Noida Bridge at Delhi by Noida Bridge at
Delhi– 2001
ACCE–L&T Endowment Award for Excellence in construction of
Industrial Structure, Raichur Natural Draft Cooling Towers by Raichur
Multiflue Chimney– 2000
IFAWPCA Certificate for Thane Creek Bridge by Thane Creek Bridge –1971
In the four month training period, I have been working in the following sections.
I. Site work
II. Material tests
III. Office work
3.1Site work
1. Surveying
2. Earth work
3. Construction of pavement layers
4. Construction of structures
5. Construction of walk way
3.1.1 Surveying
Before any construction activity all survey results are undertaken under the
supervision of the engineer‟s representative, and all the survey works are
submitted to the engineer in digital format. after the survey works are
approved by the engineers the setting out Work continues.
The detail vertical, horizontal alignments, widening and shoulders are designed
by the Engineer‟s, based on this the contactor prepares a template (Cross
sectional working drawings), which is easy to understand, using eagle point
software. After the template (Cross sectional working drawings) is approved by
the engineers, the surveyors use this template in the setting out works.
-) or fill(+)
The surveyor uses the template (cross sectional drawings) to set out all the above
information for construction of all pavements. After construction, the design elevation
of each pavement layers is cheeked (As built reading for layers above the sub grade is
taken) by consultants (with a tolerance of +2.5 for earth works).
Surveyors in consulting engineer‟s side are mainly engaged in checking each part of the
section done by contractor surveyors. After a completion of one section of a particular
layer or part of a structure they are responsible for checking the desired elevation as per
the section template or structural drawing is reached. If the result is not in a tolerable
In surveying the main task is setting out design works to the ground.
Instruments used for setting out works include total station, and leveling. I
have been with the survey staff for about 10 days, and in those days I have
tried to cover all survey works.
Works that I have executed while I was working with the surveying crew are
While this section I have performed good, this is because I have already got a good
understanding of survey works in the university and almost the same procedure
is used in the practical world.
The challenge I have faced while I was working with the surveyors is lack of knowledge
for operate total station and lack of accuracy during make correction for sub base and
base due to an uniform crown slope of the existing lane
I have solved this by using getting tutors from surveying mans and we made blue
elevation for grader machine operator and we use average crown slope per station
Earth work includes excavation of material to attain the design elevation of the road. It
includes sub grade construction including capping layer.
3.1.2.1 Cutting
Cutting is the excavation of supper elevated area to get the design elevation of the road.
It stands at or near vertical in sound rock, but in weathered rock or soil, cutting is done
with slope with respect to the soil type.
Type of material to be excavated governs the construction method, the suitability of the
cut material for the sub grade and slope that can be safely adopted.
Water table:
A water table may be permanent or seasonal. In any case its presence and characteristics
(level, flow of water etc.) is determined. Due to occurrence and level of water table
affects the method excavation and stability of cut slope and the drainage system.
Some materials need high energy to excavate and transport away from the excavation
area. For example the area which is sound rock and has a boulder needs consideration of
volume of cut and where it should be transported.
Cut section always needs always drainage to drain out the water which comes from
either cut section, catchment area or both. This accumulation of water erodes the
excavated area. So, it needs a solution to protect erosion. For example at the area where
the water flow is available from the catchment area to the cut section, intercept ditch is
built to drain out the water before it reaches the cut section.
The surveyor fixes the slope of stack limit according to the design.
Unsuitable materials are removed and replaced by appropriate materials as
per engineer‟s recommendation.
The road bed is prepared.
Field density test is taken to check whether the compaction attains its
degree of compaction at optimum moisture contain.
After showering the road bed, the material filled is dumped.
The dumped fill material fill material is mixed and placed at the moisture
content near to the optimum moisture content by the grader.
The mixed and placed material is compacted by steel roller until the
compaction attains 95% maximum dry density.
The contractor takes an agreement of the following specification of materials with ERA for
embankment.
The sub grad is prepared by either filling or cutting so as to meet the design level.
If the approved design needs cutting, the existing ground is excavated using any
suitable equipment (dozer, excavator, and grader) until the finished sub grade
level is reached.
Sub grade is the final layers of the embankment in fill and cut sections. This is the
layer just above road bed on which the pavement layers finally rest on it. Sub grade is
constructed as follows.
The setting out work is done using five pegs per station.
The surface is showered on which the sub grade layer is to be constructed.
The sub grade materials is dumped.
Sub grade
material
Sub base is a pavement layer which is laid directly above the sub grade. It is an important
layer to spread the load in the compacted pavement. Sub base layer has the following
functions.
The sub base material is prepared by blending natural material and crushed material.
Natural material source: the natural material is obtained by the nature and some tests are
taken to evaluate its engineering properties for sub base.
Crushed material source: the crushed material is produced by crushing selected (basalt)
stone.
37.5 80-100
20 60-100
5 30-100
1.18 17-75
0.3 9-50
0.075 5-25
Table 3: grading specification of sub base material
If the material being used is dry water should be added to attain the Optimum
Moisture Content (OMC). And if the material is moist, it should be mixed with a
dry material to reduce the moisture.
Base course layer is a pavement layer which is found between the sub base and asphalt
concrete layer. Its material is permeable material. The layer does not hold moisture. The
moisture is drained out to the sub base vertically and to the shoulder laterally. So, one of
the functions of base course layer is protecting the contamination of asphalt concrete layer
with moisture, because asphalt is very sensitive to the moisture effect. It has very high
bearing capacity of traffic load. This helps the asphalt concrete layer to not be deformed.
28 - - 100
Prime coat is a mixture of bitumen and kerosene. It is sprayed on the base course after
construction of base course is completed and approved. Asphalt concrete layer is paved
after spraying of prime coat. Prime coat needs at least 24 hours to be cured. So asphalt
concrete layer is paved after 24hours spraying of prime coat. Prime coat is a medium
curing. MC-30 and MC-70 are the grades which are used as the grades of prime coat.
Tack coat
It is a mixture of petroleum and bitumen added the dinorame reagent. It sets rapidly. It
has similar function with prime coat. And cares which are listed in prime coat are
applied here. Tack coat is used when asphalt concrete layer is going to be laid on the
bridges. It also used when two halves of the asphalt is ready to be joined. And when
new surface asphalt layer lay on wearing layer Tack coat is applied in such condition
because it sets rapidly.
Before application of the tack coat, the existing surface should be properly prepared in
order for a successful bond to be formed. It is important that the existing surface be dry and
free from dirt and debris. The bitumen is applied by a pressure distributor. This type of
vehicle is equipped with a tank containing the surfacing material and a spray bar with
Asphalt pavement concrete layer is the top layer of pavement layers. Traffic load is
applied on it directly. It is made with high quality paving material composed of
bitumen, aggregate and air. Asphalt concrete layer possesses the following
characteristics.
The asphalt concrete layer is made from high quality crushed stone and bitumen.
Crushed material:
It is produced by crushing high quality rock. The size of this material is less than or
equal to 25mm. filler materials (crushed rock material passing 0.075mm) are mixed
with the aggregate to get a well graded aggregate size. The crushed material has one
production plant at 10 km of our site. There are four bins of aggregate which are
blended together to get the required asphalt concrete aggregate proportion. The bins
have their own gradation specification.
Different tests are taken on the aggregate of asphalt concrete. These are:
Aggregate crushing value (ACV) test
Bitumen
Bitumen is viscous liquid or solid material which has adhesive property. It is usually
hard at normal temperature and softens flow when it is heated. It is used to bind
aggregates. Its type and grade is specified based on the environmental conditions. Grade
80/100 (80-100) of bitumen is used in this project. Per cent of the bitumen content
which is used in the project based on the mix design is 5.0%. Quality tests are taken on
the bitumen which is used in this project. The quality tests are:
Penetration test
Softening point test
Ductility test
The two materials (aggregate and bitumen) are mixed in the mix plant based on the mix
design. The asphalt concrete hot mix is transported to the site. The different tests are
taken on the asphalt concrete hot mix. The contractor accepts the following tests and
specification on the asphalt concrete mix.
Most of the time, the asphalt layer is done through half. Because there is no
detour to the current flow of traffic. So, the halves are done at different
time. At the time of laying the second half layer, the previous half is cut and
it is polished with the tack coat to join the two half layers.
One truck asphalt concrete mix covers 40m length of pavement.
Temperature has greatest effect on the asphalt concrete layer. Asphalt needs
accurate measurement of temperature. So temperature is measured at different
time and place. It is measured as follow.
Measurement taken at Temperature ⁰ c
The following techniques of construction are applied during the construction of pavement
layers.
The direction of compaction is from bottom to the top on the hilly area. This is
done to protect the sliding pavement layer during construction.
The compaction paths are overlapped each other to avoid the bulging of
materials between the two paths.
Compaction is started from the inner side of the horizontal curve and continues
to the outer side of horizontal curve. This is done to protect the sliding of
materials due to supper elevation.
STRUCTURAL WORKS
Figure 4.1 showing plan view of bridge which cuts a long curve
4.1 BRIDGES
1. Slab Bridge
2. Beam Bridge
3. Truss bridge
4. Arch bridge
1. Timber bridge
2. Concrete bridge
3. Stone bridge
4. R.C.C bridge
5. Steel bridge
6. P.C.C bridge
7. Composite bridge
8. Aluminum bridge
2. Cantilever bridge
3. Continuous bridge
According to function
3. Pedestrian bridge
4. Highway bridge
5. Railway bridge
1 Excavating the land 100mm below than the bottom level of the footing with
reference to the TBM and with the help of auto level and excavator.
2 The PCC has been done as excavation is done 100mm below that 100mm is for the
PCC which helps in the bearing strength of the soil and foundation not to be in direct
contact of the soil.
3 After PCC the laying of reinforcing bars are to be done for the foundation of the
bridge as per the drawings provided by the client.
4 After the laying of the reinforcement bars than pouring of the concrete is to be
GURU NANAK DEV ENGINEERING COLLEGE,LUDHIANA Page 40
done with the help of concrete pump.
5 When foundation of the bridge is constructed than the abutment wall is made
over the foundation at both ends of the bridge.
6 Above the abutment wall there is an abutment cap on which the elastomeric
bearing is constructed.
7 After the bearing of the bridge now the precasted RCC I-girders kept on the
bearing of the bridge from the both ends.
8 Above the precasted RCC girders there laid a Deck Slab which is used as
carriageway and above it there built a RCC Crash barrier and RCC Railing
Minor drainage structures are drainage structures which are used to drain the water that
comes from the asphalt surface, cut section and catchment area.
Minor drainage structures which are built on the road are classified into:
Side ditch is a longitudinal drainage structure which is built at the side of the road. It
collects water that comes from the surface of the road, cut section and the catchment
area and drains to the nearest
culvert. Side ditch is provided where cut section is available and flow water exists from
the catchment area to the road prism.
V ditch
U ditch
Trapezoidal ditch
Culvert is also a bridge whose span is less than 6m. The function of a culvert is to
convey surface water across a highway, railroad, or other embankment. In addition to
the hydraulic function, the culvert must carry construction, highway, railroad, or other
traffic and earth loads. Therefore, culvert design involves both hydraulic and structural
design considerations.
Culverts are available in a variety of sizes, shapes, and materials. These factors, along
with several others, affect their capacity and overall performance. Sizes and shapes
may vary from small circular pipes to extremely large arch sections that are sometimes
used in place of bridges.
The most commonly used culvert shape is circular, but arches, boxes, and elliptical
shapes are used, as well. Pipe arch, elliptical, and rectangular shapes are generally used
in lieu of circular pipe where there is limited cover. Arch culverts have application in
locations where less obstruction to a waterway is a desirable feature, and where
foundations are adequate for structural support. Box culverts can be designed to pass
large flows and to fit nearly any site condition. A box or rectangular culvert lends itself
more readily than other shapes to low allowable headwater situations since the height
may be decreased and the span increased to satisfy the location requirements.
The material selected for a culvert is dependent upon various factors, such as
durability, structural strength, roughness, bedding condition, abrasion and corrosion
resistance, and water tightness. The more common culvert materials used are concrete
and steel (smooth and corrugated).
Another factor that significantly affects the performance of a culvert is its inlet
configuration. The culvert inlet may consist of a culvert barrel projecting from the
roadway fill or mitered to the embankment slope. Other inlets have headwalls, wing
walls, and apron slabs or standard end sections of concrete or metal.
A careful approach to culvert design is essential, both in new land development and
retrofit situations, because culverts often significantly influence upstream and
downstream flood risks, floodplain management and public safety. Culverts can be
designed to provide beneficial upstream conditions and to avoid negative visual impact.
1. Excavating the land 100mm below than the bottom level of the footing with
reference to the TBM and with the help of auto level and excavator.
2. The PCC has been done as excavation is done 100mm below that
100mm is for the PCC which helps in the bearing strength of the soil
and foundation not to be in direct contact of the soil.
3. After PCC the laying of reinforcing bars are to be done for the
foundation as per the drawings provided by the client.
4. After the laying of the reinforcement bars than pouring of the concrete is to
be done with the help of concrete pump.
5. After 24 hours the shuttering which is used for stabilize the concrete is
removed.
BREAST WALL
The breast wall is a type of retaining wall which is used to prevent the sliding of
hill towards the road so that there is no problem for the running traffic on the
road in case of any landslides.
Height: - 3m throughout the road length, somewhere 6m (depend upon the sliding
risk). Dimensions: -
1. Top width of breast wall = 600 mm
3. Slope of PCC= 20 %
In civil engineering, a cut or cutting is where soil or rock material from a hill or
mountain is cut out to make way for a canal, road or railway line.
In cut and fill construction it keeps the route straight and/or flat, where the
comparative cost or practicality of alternate solutions (such as diversion) is
prohibitive. Contrary to the general meaning of cutting, a cutting in construction
is mechanically excavated or blasted out with carefully placed explosives. The
cut may only be on one side of a slope, or directly through the middle or top of a
hill. Generally, a cut is open at the top (otherwise it is a tunnel). A cut is (in a
sense) the opposite of an embankment. When used in reference to transportation
routes, it reduces the grade of the route.
Cuts can be created by multiple passes of a shovel, grader, scraper or excavator,
or by blasting. One unusual means of creating a cut is to remove the roof of a
tunnel through daylight. Material removed from cuts is ideally balanced by
material needed for fills along the same route, but this is not always the case
when cut material is unsuitable for use as fill.
TYPES OF CUT
There are at least two types of cut, side hill cut and through cut. The former
permits passage of a transportation route alongside of or around a hill, where the
slope is transverse to the roadway. A side hill cut can be formed by means of side
casting, i.e., cutting on the high side balanced by moving the material to build up
the low side to achieve a flat surface for the route. In contrast, through cuts,
where the adjacent grade is higher on both sides of the route, require removal of
material from the area since it cannot be dumped.
MATERIALS TO BE USED
For excavation as per the requirement and the direction of project manager. For
filling works wherever applicable, depending upon the contract specification,
the filling earth shall be identified and approved. The filling material shall be free
from lumps, clods, vegetation and other organic and deleterious matter.
SAFETY REQUIRMENT
Care shall be taken not to dump the excavated material near the excavation
area and follow the safety norms.
Barricading shall be provided around excavated area and signal light shall be
provided at night hours.
Excavated material shall not be dumped alongside the pit excavated.
Excavated earth shall be disposed off to designated locations as mentioned in
contract. Some quantity of excavated earth shall be retained for backfilling if
specified so. Excavation pit shall be kept free from water by suitable means of
dewatering as and when required
In case of mechanized excavator with excavators. Work shall be continued till
about 150mm above final level. Levelling and dressing shall be done
manually with light compaction, either manually or with plate compactor, as
instructed by Project Manager
All persons engaged in job shall wear PPE and the equipment‟s deployed
will be checked by HSE Officer.
This is the department, which keeps a check on the quality of the materials that are to
be used on the site. Test on bricks, aggregates, cement, fly ash, concrete (cube test)
were explained and performed in the lab. The importance of the components of
concrete was taught to us, because at the end of the day concrete covers maximum
amount of volume in our construction.
• Soil class
• Asphalt class
• Concrete class
Soil class
Different tests are done for each material. The following soil tests are carried out in the
laboratory.
This test is used to evaluate the strength of sub grade, sub base and base course
materials. The CBR value is a requirement in design in pavement materials of natural
gravel. The test covers the laboratory determination of the California Bearing Ratio of a
Calculation
The amount of water which is used to prepare a sample is obtained by the following
formula:
Plasticity index the difference of liquid limit and plastic Fig 6.3 P.I
limit. Liquid limit is the empirical established moisture
content at which a soil passes from the liquid state to the plastic state. And plastic limit
is a moisture content at which a soil becomes dry to be plastic.
PI = LL-PL
Gradation
Gradation is the determination of particle size distribution of soil which is used to
construction. If a material is well graded, it has a good inter locking of particles to each
other. The proportion of fine materials and coarse materials has a great effect on road
construction. If the percentage of the coarse material is above the limitation and the
percentage of fine material is below its specification, the material particles are not
interlocked to each other efficiently. This situation loses the strength of the material. If
the percentage of fine material is above its limitation and the course material is below
the requirement, the bearing capacity of the material is under the required capacity. It
In order to get a well graded material, sieve analysis is carried out for each soil
materials. It is taken on embankment, capping layer, sub grade, sub base, base course,
asphalt aggregate and sand. Each material has its gradation specification.
PROCEDURE:
Aggregate used in road construction should be strong enough to resist crushing under
traffic wheel loads. If the aggregates are weak, the integrity of the pavement structure is
likely to be adversely affected. The strength of coarse aggregates is measured by the
aggregate crushing value.
The aggregate crushing value (ACV) gives a relative measure of the resistance of an
aggregate to crush under a gradually applied load.
This test is carried on the stone masonry, sub base, base course, and asphalt aggregate
materials. Each material has its own aggregate crushing value limitation.
Calculation
Aggregate crushing value (ACV) is expressed as a percentage to the first decimal place
for each test specimen from the following equation.
ACV = M2 ×100
M1
Note;-
Two samples are prepared for the aggregate crushing value. One of the two is for the
dry crushing the other is socked in water and wet crushing is taken. The dry one
represents the dry season of the site the wet one represents the rainy season of the site.
The steel spheres represent a dynamic wheel load effect on the aggregate. When a
vehicle moves, it applies an impact load on the surface course and base course. This
effect is represented by Los Angeles abrasion in the laboratory. If the LAA value of a
material is above the limitation, it is rejected.
Mostly the strength of the aggregate is measured in crushing test. The Ten Percent Fine
Value (TFV) gives a relative measure of the resistance of an aggregate to crush under a
gradually applied load. In pavement design there are specific requirement for the TFV
of material test both dry and socked value.
Ten percent fine value (TFV) is determined by measuring the load required to crush a
prepared aggregate sample to give 10% material passing 2.36mm sieve after crushing.
The standard size of the aggregate 14 mm passing and 10mm retained.
Applied load for ten percent fine value is minimum 160kN. Ten percent of the prepared
sample should be crushed by 160kN or more than 160kN load to be accepted. But if ten
percent of the aggregate is crushed by less than 160kN, the material is not acceptable
because the aggregate does not tolerate heavy load vehicles.
F = 14 × f
m+4
Where
F =is the required force for the TFV
f =the maximum force read on the machine
m = the percent of material passing 2.36mm after crushing
The objective of the test is determination of the resistance aggregate being corroded by
chemicals.
The soundness test using sodium sulphate covers the test of aggregate to estimate their
soundness subjected to weathering. This is accomplished by repeated immersion of
aggregate in saturated solution of sodium sulfate. This is related the aggregate
contamination with chemicals before and after road construction.
Absorption test
Aggregate absorbs moisture. The moisture quantity which is absorbed by the aggregate
varies with respect to the season. The pore water pressure is happened due to
fluctuation of the moisture
content. This condition affects the construction negatively. The moisture which is in the
aggregate comes to the asphalt concrete layer. But asphalt concrete is sensitive for
moisture and temperature. Deformation of the asphalt concrete is happened when
moisture comes from base course layer to the asphalt layer. To avoid such problems,
absorption test is taken on the aggregates. It should be less or equal to the specification
value.
%absorption=(m1-m2)×100
m1
Where
m1 = mass of wet aggregate
m2 = mass of oven dry aggregate
Flakiness index one of the test used to classify aggregates and stones. For base course
and wearing course aggregates, the presence flaky particles are considered undesirable
as they cause inherent weakness with possibility of breaking down under heavy loads.
Aggregates are classified as flaky when they have a thickness less than 60% of their
mean sieve size.
The flakiness index of an aggregate sample is found by separating the flaky particles
and expressing their mass as a percentage of the mass of the sample. The test is applied
for the material passing 63mm sieve and retained on 6.3mm sieve.
FI = m2 × 100
m1
Calculation
Where
EI =elongation index
M1=mass of the sample
M2 =mass of the sample retained on the gage
Penetration test is used to measure the consistency of bitumen material expressed as the
penetration distance in millimetre that a standard needle penetrates a sample of bitumen
vertically under known condition of loading, loading time and temperature. The
distance which the needle penetrates is measured in 1/10mm. This is termed as
penetration value.
Penetration test is used to know the grade of bitumen. Grade of bitumen has a direct
relationship with environmental condition especially temperature. The hot areas need
high grade of bitumen. If the grade of bitumen is low in hot area, it becomes liquid
easily. This reduces the binding strength of bitumen. So the penetration value of hot
area bitumen is low. The grade of cold area bitumen is low because it is needed to be
fluid in low temperature that represents the surrounding temperature. If the grade is
high, the bitumen does not bind the aggregate. Here, the penetration value of bitumen is
high.
road up grading project uses a bitumen whose penetration value is (85/100). This value
This test provides the measure of tensile property of bituminous materials and used to
know the ductility of bitumen for the specification requirement. The ductility of a binder
indicates its elasticity and ability to deform under a load and return to its original
position when the load is removed.
The ductility of bitumen is related to the traffic load effect. If the bitumen is ductile, it
does not show rupture. If it is not ductile, rupture of bitumen is happened. This makes a
crack on the asphalt concrete layer. The minimum ductility requirement is 1m
elongation of bitumen without rupture.
The softening point test is used to measure and specify the temperature at which
bitumen begins to show fluidity. The softening point is used also useful to evaluate the
uniformity of source of supply. The softening point is also an indicative of tendency of
the material to flow at elevated temperature encountered in service.
Two steel balls are placed on a sample of binder contained in a brass ring which is
Marshal Test
The marshal test is used to measure physical properties of asphalt specimen that relate
to plastic deformation properties of asphalt mixture.
A good bitumen paving mix exhibit stability, durability, workability, and skid resistance
properties besides economy. This method works on the base of the determination of the
optimum bitumen content for a particular grading of aggregate which results good
stability and flow that satisfies the requirement when a cylindrical specimen of bitumen
paving mixture loaded on the lateral surface by means of marshal apparatus. This
method is used for the mixture containing asphalt cement and aggregate which its size is
maximum 25mm.
The main goal of the test is to measure stability and flow. Stability of the test specimen
is the maximum load resistance that the standard test specimen will develop at 60⁰ c.
The minimum stability which accepted by this project is 10kN. So every test result of
stability is greater than or equal to 10kN. Flow is the total movement or strain occurring
on the specimen when the specimen is maximally loaded during stability test. The
specification of flow which is accepted in this project is 2mm-3mm. If flow is less than
2mm, crack of pavement is happened and if the flow is greater than 3mm, the bitumen
bulges to the surface of pavement and it loses the strength of the pavement. The two
values represent the effect of traffic load on the asphalt concrete pavement.
Extraction Test
The objective of extraction test is to separating the bitumen from the aggregate to check
the bitumen amount and the gradation of the aggregate at the working site. Asphalt
This test is used to measure the proportion of bitumen and kerosene of prime coat. Prime
coat is a mixture of bitumen and kerosene which is sprayed on the base course before the
asphalt layer be paved. The proportion has been set before application. But the test is done
to check whether the proportion is applied or not. The proportion of the bitumen and the
kerosene has a significant effect on the binding of the base course aggregate. As a result
setting the correct proportion makes the asphalt concrete durable. The proportion of the
bitumen and kerosene is 60% and 40% respectively. If the percentage of bitumen is
greater than 60 it does not penetrate the base course layer it slides when the asphalt
concrete is laid on it.
Calculation:-
% bitumen = Vb ×100
Vm
Where Vb = volume of bitumen
Vm = volume of bitumen and kerosene mixture.
i. Slump test
ii. Concrete cube strength test
iii. Mortar cube strength test
iv. Consistency TEST
Slump Test
He slump test limitation accepted in this project is from 30mm to 60mm. if the slump is
under the limitation, it is not workable. It needs additional water to make it workable. If
the slump is above the limitation, it is changed to fluid. It needs removal of some
amount of water.
PROCEDURE:
1. The internal surface of the mould is thoroughly cleaned and applied with a
light coat of oil.
2. The mould is placed on a smooth horizontal, rigid, non-absorbent surface
3. The mould is then filled in 4 layers with freshly mixed concrete, each
approximately to one fourth of the height of the mould.
6. The mould is removed from the concrete immediately by raising it slowly in the
vertical direction.
7. The difference in the levels between the height of the mould and that of the
highest point of the subsided concrete is measured.
8. This difference in height min mm is the slump of the concrete.
In asphalt road up grading project, concrete is used for drainage structures such as pipe
culvert, box culvert, slab culvert and lean concrete. All concrete design is based on a
specific strength of concrete. The test is done to measure the compressive strength of the
concrete cubes. The cubed concrete is casted at the site. It is taken to the laboratory and
socked for 7days and 28days age. The concrete strength is normally tested at an age of
28 days. Sometimes this test is taken at the age of 7days. The 7day strength of the
concrete is two third of the strength of 28 days. The concrete strength of 28 days which
is used in this project varies depending on the structure. The compressive strength of
concrete is 35Gpa for pipe culvert, 30Gpa for curb stone and 25Gpa for footway curb
stone.
SPECIMEN:
5 cubes of 15 cm size Mix. M15 or above.
Procedure:
1. Representative samples of concrete shall be taken and used for casting cubes 15 cm
x 15 cm x 15 cm or cylindrical specimens of 15 cm dia x 30 cm long.
2. The concrete shall be filled into the moulds in layers approximately 5 cm deep. It
would be distributed evenly and compacted either by vibration or by hand tamping.
3. After the top layer has been compacted, the surface of concrete shall be finished
level with the top of the mould using a trowel; and covered with a glass plate to
prevent evaporation.
4. The specimen shall be stored at site for 24+ ½ h under damp matting or sack. After
that, the samples shall be stored in clean water at 27+20C; until the time of test.
5. The ends of all cylindrical specimens that are not plane within 0.05 mm shall be
capped.
6. Specimen shall be tested immediately on removal from water and while they are
still in wet condition.
7. The bearing surface of the testing specimen shall be wiped clean and any loose
material removed from the surface.
9. Align the axis of the specimen with the steel plates, do not use any packing. The
load shall be applied slowly without shock and increased continuously at a rate of
approximately 140 kg/sq.cm/min until the resistance of the specimen to the
increased load breaks down and no greater load can be sustained. The maximum
load applied to the specimen shall then be recorded and any unusual features noted
at the time of failure brought out in the report.
Mortar is a mix cement sand in 1 : 2 ratio respectively. The sand size used for mortar is
9.5mm sieve pass. Mortar is used for the construction of retaining wall and ditch. Cubed
mortar is casted at the site and taken to the laboratory. It is soaked for 7days. After
7days, strength test is taken on the casted mortar. The compressive strength of mortar is
greater than or equal to 10Gpa.
PROCEDURE:
6. Repeat the above procedure taking fresh sample of cement of different quantities of
water until the reading on the gauge is 5-7 mm.
REPORTING OF RESULTS:
Express the amount of water as a percentage of the weight of dry cement to the first
place of decimal.
This test is used to measure degree of compaction and dry density of the compacted soil
at the site. Degree of compaction and dry density of the soil has a significant effect on
the asphalt concrete pavement. If the two parameters are not fulfilled, the asphalt layer
shows the differential settlement. The test is done by sand replacement method. The test
is taken for sub grade, sub base and base course layers in the site.
The core of the asphalt concrete is cut in order to measure the thickness of the asphalt
layer, bulk specific gravity and void.
Cut of core is carried out at every 100m distance of the asphalt concrete layer. It is done
in the sequence of right, centre, and left. The core sample is taken to the laboratory and
the following tests are done.
Thickness measurement
Test of bulk specific gravity
Test of void
BATCHING PLANT
Batching Plant where the concrete ready mix prepare. We prepare here concrete
mix design M30 (1:1:1.5) (sand: cement: concrete). Batching plant can be operated by
software name “BATCHMATE” or it can be operated by manually with the buttons of
the machine.
33 grade
43 grade
53 grade
7.2 AGGREGATE:
The grade number indicates the minimum compressive strength of cement sand mortar
in N/mm2 at 28 days, as tested by above mentioned procedure. Portland Pozzolana
Cement (PPC) is obtained by either intergrading a pozzolanic material with clinker and
gypsum, or by blending ground pozzolana with Portland cement. Nowadays good
quality fly ash is available from Thermal Power Plants, which are processed and used
in manufacturing of PPC.
FINE AGGREGATE:
Aggregate which is passed through 4.75 IS Sieve is termed as fine aggregate. Fine
aggregate is added to concrete to assist workability and to bring uniformity in mixture.
Usually, the natural river sand is used as fine aggregate. Important thing to be
considered is that fine aggregates should be free from coagulated lumps. Grading of
natural sand or crushed stone i.e. fine aggregates shall be such that not more than 5
percent shall exceed 5 mm in size, not more than 10% shall IS sieve No. 150 not less
than 45% or more than 85% shall pass IS sieve No. 1.18 mm and not less than 25% or
more than 60% shall pass IS sieve No. 600 micron.
7.3ADMIXTURES:
Admixtures are those ingredients/materials that are added to cement, water, and aggregate
mixture during mixing in order to modify or improve the properties of concrete for a
required application. Broadly the following five changes can be expected by adding an
admixture
Air entertainment
Water retention
Some of the important purposes for which the admixtures could be used are
For preparing 1 m3 (cubic meter) with Concrete Mix Design M30 we use:
Cement: 410 kg
Sand: 804 kg
10 mm aggregates: 508 kg
20 mm aggregates :820 kg
Admixture: 2.46 kg
The design of asphalt concrete mixture includes the selection of best blend of aggregate
and the optimum asphalt content to provide a mixture that meets the required
specification as economically as possible. It is applied to only hot mix asphalt paving
mixture containing aggregates with maximum size of 25mm or less. The asphalt mix
design follows the following steps.
All quality tests of aggregate bitumen are done before any mix design activities
are carried out.
Aggregates which are taken from the four bins are blended based on the
proportions which meet the required specification.
The blended aggregate and bitumen are mixed on a number of briquettes,
101.6mm diameter and 60-65mm using 1200gm blended aggregate and various
percentage of bitumen both above and below the expected optimum content. The
expected bitumen content was 5% and 4%, 4.5%, 5%, 5.5% of bitumen is taken
and mixed with hot aggregate.
The expected asphalt content is estimated the following computational formula. P
= 0.035a+0.045b+kc+F
Where
p = estimated asphalt content of mix
a = percent of aggregate retained on No.8 sieve
b = percent of aggregate passing No.8 and retained on No.200 sieve c
c= percent of aggregate passing No. 200sieve
k = constant that either of 0.15, 0.18, 0.12 based on passing No. 200 sieve
F = 0 to 2 based on absorption of aggregate.
Compaction of the asphalt concrete mix is done.
Density of the compacted asphalt concrete briquettes is measured to allow for
calculation of the voids properties.
Stability and flow tests are taken on the compacted asphalt concrete sample.
The optimum asphalt content is the percentage of the bitumen content which satisfies all
the specifications.
One of the biggest machines for ARWE found 2 km far from 0+00 station 300m of
bahirdar -gondar way. It is placed on an area of 0.4km 2 and has source material for
mixing, such as asphalt, aggregate, and naphtha. There are different types asphalt based
on penetration, such as 40/50, 60/70, 85/100, and other are use. Aggregate of different
gradiation 19mm, 12.5mm, 9mm, 4.75mm, and filler are brought by dump tack from
crusher The mixer has 14 major parts as shown on the fig. The mixing process start
from four cold bin holders, each has elevator transfer to the lower elevator, which holds
blend aggregate
The operator can adjust the speed of elevator by looking the output. when the
aggregate just enter to the dryer drum,<4.75mm aggregate size are sacked to silo.
The remain aggregate will burnet a temperature of 130c˚-140c˚ for 3min.
Then hot bin elevator takes to the top of mixing plant, this elevator has spoon like
structure on the surface conveyer, rotate circularly due to two dynamos at top and
bottom.
At the top sieve shaker will separate to their aggregate size, if there is over size
aggregate is there the mixer itself take it out. The required aggregate size is
always larger than used aggregate size, unless it considers it as over flow. The
sacked dust and filler collected in the dust silo and filler silo. Since dust absorb
high asphalt amount not used in mix-design. If it
is added asphalt and aggregate not allow binding because the dust covers the aggregate
and may cause alligator crack, which is disintegration road surface. At 160c˚-170c˚
heated asphalt is stored in asphalt storage tanker, which hot naphtha circulating on the
surface of the tanker to keep the temperature hot asphalt cement. Then pumped to the
top of mixing plant the pipe is also covered with insulter sponge, and white metal shin
Our supervisor gave to us to calculate the volume of each aggregate to make this hot
mix asphalt and number batching for plant to make hot asphalt for our asphalt road
project.
Sample calculation to find the volume of bituminous material of for unit station
Specific gravity of hot mix =2.5g/cm 3
HOT MIX Property Ration in per cent Mass for 1200*g Mass per station
BIN I Pass 19mm and 6.6 79.2 1.51
retained 13mm
BIN II Pass13.2mmand 9.43 113.16 2.1689
retained 4.75 mm
BIN III Pass9.5 mm and 24.5 294 5.63
retained 4.75
BIN IV BIN IV 49.05 588.6 11.28
Pass 4.75
Filler 4.7 56.4 1.08
SAFETY
The requirement of sufficient no. safety appliances are planned well in advance and
made available at stores.
a) Head protection: Every individual entering the site must wear safety helmet
confirming to IS: 2925-1984 with the chin strapped fixed to the chin.
b) Foot and leg protection: Safety footwear with steel toe is essential on site to
prevent crush injury to our toes and injury due to striking against the object.
c) Hearing protection: Excessive noise causes damage to the inner ear and
permanent loss of hearing. To protect ears use ear plugs or ear muff as suitable.
d) Eye protection: Person carrying out grinding works, operating pavements
breakers, and those involve in welding and cutting works should wear safety
goggles and face shield suitably. Goggles, safety spectacles, face shield confirm
Road construction is not fixed at a specific place. Every task is carried out at
different station. It needs movement from one station to the other station. To do
this, transport is necessary but the cars are limited in number. So I have faced such
a challenge to do a work in the construction site.
Due to I am not taking highway II course in our school .became great handicap for
to be an intern in our company
I was travelling by dam truck when the site engineers‟ is overcrowded. Sometimes
I was travelling by machine holder vehicles. I also working through at site and
laboratory. So, I solved the transport problem using the chance that I got.
I got some lecture from my friends and I was reading highway books.
Benefits of training
The training program is very essential for students. The student who works in the training
can get much more benefits. I have gained many benefits from the training program. The
benefits that I gained are:
Theory is the basement of any activity within the road construction. But it is not enough
by itself to know the real situation which exists in a construction. It needs practical skill to
carry out every activity within a project. In the training program, I develop my practical
skill in many ways. I get enough skill how laboratory and field tests are done; in what way
the earth work is done with respect to the soil type; I develop the skill of construction of
structure, surveying work, work inspection.
I have gained a good knowledge with respect to high way engineering and soil
mechanics.
I have got a good understanding of the properties of materials and I know that
different materials are used for each construction.
I have got better understand that the quality of material has a significant effect on the
Training practice has climbed all the way to the top as one of the very pleasant chapters
of my life. It left unforgettable scenes and broadened my view of the external non-
academic world. It has possibly laid a certain amount of corner stone for my future
professional life.
My four month stay in GAMMON put in me a position where I can vouch for
the company‟s competency and task fulfilment.
But there are small details that need to be addressed if the company is to emerge as a
highly respected, world-class construction company, with a strong identity which earns
the devotion of its customers by providing quality services exceeding the expectations of
its customers.
1. The company must provide substantial medication, safety, transport facility and
payment for the workers, as its achievement in goals and objectives is in one or
another way dependent on the healthy and willingly works of each and every
employee.
2. And I think it is better for the company to have and use machineries and
modern working equipment to run its projects on schedule and to made possible
speedy, accurate and less cost work.
3. The company should also try its best to increase the awareness of the employees
in company and management appreciation. Furthermore, I highly recommend
the company to give the employees incentives, whenever possible, which would
make them want to come to work every day. It starts by giving complements
where they are due
4. Base course layer was constructed in October. It was rainy week. Compaction of
the base course is continued but there was high moisture in base course. After
compaction of base course, the contractor requested to lay asphalt layer and the
request was accepted. The asphalt layer was done. But when it was opened to the
traffic, it was deformed after three days of opening to the traffic.
Asphalt is sensitive to the moisture. If base course holds moisture above the
limit, it comes to the asphalt concrete layer and the asphalt concrete layer is
settled. So I recommend that the effect of moisture on the asphalt should get a
great emphasis.
5. Prime coat is sprayed on the base course to bind the aggregate of base course
before asphalt layer is laid. It needs at least 24hours to cure. But sometimes the
asphalt layer is laid before the sprayed prime reaches 24hour. If the prime coat
does not get enough time to cure, it does not penetrate the base course layer and it
does not bind the aggregate sufficiently. This creates the deformation of asphalt
layer. So, the prime coat should have enough time to be cured.
6. Although company is governmental company I have seen some un ethics and
un accountability finical works in the project I recommended the company to
be accountable.
7. I have seen some lack of unity within the consulting office. Road construction
I have learned that road construction needs high financial strength. Investment on road
construction needs very high capital. Road construction needs a lot of machine to be run.
The machines are also very huge and their cost is counted in millions. A number of
professions are participated. It also needs a large number of labors. The construction
materials of road construction have high cost and even sometimes the materials are not
available near to the project. So road construction needs financial strength to resist the
challenge of different type of costs.
I have gained sufficient knowledge about the standard road construction. Construction of
road is subjected to the quality of construction material. The pavement indicates the
problem of quality when the material has low quality as soon as the construction is done. I
have also understood that asphalt concrete pavement is sensitive to the moisture and
temperature. I under stood how each work flow is run.
I understood that earth work is time and capital consumer section of road construction.
Especially if the cut is rock cut, it consumes high energy and large time. After earth work
reaches to the sub grade, the remaining layers do not consume much energy and time. But
quality requirement of materials increases from sub grade to the asphalt concrete layer. I
have learned the work flow of road construction. In addition I leaned work ethics, team
playing skill, leader ship skill.
[3] IS CODES
[4] www.wikipedia.com
[5] http://www.nhai.org/